Pre Commissioning Test of Dry Type Trans
Pre Commissioning Test of Dry Type Trans
Abstract— The purpose of commissioning tests on whether they are carrying any load or not. 2). Power
transformer is to satisfy, to pre-determined standards, that all the transformer is used in generating stations and sub stations at
equipment erection is correct and that all the equipment each of a power transmission line for stepping up or stepping
connections / cables have been installed in accordance with the down the voltage. Above size 500KVA transformer is called
approved erection drawings and diagrams. Furthermore to
Power transformer. This transformer is disconnected during
demonstrate to the satisfaction of the client that the foregoing
work has been done and that the equipment functions as light load period.
designed. This paper discussed procedures and testing results of
transformer. A Dry type transformer is defined as a transformer in
which the core and windings are not immersed in an
Index Terms— Commissioning, ACSD, CRT. insulating liquid. A Dry-type transformer having one or more
windings encapsulated in solid insulation is called an
I. INTRODUCTION encapsulated winding dry-type transformer.
Transformer is a device that transfers electric energy
from one circuit to another, usually with a change in voltage.
Transformers work only with a varying electric current, such
as alternating current. Transformers are important in the
distribution of electric power. They raise the voltage of the
electricity generated at a power plant to the high levels
needed to transmit the electricity efficiently. Other
transformers reduce the voltage at the locations where the
electricity is used. Many household devices contain
transformers to raise or lower house-current voltage as
needed. For example, Television sets and stereo equipment
require high voltage where the doorbells and thermostats
require low voltages.
Fig. 1. Cast Resin type Transformer
A simple transformer consists essentially of two coils of
insulated wire. In most transformers, the wires are wound Pre-Commissioning Test: Prior to energizing the
around an iron-containing structure called the core. One coil, transformer, several pre-commissioning tests are done. The
called the primary, is connected to a source of alternating objective of these tests is to confirm that the transformer has
current that produces an alternating current in the other coil. not suffered damage during transit and also to check any
This coil, called the secondary, is connected to a separate inadvertent slips in the factory tests, or supply.
electric circuit.
Transformers are classified into mainly two categories. 1). II. PRE-COMMISIONING TESTS
Distribution transformers are used to step down the Following tests are done on the transformer to pre-
distribution voltage to a standard service voltage or from determined standards.
transmission voltage to distribution voltage. Up to size
500KVA transformer is called Distribution transformer. We A) Turn Ratio Test: Ratio between all the three
can keep this transformer in operation all the 24 hours a day corresponding H.V. & L.V. phases is to be measured on all
taps. It is desirable to do this test by a Ratio-meter. But if it In case one of the phases has shorted turns, it will draw a
is not available, a simple test of measuring voltages can also comparatively large current when it is energized. When other
serve the purpose. phases are energized, flux and hence voltage in the shorted
phase will be significantly reduced. Hence all three
observations will indicate the shorted phase. Note the
observations in the “Commissioning Report”.
TABLE III
MEASUREMENT OF HV WINDING RESISTANCE
Tap No. 1U1V 1V1W 1W1U
1 226.8 226.8 227.0
2 221.6 221.17 221.7
3 215.9 215.1 215.5
Fig. 5 Short Circuit Test 4 209.9 209.9 209.9
5 204.1 204.1 204.1
A Consistent trend indicates healthiness. If short circuit test
is not possible due to limitation of source carry out one tap b) LV winding Resistance: (in mΩ)
changing operation over the entire range increasing as well
TABLE IV
as decreasing. MEASUREMENT OF LV WINDING RESISTANCE
2U2n 1.404
III. CASE STUDY 2V2n 1.406
This is the study of tests conducted on 11th Oct 2W2N 1.408
2010 of 500 KVA Cast Resin Transformer (CRT) at
VOLTAMP TRANSFOMERS LTD. Under guidance of Mr.
Rajendra Chaudhri and Mr. Pankit patel. (E) Polarity & Vector group Verification:
The specifications of the CRT are as follows:
Job No. : 18530/1 TABLE V
POLARITY & VECTOR GROUP CHECK
KVA : 500
1U1V 425 V
Voltage ratio: 3300 / 433
Vector Group: Dyn1 1V1W 423 V
Type of tap changer: Off load tap changer 1W1U 422 V
The Calculations of various tests performed on this CRT are 1V2v 1V2w 1W2w 1W2v
as follows: 375 V 423 V 374 V 374 V
\
(A) Turn Ratio Test: Vector Group Checked (Dyn1): O.K.
TABLE I
RATIO OF HV / LV PHASE MEASUREMENT
(F) Separate Source Withstand Voltage Test:
Tap No. U/u V/v W/w a) Applied 10KV between HV winding to Earth for 1
1. 13.859 13.859 13.860 min.
2. 13.526 13.525 13.526 b) Applied 3 KV between L.V. winding & Earth for 1
3. 13.193 13.191 13.193 min.
4. 12.859 12.859 12.858
5. 12.526 12.525 12.526 (G) Induced AC over voltage withstand test:
Applied 2 x 433 Volts at 124.8 Hz for 50 Secs.
(B) Magnetic Balance Test:
(H) Open circuit test:
TABLE II PT ratio P: 660/110 =6
MEASUREMENT IN VOLTAGE
CT ratio C: 20/1 =20
2U2n 2V2n 2W2n
WMSM = 0.2
25.7 V 17.82 V 8.11 V
12.5 V 25.6 V 12.08 V
Total MF= C*P*WMSM = 24
7.99 V 17.14 V 25.34 V
TABLE VI
O.C. TEST MEASUREMENT
Load Loss in Watts (Tap 1) =(W1+W2+W3)* Total M.F.
%Voltage 90% 100% 110%
= (50)*96=4800
Vavg 65 72.5 79.5
Vrms 65 72.33 79.33 Load Loss in Watts (Tap 3) = (53)*96=5088
Ir 0.21 0.35 0.71
Iy 0.17 0.28 0.55 Load Loss in Watts (Tap 5) = (55)*96=5280
Ib 0.22 0.37 0.76
W1 20 28 48
W2 12.5 17 26 IV. CONCLUSIONS
W3 9 7 (- 4)
Dry type Resin cast Transformers requires very little
maintenance from time to time. However, inspection should
No Load Loss in Watts (90%) be made at regular intervals & corrective measures shall be
=(W1+W2+W3)* Total M.F.= (41.5)*24=996 taken when necessary to ensure the most satisfactory service
from this equipment. Evidence of rusting, corrosion on
No Load Loss in Watts (100%) = (52)*24=1248 enclosure and deterioration of the insulation and paint should
be checked and corrective measures shall be taken whenever
No Load Loss in Watts (110%) = (70)*24=1680 necessary.