Brent Spence RFP 2023
Brent Spence RFP 2023
Brent Spence RFP 2023
3. GENERAL ....................................................................................................................................... 7
3.1 Funding Sources ......................................................................................................................... 7
3.2 Federal Requirements ................................................................................................................. 7
3.3 DBE Requirements ...................................................................................................................... 7
3.4 OJT Requirements ...................................................................................................................... 7
9. PROTESTS ................................................................................................................................... 39
9.1 Written Protests Only ................................................................................................................. 39
9.2 Protest Contents ........................................................................................................................ 40
LIST OF TABLES
Table 1: Procurement Schedule ............................................................................................................. 4
LIST OF FORMS
FORM A: PROPOSAL LETTER
FORM B- 1: IDENTIFICATION OF OFFEROR AND PRINCIPAL PARTICIPANTS
FORM B- 2: INFORMATION ABOUT OFFEROR ORGANIZATION
FORM B- 3: INFORMATION ABOUT MAJOR PARTICIPANTS
FORM C: RESPONSIBLE OFFEROR QUESTIONNAIRE
FORM D: NON-COLLUSION AFFIDAVIT
FORM E: CONFLICT OF INTEREST DISCLOSURE STATEMENT
FORM F: DEBARMENT AND SUSPENSION CERTIFICATION
FORM G: DBE GOAL ATTAINMENT OR GOOD FAITH EFFORTS CERTIFICATION
FORM H: EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION
FORM I: BUY AMERICA CERTIFICATION
FORM J: CERTIFICATION REGARDING USE OF CONTRACT FUNDS FOR LOBBYING
FORM K: PREQUALIFICATIONS
FORM L: OFFEROR REGISTRATION
Offerors must comply with the terms and conditions of this ITO during the Procurement Process and in
their responses to the RFP. Respondents will be evaluated to determine their ability to meet or exceed
the Project Goals (inclusive of primary goals and contract objectives defined in Section 1.3 (Project
Goals)).
Definitions of capitalized terms used but not defined within the ITO are set forth in Exhibit A (Acronyms
and Definitions) of the Progressive Design-Build Contract (PDBC).
The Work shall be performed by the Contractor in two phases, with the first phase consisting of two
sub-phases as follows:
A. Preconstruction Phase (Phase 1)
1. Proof-of-Concept Phase (Sub-Phase 1A); and
2. Project Development Phase (Sub-Phase 1B)
B. Final Engineering and Construction Phase (Phase 2)
The Department intends that the Sub-Phase 1A Proposal will be substantially complete and agreed
prior to execution of the PDBC and that upon execution of the PDBC, the Contractor shall be entitled to
compensation with respect to the time spent in preparation and negotiation in accordance with PDBC
Section 2.3.1 (Pre-Sub-Phase 1A Work).
Sub-Phase 1A shall commence upon the execution of the PDBC and the Department’s issuance of
Sub-Phase 1A Notice to Proceed (NTP) and shall continue until the sooner to occur of (i) the Sub-
Phase 1B Change Order is executed by the Department, or (ii) the Department exercises its right to
terminate the PDBC. Sub-Phase 1A Work shall be performed under a direct labor times a multiplier
compensation arrangement that may not exceed the Maximum Sub-Phase 1A Prime Compensation
defined in Exhibit B (Contract Particulars) of the PDBC.
Sub-Phase 1B shall commence upon the Department’s issuance of the Sub-Phase 1B NTP and shall
continue until the sooner occur of (i) the Phase 1 Work is complete or (ii) the Department exercises its
right to terminate the PDBC. Sub-Phase 1B Work shall be performed under a direct labor times a
multiplier compensation arrangement that may not exceed the Maximum Sub-Phase 1B Prime
Compensation (amount to be negotiated prior to completion of Sub-Phase 1A and incorporated into the
terms and conditions of the Sub-Phase 1B Change Order). If authorized in an executed Early Work
Package, Early Work may begin before Sub-Phase 1B is completed, with Early Work and Sub-Phase
1B Work proceeding concurrently.
Phase 2 shall commence upon the execution of a Phase 2 Change Order and the Department’s
issuance of Phase 2 NTP and shall continue until the end of the Term.
The Department will retain two Independent Cost Estimators (ICE) for this Project, pursuant to the ICA.
Each ICE will develop independent cost estimates for the Project at the same milestones as the
Contractor. The purpose of the first ICE’s involvement in the Project will be to validate the cost(s) and
production proposals submitted by the Contractor at each pricing milestone. The function of the second
ICE is to develop a state Engineer’s estimate prior to final pricing agreement in accordance with ORC
5517.01.
The design of the new Companion Bridge type shall be proposed by the Offeror and approved by the
Department. The bridge type to be selected per the Finding of No Significant Impact (FONSI) (EN-03) is
either of the following:
A. Arch bridge; or
B. Cable-stayed bridge
The design of the Project is based on Concept I-W (see applicable Reference Information Documents)
for crossing the Ohio River which allows either bridge type to be delivered. This concept contemplates
that all interstate traffic for I-71 and I-75 will be accommodated via the new Companion Bridge, and all
local connectivity will be accommodated via the existing Brent Spence Bridge.
A portion of the Work conducted in conjunction with the Project will include the rehabilitation and
reconfiguration of the existing Brent Spence Bridge, reducing the number of lanes on each deck from
four lanes to three lanes and significantly increasing the inside and outside shoulder widths. Two
“Collector-Distributor (CD) Road” systems will be constructed with the Project; one CD Road to connect
I-71/I-75 traffic to and from the local street network between West 12th Street (southbound at 5th
Street) in Covington, Kentucky and Ezzard Charles Drive in Cincinnati, Ohio, and one CD Road
between south of Dixie Highway and north of Kyles Lane in both directions, allowing for upgraded
interchanges.
Local connectivity in Covington will be improved by extending frontage roads to connect 5th Street and
Pike Street going northbound and 4th Street and Pike Street going southbound.
The Project, including design of the new Companion Bridge, will include aesthetic features for which
detailed specifications will be developed. The Department will lead the development of the aesthetic
features with support of the Contractor.
The Completion Deadline for the Companion Bridge to be completed and open to traffic Milestone will
be July 15, 2029. The Substantial Completion Deadline for the Project will be September 15, 2030.
Milestone Date
Last date for Offeror team registration (Form L (Offeror Monday, February 20, 2023, at 1:00 p.m.
Registration)) Eastern Time
Pre-Proposal One-on-One Meeting No. 1 (Regarding the RFP) Thursday, February 23, 2023
Pre-Proposal One-on-One Meeting No. 2 (Regarding the RFP) Thursday, March 9, 2023
Milestone Date
Companion Bridge Open to Traffic Interim Completion Date July 15, 2029
2. RFP PROCESS
Offerors are responsible for reviewing the RFP Documents and any Addenda issued by the Department
prior to the Proposal Due Date. Offerors will be afforded an opportunity to submit written Requests for
Clarification (RFC) concerning the RFP in accordance with the process specified below. In addition,
Offerors will have an opportunity to attend two Pre-Proposal One-on-One meetings with the
Department prior to the Proposal Due Date. The Department will interview Offerors after receipt of
Proposals as part of the evaluation process.
If an award is made, the Department will execute the PDBC with the responsible Offeror that is
determined by the Department to provide the best value to the Department and be in the best interest
of the Department.
Should a question arise at any time during any portion of the Procurement Process, the Offeror may
seek clarification by submitting a clarification question using the Department’s Pre-Bid website
(referencing Project Number 233000):
http://www.dot.state.oh.us/Divisions/ContractAdmin/Contracts/Pages/PBQs.aspx.
The Department will post a response on its website to RFCs submitted. Responses to RFCs posted on
the Department’s website are not revisions to the Contract Documents and are not binding. Any
response requiring a revision to the Contract Documents will be implemented through issuance of
Addenda to the RFP.
During the Pre-Proposal One-on-One Meetings, Offerors may ask questions and the Department may
provide responses for informational purposes. Any responses provided by the Department during the
Pre-Proposal One-on-One Meetings may not be relied upon; however, the Department may, in its
discretion, and subject to Section 2.1 (Examination of RFP and Requests for Clarification) above,
respond in writing to questions or comments raised in Pre-Proposal One-on-One Meetings and/or
incorporate the substance of its responses into the RFP by Addenda. The Department reserves the
right to disclose to all Offerors any issues raised during the Pre-Proposal One-on-One Meetings if, in
the judgement of the Department, such issues would jeopardize a fair and equitable Procurement
Process. The Department will use commercially reasonable efforts to maintain the confidentiality of
information related to Offerors and their Proposals as required to comply with this Section 2.2, Section
4.4 (Confidentiality/Public Information Act Disclosure Requests), and applicable law.
Additional information regarding the Pre-Proposal One-on-One Meetings will be provided by the
Department to registered Offerors.
2.3 Addenda
The Department reserves the right, in its sole discretion, to revise, modify, or change the RFP and/or
Procurement Process at any time before the Proposal Due Date shown in Section 1.4 (Procurement
Schedule). Any such revisions will be implemented through issuance of Addenda to the RFP.
2.4 Errors
If any mistake, discrepancy, deficiency, ambiguity, error, or omission is identified by an Offeror at any
time during the Procurement Process in any of the RFP Documents supplied by the Department, the
Offeror shall notify the Department of the mistake, discrepancy, deficiency, ambiguity, error or omission
and recommend a correction in writing in accordance with Section 2.1 (Examination of RFP and
Requests for Clarification).
3. GENERAL
3.1 Funding Sources
As detailed in the ICA, the Department’s plan of finance for the Project contemplates that the
Department will fund the design and construction of the Project using a combination of federal funds,
State of Ohio funds, and funds made available by the Commonwealth of Kentucky. Payments will be
made by the Department in accordance with the negotiated PDBC and in accordance with the
procedures set forth under the ICA.
The DBE goal for Phase 1 (Preconstruction Phase including Sub-Phase 1A and Sub-Phase 1B) is 9%
of the Sub-Phase 1A and Sub-Phase 1B Contract Price.
The Department is targeting a DBE goal of at least 7% of the Contract Price for Phase 2. The DBE goal
for Phase 2 will be agreed upon between the Contractor and the Department and finalized by the
Department as part of the Phase 2 Change Order. Prior to execution of any Early Work Package or the
Phase 2 Change Order, the Contractor will be required to submit a detailed DBE Performance Plan to
achieve the DBE participation goal.
ODOT anticipates a goal of 15% of total labor hours for the Project be performed by trainees. The OJT
goal will be agreed upon between the Contractor and the Department and finalized by the Department
as part of the Phase 2 Change Order.
4. PROCUREMENT PROCESS
4.1 Procurement Method
The Procurement Process intended to be used by the Department is described below; provided that the
Department reserves the right, in its sole discretion, to modify the Procurement Process to comply with
applicable law and/or to address the best interest of the Department, including canceling the
Procurement.
Following Proposal submission, Offerors will be required to attend an interview with the Department.
Following interviews and evaluation of interviews, the Department intends to select an Offeror for
conditional award based on the Department’s determination of apparent best value and finalize a PDBC
for award and execution. If the Department and the apparent best value Offeror are unable to finalize
and execute a PDBC, the Department may award the Project to the next highest rated Offeror.
Alternatively, the Department may modify and re-issue the RFP, or terminate the Procurement Process.
Eric Kahlig
Alternative Project Delivery Administrator
Ohio Department of Transportation
1980 W. Broad Street, Columbus, Ohio 43223
E-mail: [email protected]
All official Project communications will be provided from the Department’s Authorized Representative.
Each Offeror shall timely register with the Department by submitting Form L (Offeror Registration) by
email to the Department’s Authorized Representative. Subject to applicable state and federal law as
described in Section 4.4 hereof, Form L (Offeror Registration) will remain confidential until after an
award is made. Offerors are required to register prior to the deadline established in the procurement
schedule set forth in Section 1.4 (Procurement Schedule). Any change in an Offeror team’s
organization after its registration is subject to Section 5.5 (Changes in Offeror’s Organization). The
Department reserves the right to reject any Proposal submitted by an Offeror or Offeror team that did
not timely register pursuant to this Section 4.2 (Authorized Representatives and Offeror Registration) or
that failed to timely seek approval of any post-registration change in its organization pursuant to Section
5.5 (Changes in Offeror’s Organization).
As part of Form L (Offeror Registration), each Offeror will identify a point of contact (Procurement Point
of Contact or PPC). The PPC will be responsible for initiating or receiving all communication with the
Department and must be delegated the full authority of the Offeror to communicate with the Department
throughout the Procurement Process. Following registration, all Offeror submissions and
communications with the Department should be made through the PPC.
The Department will not be responsible for any oral communication or any other information or contact
that occurs outside the official communication process specified in this ITO.
After a Offeror’s submission of its Form L (Offeror Registration), neither the Offeror nor any Component
Firm thereof may communicate with another Offeror or Component Firm associated with another
Offeror with regard to the Project, the Proposal, or any other Offeror’s Proposal, except that an Offeror
may communicate with an individual or Component Firm that is included in more than one Offeror
organizations, so long as those Offerors have an established, documented protocol to ensure that such
individual person or firm will not act as a conduit of information between the respective Offeror
organizations.
Any verified allegation that an Offeror or Component Firm member has engaged in such prohibited
communications or attempted to unduly influence the selection process may be cause for the
Department to disqualify the Offeror or to disqualify the Component Firm from participating with any
Offeror; all at the sole discretion of the Department.
Notwithstanding anything to the contrary contained herein, Offerors are advised that the information
contained in Form B-1 (Identification of Offeror and Principal Participants) and Form E (Conflict of
Interest Disclosure Statement) of each Proposal may be publicly disclosed by the Department at any
time, in the Department’s sole discretion. Proposal materials will not be returned to the submitting party,
except as determined by the Department in accordance with applicable laws.
Nothing contained in this RFP shall modify or change the obligations of the Department under the
federal Freedom of Information Act (FOIA) or other applicable law. Determinations regarding the
confidentiality of Proposal information or other materials submitted as part of this Procurement Process
will be made by the Department in accordance with applicable law. Under no circumstances will the
Department be responsible or liable to an Offeror or any other party as a result of disclosing any such
materials.
In the event the Department is requested to disclose any information that has been marked as “trade
secret”, the Department shall respond with a redacted copy prepared by the Department (the
“Department Response”).
In the event that an Offeror asserts a right to any redacted information in the Department Response
with regard to any complete or partial document(s), data, or record(s), the Department intends to notify
the Contractor of the assertion of right(s) (the “Notice of Rights”), and from the date the Contractor
receives the Notice of Rights, the Contractor shall have the responsibility to respond to the requestor
asserting that the information requested is exempt from disclosure under applicable law.
The Department shall not be obligated to maintain in confidence any information that is not a trade
secret including information that (a) is already known by the State, (b) is or comes into the public
domain through no fault of the State, (c) is independently developed by the State, or (d) comes to the
State from a third-party in a manner not in violation of any obligation of confidentiality by such third
party to the Offeror.
State law generally requires that documents which contain both confidential/trade secret and non-
confidential information be disclosed with confidential information redacted.
do business in the State of Ohio and Commonwealth of Kentucky for the duration of the Project. If an
Offeror has not performed work in Ohio or Kentucky, it must also be in good standing to do business in
its home jurisdiction.
The Offeror is responsible for ensuring all Component Firms responsible for professional and
construction services on the Project are prequalified with the Department and KYTC, as applicable, in
accordance with Form K (Prequalification). Failure by the Offeror to meet the requirements of
Prequalification may result in the Offeror being disqualified from the Procurement Process.
Each Offerors’ attention is directed to Federal Code Section 23 CFR Part 636 Subpart A and in
particular Section 636.116 regarding organizational conflicts of interest. Section 636.103 defines
“organizational conflict of interest” as follows:
“Organizational conflict of interest means that because of other activities or relationships with other
persons, a person is unable or potentially unable to render impartial assistance or advice to the
owner, or the person's objectivity in performing the contract work is or might be otherwise impaired,
or a person has an unfair competitive advantage.”
Offerors are prohibited from receiving any advice or discussing any aspect relating to the Project or
Procurement Process with any person or entity with an organizational conflict of interest. The
Department may disqualify an Offeror if an organizational conflict of interest exists.
Each Offeror agrees that if an organizational conflict of interest is discovered, the Offeror must make an
immediate and full written disclosure to the Department that includes a description of the action that the
Offeror has taken or proposes to take to avoid or mitigate such conflicts. If an organizational conflict of
interest is determined to exist, the Department may, at its discretion, cancel the contract for this Project.
The Offerors’ attention is further directed to Ohio Administrative Code (OAC) Section 4733-35-05 (C),
201 KAR 18:142, and the requirements regarding organizational conflicts of interest. For guidance in
determining if you would have a Conflict of Interest, please review the Department’s Specifications for
Consultant Services (primarily sections 2.15 through 2.18) and the referenced Codes within those
applicable sections.
While all of the references are for engineering or surveying services, the Department will use the same
level of scrutiny for any consultant service.
Each Offeror shall require its Component Firms to identify potential conflicts of interest or a real or
perceived competitive advantage relative to this Procurement Process. Offerors are notified that prior or
existing contractual obligations between a company and a federal or state agency relative to the Project
or Department’s Progressive Design-Build program may present a conflict of interest or a competitive
advantage. If a potential conflict of interest or competitive advantage is identified, the Offeror shall
submit in writing the pertinent information to the Department’s Office of Consultant Services prior to the
submittal of the Proposal and the Offeror may request a waiver of the conflict of interest for the
Department’s consideration. Information on submitting a Conflict Waiver Request can be found at:
http://www.dot.state.oh.us/Divisions/Engineering/Consultant/Pages/Manuals-and-Contract-Documents-
.aspx.
The Department, in its sole discretion, will make a determination relative to potential organizational
conflicts of interest or a real or perceived competitive advantage, and its ability to mitigate such a
conflict. An organization determined to have a conflict of interest or competitive advantage relative to
this procurement that cannot be mitigated, shall not be allowed to participate as an Offeror or
Component Firm for the Project. The Department will attempt to make all reasonable efforts to timely
respond to a waiver request.
The following firms will not be allowed to participate as an Offeror or a Component Firm due to a known
conflict of interest. This list shall not be considered all-inclusive and may be supplemented by the
Department throughout the Procurement Process.
A. HNTB Corporation
B. HMB Professional Engineers, Inc.
C. KBHR Access
D. Rasor Marketing Communications, LLC
E. American Structurepoint, Inc.
F. Geotechnology, LLC
G. T2 Utility Engineers
After Proposals are submitted, individuals, Principal Participants, and Major Participants identified in the
Proposal may not be removed, replaced, or added to without the written approval of the Department.
The Department may revoke an awarded contract if any individual, Principal Participants, or Major
Participants identified in the Proposal is removed, replaced, or added to without the Department’s
written approval. To qualify for the Department’s, approval, the written request must document that the
proposed removal, replacement, or addition will be equal to or better than the individual or design-build
firm provided in the Proposal. Requests shall demonstrate, to the Department’s satisfaction, that (a) the
current Offeror team, including any replacement entity, meets the criteria set forth in the ITO and (b) the
replacement or removal of any individual Principal Participants, or Major Participants identified in its
Proposal will not affect, in whole or in part, the basis upon which the Offeror is evaluated. Requests for
removals, replacements and additions must be submitted in writing to the Department’s Authorized
Representative as described in Section 4.2 (Authorized Representatives and Offeror Registration). The
Department is under no obligation to approve such requests and may approve or disapprove in writing
a portion of the request or the entire request at its sole discretion.
6. PROPOSAL REQUIREMENTS
6.1 General Provisions Regarding Proposals
Proposal contents, information, organization, formatting, and submission shall adhere to the
requirements of this ITO and ITO forms. Any failure to provide all the information, all completed forms
or information in the format and organization specified, or the submittal of a Proposal subject to any
reservations, qualifications, conditions, assumptions or which contains an alteration, deviation, or is
non-compliant in any manner, may result in the Department’s rejection of the Proposal or giving it a
lower rating, in its sole discretion.
