Question: 1
A product's scope and acceptance criteria have been defined, and the product is planned for release
at the end of the next quarter. What should the project team do next?
Answer: A
Question: 2
Following an upgrade, a software support team is overwhelmed by the number of tickets being
submitted by end users. The team's manager is pushing the team to "work smart" by focusing on
activities that deliver the most value in the least amount of time.
What should the team do?
Answer: C
Question: 3
A scrum team has eight developers, but only two are database engineers. During the last few
retrospectives, the team identified that most sprint stories are dependent upon database engineers.
This has created a bottleneck in completing stories.
What should be proposed to the team?
Answer: C
https://www.Pass4Future.com
Questions & Answers PDF Page 3
Question: 4
A product owner adds a 21-point. high-priority story to a sprint backlog. The team is concerned that
it cannot be completed during the current sprint. What should the team do?
A. Advise the product owner that the story will have to wait until the next sprint.
B. Work extra hours to complete the story and satisfy the customer's requirements.
C. Break down the story into smaller increments and negotiate other stories on the sprint backlog.
D. Increase the length of the sprint to accommodate the story.
Answer: A
Question: 5
A team is creating a highly marketed, time-sensitive product. The agile coach is concerned that
anything other than exceptional quality will result in bad publicity for the company.
What should the agile coach ensure that developers do?
Answer: D
Question: 6
The agile practitioner has determined that two different team members are working on addressing
the same major issue on the project. How should the agile practitioner address this?
A. Implement a burnup chart and add the issue resolution as a task to the product backlog for the
customer to prioritize.
B. Add the issue to the kanban board and assign the it to the team member who has made the most
progress on resolving it.
C. Conduct a root-cause analysis on the issue and identify related risks and risk response owners at
the next retrospective.
D. Document all project issues in a common space and ask the team members to decide on task
allocation principles.
Answer: D
Question: 7
Toward the end of a project, the product owner discovers that the project has a high probability of
failure due to a critical feature not functioning as expected. What should the product owner do?
https://www.Pass4Future.com
Questions & Answers PDF Page 4
Answer: D
Question: 8
During mid-sprint changes, an agile facilitator meets with the executive and development teams.
During the meeting, executive team members resolve conflicts, and on their own initiative, review
the iteration charts to discuss changes to the iteration's functional goal.
What practice is the agile facilitator implementing?
Answer: A
Question: 9
A product owner for two highly visible projects spends a great deal of time meeting with and
reporting to senior stakeholders. The product owner is overwhelmed because
both project teams request clarification on the requirements and the overall priorities. What should
the agile project manager do?
Answer: C
Question: 10
An agile team is preparing a release plan for a project. What information will the team need to
complete this plan?
https://www.Pass4Future.com
Questions & Answers PDF Page 5
Answer: D