Carl Betterton's construction project
IMMEDIATE
ACTIVITY PREDECESSOR(S) TIME (DAYS)
A - 3
B A 4
C A 6
D B 6
E B 4
F C 4
G D 6
H E, F 8
Draw the activity-on-node (AON) project network associated with the following activities for Carl Betterton's construction p
START A E
How long should it take Carl and his team to complete this project?
Ans: 21 days
What are the critical path activities?
Ans: A-C-F-H
for Carl Betterton's construction project
D G
Slacks (LS-ES) On CP
0 Yes
2 No
0 Yes
2 No
2 No
0 Yes
2 No
0 Yes
Problem 3.6
Given the activities whose sequence is described by the following table:
IMMEDIATE
ACTIVITY TIME (DAYS)
PREDECESSOR(S)
A - 5
B A 2
C A 4
D B 5
E B 5
F C 5
G E, F 2
H D 3
I G, H 5
Draw the appropriate activity-on-arrow (AOA) network diagram
B D
22 3
A
B
11 4
A
22 55
C F
8 I
E
G
66
F
Slacks (LS-ES) On CP
0 Yes
1 No
0 Yes
1 No
2 No
0 Yes
0 Yes
1 No
0 Yes
Problem 3.8
Roger Ginde
IMMEDIATE
ACTIVITY TIME (DAYS)
PREDECESSOR(S)
A - 2
B - 5
C - 1
D B 10
E A, D 3
F C 6
G E, F 8
A E
START B D
C F
On CP
No
Yes
No
Yes
Yes
No
Yes
Problem 3.9
Jim Goodale's Carbondale, Illinois
A C E
START
B D
Immediate
Activity Time(hours) ES EF LS LF Slacks (LS-ES)
Predecessor(s)
Start 0 0 0
A - 6 0 6 0 6 0
B - 7.2 0 7.2 3.8 11 3.8
C A 5 6 11 6 11 0
D B, C 6 11 17 11 17 0
E B, C 4.5 11 15.5 20.2 24.7 9.2
F D 7.7 17 24.7 17 24.7 0
G E, F 4 24.7 28.7 24.7 28.7 0
Total 40.4
Task
E
G
E G
D F
On CP
Yes
No
Yes
Yes
No
Yes
Yes
IMMEDIATE
ACTIVITY TIME
PREDECESSOR(S)
A - 9
B A 7
C A 3
D B 6
E B 9
F C 4
G E, F 6
H D 5
I G, H 3
a) Draw the appropriate AON PERT diagram for J.C.Howard's management team
START A
C F