A cover sheet shall be provided within the submission, and it shall list the page numbers of every
occurrence of a “trade secret” within the Proposal.
Administrative Proposal
Technical Proposal
in Section 1.4 (Procurement Schedule). Additional information on ODOT LiquidFiles can be found at:
https://fileshare.dot.state.oh.us/img/External-Invited-User-Guide-ODOT-LiquidFiles.pdf.
Contact the Department (Eric Kahlig, Ph. 614-387-2406) to establish a LiquidFiles account and to
submit test submissions for verification.
The Department’s Office of Contracts will provide Offerors with RFP Documents and any required
Addenda through the Department’s website. Addenda will not be provided by hard copy but will be
available on the Office of Contracts website at: http://contracts.dot.state.oh.us.
Any interested parties and Offerors will be notified of all addenda via email by requesting to be
considered “Plan Holders”. To be considered a “Plan Holder”, submit the necessary information at the
following website:
https://www.dot.state.oh.us/Divisions/ContractAdmin/Contracts/Pages/planholders.aspx.
All proposals, plans, Project Bids (EBSX) files and addenda are also available on the Office of
Contracts website (Project Number 233000): http://contracts.dot.state.oh.us/home.do.
Addenda and/or amendments to the RFP must be acknowledged in the Bid Acknowledgement section
of the Project Bids (EBSX) file in order for any Offeror’s Proposal to be considered for award of the
PDBC. The section contains the certification of receipt of all proposals, addenda, amendments, plans,
standard specifications and supplemental specifications. Supplemental Questionnaire information
regarding the Offeror’s outstanding ODOT and non-ODOT work have also been included in this Section
6.6.2. Bid Express will not accept Proposals that do not have amendments incorporated. Failure to
incorporate changed quantities or items in your Proposal (EBSX) submissions will result in the rejection
of your Proposal.
The Department will ensure that this electronic bid depository is available for a two-hour period prior to
the deadline for submission of Proposals. In the case of disruption of national communications or loss
of services by http://www.bidx.com during this two-hour period, the Department will delay the deadline
for bid submissions to ensure the ability of potential Offerors to submit Proposals. If this occurs,
instructions will be communicated to potential Offerors.
Submissions will NOT be accepted after the time specified except in extreme and unusual
circumstances recognized by the Department.
The Administrative Proposal shall include a completed chart on Form B-1 (Identification of Offeror and
Principal Participants), including the names, contact information, role in the organization, licensing
information, and description of Work (if applicable) for Offeror and Principal Participants.
The Administrative Proposal shall include a completed Form B-2 (Information About Offeror
Organization) providing information about the Offeror organization and its team as specified therein.
The Administrative Proposal shall include a completed Form B-3 (Information About Major Participants)
providing information regarding each Major Participant (excluding Principal Participants).
The Administrative Proposal shall include copies of organizational documentation described in the
section entitled “Additional Information to Be Provided with Proposal Letter” of Form A (Proposal Letter)
for Offeror, Contractor and Principal Participants, as well as other documentation required by Form B-2
(Information About Offeror Organization). If any modification to the organizational documents for such
entity is contemplated prior to award or if Offeror intends to form an affiliated entity to be the Contractor,
Offeror shall provide a brief description of the proposed legal structure and draft copies of the
underlying organizational documents (described in the section entitled “Additional Information To Be
Provided With Proposal Letter” of Form A (Proposal Letter) for such proposed entity.
6.7.7 DBE Goal Attainment or Good Faith Efforts Certification (Form G and
Phase 1 DBE Performance Plan)
The Administrative Proposal shall include Form G (DBE Goal Attainment or Good Faith Efforts
Certification) confirming that Offeror will meet or exceed the DBE participation goal or will exercise
good faith efforts to substantiate its attempts to meet the goal. The Administrative Proposal shall also
include the Phase 1 DBE Performance Plan meeting the requirements in Exhibit L (Disadvantaged
Business Enterprise (DBE) Performance Plan and Good Fail Efforts) of the PDBC except the DBE
Performance Plan shall include participation percentages instead of dollar amount of the participation of
each DBE firm used to meet the DBE goal.
Each organization chart shall show the “chain of command” of the required key personnel roles
proposed for the Offeror’s organization regarding the Project. Include any other roles critical to the
Offeror’s approach. At a minimum, the organization charts shall show all Key Personnel and how the
Contractor is structured to deliver the Work.
Font requirements on the organization charts will not be enforced, but Offerors shall ensure it is legible
and clear.
6.8.1.1.2 Narrative
The Offeror shall include a narrative to describe the interactions between positions, functions of shown
intended roles, and other planned team integration techniques intended.
6.8.1.2 Key Personnel
This Section 6.8.1.2 shall include resumes of Key Personnel as described in Table 4 (Key Personnel).
Resumes shall be limited to no more than one page per individual. Key Personnel roles may only be
performed by one person. One individual may not fill the role of more than one position. Resumes for
individuals shall be on separate and distinct pages.
Resumes should demonstrate the abilities of all identified Key Personnel through a description of
qualifications, experiences, and performance of similar tasks on previous similar recent relevant
projects. These qualifications and experience should provide confidence to the Department that the
Project will be effectively managed through personal competence and accountability.
Resumes for all Key Personnel shall provide the following information:
A. The individual’s position and authority within the Offeror’s team.
B. Previous projects, similar in nature to the proposed project or other significant efforts for
which the individual has performed a similar function.
C. Identify estimated percentage of their weekly time that the individual will be dedicated to the
Project during the Preconstruction Phase and the Construction Phase.
D. Relevant experience, professional registrations, education, and other components of
qualifications applicable to this Project.
E. Any unique qualifications.
F. A statement indicating that the individual is currently employed by a member of the Offeror’s
team at the time of the Proposal Submittal.
Table 4: Key Personnel
Describe any notable expertise or other special capabilities of Component Firms or personnel that are
critical to your project approach. Firms shown on organization charts and/or represented in the
technical experience attachments shall be specifically addressed as to their role on the Offeror’s team.
It is the Offeror's responsibility to ensure contact information is up to date. Information which cannot be
verified shall be scored accordingly.
A. The letter includes a statement that the Offeror is capable of obtaining a performance bond
and payment bond for a minimum amount of $3.1B each, and may not state that the Offeror
has “unlimited” bonding/security capability;
B. Such surety company is listed in the current United States Secretary of the Treasury, Fiscal
Service, Circular 570, Companies Holding Certificates of Authority as Acceptable Sureties on
Federal Bonds and as Acceptable Reinsuring Companies;
C. Such surety company is rated in the top two categories by two nationally recognized rating
agencies or has at least an A minus (A-) or better and Financial Size Category of Class VIII or
better rating by A.M. Best and Company, and evidence of the surety company’s rating must
be attached to the letter; and
D. The letter must include a statement that the surety company has read the RFP and has
evaluated the backlog and work-in-progress of the Offeror and relevant Component Firms in
determining its bonding capacity.
Markup will be applied in accordance with Exhibit G (Pricing Process) of the PDBC.
Department does not intend to award the PDBC to the Offeror; or (d) such Offeror is not the apparent
best value or next highest ranking Offeror.
If the next best Offeror is notified during the 120-day period that it is selected for negotiations, such
Offeror shall be automatically deemed to have extended the validity of its Proposal for the period until
180 days after the Proposal Due Date. Any Offeror may elect to extend the validity of its Proposal
beyond the time periods set forth above.
Proposals received after the time due on the Proposal Due Date may be rejected without consideration
or evaluation. It is an Offeror’s sole responsibility to see that its Proposal is received as required by this
ITO.
7. EVALUATION PROCESS
7.1 Overview
The Department’s goal is to create a fair and uniform basis for the evaluation of the Proposals in
compliance with all applicable legal requirements governing this Procurement Process. Technical
Proposals will be evaluated by the Proposal Advisory Group. The Proposal Advisory Group consists of
a Proposal Evaluation Team and an Executive Management Team. The Proposal Advisory Group may
be assisted by any number of subgroups and/or subject matter experts within the Department, other
involved agencies, and/or entities contracted by the Department.
Proposals will first be reviewed by a Proposal Evaluation Team for conformance to this ITO regarding
organization and format, the responsiveness of the Offeror to the requirements set forth in this ITO, and
completeness of the Proposal. If responsive, Proposals will then be reviewed for compliance with the
pass/fail criteria identified herein, as more fully set forth in Section 7.2 (Responsiveness and Pass/Fail
Evaluation).
Responsive, “passing” Proposals will be further evaluated based on the Offeror’s ability to meet and
exceed the requirements and objectives established in the RFP in a beneficial way that provides a
consistently outstanding level of quality. The extent to which the Offeror meets or exceeds the
evaluation criteria in Section 7.3 (Evaluation of Technical Proposals) and Section 7.6 (Evaluation of
Financial Proposal) will be determined by the Proposal Evaluation Team in its sole discretion and will
be reflected in the rating of each Proposal.
The Proposal Evaluation Team will present their findings and recommended scoring information to the
Executive Management Team for consideration. The Executive Management Team will examine the
Proposal Evaluation Team’s findings and ratings. The Proposal Evaluation Team will establish Proposal
scores with concurrence from the Executive Management Team based on the scoring guidelines within
the ITO/RFP.
Thereafter, qualitative evaluation of Offerors’ respective interview performance will result in an interview
score for each Offeror. An overall Proposal score inclusive of the interview score will result as further
described in Section 7.7 (Overall Proposal Score).
In each step, the Department may issue request for clarification to ensure Proposals are fully
evaluated, and Offerors are given the opportunity to afford the Department clarifying information to aid
in the evaluation, as more fully set forth in Section 7.8 (Requests for Proposal Clarifications/Revisions).
2. Been convicted or included as the defendant in a criminal or civil judgment involving fraud,
anti-trust violations, theft, official misconduct, or other offenses indicating a lack of business
integrity or business honesty;
3. Been indicted or otherwise criminally or civilly charged by a Governmental Authority with
fraud, anti-trust violations, theft, official misconduct, or other offenses indicating a lack of
business integrity or business honesty; or
4. Participated as a prime contractor or equity partner in (i) a contract that was terminated for
cause or default by the State of Ohio, State of Kentucky, or the federal government or (ii)
contracts that were terminated for cause or default by two or more other Governmental
Authorities.
D. All Major Participants responsible for design and construction services on the Project are
prequalified in accordance with Section 5.2 (ODOT and KYTC Prequalification) and Form K
(Prequalification) prior to the Anticipated Award Date.
The evaluation criteria for each category are described below. Each of the evaluation criteria will be
evaluated and scored as noted. The Department will add the points awarded for each evaluation factor
to determine the Technical Proposal score.
The information provided in the Technical Proposal regarding the Offeror’s Key Personnel, including
resumes, will be used as deemed appropriate by the Department to assist in the evaluation of the Key
Personnel qualifications and experience. At its discretion, the Department may elect to use reference
information and disclosures, to make inquiries about or otherwise further examine the Offeror’s
technical qualifications and capability and may take into account such inquiries and examinations in
assessing the criteria above.
Experience on completed projects will be given more weight than projects in progress.
The information provided in the Technical Proposal regarding the Major Participants’ project experience
will be used as deemed appropriate by the Department for the evaluation of such firms’ technical
experience and capability. At its discretion, the Department may elect to use reference information and
disclosures, to make inquiries about or otherwise further examine the Offeror’s technical experience
and capability and may take into account such inquiries and examinations in assessing the criteria
above.
The Department will add the points awarded for each evaluation factor to determine the Project
Understanding and Approach score.
Each Offeror may bring to its interview any material that it believes may assist the Department in
evaluating the Proposal. Each team will be required to attend the interview with all Key Personnel in
attendance.
The Offeror may bring other individuals so long as the total number of attendees does not exceed
twelve.
The Offeror may submit an abstract for each innovative and feasible concept (up to five concepts)
intended to be presented two Working Days prior to the interview. Each abstract shall be one (1) 11-by-
17 inches. The Offeror shall submit to the Department using LiquidFiles. See Section 6.6.1 (Electronic
Submittal of Proposal).
The presentation and question and answer (Q&A) period will last approximately 120 minutes and will be
qualitatively evaluated and scored by the Department.
The following definitions will be used by the Proposal Advisory Group when evaluating Technical
Proposals and Interviews:
Strengths — represents a benefit to the Project and is expected to increase the Offeror’s ability to
advance the Project Goals and exceed requirements.
• Significant Strength has a considerable positive influence on the Offeror’s ability to advance the
Project Goals or exceed requirements.
• Strength has a slight positive influence on the Offeror’s ability to advance the Project Goals and
exceed requirements.
Weaknesses — represents a negative influence on the Offeror’s ability to advance the Project Goals
and values, meet requirements or provide efficient or effective performance.
• Weakness has a considerable negative influence on the Offeror’s ability to advance the Project Goals,
meet requirements or provide efficient or effective performance.
• Minor weakness has a slight negative influence on the Offeror’s ability to advance the Project Goals,
meet requirements or provide efficient or effective performance.
Within each scoring range, points will be based on a balance of the relative significance of the
strengths, weaknesses, and clarity in demonstrating the Offeror’s ability in advancing the Project Goals.
The Department may, at any time after receipt of Proposals and prior to execution of the Contract,
determine that it is appropriate to request changes to the Proposals (“Proposal Revisions”). Before
requesting any such Proposal Revisions, the Department will engage in separate discussions (either in
writing or in person through Pre-Proposal One-on-One Meetings) with each Offeror and in accordance
with the procedures for proposal revisions described in 23 CFR Part 636.501 et seq. The request for
Proposal Revisions will identify any revisions to the RFP and will specify terms and conditions
applicable to the Proposal Revisions, including identifying a time and date for delivery. Any such
Proposal Revisions will be required to be delivered to the Department by email to the Department’s
Authorized Representative unless otherwise directed by the Department.
Upon receipt of Proposal Revisions, the Department will re-evaluate the Proposals as revised, and will
revise ratings as appropriate following the process described above.
If a PDBC satisfactory to the Department cannot be negotiated with the best value Offeror, the
Department will, formally and in writing, end negotiations with that Offeror and take alternative action.
Such action may, at the Department’s discretion, include:
A. Requiring the next best value Offeror to enter into the PDBC in the form included in the RFP,
without variation and include information that the form of the PDBC indicates is required from
the Proposal, and subject to negotiation of any exceptions that the next best value Offeror
expressly identified in its Administrative Proposal;
B. Rejection of all Proposals;
C. Issuance of a request for Proposal Revisions to Offerors; or
D. Proceeding to the next best value Offeror to attempt to negotiate a PDBC with that Offeror in
accordance with this Section 8.1.
If option 8.1 D is selected, the Offeror that submitted the next best value Proposal will be considered
the best value Offeror for purposes of this Section 8.1.
In the event the Department elects to commence negotiations with an Offeror, such Offeror will be
deemed to have failed to engage in good faith negotiations with the Department; if Offeror (x) fails to
attend and actively participate in reasonably scheduled negotiation meetings with the Department or (y)
insists upon terms or conditions for any documents to be negotiated or provided by the Offeror
hereunder that are inconsistent with form of PDBC.
As a condition to execution of the Contract, the Offeror shall deliver drafts of the deliverables identified
in Section 8.3 (Execution and Delivery of Contract) for pre-approval by the Department.
8.4 Debriefings
All Offerors submitting Proposals will be notified in writing of the results of the evaluation process.
Offerors not selected for award may request a debriefing. Debriefings will be provided at the
Department’s earliest convenience after execution of the Contract. The debriefing will be conducted by
a procurement official familiar with the rationale for the selection decision and PDBC award as
determined by the Department. Consistent with ORC 9.28(B), no evaluation information will be shared
until after PDBC Execution.
Debriefings shall:
A. Be limited to discussion of the unsuccessful Offeror’s Proposal and may not include specific
discussion of a competing Proposal;
B. Be factual and consistent with the evaluation of the unsuccessful Offeror’s Proposal;
C. Provide information on areas in which the unsuccessful Offeror’s Proposal had weaknesses
or deficiencies; and
D. May not include discussion or dissemination of the thoughts, notes, or rankings of individual
members of any evaluation committee, but may include a summary of the rationale for the
selection decision and PDBC award.
9. PROTESTS
This Section 9 sets forth the exclusive protest remedies available with respect to the RFP (a “Protest”).
By the submission of a Proposal, the Offeror expressly recognizes the limitation on its rights to file a
Protest to only those rights and provisions contained herein. The Offeror expressly waives all other
rights, remedies, and agrees that this Section 9 sets forth all rights and remedies of the Offeror
regarding Protests. This provision included in the RFP are provided in consideration of such waiver and
agreement by the Offeror. If an Offeror disputes or does not follow the exclusive protest remedies set
forth in the RFP, the Offeror must indemnify, defend, and hold harmless the Department, its directors,
officers, officials, employees, agents, representatives, and consultants from and against all liabilities,
expenses, costs (including attorneys’ fees and costs), fees, and damages incurred or suffered as a
result of such Offeror action. The submission of a Proposal by an Offeror is deemed to include the
Offeror’s irrevocable and unconditional agreement with respect to such indemnification obligation.
Any Protest not received in writing by the Protest Official within seven days of Offeror's knowledge, or
when the Offeror should have gained the knowledge of the action on which the protest is based will be
considered null and void and will not be considered for investigation or resolution. In addition, any
Protest may be filed only after the respective Offeror has first discussed the nature and basis of the
Protest with the Department’s Authorized Representative in an effort to resolve the matter through
discussion.
The Protest Official may, in his discretion, discuss the written Protest with the respective Offeror prior to
issuance of the Protest Official’s written decision. The Offeror shall possess, and maintain throughout
the Protest process, the burden of proof regarding the Protest by clear and convincing evidence. No
hearing will be assembled on the Protest and the Protest Official will resolve the Protest in a written
decision issued to the protesting Offeror. The Offeror may appeal the decision of the Protest Official by
filing a written appeal as described in Section 9.4 (Rights of Appeal).
It is the Offeror’s sole responsibility to deliver the Protest to the Protest Official at the location noted and
for obtaining a written receipt appropriate to the means of delivery at the time of delivery. The
Department bears no liability, and accepts no responsibility, for an Offeror not meeting the appropriate
deadline(s) for any such Protest or appeal.
Any Protest information and documentation provided under oath could result in a penalty of perjury,
should the information be proven to be inaccurate.
The Offeror agrees that if an appeal of the Protest Official’s decision is not submitted within seven days
of the Protest Official’s written decision, the decision of the Protest Official will be deemed to be final
action and non-appealable. Any appeal within seven days will be handled as described in Section 9.4
(Rights of Appeal).
The Protest Official will not be obligated to postpone the public announcement of award or execution of
the PDBC in order to allow the respective Offeror an opportunity to file or correct a Protest or appeal,
unless otherwise required by law.
The Chief Engineer will provide a final decision on the Protest, either concurring with the decision of the
Protest Official or amending the decision and will notify the respective Offeror in writing in a prompt
manner of its decision.
The Department’s decision after review of the appeal by the Chief Engineer will constitute final action
by the Department. If the Offeror appeals the final action by the Department, to a court of competent
jurisdiction, the Department may, in its sole discretion, proceed with the Procurement Process, unless
otherwise directed or ordered by a judicial authority.
The issuance of the RFP is not a commitment by the Department to enter into the Contract, nor does it
obligate the Department to pay for any costs incurred in preparation and submission of the Proposal or
in anticipation of the Contract. By submitting a Proposal, an Offeror disclaims any right to seek
compensation for such costs from the Department. By submission of a Proposal in response to the
RFP, the Offeror thereby specifically acknowledges acceptance of the above rights and disclaimers.
EXHIBIT A: FORMS
The undersigned (“Offeror”) submits this proposal (this “Proposal”) in response to that certain
Request for Proposals (RFP) issued by the Ohio Department of Transportation (the Department),
dated February 17, 2023, as amended, to develop, design, and potentially construct the Brent
Spence Bridge Corridor Project (the Project), as more specifically described in the RFP Documents.
Initially capitalized terms not otherwise defined herein shall have the meanings set forth in the RFP
and the RFP Documents.
In consideration for the Department supplying us, at our request, with the RFP Documents and
agreeing to examine and consider this Proposal, the undersigned undertakes [jointly and severally] [if
Offeror is a joint venture or association other than a corporation, limited liability company or a
partnership, leave in words “jointly and severally” and delete the brackets; otherwise delete the entire
phrase]:
(1) To keep this Proposal open for acceptance initially for 120 days after the Proposal
Due Date, and if the undersigned is notified within such 120-day period that it is the next best value
Offeror, for an additional 60 days, without unilaterally varying or amending its terms and without any
member or partner withdrawing or any other change being made in the composition of the
partnership/joint venture/limited liability company/consortium on whose behalf this Proposal is
submitted, without first obtaining the prior written consent of the Department, in the Department’s
sole discretion; and
(2) If this Proposal is accepted, to provide security (including bonds and insurance) for the
due performance of the Contract, as stipulated in the RFP.
If selected by the Department as the best value Offeror, Offeror agrees to do the following or, if not the
Contractor, to cause the Contractor to do the following: (a) if requested by the Department in its sole
discretion, enter into good faith negotiations with the Department regarding the terms of the PDBC, in
accordance with the requirements of the RFP; (b) enter into the PDBC without varying or amending its
terms; (c) satisfy all other conditions to award of the PDBC; and (d) perform its obligations as set forth
in the Instructions to Offerors (ITO), as amended, and the form of PDBC, including compliance with all
commitments contained in this Proposal.
The following individual is designated as the Offeror Point of Contact in accordance with Section 4.2
(Authorized Representatives and Offeror Registration):
Enclosed, and by this reference incorporated herein and made a part of this Proposal, are the following:
• Administrative Proposal;
• Technical Proposal; and
• Financial Proposal.
Offeror acknowledges receipt of the following Addenda and sets of questions and responses:
[List all Addenda by number and date issued.
Responses issued [list dates on which the Department responded to Offerors’ questions regarding
the RFP Documents or this procurement.]
Offeror certifies that its Proposal is submitted without reservation, qualification, assumptions, or
conditions. Offeror certifies that it has carefully examined and is fully familiar with all of the provisions of
all of the RFP Documents, the Addenda (if any), and Department responses to questions (as and when
posed), and is satisfied that the RFP Documents provide sufficient detail regarding the obligations to be
performed by the Contractor and do not contain internal inconsistencies; that it has carefully checked all
the words, figures and statements in this Proposal; that it has conducted such other field investigations
and additional design development which are prudent and reasonable in preparing this Proposal; and
that it has notified the Department of any deficiencies in or omissions from any RFP Documents or
other documents provided by the Department and of any unusual site conditions observed prior to the
date hereof.
Offeror acknowledges the requirements of Section 7.3 C (Administrative Proposals) and hereby
certifies that all Principal and Major Participants and their respective employees meet such
requirements as of the date of this Proposal.
Offeror acknowledges the requirements of Section 3.4 (OJT Requirements) and hereby certifies that it
will meet such requirements.
Offeror represents that all statements made in the Proposal are true, correct, and accurate as of the
date hereof, except as otherwise specified in the enclosed Proposal and Proposal forms.
Offeror understands that the Department is not bound to accept any Proposal that the Department may
receive.
Offeror further understands that all costs and expenses incurred by it in preparing this Proposal and
participating in the RFP process will be borne solely by the Offeror.
Offeror consents to the Department’s disclosure of its Proposal pursuant the applicable provisions of
law to any Persons in the Department’s sole discretion after award of the PDBC by the Department.
Offeror acknowledges and agrees to the disclosure terms described in ITO Section 4.6 (Improper
Conduct and Non-Collusion). Offeror expressly waives any right to contest such disclosures as may
exist under applicable law.
Offeror agrees that the Department will not be responsible for any errors, omissions, inaccuracies, or
incomplete statements in this Proposal.
This Proposal shall be governed by and construed in all respects according to the laws of the State of
Ohio.
[Insert appropriate signature block from following pages; note: signatures should be in blue ink.]
1. Sample signature block for corporation or limited liability company:
By:
Print Name:
Title:
By:
Print Name:
Title:
By:
Print Name:
Attorney in Fact
authorized officer of such joint venture member. If the Offeror is a joint venture or a partnership, the
Proposal must be executed by all joint venture members or all general partners, as applicable.
C. The Contractor partnership agreement, limited liability company operating agreement, and joint
venture agreement, as applicable, must include an express provision satisfactory to the
Department, in its sole discretion, stating that, in the event of a dispute between or among joint
venture members, partners or members, as applicable, no joint venture member, partner or
member, as applicable, shall be entitled to stop, hinder, or delay work on the Project. Offerors
should submit the applicable agreement to the Department and identify on a cover page where in
the agreement the provision can be found. If the Contractor is not yet formed, provide draft
organizational documents and indicate where the provision is found.
Name of Entity and Contact Information Ohio and Kentucky Contractor License Description of Work/Services To Be
Role in Organization
(address, representative, phone, e-mail) and License Limit (if applicable) Performed By Entity (if applicable)
By:
Name:
Title:
Telephone Email
4.0 How many years has the Offeror and each Principal Participant been in its current line
of business, and how many years has each entity been in business under its present name?
5.0 Under what other or former names have the Offeror and Principal Participants operated?
Offeror:
6.0 List all Ohio and Kentucky professional licenses held by the Offeror and any Principal
Participants. Attach copies of all Ohio and Kentucky licenses. Attach a separate sheet if
necessary.
The Proposal shall include the following information regarding the Surety(ies)
committing to provide the bonds in accordance with the Design-Build Agreement:
(a) Name(s), address(es) and phone numbers of the Surety(ies) that will provide the
above- referenced bonds (must be rated in the top two categories by two nationally
recognized rating agencies or at least A minus (A-) or better and Class VIII or better
by A.M. Best Company, Inc.), and the name(s), address(es) and phone number(s)
of the designated agent(s).
(b) Whether or not each listed Surety has defaulted on any obligation within the
past 10 years, and, if so, a description of the circumstances and the outcome of
such default.
STATE OF
COUNTY OF
Each of the undersigned, being first duly sworn, deposes and says that
is the of
and is the
of , which entity(ies) is/are the
of , the entity making the foregoing Proposal, and that the
answers to the foregoing questions and all other statement therein are true and correct.
(Signature) (Signature)
(Title) (Title)
[Seal]
My commission expires:
[This form will be used to provide information about any Major Participants]
Offeror Name
The undersigned Offeror hereby certifies that it has not entered into any substantive negotiations with
Major Participants resulting in an agreement to enter into any Subcontracts with respect to the Project,
except for those listed above. The Offeror agrees that it will follow applicable Progressive Design-Build
requirements with respect to Subcontractors. Offeror further declares that it has carefully examined the
RFP Documents, including the DBE requirements for the Project, acknowledges the requirements
thereof, and agrees that Offeror’s efforts to obtain participation by Subcontractors can reasonably be
expected to accomplish DBE participation goals for the Project once identified in accordance with the
PDBC.
I declare under penalty of perjury under the laws of the State of Ohio that the foregoing declaration is
true and correct.
Executed: , 202__.
(Signature)
(Name printed)
(Title)
(Offeror)
STATE OF
COUNTY OF
Each of the undersigned, being first duly sworn, deposes and says that
is the of
and is the
of , which entity(ies) is/are the
of , the entity making the foregoing questionnaire, and that the
answers to the foregoing questions and all other statement therein are true and correct.
(Signature) (Signature)
(Title) (Title)
[Seal]
My commission expires:
OFFEROR NAME:
Yes No
Yes No
c) Had filed against it, him or her, any criminal complaint, indictment, or information
alleging fraud, bribery, collusion, conspiracy, or any action in violation of state or
federal antitrust law in connection with the bidding or proposing upon, award of or
performance of any public works contract with any public entity?
Yes No
d) Had filed against it, him or her, any civil complaint (including but not limited to a
cross- complaint) or other claim arising out of a public works contract, alleging fraud,
bribery, collusion, conspiracy, or any act in violation of state or federal antitrust law
in connection with the bidding or proposing upon, award of or performance of any
public works contract with any public entity?
Yes No
Yes No
Yes No
Yes No
h) Been assessed liquidated or other damages for failure to complete any contract on
Yes No
Explain the circumstances underlying any “yes” answers for the aforementioned questions
on separate sheets attached hereto.
2. Verification / Declaration
I declare under penalty of perjury under the laws of the State of Ohio that the foregoing
declaration is true, correct and accurate to the best of my knowledge following due inquiry.
Executed , 2023.
(Signature)
(Name printed)
(Title)
(Name of Organization)
STATE OF
COUNTY OF
Each of the undersigned, being first duly sworn, deposes and says that:
A. is the of and
is the of , which entity(ies) are the
of , the entity making the foregoing Proposal.
B. The Proposal is not made in the interest of, or on behalf of, any undisclosed person,
partnership, company, association, organization, joint venture, limited liability company or
corporation; the Proposal is genuine and not collusive or a sham; the Offeror has not
directly or indirectly induced or solicited any other Offeror to put in a false or sham
Proposal, and has not directly or indirectly colluded, conspired, connived or agreed with any
Offeror or anyone else to put in a sham Proposal or that anyone shall refrain from
proposing; the Offeror has not in any manner, directly or indirectly, sought by agreement,
communication or conference with anyone to fix the prices of the Offeror or any other
Offeror, or to fix any overhead, profit or cost element included in the Proposal, or of that of
any other Offeror, or to secure any advantage against the Department or anyone interested
in the proposed agreement; all statements contained in the Proposal are true; and further
the Offeror has not, directly or indirectly, submitted its prices or any breakdown thereof, or
the contents thereof, or divulged information or data relative thereto, or paid, and will not
pay, any fee to any corporation, partnership, company, association, joint venture, limited
liability company, organization, Proposal depository or any member, partner, joint venture
member or agent thereof to effectuate a collusive or sham Proposal.
C. The Offeror will not, directly or indirectly, divulge information or data regarding the price or
other terms of its Proposal to any other Offeror, or seek to obtain information or data
regarding the price or other terms of any other Proposal, until after award of the PDBC or
rejection of all Proposals and cancellation of the RFP.
(Signature) (Signature)
(Name (Name
Printed) Printed)
(Title) (Title)
[Seal]
My commission expires:
[Duplicate or modify this form as necessary so that it accurately describes the entity making the
Proposal and so that it is signed on behalf of the entity(ies) making the Proposal.]
• Organizational conflict of interest means that because of other activities or relationships with
other persons, a person is unable or potentially unable to render impartial assistance or advice
to the owner, or the person’s objectivity in performing the contract work is or might be otherwise
impaired, or a person has an unfair competitive advantage.
Offerors are advised that certain firms will not be allowed to participate on any Offeror’s team for the
Project because of their work with the Department in connection with the Project procurement and
document preparation and the Design-Build Agreement.
2. Explanation
In the space provided below, and on supplemental sheets as necessary, identify steps that
have been or will be taken to avoid, neutralize, or mitigate any organizational conflicts of
interest described herein.
3. Certification
The undersigned hereby certifies that, to the best of his or her knowledge and belief, no
interest exists that is required to be disclosed in this Conflict of Interest Disclosure Statement,
other than as disclosed above.
Signature
Name
Title
Company Name
, 2023
Date
Name of Offeror:
Name of Firm:
Complete one copy of form to cover all Major Participants as identified on Form B-3
(Information About Major Participants).1
1. None of the Offeror and the Major Participants1 are currently debarred, suspended,
disqualified, or is currently removed from bidding or performing work, voluntarily or
involuntarily, for the State of Ohio or the State of Kentucky, the federal government or
more than three state governments.
2. None of the Offeror and the Major Participants 1 have been debarred suspended,
disqualified, or removed from bidding or performing work, voluntarily or involuntarily, the
State of Ohio and Kentucky, the federal government or more than three state
governments during the past three years.2
3. None of the Offeror and the Major Participants 1 is subject to any proposed or pending
debarment, suspension, or similar actions.
Offeror Certification:
I hereby certify that, to the best of my knowledge, the three above statements are valid, true,
and represent a complete and accurate understanding of the condition of the firms represented
and identified on Form B-3 (Information About Major Participants). as a Major Participant1. It is
understood and agreed upon that any false acknowledgement, misrepresentation, or
inaccuracy may be cause for disqualification of the Offeror from the Procurement Process
whether discovered during the Procurement Process or after the Design-Build Team selection
has been completed.
(Printed Name)
Date:
(Signature)
(Title)
Failure to submit this Form G and the Phase 1 DBE Performance Plan may result in the Offeror’s
Proposal being considered non-responsive.
`
[Name]
`
[Title]
☐ It has developed and has on file at each establishment affirmative action programs pursuant to
41 CFR Part 60-2 (Affirmative Action Programs).
☐ It is not subject to the requirements to develop an affirmative action program under 41 CFR
Part 60-2 (Affirmative Action Programs).
☐ It has not participated in a previous contract or subcontract subject to the equal opportunity
clause described in Executive Orders 10925, 11114 or 11246.
☐ It has participated in a previous contract or subcontract subject to the equal opportunity clause
described in Executive Orders 10925, 11114 or 11246 and, where required, it has filed with the
Joint Reporting Committee, the Director of the Office of Federal Contract Compliance, a
Federal Government contracting or administering agency, or the former President’s Committee
on Equal Employment Opportunity, all reports due under the applicable filing requirements.
Signature:
Title:
Date:
Note: The above certification is required by the Equal Employment Opportunity Regulations of the
Secretary of Labor (41 CFR 60-1.7(b)(1)) and must be submitted by Offerors only in connection with
contracts which are subject to the equal opportunity clause. Contracts that are exempt from the
equal opportunity clause are set forth in 41 CFR 60-1.5. (Generally, only contracts of $10,000 or
under are exempt.) Currently, Standard Form 100 (EEO-1) is the only report required by Executive
Orders or their implementing regulations.
Offerors, Major Participants, and proposed subcontractors who have participated in a previous
contract subject to the Executive Orders and have not filed the required reports should note that 41
CFR 60- 1.7(b)(1) prevents the award of contracts and subcontracts unless such contractor submits
a report covering the delinquent period or such other period specified by the Federal Highway
Administration or by the Director, Office of Federal Contract Compliance, U.S. Department of Labor.
The undersigned certifies on behalf of itself and all proposed subcontractors (at all tiers) that only
domestic materials will be used in the Project.
A. Offeror shall comply with the applicable provisions of the Infrastructure Investment and Jobs
Act, Pub. L. No. 117-58, which includes the Build America, Buy America Act Pub. L. 117-58, §§
70901-52, which permits FHWA participation in the Design-Build Agreement only if domestic
materials will be used on the Project, and which also applies to utility work on the Project.
All steel or iron products incorporated permanently into the Work must be made of steel or iron
produced in the United States and all subsequent manufacturing must be performed in the
United States. Manufacturing is any process that modifies the chemical content; physical shape
or size; or final finish of a product. Manufacturing begins with the initial melting and mixing and
continues through the bending and coating stages. If a domestic product is taken out of the
United States for any process, it becomes a foreign source material.
All manufactured products used in the project are not required to be produced in the United
States.
All construction materials are manufactured in the United States—this means that all
manufacturing processes for the construction material occurred in the United States.
“Construction materials” includes an article, material, or supply—other than an item of primarily
iron or steel; a manufactured product; cement and cementitious materials; aggregates such as
stone, sand, or gravel; or aggregate binding agents or additives—that is or consists primarily of:
• Non-ferrous metals;
• Plastic and polymer-based products (including polyvinylchloride, composite building
materials, and polymers used in fiber optic cables);
• Glass (including optic glass);
• Lumber; or
• Drywall.
To provide clarity to item, product, and material manufacturers and processers, we note that
items that consist of two or more of the listed materials that have been combined together
through a manufacturing process, and items that include at least one of the listed materials
combined with a material that is not listed through a manufacturing process, should be treated
as manufactured products, rather than as construction materials. For example, a plastic framed
sliding window should be treated as a manufactured product while plate glass should be treated
as a construction material.
This requirement does not preclude a minimal use of foreign steel and iron materials, provided
the cost of such materials does not exceed 0.1% of the price under the Progressive Design-
Build Contract.
The Buy America preference only applies to articles, materials, and supplies that are consumed
in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools,
equipment, and supplies, such as temporary scaffolding, brought to the construction site and
removed at or before the completion of the infrastructure project. Nor does a Buy America
preference apply to equipment and furnishings, such as movable chairs, desks, and portable
computer equipment, that are used at or within the finished infrastructure project, but are not an
integral part of the structure or permanently affixed to the infrastructure project.
B. A false certification is a criminal act in violation of 18 U.S.C. 1001. Should this PDBC be
investigated, Offeror has the burden of proof to establish that it is in compliance.
C. At Offeror’s request, the Department may, but is not obligated to, seek a waiver of Buy America
requirements if grounds for the waiver exist. However, Offeror certifies that it will comply with
the applicable Buy America requirements if a waiver of those requirements is not available or
not pursued by the Department.
OFFEROR
SIGNATURE
TITLE
DATE
1. No Federal appropriated funds have been paid or will be paid, by or on behalf of the
undersigned, to any person for influencing or attempting to influence an officer or employee
of any Federal agency, a member of Congress, an officer or employee of Congress, or an
employee of a member of Congress in connection with the awarding of any Federal contract,
the making of any Federal grant, the making of any Federal loan, the entering into of any
cooperative agreement, and the extension, continuation, renewal, amendment, or
modification of any Federal contract, grant, loan, or cooperative agreement;
2. If any funds other than Federal appropriated funds have been paid or will be paid to any
person for influencing or attempting to influence an officer or employee of any Federal agency,
a member of Congress, an officer or employee of Congress, or an employee of a member of
Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the
undersigned shall complete and submit Standard Form-LLL, “Disclosure Form to Report
Lobbying,” in accordance with its instructions.
This certification is a material representation of fact upon which reliance was placed when this
transaction was made or entered into. Submission of this certification is a prerequisite for making or
entering into this transaction imposed by 31 U.S.C. § 1352. Any person who fails to file the required
certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for
each such failure.
The undersigned shall require that the language of this certification be included in all lower tier
subcontracts which exceed $100,000 and that all such recipients shall certify and disclose accordingly.
By:
Signature
Title
Date
[Duplicate or modify this form as necessary so that it accurately describes the entity making the
Proposal and so that it is signed on behalf of all partners, members, or joint venturers of the Offeror and
all other Major Participants]
FORM K: PREQUALIFICATIONS
2 Building Removal X
6 Incidental Grading X
7 Soil Stabilization X
9 Aggregate Bases X
10 Flexible Paving X
12 Rigid Paving X
14 Concrete Texturing X
15 Sawing X
16 Flexible Replacement X
19 Structure Removal X
20 Level 1 Bridge X
21 Level 2 Bridge X
22 Level 3 Bridge X
23 Reinforcing Steel X
25 Stud Welding X
29 Structure Repairs X
30 Hydrodemolition X
32 Heat Straightening X
33 Tieback Installation X
36 Guardrail / Attenuators X
37 Fence X
38 Misc. Concrete X
39 Maintenance of Traffic X
40 Waterproofing X
42 Signing X
43 Highway Lighting X
45 Pavement Markings X
46 Landscaping X
47 Mowing X
48 Trucking X
49 Herbicidal Spraying X
51 Micro Tunneling X
52 Tunneling X
53 Piling X
F SIGNS X
G LIGHTING X
G1 LIGHTING - AIRPORT
H LANDSCAPING X
I05 FENCING X
I12 SIDEWALK X
I15 CULVERTS X
I22 DREDGING X
I27 DEMOLITION X
I33 UTILITIES X
I46 WATERPROOFING X
I49 TUNNELS
I54 ROOFING
I65 SHORING X
I67 GUNITE/SHOTCRETE X
I68 TRENCHING X
I73 UNDERDRAINS X
I74 SWEEPING
I80 CAISSONS X
I95 WALLCOVERING X
J10 SHOTCRETE X
J23 WELLS
J34 FLOORCOVERING
J36 SEALCOATING X
J42 WELDING X
J44 MECHANICAL
J50 MUDJACKING
J59 FERTILIZATION X
J61 MICROSURFACING
J90 ELECTRICAL X
Safety Study
Environmental – General
Waterway Permits X
Archaeological Investigations
History/Architectural Investigations
Surveying X
Value Engineering
E-Plan Room
Utility Design
Communication
Electrical Level 1
Electrical Level 2
Gas Level 1 X
Gas Level 2 X
Petroleum
Structure Design
Geotechnical Drilling X
Geotechnical Engineering X
Traffic Operations
Traffic Engineering X
Transportation Planning
Traffic Forecasting
Appraisal Review
Landscaping Arboriculture
Prehistoric Archaeology X
Historic Archaeology X
Socio-Economic Analysis
Cultural-Historic Analysis X
Architecture Development
Transit Management T
The following individual is identified as the Offeror’s Procurement Point of Contact (PPC), authorized to
submit this Form L on behalf of the Offeror:
Name:
Title:
Firm:
Telephone:
Email Address:
Mailing Address:
As Offeror’s PPC, I certify that the above information is true, correct, and accurate. By:
Name:
January 3, 2023
TABLE OF CONTENTS
1 CONTRACT DOCUMENTS AND INTERPRETATION .........................................................2
9.1 Introduction.................................................................................................................69
9.2 Labor Laws to be Observed ........................................................................................69
9.3 Non-Discrimination Regulations ..................................................................................69
9.3.1 Compliance with Regulations .................................................................................70
9.3.2 Non-discrimination .................................................................................................70
9.3.3 Solicitations of Subconsultants, including procurement of Materials and Equipment
70
9.3.4 Information and Reports .........................................................................................70
9.3.5 Sanctions for Noncompliance .................................................................................70
9.3.6 Pertinent Non-Discrimination Authorities ................................................................70
9.3.7 49 CFR Part 26.13(b) .............................................................................................72
9.3.8 Incorporation of Provisions .....................................................................................72
10 AUTHORIZED REPRESENTATIVES AND KEY PERSONNEL .........................................73
15 WEATHER....................................................................................................................... 111
B Contract Particulars
C Proposal Commitments
E Technical Requirements
G Pricing Process
I Delay Costs
L Disadvantaged Business Enterprise (DBE) Performance Plan and Good Faith Efforts
R Facilitated Partnering
Z Risk Register
This Progressive Design-Build Contract (hereinafter the “PDBC”) for the Brent Spence Bridge
Corridor Project is entered into as of _____ (the “Effective Date”), by and between the State of
Ohio, Department of Transportation (hereinafter the “Department”), acting through its Director
and _________________ (hereafter the “Contractor” and together with the Department,
hereinafter referred to as the “Parties”).
WITNESSTH:
WHEREAS, pursuant to the ICA, the Department was designated as the Lead Agency (as
defined in the ICA) and charged with procuring a contractor to undertake the Project.
WHEREAS, in furtherance of its duties under the ICA and pursuant to Section 5517.011
of the Ohio Revised Code and related provisions of Ohio law and federal law, the Department
issued a Request for Proposals (RFP) together with Instructions to Offerors (ITO) for the Project
on ____ ____, 2023.
WHEREAS, in response to the RFP, the Department received ___ Proposals on ____
_____, 2023.
WHEREAS, this PDBC and the other Contract Documents collectively constitute a part of
the Contract and are entered into in accordance with the provisions of the RFP.
NOW, THEREFORE, in consideration of the mutual covenants herein set forth to be kept
and performed, it is agreed by the Parties as follows:
Work in Ohio shall conform to ODOT Standards and Specifications, and Kentucky work starting
at the northern approach of the Companion Bridge shall conform with KYTC Standards and
Specifications. More specifically, the forward abutment backwall, substructure unit, and
expansion joint of the Companion Bridge just to the north side of the Ohio River in Cincinnati,
Ohio shall conform to the KYTC Standards and Specifications. The approach slab and all other
work north of the expansion joint shall conform to ODOT Standards and Specifications. Any
ground improvements on the north side of the Ohio River such as paving, curb, sidewalk,
drainage, etc. shall be per ODOT Standards and Specifications.
B. The Technical Requirements (including the Base Design and Conceptual Design as
incorporated into the Technical Requirements and to the extent not superseded by the
applicable Project Scope;
C. With respect to Work in Ohio and the administration of the PDBC, the ODOT
Standards and Specifications;
D. With respect to the Work in Kentucky, the KYTC Standards and Specifications;
E. Proposal Commitments in Exhibit C (Proposal Commitments) and Special Provisions;
F. Supplemental Specifications;
G. Standard Construction Drawings applicable to the corresponding Work; and
The Contractor hereby covenants and agrees to notify the Department in writing of any conflicts,
ambiguities or inconsistencies among the Project Standards upon identification of the same,
after which the Department shall review such conflict and issue a determination, which shall be
determinative and binding upon the Contractor.
1.2 Definitions
Exhibit A (Acronyms and Definitions) contains definitions applicable to the Contract Documents.
A. Change Orders issued subsequent to the then-current Phase Change Order or Early
Work Package Change Order (as applicable);
B. The applicable Phase Change Order or any Early Work Package Change Order (as
applicable);
C. Supplemental Agreements;
D. This PDBC and Exhibits (excluding Exhibit E (Technical Requirements)); and
E. All Submittals prepared during the performance of the corresponding Work that the
Department determines in writing shall be Contract Documents.
1.4 Interpretation and Construction of Contract Documents
In the Contract Documents, where appropriate:
deemed part of the Contract Documents and shall not be binding in interpreting the Contract
Documents unless included in the Contract Documents pursuant to an addendum or
amendment thereto or specifically directed in writing by the Department.
The fact that the Contract Documents omit or misdescribe any detail of the Work that is
otherwise necessary to carry out the intent of the Contract Documents and delivery of the
Project, or that are customarily performed, shall not relieve the Contractor from its obligation to
perform such omitted or misdescribed details as if fully and correctly set forth in the Contract
Documents, which omissions, correction of misdescriptions, or performance of those aspects
customarily performed shall not in itself be the basis for contractual relief, or other claim at law
or in equity.
Wherever the word "including," and variants, shall be deemed to be followed by the words
"without limitation". "Or" means the inclusive connotation of "or" (i.e., meaning one, some, or all
of a number of possibilities). "May," when used in the context of the PDBC shall mean a power
or right exercisable by the Department or Cabinet (or either's designee) means the power to
exercise that right or power in its sole discretion. "May," when used in all other contexts,
indicates permission by the Department or Cabinet for the Contractor, or one of its Affiliates or
Subcontractors, to do (or refrain from doing) an action.
All references inconsistent with any terms of this PDBC, including to measurement and payment
in the Standard Specifications, shall not apply. Measurement and payment shall be deemed as
references to equivalent provisions in this PDBC.
All references to time are to prevailing Eastern Standard time. Reference to a right include any
benefit, remedy, discretion, authority, or power associated with such right.
1.5 Term
Without limiting Section 26.5 (Survival) and post-termination obligations under Section 21
(Termination for Convenience), this Contract shall take effect on the Effective Date and will
remain in effect until:
The Contractor shall comply with and shall cause its Subcontractors of all tiers to comply with all
Federal Requirements. The Contractor shall include the Federal Requirements in all
Subcontracts on the Project, so that such provisions will be binding upon each Subcontractor
working on the Project. The Contractor shall take such action with respect to any Subcontract or
purchase order as the Department may direct as means of enforcing such provisions.
A. Compliance with 23 CFR 636.109: Federal Requirements prohibit private entities from
independently preparing NEPA documents or from having any decision-making
responsibility in the NEPA process. Therefore, the Department shall retain all NEPA
decision-making responsibility and the Contractor acknowledges that it shall be strictly
Following the Contractor’s submission of the draft Sub-Phase 1A Proposal, the Department
shall review the draft Sub-Phase 1A Proposal, and the Department and the Contractor shall
engage in good faith negotiations to finalize the terms and conditions of the Sub-Phase IA
Proposal to be incorporated into the Sub-Phase 1A Change Order. At the Department’s request,
the Contractor shall meet with the Department to review and discuss the draft Sub-Phase 1A
Proposal and adjustments to the Sub-Phase 1A Project Scope. When the Parties have agreed
to the Sub-Phase 1A Proposal, the Department shall prepare the Sub-Phase 1A Change Order
incorporating the Sub-Phase 1A Proposal.
The Contractor’s compensation for the preparation and negotiation of the Sub-Phase 1A
Change Order shall be determined based upon agreed upon hourly rates, multiplied by the
number of hours (or portions thereof) expended by Contractor’s personnel engaged in the
preparation and negotiation of the Sub-Phase 1A Change Order and shall be paid by the
Department in conjunction with the first Estimate submitted by the Contractor after the issuance
of the Sub-Phase 1A NTP; provided however, in the event the Parties do not agree upon the
terms and conditions of the Sub-Phase 1A Proposal or fail to execute the Sub-Phase 1A
Change Order, then the Department may exercise its right to terminate this Contract under
Section 21 (Termination for Convenience).
The Department shall review the Contractor’s Sub-Phase 1B Proposal and the Department and
the Contractor shall engage in good faith negotiations to finalize the Sub-Phase 1B Proposal
prior to the expiration of Sub-Phase 1A. At the Department’s request, the Contractor shall meet
with the Department to review and discuss the draft Sub-Phase 1B Proposal and adjust the
Sub-Phase 1B Scope. When the Parties have agreed to the Sub-Phase 1B Proposal, the
Department shall prepare a Sub-Phase 1B Change Order incorporating the Sub-Phase 1B
Proposal.
During the performance of the Sub-Phase 1B Work, the Contractor may elect to submit an Early
Work Package Proposal or the Department may elect to request an Early Work Package
Proposal from the Contractor. In each case, any Early Work Package Proposal shall include the
performance of a portion of the Phase 2 Work concurrent with the performance of the Phase 1B
Work.
Any Early Work Package Proposal shall be subject to the Department’s approval in its sole and
absolute discretion.
Upon submittal to the Department by the Contractor, an Early Work Package Proposal will
constitute an offer that is binding on the Contractor for the validity period stated in that Early
Work Package Proposal.
Except as otherwise expressly provided herein, each Early Work Package Proposal submitted
to the Department under this Section 2.3.3.1 shall comply with the requirements that are
established during Sub-Phase 1A for the Form of an Early Work Package Proposal.
Each Early Work Package Proposal that is agreed to by the Department in accordance with this
Section 2.3.3.1 shall be deemed a sub-set and a part of the build-up of the Phase 2 Proposal,
and any Phase 2 Change Order agreed and executed shall be deemed to incorporate any Early
Work Package Change Order.
If an Early Work Package Proposal is not accepted by the Department in accordance with this
Section 2.3.3.1, the scope of the Early Work Package shall be included within the Phase 2
Proposal submitted by the Contractor under Section 2.3.3.2 (Phase 2 Proposal).
If the scope of an Early Work Package is removed from the Phase 2 Work, the Department
may, in its sole discretion, proceed with any other action as the Department deems appropriate
for delivery of that Early Work Package, including soliciting from, negotiating with, or awarding a
contract to any other Person for any part of that Early Work Package.
Within 60 Days of the Department’s Notice, the Contractor shall submit its draft Phase 2
Proposal to the Department. Upon submittal to the Department by the Contractor, the Phase 2
Proposal shall constitute an offer that is binding on the Contractor.
The Phase 2 Proposal shall be in the form agreed by the parties during Sub-Phase 1A and shall
include:
A. The Contract Price for the Work, together with all required supporting forms and
information as required by Exhibit G (Pricing Process);
B. Proposed updates to the Baseline Project Schedule to incorporate the Phase 2 Work,
including the Substantial Completion Deadline and the Completion of the Contract
Deadline;
C. The initial cost and resource loaded schedule upon which the Contract Price for the
Phase 2 Proposal is based;
D. Subject to Section 8 (Subcontracting Requirements), an updated list of the Major
Subcontractors proposed to perform the Phase 2 Work in compliance with the
Subcontractor Bidding and Selection Plan;
E. The proposed organization chart for Phase 2 and a description of any additions or
changes to the Key Personnel, in each case in the form and with the supporting
information required under Section 10 (Authorized Representatives and Key
Personnel);
F. A report that summarizes the agreed assumptions upon which the Phase 2 Proposal
is based;
G. The Phase 2 Project Scope developed in accordance with Section 3.3 (Phase 2
Project Scope);
H. The Parties’ respective obligations for obtaining any required Governmental Approvals
or new Governmental Approvals;
I. DBE Forms required in accordance with Section 9 (Labor Requirements);
J. An updated DBE Performance Plan prepared in accordance with Exhibit L (DBE
Performance Plan and Good Faith Efforts) evidencing how the Contractor will achieve
its listed commitments for the Phase 2 Work through the utilization of DBE firms;
K. Completed certifications for the Phase 2 Proposal completed in the form agreed by the
parties during Sub-Phase 1A;
L. The Home Office Overhead Payment (HOOP) for Phase 2 as set forth in Exhibit I
(Delay Costs, Part (f) Home Office Overhead);
M. A list of the Design Documents, including all addenda thereto, used in preparation of
the GMP / Lump Sum, including a list of the clarifications and assumptions made to
supplement the information contained in the Design Documents;
N. ROW acquisition responsibilities and schedule;
O. The studies, plans, and reports generated as part of Sub-Phase 1B, including any site
investigation reports, the Utility Map, ROW Plans, Regulated Materials Report, Project
Management Plan, Quality Management System Plan, Safety Plan, and DBE
Performance Plan;
P. Description of agreed Noncompliance Points consistent with the Noncompliance
Points Table included in Exhibit F (Noncompliance Points System);
Q. Description of the agreed disincentives for Lane Closure Charges consistent with the
Lane Value Tables included in Exhibit S (Lane Value Contract);
R. Any other document, report, or information required under the terms of this Contract to
be submitted with or as part of the Phase 2 Proposal;
S. Such other supporting documentation as may be reasonably requested by the
Department; and
T. The allocation between the Contractor and the Department of the risks set forth in the
Risk Register.
Portions of the Phase 2 Proposal may be attached at the Department’s discretion, as exhibits
and incorporated into the Phase 2 Change Order and if attached will become binding Contractor
commitments under the PDBC, as amended.
If the Phase 2 Proposal submitted by the Contractor is acceptable to the Department, in its sole
discretion, the Department will Notify the Contractor of its acceptance, following which:
election to issue a written notice to not proceed to the Contractor in accordance with Section
2.3.3.3.2 (Failure to Agree to a Phase 2 Change Order), (iii) the expiration of the term of Sub-
Phase 1B as set forth under the Sub-Phase 1B Change Order, or (iv) the Department’s election
to terminate this Contract for convenience in accordance with Section 21(Termination for
Convenience).
A. Not proceed with requiring the Contractor to submit a Phase 2 Proposal, including as
a result of a delay or failure in the satisfaction of the conditions under Section 2.3.3.2
(Phase 2 Proposal); or
B. Reject, at its sole discretion, the Phase 2 Proposal and not proceed to negotiate,
agree or execute a Phase 2 Change Order.
2.3.3.3.3 Actions Following Notice of Failure to Agree Phase 2 Change Order
Following delivery of a written notice under Section 2.3.3.3.2 (Failure to Agree to a Phase 2
Change Order) or a failure by either Party to execute a Phase 2 Change Order after the
Department’s acceptance of the Phase 2 Proposal in accordance with Section 2.3.3.3.1 (Initial
Review and Negotiation of Phase 2 Proposal):
A. The Department and Contractor may agree to a Change Order that obligates the
Contractor to perform and complete any part of the Phase 2 Work as an Early Work
Package prior to expiration of the term of Phase 1B, or such longer period as may be
agreed upon between the Parties;
B. The Contractor shall continue to perform and complete the Phase 1B Work (other than
that part of the Phase 1B Work requiring preparation of a Phase 2 Proposal or solely
for the purposes of preparing a Phase 2 Proposal);
C. Upon the Department’s written notice, the Contractor shall assign to the Department
all of the right, title, and interest of the Contractor in and to the work products
developed under the Phase 1 Work; including the Design Work;
D. Upon completion and the Department’s written acceptance of the Design Work and
any remaining obligations under the Phase 1B Work, this Contract will expire in
accordance with Section 1.5 (Term);
E. Title to the Design Work will remain vested in or pass to the Department in
accordance with Section 26.14 (Ownership and Copyright of Submittals). Any
Submittals which are provided to the Department by the Contractor or Subcontractors
as part of the Phase 1 Work may be used and disclosed by the Department in
accordance with Section 26.15 (Intellectual Property);
F. The Department may, in its sole discretion, proceed with any other action as the
Department deems appropriate for delivery of the Phase 2 Work, including soliciting
from, negotiating with, or awarding a contract to any other Person for any part of the
Phase 2 Work; and
G. The Department may, in its sole discretion, terminate this PDBC pursuant to Section
21 (Termination for Convenience) if it determines to not proceed with the Phase 2
Work.
2.4 Phase 2: Final Design and Construction
2.4.1 Phase 2 Change Order
Phase 2 shall commence upon the Department’s issuance of a Phase 2 NTP and shall continue
until the end of the term of the Phase 2 Work as set forth in the Phase 2 Change Order. If
authorized in an executed Early Work Package, Early Work on Phase 2 may begin before
Phase 1B is completed, with Early Work and Phase 1B proceeding concurrently.
The Phase 2 Change Order shall include the content specified in the Project Scope and
generally apply to all Work Packages. The executed Phase 2 Change Order shall not be
modified except through a Change Order.
A. In the case of an Early Work Package, the Contractor’s reasonable, good faith
estimate of the cost of the Phase 2 Work authorized therein in a format developed
pursuant to the protocols in Exhibit G (Pricing Process);
B. In the case of the Phase 2 Change Order, the Contract Price reflected in any
previously executed Early Work Packages, as well as the Contractor’s reasonable,
good faith estimate of the cost of the Work for the balance of the Design and
Construction Work in a format developed pursuant to the protocols in Exhibit G
(Pricing Process); and
C. Any allowances stipulated by the Department and a statement of their basis (e.g.,
quantities, unit prices).
The backup support for the calculation of the Contract Price shall be provided to the Department
in a manner and in the format developed pursuant to the protocols in Exhibit G (Pricing
Process).
The Department and the Contractor may agree in any Early Work Package Change Order or in
the Phase 2 Change Order that a portion or all of the Work referenced therein shall be
performed on the basis of a Lump Sum or as a Guaranteed Maximum Price (GMP).
A. Develop, review and make updates to the Risk Register, attached hereto as Exhibit Z
including identifying new risks and reflecting discussions and decisions made during
risk management meetings;
B. Develop proposals and seek solutions for avoiding and mitigating the risks listed on
the Risk Register during the development of the Design Documents, the development
of the Baseline Schedule, and the DBT PMP;
C. Develop qualitative and quantitative analysis of the risks;
D. Develop methods to track costs and time incurred directly associated with such risks;
E. Consider different approaches to the risk allocation for the Construction Work and
determine the risk allocation assumptions for the purposes of preparing any Early
Work Package Proposal and the Phase 2 Proposal;
F. Determine the specific mitigation actions to be taken by each Party in response to the
risks listed on the Risk Register;
G. Close in the Risk Register those risks which have been avoided or passed and
document the resolution; and
H. Otherwise assess, review and monitor risks and risk response strategies as required
under the Project Scope.
Risks applicable to the Phase 2 Work will be identified jointly during Phase 1 and the Parties
shall endeavor to agree to the probability of occurrence, ranges of potential cost impact,
potential schedule impact and mitigation measures.
The Department will consider changes to the initial allocation of risk resulting from the process
outlined in this Section 2.6.1 (Risk Approach) during the negotiation of a Phase 2 Change
Order.
The Contractor shall be responsible for maintaining and updating the Risk Register. The Risk
Register shall identify potential risk issues related to Construction Work (each a “Risk Register
Event”). All Risk Register Events shall be categorized as either a Department Risk, a
Provisional Risk, or a Contractor Risk.
The Risk Register shall include dates on which the Department gives its approval of a particular
Risk Register Event, and the Risk Register Event shall be deemed as being in effect of that
date. All Phase Change Orders shall include the most-current Risk Register as of the effective
date of the Phase Change Order updated with all Risk Register Events reasonably expected to
be applicable to the Work Package.
The Risk Register shall also define mitigation strategies to be used by the Parties with respect
to Risk Register Events and identify any potential cost, if any, and/or time impacts, if any, to the
Project.
If a Risk Register Event occurs while performing Construction Work, and the Risk Register
Event is a Department Risk, then the Contractor shall be entitled to seek a Change Order in
accordance with Section 12.3 (Change Orders).
submit a written Notice of Potential Change Order in accordance with Section 12.3 (Change
Orders).
If a Risk Register Event expressly identifies a Shared Provisional Sum, then upon achievement
of Substantial Completion, or other such date determined by the Department, any unused
Shared Provisional Sums across all Work Packages shall be allocated 90% to the Department
and 10% to the Contractor, unless otherwise negotiated during Phase1 and the Contractor’s
share shall be included in the Project finalization process as provided in Section 5.14.2.2
(Finalization).
D. Following the risk management meetings, the Contractor shall submit to the
Department for its review, a written report of the points discussed and agreed at the
risk management meeting and any consequential impact on the Project and shall
update and re-submit any such written report to incorporate any corrections notified to
it by the Department.
2.7 Cost Submittals
2.7.1 Sub-Phase 1A Opinion of Probable Cost
In collaboration with the Department, the Contractor shall develop an Opinion of Probable Cost
(OPC) for the Sub-Phase 1B Work and the Phase 2 Work consistent with the Base Design (as
amended during Sub-Phase 1A) and developed in accordance with Exhibit G (Pricing Process).
The Contractor shall submit the Phase 2 Proposal for the remaining Phase 2 Work not already
authorized as an Early Work Package following the protocols in Exhibit G (Pricing Process). The
Contractor is entitled to treat such Submittals as Escrow Documents in accordance with Section
25.7 (Escrow Documents). The Contractor shall develop each GMP or Lump Sum through
negotiation on an Open Book Basis, allowing the Department to review and evaluate all cost
data and underlying assumptions, supported by a transparent and competitive Subcontractor
procurement processes further described in Section 8 (Subcontracting Requirements), and
subject to the self-performance provisions described in Section 8 (Subcontracting
Requirements).
As further described in Exhibit G (Pricing Process) Part C: (Basis for Establishing Price), the
Contract Price for each Work Package will be based on the reasonably estimated actual cost of
completing the associated Work including the Project Mark-up. The Project Mark-up will be
established as of the Effective Date and will not be renegotiated as part of any GMP or Lump
Sum Proposal negotiation.
A. The Contract has been executed and the Contractor has submitted and the
Department has accepted the Sub-Phase 1A Proposal;
B. The Department has received the Contractor’s required insurance certificates and
associated documentation for the Sub-Phase 1A Services in accordance with Section
17 (Insurance Requirements); and
C. The Contractor has designated the initial Contractor’s Representative in accordance
with Section 10.1 (Authorized Representatives).
2.8.3 Notice to Proceed for the Sub-Phase 1B Work
The Contractor shall not perform or permit performance of any part of the Sub-Phase 1B Work
until the Commencement Date stated in the Sub-Phase 1B NTP. The Department will issue the
Sub-Phase 1B NTP no later than 30 Days after the following conditions have been satisfied:
A. The Parties have agreed and executed the Sub-Phase 1B Change Order;
B. The Department has received the Contractor’s required insurance certificates and
associated documentation for the Sub-Phase 1B Work in accordance with Section 17
(Insurance Requirements); and
C. The Contractor has satisfied any other conditions to the issuance of Phase 1B NTP as
agreed by the Parties during Phase 1A.
2.8.4 Notice to Proceed for Early Work
The Contractor shall not commence performance of that part of the Phase 2 Work included in
any Early Work Package until the Commencement Date stated in an Early Work Package NTP.
The Department will issue an Early Work Package NTP no later than 45 Days after the following
conditions have been satisfied:
A. The Early Work Package has been authorized under a Change Order;
B. The Department has received the Contractor’s Performance Bonds and Payment
Bonds and required insurance certificates for that Early Works Package in accordance
with the Early Work Change Order; and
C. The Contractor has obtained any and all Governmental Approvals (other than any the
Department-Provided Approvals) required for the performance of that Early Work
Package.
2.8.5 Notice to Proceed for Phase 2 Work
The Contractor shall not perform or permit the performance of any part of the Phase 2 Work
until the Commencement Date stated in the Phase 2 NTP. The Department will issue the Phase
2 NTP no later than 45 Days after the following conditions have been satisfied:
A. The Parties have agreed and executed the Phase 2 Change Order;
B. The Department has received the Contractor’s Performance Bonds and Payment
Bonds and required insurance certificates and documentation for the Phase 2 Work in
accordance with the Phase 2 Change Order;
C. The Contractor has completed any other conditions precedent to the issuance of the
Phase 2 NTP under the Phase 2 Change Order;
D. The Contractor has obtained any and all Governmental Approvals (other than any
Department-Provided Approvals) required to commence the performance of the Phase
2 Work;
E. The Department has approved the DBT PMP and Quality Management System Plan;
and
F. The Department has approved the Project Baseline Schedule.
Issuance of Phase 2 NTP authorizes the Contractor to perform all other Work and activities
pertaining to the Project.
A. Whether or not it is in the best interest of the Department and the general public for
the Department to continue to work with the Contractor after completion of the Phase
1 Work;
B. Whether or not to require that the Contractor submit a Phase 2 Proposal;
C. Whether or not to accept any Early Work Package Proposal or execute an Early Work
Package Change Order; and
D. Whether or not to accept the Contractor’s Phase 2 Proposal or execute the Phase 2
Change Order.
The Contractor is not entitled to claim or seek payment from the Department of any amount as a
result of the Department making a determination not to proceed with requiring submittal of and
Early Work Package Proposal, a Phase 2 Proposal, a Phase 2 Change Order, or otherwise
authorize the Contractor to perform the Phase 2 Work (in whole or part) or to award the Phase 2
Work (in whole or in part) to another Person or taking any other action or exercising any other
right under this Section 2.9.
The Department's rights under Section 2.3.3.3.2 (Failure to Agree to a Phase 2 Change Order)
are without prejudice to its rights and remedies for a Contractor Default under Section 19
(Default), including where such Contractor Default results in a failure to agree to a Phase 2
Change Order, and the Department may terminate this Contract for any or no reason at its
convenience in accordance with Section 21( Termination for Convenience).
1The Sub-Phase 1A Proposal (incorporating the Subphase 1A Project Scope) negotiated prior to
execution of the PDBC will replace the preliminary version in this Section 3.1.
R. Development of the Project Schedule for all Phases to the stage and level of detail
described in Exhibit T (Critical Path Method Progress Schedule);
S. Updating and further development of the Project Risk Register and pricing of risks as
further described in Section 2.6 (Risk Identification. Pricing and Assignment);
T. Development of a preliminary Construction Management Plan;
U. Development of a preliminary Subcontractor Bidding and Selection Plan;
V. Validation of the Base Design to establish Proof-of-Concept;
W. Update the Base Design as necessary to determine the Opinion of Probable Cost
(OPC);
X. Development of the Cost Model and Estimating Methodology Report for development
of the GMP / Lump Sum as further described in Exhibit G (Pricing Process);
Y. Development of the OPC for the updated Base Design as further described in Exhibit
G (Pricing Process); and
Z. Development of the Sub-Phase 1B Proposal including the Maximum Sub-Phase 1B
Prime Compensation.
3.2 Sub-Phase 1B Project Scope
The Sub-Phase 1B Project Scope will be developed and agreed during Sub-Phase 1A and is
expected to include the following activities and deliverables:
L. Causing the conduct of required investigations and surveys including geotechnical and
SUE and reporting the results and setting forth the potential impact on the Project;
M. Further investigation and analyses such as structural, hydraulic, drainage,
geotechnical as necessary and appropriate to develop the Design Documents, the
Baseline Schedule, and the DBT PMP;
N. Generate the cost and resource loaded schedule necessary to establish GMP or
Lump Sum(s) for Early Work Packages and Phase 2 Change Order;
O. Coordinate with Independent Cost Estimator (ICE) and the State Cost Estimator
(SCE) to develop the GMP or Lump Sum Price Proposals using the applicable
approach in Exhibit G (Pricing Process);
P. Identify Early Work and submit Early Work Package Proposal(s);
Q. Submit Phase 2 Proposal; and
R. Required Payment Bond and Performance Bond for Early Work Packages and Phase
2.
3.3 Phase 2 Project Scope
The Phase 2 Project Scope shall include performance requirements, Project Standards,
specifications, the Technical Requirements, drawings and other documents applicable to the
Phase 2 Work, as set forth in the Phase 2 Change Order, and describing the Contractor’s
responsibilities. The Department’s initial requirements and a framework for the Phase 2 Project
Scope shall be developed and agreed between the Parties as part of the Sub-Phase 1A Work.
The Department is entitled to supplement the Phase 2 Project Scope at any time during Phase
1 and any impact, if any, upon the Phase 1 Work will be administered through the process
described in Section 12 (Contract Changes). The Contractor is responsible for identifying
additions or amendments to the Phase 2 Project Scope necessary to appropriately define and
perform the Work and, subject to the Department’s approval, such additions and amendments
may be incorporated into the Phase 2 Project Scope during Phase 1.
The Phase 2 Project Scope will be considered a part of and included in an exhibit to the PDBC
at the execution of the Phase 2 Change Order and at that time will incorporate and supersede
all matters governing the Phase 2 Work that formerly appeared in the Technical Requirements.
Subsequent changes to the Phase 2 Project Scope will be in accordance with the Change Order
process as set forth in Section 12.
https://www.dot.state.oh.us/Divisions/ConstructionMgt/design-build/bsb-project-
procurement/ReferenceFiles/Forms/AllItems.aspx
RIDs may include electronic copies of existing reports, plans, photographs, topographic
mapping, traffic data and projections, utility information, administrative guidelines, directives,
technical manuals, specifications, and other documents pertinent to the Phase 1 Work.
The Contractor shall, prior to the kick-off Risk Management Meeting, as described in Section
2.6.2 (Risk Management Meetings), in accordance with prudent and generally accepted
engineering and construction practices, review and analyze the RIDs, including but not limited
to, the boring logs and other geotechnical information, drainage information, and environmental
information contained therein, and inspect and examine the Project Site and surrounding
locations.
At the kick-off Risk Management Meeting, described in Section 2.6.2, the Contractor and
Department shall address (1) the Contractor’s review and analysis of the RIDs and (2) based on
Contractor’s review and analysis of the RID’s, the Contractor’s determination and assessment of
the additional testing necessary and appropriate to perform the Work.
The Contractor hereby agrees and acknowledges that as a result of its review and analysis of
the RIDs, its inspection and examination of the Project Site and surrounding areas, the
Contractor is familiar with the Project Site and acknowledges and agrees that it is responsible
for determining and obtaining any additional information and testing the Contractor deems
necessary and appropriate to perform the Work in accordance with the Contract Documents.
The Department may review Submittals based upon the RIDs and provide comments where
necessary. Such review shall not relieve the Contractor of any obligation concerning accuracy
or completeness of Submittals based upon the RIDs.
Additional Documents may be proposed to be added to the RIDs by either Party at any time
during Phase 1. For the Phase 2 Work, portions of the RIDs may be explicitly referenced in a
Phase 2 Change Order for the purpose of defining the Department’s requirements. Such
portions are deemed incorporated in the PDBC solely to the extent that they are so referenced.
In the performance of the Phase 2 Work, the Contractor may rely on the RIDs only to the extent
expressly agreed upon and set forth in the Phase 2 Change Order.
The Contractor shall validate the Base Design during Sub-Phase 1A to establish Proof-of-
Concept and shall identify, for the Department’s review and comment, any suggested
amendments to the Base Design. Upon the Department’s approval of any Contractor-identified
amendments to the Base Design, the Contractor shall update the Base Design prior to the start
of Sub-Phase 1B such that the Base Design depicts the layout of the Project and all the
requirements necessary to develop the Opinion of Probable Cost (OPC).
The contractor shall update the Base Design during Sub-Phase 1B such that the Base Design
depicts the layout of the Project used to develop the Phase 2 Change Order.
The Contractor shall complete the Sub-Phase 1A Work in accordance with the scheduled
Completion Deadline for the Sub-Phase 1A Work established in the Project Schedule.
The Contractor shall perform and complete all Phase 1 Work, notwithstanding the execution of
any Early Work Package Change Order or Phase 2 Change Order and the resulting concurrent
obligation to perform any Early Work Package or the Phase 2 Work.
As part of the Phase 2 Work the Contractor shall procure all Governmental Approvals ; pay all
charges, fees, and taxes; and provide all notices necessary and incidental to the due and lawful
prosecution of the Work. It is the responsibility of the Contractor to obtain any Governmental
Approvals and pay any costs required by the local road or street agency for the use of any Right
of Way in connection with the Work.
A. Consult with Department to understand the requirements for the Project and review
available data.
B. Advise the Department as to the necessity of providing or obtaining from others
additional reports, data or services and assist the Department in obtaining such
reports, data, or services.
C. Develop Ohio Maintenance of Traffic (MOT) plans in accordance with the Standard
Construction Drawings, Location and Design Manual, and OMUTCD. Develop
Kentucky MOT plans in accordance with MUTCD, except when the KYTC Standard
Drawings or Standard Specifications are more restrictive, the KYTC Standard
Drawing and Specifications shall govern.
D. Develop and maintain and make available to the Department a project record which
includes all significant events (changes, comments, etc.) which influenced the
development of the Project.
E. Perform any surveys (for Ohio pursuant to ODOT Survey Manual; for Kentucky
pursuant to KYTC Highway Design Manual and Standard Specifications) required for
the Project.
F. Perform hydraulic analysis as set forth in the Project Scope. The results of the
analyses must show no harmful interference to adjacent riparian vegetation (along
streams) resulting from the Work. Results must be certified by the Contractor. The
certification must state that the proposed structure will have an equal to or greater
hydraulic capacity and that a deletion or reduction of existing auxiliary openings and
overflow areas is not planned.
G. Perform any additional needed soils surveys, soils borings, and geotechnical
investigations, as appropriate with analysis necessary to develop the Design
Documents.
H. Reference the appropriate Technical Requirements, including the ODOT Construction
and Materials Specifications or KYTC Standard Specification for Road and Bridge
Construction, as appropriate, in the Plans for all Construction Work to be performed
and all Materials to be furnished.
I. Provide Plans, specifications and supporting documents for review by the Department
at each stage of plan development required by the Project Scope.
J. Provide written approval on Contractor accepted Shop Drawing(s). Contractor’s
written approval shall be provided with all Submittals to the Department.
K. Provide approval between the Designer and the individual within the Contractor’s
organization responsible for erection and temporary works regarding acceptability of
developed Engineered Drawings identified in the following ODOT C&MS Sections:
501.05.A 1(Bracing adjacent to railroad tracks), 501.05A 2 (Demolition of Structures
over or within 14 feet of railroad tracks), 501.05.A 3 (Erection of structural members
over or within 14 feet of railroad tracks), 501.05B 3 (Falsework for cast-in-place
concrete slab bridges), & 501.05B 6 (Total load applied during construction exceeds
75 percent of legal limit). Contractor’s written approval shall be provided with the
Submittal to the Department.
L. Provide concurrence on acceptability of Corrective Work Plan (CWP) as described in
ODOT C&MS Section 501.05.C (Corrective Work). Written concurrence shall be
provided with the submittal to the Department.
4.1.4 Design and Professional Services Prequalification
Design Work or Professional Services that requires prequalification may only be performed by
firms that are prequalified for that Work at the time of performance of the Design Work or
Professional Services.
The Contractor shall cause the Designer and all other Subconsultants performing Design Work
or Professional Services to be prequalified by ODOT or KYTC, as appropriate to the JDM for the
Work and in the category for which each organization is performing the Work.
The Designer and all Subconsultants’ names and addresses must be the same as those on file
with ODOT or KYTC as appropriate. All Professional Services must comply with Section
4733.16 of the Ohio Revised Code for Work within Ohio’s jurisdiction or Kentucky Revised
Statute 322.060 for work within Kentucky’s jurisdiction.
The Contractor shall interpret all references to guidelines, recommendations and considerations
within applicable design manuals as minimum requirements except when specifically excluded
within the Project Scope. The Contractor shall perform recommended evaluations if not
provided by the Department.
solution. A Standards Deviation shall not be included in the Design Documents without the
Department’s written approval.
The Department shall have the discretion to determine the level of review required for any
Submittal in accordance with Section 4.7 (Contractor Submittals Listing & Schedule). The
Contractor bears sole responsibility for the quality, accuracy, completeness, and compliance
with the requirements of the Contract Documents regardless of the Department’s level of
review.
The Department’s failure to identify improper or incorrect design (including any errors and
omissions in the Base Design) shall not, in any way, prevent later rejection of a Design
Document if an improper or incorrect design is discovered, or obligate the Department to grant
acceptance under Section 5.14.1 (Partial Acceptance) or Section 5.14.4 (Completion of the
Contract and Continuation of Contractor’s Responsibilities).
In the event of any negligent act, error or omission which the Department determines to be the
responsibility of the Contractor, the correction, repair or reconstruction of which may require
additional field or office work, the Contractor shall perform such corrective action as may be
necessary.
The Contractor shall be responsible for damages including but not limited to economic waste,
direct and indirect damages incurred as a result of its negligent act, error or omission, and for
losses or costs to repair or remedy construction.
2. The planned schedule for submittal of the Contractor Submittals, which shall be
consistent with the Project Schedule and any time period for Submittals under this
PDBC;
3. The required or proposed level of review to be provided by the Department; and
4. Any required reviews or approvals of Contractor Submittals by third parties.
C. The Submittals Listing & Schedule shall be submitted as part of the DBT PMP for the
Sub-Phase 1A Work and shall include a list of Contractor Submittals to be submitted
to the Department in relation to the performance of the Phase 1 Work.
D. The Contractor shall maintain, update, and re-submit its Submittals Listing &
Schedule:
1. At least monthly if there have been any material changes in the prior month;
2. Together with its initial submittal and each subsequent submittal of its Design
Quality Management Plan, so as to include all Design Documents;
3. Together with submittal of any Early Work Package Proposal;
4. Together with submittal of its Phase 2 Proposal; and
5. During the performance of the Phase 2 Work to establish all Submittals associated
with Final Design, the Construction Work and the As-Built Drawings.
E. The Department will complete its review of the initial Submittals Listing & Schedule
and any update to it, issue its comments, and confirm its acceptance or rejection,
within 15 Days of receipt. If the Department does not provide its acceptance or
rejection or provide comments within such time period, the Contractor may proceed to
submit Contractor Submittals in accordance with the Submittals Listing & Schedule.
4.8 Department Review of Contractor Submittals
A. The Contractor shall submit all Contractor Submittals to the Department within the
time periods under the accepted Submittals Listing & Schedule.
B. For those Contractor Submittals which have been designated as requiring the
Department’s review and approval, unless a different review period is agreed between
the Parties and inserted in the Submittals Listing & Schedule, the Department will
complete its review, issue its comments, and confirm its approval or rejection, within
15 Working Days of the Department’s receipt beginning on the first Working Day
following the Submittal Date.
C. Whenever there are more than five concurrent Submittals within an individual
discipline under review by the Department, an additional five Working Days shall be
added to the prescribed review period for each additional increment of 5 concurrent
Submittals within that discipline. For example, if there are between six and 10
Submittals in concurrent review within the “roadway” discipline, then an additional five
Business Days shall be added to the prescribed review period for each Submittal
within that discipline; if there are between 11 and 15 Submittals in concurrent review,
then an additional 10 Working Days shall be added to the prescribed review period for
each Submittal within that discipline, and so forth. For the purpose of this Part C, one
Submittal may not contain more than 200 sheets excluding technical reports,
calculations and cross sections sheets unless approved by the Department.
The Contractor shall prepare Working Drawings when required by the Contract Documents and
after verifying applicable field and plan elevations, dimensions, and geometries. Where Work
consists of repairs, extension, or alteration of existing structures, the Contractor shall take
measurements of existing structures to accurately join old and new Work.
Unless otherwise indicated, the Department will review Working Drawing Submittals to ensure
conformance with the Contract and to provide the Contractor a written response to document
the results of its review as follows:
5 CONTROL OF WORK
5.1 Authority of the Department
The Department shall determine in its sole discretion:
The Department will not supervise, direct or have control or authority over, nor be responsible
for the Subcontractors’ or Subconsultants’ means, methods, techniques, sequences or
procedures of construction, design, or the safety precautions and programs incident thereto, or
for any failure of Contractor to comply with Laws and regulations applicable to the furnishing or
performance of the Work.
The Department will not be responsible for the Contractor’s failure to perform or furnish the
Work in accordance with the Contract Documents. The Department may order immediate
remediation of conditions which endanger the public safety or welfare as set forth in Section
5.10.6 (Public Convenience and Safety), Section 5.11.1 (Maintenance During Construction),
Section 5.11.2 (Failure to Maintain Roadway or Structure), Section 5.11.6 (Protection and
Restoration of Property), Section 5.12 (Contractor’s Use of the Right of Way or Other
Department-Owned Property), and Section 17 (Insurance Requirements).
At or before the preconstruction meeting, the Contractor shall submit the updated Progress
Schedule to the Department and furnish to the Department a list of proposed Subcontractors
and major Material suppliers not included in the Phase 2 Change Order or Early Work Package,
as applicable. If the Contractor fails to deliver the required submissions to the Department at or
before the preconstruction meeting, the Department may order the meeting suspended until the
required submissions are furnished to the Department. The Contractor shall not be permitted to
commence the corresponding Construction Work until the meeting is reconvened and
concluded or the Department gives specific written permission to proceed with the
corresponding Construction Work.
The Contractor covenants and agrees to conduct monthly Progress Meetings with the
Department unless an alternate frequency is otherwise determined and agreed upon in writing
by the Department at the preconstruction meeting. The Contractor covenants and agrees to
coordinate with the Department to determine agenda topics prior to each meeting. The purpose
of Progress Meetings is to maintain and foster open communication between the Contractor and
the department. The Contractor’s senior personnel team shall participate in all Progress
Meetings. The agendas for the Progress Meetings shall include Partnering in accordance with
the department facilitated partnering process as described in Exhibit R (Facilitated Partnering).
After adoption of the DBT PMP, the Contractor covenants and agrees to implement the DBT
PMP to accomplish the quality functions and objectives set forth in the Technical Requirements
as may be amended in the Project Scope.
Any action or inaction of the Inspector does not constitute a waiver of the Department’s right to
pursue any and all legal remedies for Nonconforming Work, or work performed by the
Contractor in an un-workmanlike manner.
When directed by the Department, the Contractor shall remove or uncover completed Work to
allow inspection. After the Department’s inspection, the Contractor shall restore the Work
according to the requirements of the Contract Documents. If the inspected Work conformed to
the requirements of the Contract Documents, the Department will pay for uncovering or
removing and restoring the Work as Extra Work according to Section 12 (Contract Changes).
The Department will not pay for uncovering or removing and restoring Nonconforming Work.
The Department shall have the discretion to determine the level of inspection for any item of
Work. The Contractor bears sole responsibility for the quality of Work and compliance with the
Contract Documents regardless of the Department’s level of inspection.
The Department’s failure to identify Nonconforming Work shall not, in any way, prevent the
Department’s subsequent rejection if Nonconforming Work is discovered, or obligate the
Department to grant acceptance under Section 5.14.1 (Partial Acceptance) or Section 5.14.4
(Completion of the Contract and Continuation of the Contractor’s Responsibilities).
Inspection of Work may also include inspection by representatives of KYTC, the federal
government, other Government Entities or railroad corporations that pay a portion of the cost of
the Work. Such inspections will not make such organizations a party to the PDBC and will not
be considered as interfering with the rights of the Contractor or Department.
The Contractor shall comply with the requirements of ORC 5517.01, 29 CFR 1926, KRS
322.470 and shall notify the property owner or person in possession of the property at least 48
hours prior to entry into said property. The notification format shall be approved by the
Department (or the Cabinet with respect to property in Kentucky) before use.
The Sub-Phase 1A NTP shall constitute permission for the Contractor to occupy public Right-
of-Way within the Project area for the performance of the Phase 1 Work in compliance with
Section 11 of the Technical Requirements (Right of Way) as may be amended in the Project
Scope.
The Department, with respect to Project ROW located in Ohio, and the Cabinet, with respect to
Project ROW in Kentucky, are responsible for securing all necessary Project ROW in advance
of Construction Work. Provisions governing access dates to each parcel are set forth in Section
11 of the Technical Requirements as may be amended in the Project Scope. Any exceptions will
be identified at the time of the Phase 2 NTP. If any parcels have not already been cleared for
access by the Contractor on the date of the Phase 2 NTP, the Department will identify in the
Phase 2 Change Order the specific dates such parcels will be made available to the Contractor.
Where proposed Work is beyond the Project ROW limits, the Contractor shall not commence
any Construction Work outside of the Project ROW until notified by the Department that the
needed additional Project ROW has been acquired and is otherwise available for Construction
Work.
Unauthorized Work is Work done contrary to the instructions of the Department, beyond the
plan lines, or any Extra Work done without the Department’s permission. The Department will
not pay for Unauthorized Work. The Department may order the Contractor to remove or replace
Unauthorized Work at no expense to the Department.
If the Contractor fails to comply with the Department’s orders under the provisions of this
Section 5.9.1 (Nonconforming and Unauthorized Work), the Department may correct or remove
and replace Nonconforming Work or Unauthorized Work and deduct the costs from the Contract
Price.
The Contractor shall pursue the Work diligently and continuously as to achieve the Completion
Deadlines for each Milestone and achieve Substantial Completion of the Project by the
Substantial Completion Deadline.
The Contractor shall operate Equipment of a weight or so loaded as to not cause damage to
Structures, to Roads, or to other types of construction. The Contractor shall comply with ODOT
C&MS subsection 501.05.B.6 (Total load applied to a structure during construction exceeds 75
percent of legal limit) for allowed loads on Bridges for Work undertaken in Ohio and KYTC SS
105.10 for Work undertaken in Kentucky.
The Contractor shall not (i) use off road vehicles on bases or pavements unless permitted by
the Department in writing, (ii) haul on concrete pavement, base, or Structures before the
expiration of the curing period or (iii) exceed the legal load limits in this section unless permitted
by the Department in writing.
shall revise the proposed haul route provided in the original written notification and resubmit to
the Department.
If the Department determines that haul route roads were properly used by the Contractor for any
purpose in connection with the Work and that the haul route roads were damaged, then the
Department may order the Contractor to perform immediate and practical repairs to ensure
reasonably normal traveling conditions. The Department will pay for repairs according to
applicable provisions of Section 12 (Contract Changes).
The Contractor shall not file a Claim for delays or other impacts to the Work caused by disputes
with Government Entities regarding the use of local roads or streets as haul routes. The
Contractor shall save the Department harmless for any closures or hauling restrictions outside
the Project Limits beyond the control of the Department.
Any individual, firm, or corporation wishing to make an opening in the highway must secure a
permit from the JDMA. The Contractor shall allow parties bearing such permits, and only those
parties, to make openings in the highway. When ordered by the Department, the Contractor
shall make in an acceptable manner all necessary repairs due to such openings. The necessary
repairs will be paid for as Extra Work, or as provided in the Contract Documents, and will be
subject to the same conditions as the original Work performed.
Any illegal drugs, drug paraphernalia, mobile drug labs or dumps, weapons or firearms found on
the Project ROW shall be considered a potential crime scene and shall not be handled or
moved. In such an event, the Contractor shall immediately notify law enforcement and the
Department.
The Contractor shall maintain the previous courses or subgrade during all construction
operations, when placing a course upon other courses of embankment, base, subgrade,
concrete or asphalt pavement, or other similar items previously constructed. This maintenance
includes, but is not limited to draining, re-compacting, re-grading, or if destroyed, the removal of
Work previously accepted by the Department.
The Contractor shall maintain the post construction storm water Best Management Practice
(BMP) features. The Contractor shall prevent sediment laden surface water from coming in
contact with the BMP features during construction.
The Contractor shall maintain the Work during the Construction Period and before acceptance
of the Work under Section 5.14.4, except for portions of the Work accepted under Section
5.14.1. The Department will not provide additional compensation for maintenance Work. All cost
of maintenance Work during construction and before the project is accepted shall be included in
the Contract Price and the Contractor will not be paid an additional amount for such Work.
Snow and ice control during the Construction Period will be by the JDMA and applicable
Government Entities. The Contractor’s incident management responsibilities during the
construction Period shall be in accordance with the Incident Management Plan (IMP) to be
developed by the Contractor as further described in Technical Requirements Section 21
(Maintenance of Traffic) as may be amended in the Project Scope.
The Contractor shall not be required to assume any maintenance responsibilities until NTP for
Construction Work pursuant to an Early Work Package Change Order or the Phase 2 Change
Order, following which the Contractor shall be responsible for maintenance of existing facilities
within the Project Limits as described herein. The Contractor shall not be required to assume
maintenance responsibility for the Existing Brent Spence Bridge until the start of physical work
on the Existing Brent Spence Bridge and only until partial acceptance of the physical work on
the Existing Brent Spence Bridge or Completion of the Contract whichever is the earlier.
The Contractor shall perform a baseline inspection and submit a baseline inspection report that
shall be used as a benchmark to determine the minimum required maintenance condition of all
existing project elements throughout the Construction Period. Subject to the requirements of the
Phase 2 Change Order, the Contractor shall maintain all elements within the Project limits such
that the baseline element condition is equaled or exceeded.
1. Arrow board;
2. Work zone signal, pole, or controller;
3. Lighting unit or pole;
4. Changeable message sign;
5. Work Zone Impact Attenuator;
6. Truck Mounted Impact Attenuator; or
7. Digital Speed Limit Sign Assembly.
In case of suspension of Work by the Contractor or under the provisions of Section 20.2
(Department Suspension for Cause), the Contractor shall be responsible for the Project and
shall take necessary precautions to prevent damage to the Project; provide for normal drainage;
and erect any necessary temporary structures, signs, or other facilities at its expense. During
such period of suspension of Work, properly and continuously maintain in an acceptable
growing condition all living material in newly established plantings, seedings, and soddings
furnished under the Contract Documents, and take adequate precautions to protect new tree
growth and other vegetative growth against injury.
The Contractor is responsible for all damage or injury to property, during the prosecution of the
Work, resulting from any act, omission, neglect, Nonconforming Work or misconduct in the
manner or method of executing the Work. The Contractor will remain responsible for all damage
and injury to property until the Project is accepted under Section 5.14.4 (Completion of the
Contract and Continuation of Contractor’s Responsibilities), except for portions of the Work
accepted under Section 5.14.1 (Partial Acceptance).
If the Contractor causes any direct or indirect damage or injury to public or private property by
any act, omission, neglect, or misconduct in the execution or the non-execution of the Work,
then it must restore, at its own expense, the property to a condition similar or equal to that
existing before the damage or injury.
If mail boxes, road, or street name signs and supports interfere with the Work, the Contractor
shall remove and erect those items in a temporary location during the Construction Period in a
manner satisfactory to and as directed by the Department. After Substantial Completion of the
Work and before Completion of the Contract, the Contractor shall erect the mailboxes, road, or
street name signs and supports in their permanent locations according to the Plans unless
otherwise directed by the Department.
The Contractor shall cooperate with the Department in protecting and preserving survey
monuments that are affected by the Work as required by ORC 5519.05 and KRS 433.770. At
the beginning of the Work, the Contractor shall verify the position of all survey monuments in the
area to be improved, according to ODOT C&MS Section 623 (Construction Layout Stakes and
Survey Monuments). If survey monuments not shown in the Contract Documents are
unexpectedly encountered, then the Contractor shall protect, reference, and preserve those
survey monuments in the same manner as survey monuments that are shown in the Contract
Documents.
The Contractor shall not create staging areas, store Materials and Equipment, or borrow or
waste materials in areas identified as an environmental resources areas in the Contract
Documents. All properties to be utilized by the Contractor outside the Project Limits shall be
cleared for all environmental resource impacts prior to the beginning of Construction Work.
Environmental resources include but may not be limited to:
1. Cultural Resources:
a. Buildings, structures, objects, and sites eligible for or listed on the National
Register of Historic Places; and
b. Historic or prehistoric human remains, cemeteries, and/or burial sites (pursuant
with ORC 2909.05 and 2927.11, KYTC’s Right of Way Guidance Manual (Section
ROW-1202), and the Advisory Council on Historic Preservation’s (ACHP) Policy
Statement Regarding Treatment of Human Remains and Grave Goods.
2. Ecological Resources:
a. Wetlands;
b. Streams; and
c. Wooded areas with trees to be removed in excess of 8 inches diameter at breast
height.
3. Public Lands:
a. Lands meeting the criteria of 49 U.S.C. 303, 23 CFR 771.I35: 4(f); and
b. Lands meeting the criteria of 16 U.S.C. 4601-4, 36 CFR59.1: 6(f).
4. FEMA Mapped 100 year Floodplains; and
1. Reuse of Clean Hard Fill as described in CA-EW-20 (ODOT Beneficial Reuse Form).
Prior to transferring Clean Hard Fill from the project, fully execute form CA-EW-20 and
provide appropriate documentation to the Department as described for each reuse
option.
All areas proposed to be utilized by the Contractor outside the Project Limits and not described
above shall be reviewed by environmental Subcontractor(s) that are prequalified by the
Department for each environmental resource. The Contractor shall cause the environmental
Subconsultant(s) to certify that the proposed site to be utilized for the Contractor will not impact:
1. Cultural Resources;
2. Ecological Resources;
3. Public Lands;
4. FEMA Mapped 100 year Floodplains; or
5. Hazardous Waste Areas.
The Contractor shall provide all documentation and the environmental Subconsultant
certification to the Department.
In the event that the areas proposed for use by the Contractor outside the Project ROW contain
environmental resources, the Contractor shall be responsible to the Department for all
environmental clearances and permits prior to the beginning Construction Work.
The Contractor shall cooperate with the owners of any underground or overhead utility lines in
their removal and rearrangement operations to ensure these operations progress in a
reasonable manner, that duplication of rearrangement Work may be reduced to a minimum, and
that services rendered by those parties will not be unnecessarily interrupted.
In the event interruption to underground or overhead utility services results from an accidental
breakage or from being exposed or unsupported, the Contractor shall immediately alert the
occupants of nearby premises as to any emergency that the accidental breakage may create at
or near such premises. The Contractor shall then notify the Department and the Utility Owner of
the utility facility of the disruption and cooperate with the said Utility Owner or operator in the
restoration of service. If water service is interrupted, the Contractor shall perform the repair work
continuously until the service is restored unless the repair work is performed by the local
governmental authority. The Contractor shall not begin Work around fire hydrants until the local
fire authority approves provisions for continued service.
A. If the Contract Documents identify locations for the disposal of waste material and
construction debris or excavation of borrow material within the Project ROW or on
other Department-owned property, then only perform these operations in these
designated locations.
B. If the Contract Documents do not identify locations for the disposal of waste material
and construction debris or excavation of borrow material within the Project ROW or on
other Department-owned property, then do not assume that the Department will make
such locations available.
If the Contractor’s request to use locations within the Project ROW or on other Department-
owned property is approved by the Department, then the Department will allow the Contractor to
dispose of waste material and construction debris or excavate borrow material for a negotiated
fee per cubic yard.
5.12.2 Contractor’s Use of Portable Plants Within the Project Right of Way
or on Other Department-Owned Property
The Contractor’s use of portable plants within the Project ROW or on other Department-owned
or KYTC-owned property is limited.
The Contract Documents do not identify locations within the Project ROW or on other
Department-owned or KYTC-owned property to place a portable plant. The Contractor shall not
assume that the Department will make such locations available.
C. Provide the Department written certification that the plant will supply Material only for
the Project for which it was approved. The plant shall not be used to supply any other
project or to sell materials commercially.
D. Submit a traffic control plan to the Department for approval that details the anticipated
truck movements and provides acceptable protection, warning, and guidance to
motorists, pedestrians, and the workers.
5.12.4 Equipment Storage and Staging
The Contractor may use, fee-free, any portion of the Project ROW for staging, Equipment
storage, or an office site with the approval of the Department, provided such usages do not
interfere with the Work and are not prohibited by the Contract Documents.
By execution of this PDBC, the Contractor, will be deemed to have stipulated as follows:
A. That any facility that is or will be utilized in the performance of this contract, unless
such contract is exempt under the Clean Air Act, as amended (42 U.S.C. 1857 et seq.,
as amended by Pub.L. 91-604), and under the Federal Water Pollution Control Act, as
amended (33 U.S.C. 1251 et seq., as amended by Pub.L. 92-500), Executive Order
11738, and regulations in implementation thereof (40 CFR 15) is not listed, on the
date of contract award, on the U.S. Environmental Protection Agency (EPA) List of
Violating Facilities pursuant to 40 CFR 15.20.
B. That the Contractor agrees to comply and remain in compliance with all the
requirements of Section 114 of the Clean Air Act and Section 308 of the Federal
Water Pollution Control Act and all regulations and guidelines listed thereunder.
C. That the Contractor shall promptly notify the Department of the receipt of any
communication from the Director, Office of Federal Activities, EPA, indicating that a
facility that is or will be utilized for the contract is under consideration to be listed on
the EPA List of Violating Facilities.
D. That the Contractor agrees to include or cause to be included the requirements of
paragraph A. through D. of this Section 5.13.1 in every nonexempt subcontract, and
further agrees to take such action as the government may direct as a means of
enforcing such requirements.
The following provisions with respect to permits shall be read in conjunction with Technical
Requirements Section 7.2 (Permitting).
Causeways for stream and river crossings or for Work below a Bridge are permitted provided:
A. The causeway complies with the requirements of the 404 Permit the Department
obtained for the Project.
B. The Contractor obtains a 404 Permit from the U.S. Army Corps of Engineers if the
Department has not obtained such a permit. The Contractor shall obtain the 404
Permit prior to beginning construction of the causeway. The Department does not
guarantee that the Contractor will be able to obtain a 404 Permit.
The Contractor shall comply with the Ohio Water Pollution Control Act (OWPCA), (ORC Chapter
6111), and the KYTC Storm Water Quality Management Plan. The Department will obtain a
storm water permit when the plan work acreage requires a permit. The Contractor shall apply for
a permit to cover operations outside the Project limits shown on the plans as required by the
OWPCA provisions. When the Department has not applied for a permit on the Project and a
permit is required because of the total area of the Contractor’s Work, the Contractor shall apply
for, obtain, and comply with the required permit for both the Work within Project Limits and the
Contractor’s Work.
The Department has obtained the required permits from the U.S. Army Corps of Engineers and
Ohio EPA for Work in the “Waters of the United States” and isolated wetlands under ORC
Chapter 6111 and the KYTC Storm Water Quality Management Plan. The Contractor shall
comply with the requirements of these permits.
When Equipment is working next to a stream, lake, pond, or reservoir, appropriate spill
response Equipment is required. The Contractor shall not stockpile erodible material next to a
stream, lake, pond, or reservoir.
The Contractor shall take precautions to avoid demolition debris and discharges associated with
the excavation and hauling of material from entering the stream. In addition, the Contractor shall
remove any material that does fall into the stream as soon as possible.
When excavating in or adjacent to streams, the Contractor shall separate such areas from the
main stream by a dike or barrier to keep sediment from entering the stream. The Contractor
shall take care during the construction and removal of such barriers to minimize sediment
entering the stream.
The Contractor shall contain, collect, characterize and legally dispose of all liquid waste and
sludge generated during the Work. The Contractor shall not mix wastes with storm water. The
Contractor shall not discharge any liquid waste without the appropriate regulatory permits. The
Contractor shall manage liquid waste and sludge in accordance with ORC Chapter 6111, the
KYTC Storm Water Quality Management Plan, KYTC SS Section 213, and all other laws,
regulations, permits and local ordinances relating to this waste.
The Contractor shall control the fugitive dust generated by the Work according to OAC-3745-17-
07(B), OAC-3745-17-08, OAC-3745-15-07, and OAC-3745-17-03, KRS Chapter 77, KRS
Chapter 224, and local ordinances and regulations. Prior to the initiation of abrasive coating
removal, pavement cutting or any other construction operation that generates dust, the
Contractor shall demonstrate to the Department that construction related dust will be controlled
with appropriate Reasonable Available Control Measures (RACM) as described in OEPA
Engineering Guide #57 (http://epa.ohio.gov/dapc/engineer/eguides.aspx).
In addition, the Contractor shall use dust control measures when fugitive dust creates unsafe
conditions as determined by the Department.
In Ohio, the Contractor shall perform open burning according to Section 5.3.12 (Borrow and
Waste Areas), and in Kentucky, the Contractor shall act in accordance with Regulation (KAR)
Title 401.
The Contractor shall ensure that all side slopes of all waste areas do not reduce horizontal sight
distance as defined by the Department’s Location and Design Manual.
The Contractor shall (i) have the proposed borrow and waste areas reviewed by an
environmental Subconsultant that is pre-qualified by the Department and Cabinet as appropriate
for ecological work; and (ii) have the environmental Subconsultant certify that the proposed
borrow and waste operations will not impact the “Waters of the United States” or an isolated
wetland. If Subconsultant certification is not provided, the Contractor shall obtain the 404/401
permits necessary to perform the operations as proposed. The Contractor shall have the
environmental Subconsultant certify that the Work conforms to the requirements of the
permit(s). The Contractor shall provide all documentation submitted to obtain the appropriate
permit(s) and a copy of the permit(s) to the Department.
If burning is permitted in Ohio under the OAC-3745-19 and ORC 1503.18, the Contractor shall
submit a copy of the Ohio EPA permit and the Ohio DNR permit to the Department and copies
of all information used to obtain the permit. In Kentucky, the Contractor shall comply with 401
KAR 63:005, KRS 149, and any Local Ordinances.
Prior to the disposal of waste materials, the Contractor shall submit to the Department an
executed copy of the contract or permission statement from the property owner. The contract or
permission statement must indicate that the waste materials are not the property of the
Department or the Cabinet. Further, the contract or permission statement must expressly state
that the Department and Cabinet is not a party to the contract or permission statement and that
the Contractor and property owner will hold the Department and Cabinet harmless from claims
that may arise from their contract or permission statement.
The Contractor shall restore all borrow or waste areas including cleanup, shaping, replacement
of topsoil, and establishment of vegetative cover by seeding and mulching according to Section
5.13.4 (Cleaning Up) and Ohio Item 659 (Seeding and Mulching) where in Ohio. In Kentucky,
the Contractor shall follow Section 204, 209, 211 and 212 of KYTC SS. The Contractor shall
ensure the restored area is well drained unless approval is given by the Department to convert a
pit area into a pond or lake, in which case confine restoration measures to the disturbed areas
above the anticipated normal water level.
For waste sites shown on the plan, the plan will indicate if the clearances have or have not been
obtained for the project right-of-way locations. No extension of time or additional compensation
will be paid for any delays due to not having the written permit(s) to waste in a floodplain.
The allowed use of Project ROW and other Department and Cabinet property for borrow and
waste is detailed in Section 5.13.3 (Rights in and Use of Materials Found in the Work), Section
5.12 (Contractor’s Use of the Project ROW or Other Department-Owned Property) and KYTC
SS.
Borrow and Waste Area shall adhere to Section 5.11.6 (Protection and Restoration of Property)
and KYTC SS.
5.13.4 Cleaning Up
The Contractor shall maintain the Project in a presentable condition. The Contractor shall
remove all rubbish, layout stakes, sediment control devices as directed by the Department,
excess material, temporary structures, and Equipment, including stream channels and banks
within the Right-of-Way at drainage structures, and all borrow and waste areas, storage sites,
temporary plant sites, haul roads, and other ground occupied by the contractor in connection
with the Work. The Contractor shall establish suitable vegetative cover in these areas by
seeding and mulching according to Item 659, except for cultivated fields and leave the Project
Site in an acceptable condition as determined by the Department.
The Contractor shall legally dispose of debris containing wood, road metal, or plaster at a
licensed construction and demolition debris site.
Under the regulations cited above the disposal of brush, trees, stumps, tree trimmings,
branches, weeds, leaves, grass, shrubbery, yard trimmings, crop residue, and other plant matter
is restricted. If allowed by the Contract Documents, the Contractor may waste brush, trees,
stumps, tree trimming, branches, weeds, leaves, grass, shrubbery, yard trimmings, crop
residue, and other plant matter within the Project ROW. Otherwise, the Contractor shall submit
a plan and any required permits to legally dispose of these materials off the Project ROW to the
Department and shall provide all documents submitted to obtain any permits to the Department.
When wasting PCC, the Contractor shall (i) mix the PCC with at least 30 percent natural soil to
construct an inner core in the waste area; (ii) cover this inner core with 3 feet (1.0 m) of natural
soil on the top and 8 feet (2.4 m) on the side slopes; and (iii) place and compact the material
according to ODOT C&MS 203.06.D (Spreading and Compacting Random Materials), where in
Ohio, or KYTC SS 204, where in Kentucky, to prevent future settlement and sliding.
Clean Hard Fill consisting of reinforced or non-reinforced concrete, asphalt concrete, brick,
block, tile or stone that is free of all steel as per ODOT C&MS 703.16 (Suitable Materials for
Embankment Construction) shall be managed in one or more of the following ways:
A. the Contractor has given timely notice of the corresponding condition and the
Unknown Regulated Materials as required in this Section 5.13.7.3, and, where
applicable, Section 13 (Time Extension to the Completion Deadlines and Payment for
Excusable Delays) for Critical Path delay impacts and Section 12.8 (Changes and
Extra Work Price Determination) to compensate the Contractor for the added costs
and delay;
B. the Contractor has given the Department (and, if applicable, the Cabinet) to
investigate prior to the asserted condition and Unknown Regulated Materials being
disturbed in accordance with this Section 5.13.7.3; and
C. the Unknown Regulated Materials are not Contractor-Generated Regulated Materials.
Any Disputes as to whether the conditions pertaining to Unknown Regulated Materials have
caused a decrease or increase in the Contract Price or require an extension of the Contract
Time shall be addressed in accordance with the Partnering and Dispute Resolution provisions
set forth under Section 18 (Partnering and Dispute Resolution) hereof.
provided in this PDBC, the Department’s use of other third-party contractors shall not constitute
a basis for the Contractor to submit an NPCO or EDR.
Notwithstanding anything to the contrary contained herein or under any applicable Law or
Government Regulation, the Contractor (and not the Department or the Cabinet) acknowledges
and agrees that the Contractor shall be considered the “generator” under the following
circumstances:
A. the Regulated Materials are transported onto the Site by the Contractor or any
Component Firm or the Regulated Materials were generated on the Site; or
B. any spill, leak, emission, release, discharge, injection, escape, dumping or disposal of
Regulated Materials into the soil, air, surface water, groundwater, or environment is
caused by the Contractor or any Sub-Contractor, including the Contractor’s or any
Component Firm’s exacerbation of an existing release or condition of Regulated
Materials contamination (whether known or unknown), or any breach by the
Contractor or any Component Firm of any applicable Law, Governmental Approval or
this PDBC, and/or the negligence, or willful misconduct of the Contractor or any
Component Firm ((A) and (B) together constitute “Contractor-Generated Regulated
Materials”).
5.14 Completion Deadlines and Acceptance
5.14.1 Partial Acceptance
Upon completion of a portion of the Work including but not limited to a Work Package, the
Contractor may request acceptance of a completed portion of the Work.
2. The Contractor will not return to the Bridge for any Work except as allowed in part
4 below (painting of structural steel);
3. Traffic is in its final pattern;
4. Painting of structural steel is either completed or scheduled to be performed and
won’t impact traffic; and
5. The Work is in accordance with provisions of the Contract Documents.
The Department will grant written partial acceptance for that portion of the Work or reject the
Contractor’s request. Such written partial acceptance will designate what portion of the Work is
accepted, the date of acceptance, and the warranty provisions started by the partial acceptance.
Partial acceptance will relieve the Contractor of maintenance responsibility for the designated
portion of the Work as further described in Section 5.11.1 (Maintenance During Construction).
This does not relieve the Contractor of responsibility to correct Nonconforming Work or repair
damage caused by the Contractor or waive any other remedy to which the Department is
entitled at law or in equity.
The Department will perform a Final Inspection for the purpose of relieving the Contractor of
maintenance responsibility for the Work per Section 5.11.1 (Maintenance During Construction).
The Final Inspection shall be a limited visual review of the Work and shall serve as the
Department’s verification that the Work appears to have achieved Substantial Completion. Final
Inspection does not waive any available rights or remedies of the Department, nor divest the
Contractor of any responsibility for compliance with the Contract Documents or liability for
damages.
The Contractor shall notify the Department when the Contractor considers the Project has
achieved Substantial Completion and all of the Project Punch List items are complete. If the
Department agrees the Project is complete, then within 15 Working Days the Department will
inspect the Work and categorize it as one of the following:
damage caused by the Contractor or waive any other remedy to which the Department is
entitled at law or in equity. The Department will issue a Final Inspection report that will
document the findings of the inspection and start any warranty period.
5.14.2.2 Finalization
The Contractor shall supply all documents necessary for Project finalization within 60 Days from
the date of Substantial Completion. These documents include:
F. Receipt of all original project files and notes utilized in the preparation of the survey,
design and construction of the Project; and
G. Receipt of As-Built Drawings.
5.14.4 Completion of the Contract and Continuation of Contractor’s
Responsibilities
The Contract is complete, except for items covered by the required bonds, when the Contractor
receives final payment. The Department will issue a letter confirming Completion of the
Contract, noting any exception as provided in ODOT C&MS Items 659 (Seeding and Mulching),
KYTC SS Section 212 and C&MS 661 (Planting Trees, Shrubs, Perennials and Vines), KYTC
SS 724 and any warranty. The date the final payment is approved by the Department
constitutes acceptance for the purpose of ORC 5525.16. Neither Completion of the Contract nor
Substantial Completion relieves the Contractor of any responsibilities to properly perform or
correct the Work or to repair damage or waives any remedies to which the Department is
entitled at law or in equity.
6 CONTROL OF MATERIALS
6.1 Source of Supply and Quality Requirements
The Contractor shall notify the Department of the proposed sources of supply before the
delivery of Materials. The Department is entitled to approve Materials at the source of supply
before such Materials are delivered to the Project Site. If the proposed sources of supply cannot
produce the specified Material, then the Contractor shall furnish Materials from alternate
sources without adjustment to the Contract Price or Substantial Completion Deadline. The
Contractor shall comply with the requirements of Exhibit X (Digital Data for Material Ticketing). If
the Department determines that previously approved materials from any source are not uniform
and satisfactory or that the product from any source proves unacceptable, the Contractor shall
cease operations until the Contractor demonstrates to the Department’s satisfaction that the
material is acceptable. The Contractor shall not use material which, after approval, has in any
way become unfit for use. The Contractor shall use only new materials unless approved by the
Department.
The Contractor shall equip all transports and distributors hauling asphalt material with an
approved submerged asphalt material sampling device.
A. Where similar Materials from the same source have recently been approved.
B. Where the Materials, in the judgment of the Department, will serve the intended
purpose.
6.4 Plant Sampling and Testing Plan
The Department is entitled to undertake the inspection of Materials at the source.
In the event plant sampling and testing is undertaken, the Contractor and its Material provider
shall:
A. Cooperate and assist the Department with the inspection of Materials. Provide full
entry to the Department at all times to such parts of the plant as may concern the
manufacture or production of the Materials being furnished. Agree to all
documentation and inspection requirements of ODOT’s TE-24 plant sampling and
testing plan.
B. If required by the Department, arrange for the Department’s Inspector to use an
approved building on the site of the plant. The building should be located near the
plant and independent of any building used by the Material producer.
C. Maintain and provide adequate safety measures at the plant at all times.
The Department reserves the right to retest all Materials that have been tested and accepted at
the source of supply before their incorporation into the Work. After Materials that have been
tested by the Department at the plant have been delivered to the Site, the Department may
reject any such Materials that when retested do not meet the requirements of the Contract
Documents.
Areas used to store Materials shall conform to Section 5.11.6 (Protection and Restoration of
Property) and KYTC SS 107.
Payment for materials and equipment manufactured for the Project and stored on or off the
Project Site shall be conditioned upon compliance by the Contractor with procedures
satisfactory to the Owner to establish the Owner's title to such materials and equipment or
otherwise protect the Owner's interest, and shall include applicable insurance, storage and
transportation to the Project Site, for such materials and equipment stored off the Project Site.
The Contractor shall also comply with the following specific requirements:
C. The consent of any surety shall be obtained to the extent required prior to payment for
any materials stored off the Project Site.
D. Representatives of the Owner shall have the right to make inspections of the storage
areas at any time.
E. Such materials shall be (1) protected from diversion, destruction, theft and damage to
the satisfaction of the Owner, (2) specifically marked for use on the Project, and (3)
segregated from other materials at the storage facility.
The Contractor shall reimburse the Owner for any loss or damage to such unincorporated
materials or equipment not covered by insurance.
Areas used to store Materials shall conform to Section 5.11.6 (Protection and Restoration of
Property) and KYTC SS 107.
a. Handle all Materials in such manner as to preserve their quality and fitness for the
Work;
b. Transport aggregates from the storage site to the Project Site in vehicles constructed
to prevent loss or segregation of Materials after loading and measuring; and
c. Ensure that there are no inconsistencies in the quantities of Materials loaded for
delivery and the quantities actually received at the place of operations.
6.7 Unacceptable Materials
Unacceptable Materials are all Materials not conforming to the requirements of the Contract
Documents at the time they are used and shall be considered Nonconforming Work. The
Contractor shall immediately remove all unacceptable Materials from the Project Site unless
otherwise instructed by the Department. The Department will determine if unacceptable
Materials may remain according to the process set forth in ODOT Supplement 1102
(Acceptance of Non-Specification Material on Construction Projects). The Department must
approve the use of previously identified unacceptable Materials that have been corrected or
repaired before such Materials are incorporated into the Work. If the Contractor fails to comply
immediately with any order of the Department made under the provisions of this Section 6.7, the
Department will have authority to remove and replace unacceptable Materials and to deduct the
cost of removal and replacement from any monies due or to become due to the Contractor.
The Department will deliver any Department-furnished Materials to the Contractor at the points
specified in the Contract Documents.
The Contractor shall include the cost of handling and placing of all Department-furnished
Materials in the Contract Price for the Contract Item for which they are used.
The Department will hold the Contractor responsible for all Department-furnished Materials
upon their delivery to the Project Site. The Department will make deductions from any monies
due the Contractor to make good any shortages and deficiencies, for any cause whatsoever,
and for any damage that may occur to such Materials after such delivery, and for any
demurrage charges.
Unless otherwise provided for by the Contract Documents, the Department will direct Utility
Owners to relocate or adjust water lines, gas lines, wire lines, service connections, water and
gas meter boxes, water and gas valve boxes, light standards, cableways, signals, and all other
utility appurtenances within the Project Limits, such work by the Utility Owner being
compensable to the Contractor except as otherwise provide in this Section 7.1.
The Contractor shall cooperate fully with each Utility Owner and make every effort to avoid
delays and conflicts. The Project Schedule shall contain and include all reasonable effort
required to resolve utility conflicts. When Utility Relocations are necessary, coordination and
scheduling of these relocations with the involved Utility Owners shall be the responsibility of the
Contractor.
If required under any Work Package Proposal, the design for all Utility Relocations within the
Project Limits shall be coordinated by the Contractor. The Contractor shall determine and show
on the Plans the names of all existing Utilities within Project Limits. The contractor shall
reference Section 9 (Utilities) of the Technical Requirements for design and coordination
requirements.
If the Contractor is directed by a Utility Owner to perform any work not specifically identified as
Utility Relocation Work within the Contract Documents, the Department will not compensate the
Contractor for this work unless the Department approves the request in writing before the work
begins. If the work is not preapproved by the Department, the Contractor will be responsible for
obtaining reimbursement for its work from the Utility Owner which directed the Contractor to
perform the work.
In the event that the Contractor requests that additional work not specifically contained in
Contract Documents be performed by a Utility Owner, the Contractor will be responsible for
reimbursing the Utility Owner for the additional work unless the Department has agreed in
writing to pay for the additional work before the work begins.
The Contract Documents (including the Utility Agreements) will describe the Utility Relocation
Work and indicate a time frame or date when the Department expects the Utility Owners to
complete Utility Relocation Work. The Contractor shall provide adequate notification to Utility
Owners performing Utility Relocation Work to prevent conflict with the Contractor’s schedule of
operations. The Contractor shall also indicate the various utility items, impacted utilities and
indicate the time frame or date when the Utility Owners are expected to complete Utility
Relocation Work in the Design Documents.
If a Utility Owner fails to perform Utility Relocation Work as provided for in the Contract
Documents or Utility Agreements and the Contractor sustains losses or delays that could not
have been avoided by the judicious design efforts, and reasonable accommodation or by
judicious handling of forces, Equipment, and plant, or by reasonable revisions to the schedule of
operations, then the Department will adjust the Contract according to Section 13 (Time
Extension to the Completion Deadlines and Payment for Excusable Delays) for Critical Path
delay impacts and Section 12.8 (Changes and Extra Work Price Determination). The Contractor
shall be eligible for additional compensation and extension of contract time only if:
A. The Contractor has made every effort to prosecute the Work and mitigate impacts
despite any delays encountered or revisions in the Contractor’s scheduling of Work.
B. The Contractor has made a reasonable effort to design and construct the Work to
reasonably avoid the Utilities.
In accordance with ORC 153.64 for Work performed in Ohio, the Contractor shall notify the
Department, the registered utility protection service, and any Utility Owners that are not
members of the registered utility protection service at least 2 Workdays prior to commencing
construction operations in an area that may affect underground utilities shown on the Plans.
Prior to any excavation activities within Kentucky, the Contractor shall comply with the
requirements for Excavators in the Underground Facility Damage Prevention Act of 1994 which
is contained in KRS 367.4901 through 367.4917.
Utility Owners in Ohio are required under applicable codes and regulations, to start staking,
marking, or otherwise designating the location, course, 2 feet (0.6 m), together with the
approximate depth of Utilities in the construction area within 48 hours after notice is received,
excluding Saturdays, Sundays, and legal holidays.
If the Contractor and the Utility Owner agree that a Betterment will be performed as part of a
Utility Relocation, then:
A. The terms agreed between the Contractor and the Utility Owner for performance of
such Betterment shall be addressed in an amendment to the applicable Utility
Agreement;
B. Such Betterment will be subject to the same standards and requirements as if it were
a necessary Utility Relocation;
C. The Contractor shall undertake such Betterment in accordance with the requirements
for Utility Relocation Work; and
D. If the Betterment is not completed in accordance with the initial Change Order, the
Department shall be entitled to a subsequent Change Order to omit or adjust the
scope of the work and the Contractor’s compensation to suit the Work performed.
7.3 Railroads
The Contractor shall design the Project to keep the scope and extent of railroad conflicts,
interactions, and railroad flagmen needs to a reasonable minimum consistent with the Project
Goals. The Contractor shall proceed with the Construction Work to minimize the scope and
extent of railroad conflicts, interaction, and railroad flagmen needs in accordance with the
Project design. The Contractor shall follow applicable submittal and construction requirements
as outlined Section 10 (Railroads) of the Technical Requirements.
The Contractor shall cooperate fully with each impacted railroad company within the Project
Limits and shall make every effort to avoid delays and conflicts to either the Project or the
railroad company. The Project Schedule shall include all reasonable effort required to resolve
railroad conflicts. In addition, the Project Schedule shall include flagmen notifications activities
for each construction phase, Buildable Unit submittal reviews, and contractual timeframes for
review and comments. In the event that the Contract Documents show different durations for
railroad review, the longest railroad review period within the Contract Documents shall prevail.
The design of the Project shall be performed to maximize distance from railroad loading
influence so to minimize impacts to permanent railroad infrastructure. The Contractor shall
ensure that permanent improvements (i.e. abutments, piers, etc.) are not placed within railroad
right-of-way.
The Contractor shall coordinate all needed railroad design reviews and shall coordinate with the
applicable railroad(s) to determine plan package submissions required for railroad review
including defining limits of railroad regions of concern. In addition, plan package review
submissions shall be developed in the agreed defined limits of railroad regions of concern as
applicable to the impacted railroad. Design packages shall be submitted at interim, final, and
construction unless otherwise agreed with the applicable railroad(s). Submittals shall include all
Work within the applicable railroad region of concern (as agreed with the railroad and
Contractor) and shall not be segmented partial design pieces of an entity but shall be the overall
design phased submission of the entity. Buildable Unit Submittals for railroad review shall not be
defined by types of Work, but shall be determined by the limits of railroad regions of concern.
Construction submittals for track protection, construction erection procedures, and other
construction related submittals which require railroad approval and review shall be submitted
with the construction design submittal to the railroad. These submittals shall be concurrent to
the Department.
The Contractor shall coordinate responses to railroad review comments ensuring adequate and
reasonable responses to all railroad review comments and shall coordinate, with the
Department’s assistance, all identified railroad flagmen needed for construction operations.
If the Contractor is directed by a railroad company to perform work not specifically required by
the Contract Documents or a Railroad Agreement, the Department will not compensate the
Contractor for this work unless the Department approves the request in writing before the work
begins. The Department will not compensate the Contractor if the railroad’s direction is
reasonably and ordinarily expected while considering similar conditions at the same time and
locality.
The Contract Documents will indicate various railroad review time frames for technical
submittals, which the Contractor shall validate with the railroad(s) as part of the Phase 2
Proposal. Upon approval by the Department of the adjusted railroad’s technical submittal review
time, the Contractor shall cooperate with the Department to ensure the revised technical
submittal review times are adopted in the railroad’s updated schedule. The Contractor shall
ensure that the Project Schedule includes all needed railroad interaction timings. The Phase 2
Change Order will include dates when the Department expects the railroad to complete railroad
infrastructure relocation or adjustment, if applicable. The Contractor shall provide adequate
notification consistent with the notification protocols in the applicable railroad’s manual
throughout the Construction Period to railroads who are required to adjust their infrastructure to
prevent conflict with the Contractor’s schedule of operations. The Contractor shall reasonably
adjust its operations if its planned construction efforts conflict with railroad infrastructure
adjustment or relocations. The Contractor shall provide sufficient detail with respect to each
railroad’s infrastructure relocations and show the time frame or date when the railroads are
scheduled to complete their railroad infrastructure relocations or adjustments in the Design
Documents. The Contractor shall provide a complete listing and details of railroad infrastructure
relocations or adjustments required to deliver the Work within the Phase 2 Proposal and any
omissions therefrom shall not be grounds for a Claim.
The Contractor shall consider all past railroad interactions when determining phasing, response
times, and past railroad responses when preparing the Phase 2 Proposal, and shall anticipate
and incorporate sufficient Float in the Project Schedule to accommodate railroad actions which
may include re-submittals of plan review packages.
If any railroad fails to relocate or adjust infrastructure as provided for in the Contract
Documents, or fails to meet reasonable and defined submittal review timeframes, and the
Contractor sustains losses or delays that could not have been avoided by the judicious design
efforts, reasonable accommodation or by judicious handling of forces, Equipment, and plant, or
by reasonable revisions to the schedule of operations, then the Department will adjust the
Contract according to Section 13 (Time Extension to the Completion Deadlines and Payment for
Excusable Delays) for Critical Path delay impacts and Section 12.8 (Changes and Extra Work
Price Determination). The Contractor shall be eligible for additional compensation and extension
of contract time only if:
A. The Contractor has made every effort to prosecute the Work and mitigate impacts
despite any delays encountered or revisions in the Contractor’s scheduling of Work.
B. The Contractor has made every reasonable effort to design and construct the Work to
reasonably avoid the railroad impact.
7.4 Railroad Agreements
The Department has entered into, or is in the process of entering into, Railroad Agreements with
each of the affected railroads which will be included in the Phase 2 Change Order. Technical
coordination shall be handled by the Contractor with notification to the Department.
8 SUBCONTRACTING REQUIREMENTS
8.1 Compliance with Subcontracting Requirements
The Contractor shall comply with all applicable requirements of the Contract Documents relating
to Subcontracts and shall ensure that all Subcontractors and Subconsultants performing Work
on the Project comply with all applicable requirements of the Contract Documents relating to
Subcontracts and subcontracting generally.
The Subcontractor Bidding and Selection Plan shall identify self-performance and
subcontracting percentages and shall separately identify the percentage of the Work that the
Contractor intends to subcontract to Affiliates and the percentage of the Work that the
Contractor intends to subcontract through an arm’s length transaction in which the Contractor
and Affiliates may not bid. The Contractor’s percentage of the total Contract Price includes the
cost of Materials and manufactured products purchased by the Contractor, but not the cost of
Materials and manufactured products purchased by Subcontractors.
The Department will calculate the Contractor’s percentage based on the quantities shown in
each Work Package Proposal and the unit prices of the Contract Items to be performed by the
Contractor’s organization. If the Contractor performs only a portion of a Contract Item, then the
Department will determine the proportional value administratively on the same basis. The
Department will follow this procedure even when the part not subcontracted consists only of the
procurement of Materials. However, if a firm both sells the Materials to the Contractor and
performs the Work of incorporating the Materials into the Project, then the Department will
consider these two phases in combination and as a single subcontract. If an affiliate of the firm
either sells the Materials or performs the Work, the Department may refuse approval. An affiliate
is one who has some common ownership or other close relation to said firm.
The Contractor shall use actual Subcontractor and Subconsultant prices for calculating
compliance with any Disadvantaged Business Enterprise (DBE) percentage subcontracting and
subconsulting obligations. If only a part of a Contract Item is sublet, then determine its
proportional value administratively on the same basis. The Department will follow this procedure
even when the part not sublet consists only of procuring Materials. However, if a firm both sells
the Materials to the Contractor and performs the Work of incorporating the Materials into the
Project, then the Department will consider these two phases in combination and as a single
Subcontract. If an affiliate of the firm either sells the Materials or performs the Work, the
Department may refuse approval.
Subcontracted Work that is not competitively bid will be subject to the pricing process included
in Exhibit G (Pricing Process). In the event that the selected Subcontractor’s bid exceeds the
independent estimate for that subcontract package by more than 10 percent, and the Work
cannot be reconciled to within 10 percent of the independent estimate for that subcontract
package, the Department shall be entitled to require the Contractor, at no additional cost to the
Department, to competitively procure the Work.
The Contractor shall submit any request to substitute a Subcontractor or Subconsultant or any
request for subcontracted Work to be performed by any Person other than the approved
Subcontractor of Subconsultant to the Department by no later than 10 Days prior to the date of
the proposed substitution together with a written statement setting for the reasons for the
proposed substitution. In the event the Subcontractor or Subconsultant that is proposed to be
replaced constitutes a DBE, then the Department must also consent to such substitution of the
DBE Subcontractor or DBE Subconsultant. The Contractor shall submit a termination or
replacement form consistent with the requirements in Exhibit L (Disadvantaged Business
Enterprise (DBE) Performance Plan and Good Faith Efforts) prior to the change occurring and
obtain the Department’s consent before taking any action.
Subject to the Department's approval and the requirements of Section 1.6 (Federal
Requirements), the Contractor shall negotiate price and terms for each Professional Services,
Planning and Pre-construction Work Subcontract that conform to standard industry practice for
work of similar scope and complexity.
6. No Affiliate shall be engaged to perform any Work that would be inconsistent with the
requirements of the Contract Documents or the Standard of Care.
Before entering into a written Subcontract, supplement, or amendment with an Affiliate, the
Contractor shall submit a true and complete copy of the proposed Subcontract to the
Department for Approval with a cover memorandum orienting the Department to all pricing
terms. The Department will have 20 Business Days after receipt to deliver its comments to the
Contractor.
The Contractor shall make no payments to Affiliates for Work in advance of performance
thereof, except for reasonable mobilization payments or other payments consistent with arm's
length, competitive transactions of similar scope. Advance payments in violation of this provision
shall be excluded from the calculation of termination compensation under Section 21
(Termination for Convenience).
1. Each Subcontract of any tier shall include terms substantially similar to the terms in
this Contract to the extent that such terms are relevant to such Subcontract. “Terms
substantially similar” in all instances shall include:
a. Grants of Intellectual Property Rights;
b. Access constraints and requirements pertaining to the Project Site;
c. Maintenance of books and records;
d. Joinder to, obligation to offer evidence in, Dispute Resolution Procedures, if
necessary, in the Department's sole judgment, to resolve a Dispute;
e. Compliance with all Federal Requirements, including the attachment of FHWA
Form 1273 in the exact form as provided in Exhibit N (Contract Provisions for
Federal Aid Construction Contracts); and
f. Non-discrimination provisions as required by Section 9.3.8 (Incorporation of
Provisions).
2. Each Subcontract of any tier shall include a provision that states that the
Subcontractor is not a third-party beneficiary to the PDBC.
3. Each Construction Phase Subcontract of any tier shall:
Further, each Subcontractor, Subconsultant and Supplier shall covenant and agree in their
corresponding Subcontract or supplier agreement to make payment to each lower tier
subcontracting or subconsultant entity or lower tier supplying entity within 10 Days after
Subcontractor’s, Subconsultant’s or Supplier’s receipt of payment from the Contractor for Work
performed or Materials delivered or incorporated into the Project, provided that the Estimate
prepared by the lower tier subcontracting or subconsulting entity or lower tier supplier entity was
incorporated and relied upon by the Subcontractor, Subconsultant or Supplier in its Estimate to
the Contractor for Work performed or Materials delivered or incorporated into the Project. The
Contractor hereby acknowledges and agrees that it shall be prohibited from holding retainage
from Subcontractors, Subconsultants or Suppliers that can provide a Surety Bond. For
unbonded Subcontractors, Subconsultants and Suppliers, the Contractor shall promptly release
any retainage held, as set forth in any Subcontract or supplier agreement, 30 Days after the
Work has met satisfactory completion.
For the purposes of this section, “satisfactory completion” of the Construction Work will be
interpreted as occurring when the applicable Subcontractor has completed all physical work and
submitted any necessary documentation required by the Contract Documents and the
Department and “satisfactory completion” of all other Work will be interpreted as occurring when
the applicable Subcontractor or Subconsultant has completed all Work or the applicable
Supplier has delivered all Materials and, in each case, submitted all necessary documentation
required by the Contract Documents and the Department.. No Subcontract provision shall
permit the Contractor to delay any Subcontractor’s Subconsultant’s or Consultant retainage
payments until the Project’s final payment.
The Contactor further covenants and agrees to require all Subcontractors, Subconsultants and
Suppliers to incorporate the foregoing contractual obligations in each of their respective lower
tier contracts.
and those Subcontractors, Subconsultants and Suppliers who are subject to evaluation by the
Department.
To demonstrate its compliance with Ohio’s prompt payment statute and related provisions,
Contractor hereby covenants and agrees to comply with the reporting requirements set forth in
Exhibit Q (Prompt Payment - ODOT Let Construction Projects).
9 LABOR REQUIREMENTS
9.1 Introduction
The Contractor shall comply with comply with the following Exhibits:
The Contractor, Subcontractor, consultant, Subconsultant, nor any person on their behalf shall,
in any manner, discriminate against or intimidate any employee hired for the performance of
Work under this PDBC on account of race, religion, color, sex, national origin, disability or age.
The Contractor shall comply with OAC-4123:1-3, entitled “Specific Safety Requirements of the
Industrial Commission of Ohio Relating to Construction,” as amended, and with the Federal
Occupational Safety and Health Act of 1970 and Code of Federal Regulations, Title 29, Chapter
XVII, Part 1926 and as amended for work in Ohio.
As provided in KRS Chapter 338 in the Kentucky Occupational Safety and Health Act and in
subsequent regulations and standards promulgated by the Kentucky Occupational Safety and
Health Standards Board, do not require any personnel employed in performance of the
Contract, including employees of Subcontractors, to work in surroundings or under working
conditions that are unsanitary, hazardous, or dangerous to the employee’s health and safety for
Work with the Commonwealth of Kentucky.
The Contractor shall comply with Federal, State, and local laws, rules, and regulations that
prohibit unlawful employment practices including that of discrimination because of race, religion,
color, sex, national origin, disability or age and that define actions required for Affirmative Action
and Disadvantaged Business Enterprise (DBE) programs.
9.3.2 Non-discrimination
The Contractor, with regard to the Work, will not discriminate on the grounds of race, color,
national origin, sex, age, disability, low-income status, or limited English proficiency in the
selection and retention of Subcontractors / Subconsultants, including procurements of Materials
and leases of Equipment. The Contractor will not participate directly or indirectly in the
discrimination prohibited by the Acts and the Regulations as set forth in Section 9.3.6 (Pertinent
Non-discrimination Authorities), including employment practices when the contract covers any
activity, project, or program set forth in Appendix B of 49 CFR Part 21.
A. Withholding payments to the Contractor under the PDBC until the Contractor
complies; and/or
B. Cancelling, terminating, or suspending the PDBC, in whole or in part.
9.3.6 Pertinent Non-Discrimination Authorities
During the performance of the Phase 1 Work, the Contractor, for itself, its assignees, and
successors in interest (hereinafter referred to as the “contractor,” which includes consultants)
agrees to comply with the following non- discrimination statutes and authorities; including but
not limited to:
A. Title VI of the Civil Rights Act of 1964 (42 U.S.C. § 2000d et seq., 78 stat. 252)
(prohibits discrimination on the basis of race, color, national origin); and 49 CFR Part
21.
B. The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970
(42 U.S.C. § 4601) (prohibits unfair treatment of persons displaced or whose property
has been acquired because of Federal or Federal-Aid programs and projects).
C. Federal-Aid Highway Act of 1973 (23 U.S.C. § 324 et seq.) (prohibits discrimination on
the basis of sex).
D. Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. § 794 et seq.), as amended
(prohibits discrimination on the basis of disability) and 49 CFR Part 27.
E. The Age Discrimination Act of 1975, as amended (42 U.S.C. § 6101 et seq.) (prohibits
discrimination on the basis of age).
F. Airport and Airway Improvement Act of 1982 (49 U.S.C. § 471, Section 47123), as
amended (prohibits discrimination based on race, creed, color, national origin, or sex).
G. The Civil Rights Restoration Act of 1987 (PL 100-209) (broadened the scope,
coverage, and applicability of Title VI of the Civil Rights Act of 1964, the Age
Discrimination Act of 1975, and Section 504 of the Rehabilitation Act of 1973, by
expanding the definition of the terms “programs or activities” to include all of the
programs or activities of Federal-Aid recipients, sub-recipients, and contractors,
whether such programs or activities are Federally funded or not).
H. Titles II and III of the Americans with Disabilities Act (42 U.S.C. §§ 12131-12189), as
implemented by Department of Transportation regulations at 49 CFR parts 37 and 38
(prohibits discrimination on the basis of disability in the operation of public entities,
public and private transportation systems, places of public accommodation, and
certain testing entities).
I. The Federal Aviation Administration’s Non-Discrimination Statute (49 U.S.C. § 47123)
(prohibits discrimination on the basis of race, color, national origin, and sex).
J. Executive Order 12898, Federal Actions to Address Environmental Justice in Minority
Populations and Low-Income Populations (ensures non-discrimination against minority
populations by discouraging programs, policies, and activities with disproportionately
high and adverse human health or environmental effects on minority and low-income
populations).
K. Executive Order 13166, Improving Access to Services for People with Limited English
Proficiency, and resulting agency guidance, national origin discrimination includes
discrimination because of limited English proficiency (LEP). To ensure compliance
with Title VI, you must take reasonable steps to ensure that LEP persons have
meaningful access to your programs (70 Fed. Reg. at 74087 to 74100).
L. Title VIII of the Civil Rights Act of 1968 (Fair Housing Act), as amended (prohibits
discrimination in the sale, rental, and financing of dwellings on the basis of race, color,
religion, sex, national origin, disability, or familial status (presence of child under the
age of 18 and pregnant women).
M. Title IX of the Education Amendments Act of 1972, as amended (20 U.S.C. 1681 et
seq.) (prohibits discrimination on the basis of sex in education programs or activities).
N. Uniformed Services Employment and Reemployment Rights Act of 1994 (USERRA 38
U.S.C. 4301-4335) (prohibits discrimination on the basis of present, past or future
military service).
O. Genetic Information Nondiscrimination Act (GINA) (29 CFR Part 1635, 42 U.S.C.
2000ff).
9.3.7 49 CFR Part 26.13(b)
The Contractor agrees not to discriminate on the basis of race, color, national origin, or sex in
the performance of this contract. The Contractor agrees to carry out applicable requirements of
49 CFR Part 26 in the award and administration of DOT-assisted contracts. The Contractor
understands that failure to carry out these requirements is a material breach of this PDBC,
which may result in the termination of this PDBC or such other remedy as the Department
deems appropriate, which may include, but is not limited to: a) Withholding monthly progress
payments; b) Assessing sanctions including any of the following:
A. Letter of reprimand;
B. Contract termination; and/or
C. Other remedies available by law including administrative suspension (consultant
debarred from pursuing additional contracts).
9.3.8 Incorporation of Provisions
The Contractor shall include the provisions of Section 9.3.1 (Compliance with Regulations)
through Section 9.3.7 (49 CFR Part 2613(b)) above in every Subcontract, including
procurements of Materials and leases of Equipment, unless exempt by the Acts, the
Regulations, and directives issued pursuant thereto. The Contractor shall take action with
respect to any subcontract or procurement as the Department or FHWA may direct as a means
of enforcing such provisions including sanctions for noncompliance. Provided, that if the
Contractor becomes involved in, or is threatened with litigation by a Subconsultant, or supplier
because of such direction, the Contractor may request the Department to enter into any
litigation to protect the interests of the Department. In addition, the Contractor may request the
United States to enter into the litigation to protect the interests of the United States.
The Department Authorized Representatives, and the authority and responsibilities of the
Department Authorized Representatives, may from time to time be changed by Notice to the
Contractor from the Department.
Nothing in this Contract shall be construed to bind the Department for acts of any Department
employee or any other Person that exceed the authority delegated to them under this Contract
or in any other written delegation.
The Contractor’s Representative shall act for the Contractor in all matters concerning the Work
and, subject to all requirements of this Contract, shall have the following authority and
obligations:
The Contractor’s Representative may be the same individual or a different individual to the
individual designated as the Contractor‘s 'Project Manager' under the Key Personnel provided
that if the Contractor’s Representative is a different individual to the individual designated as
'Project Manager', the Contractor’s Representative shall be an individual with authority over the
Contractor's designated 'Project Manager'.
The contractor shall be required to use Equipment of sufficient size and mechanical condition to
complete the Project by the Substantial Completion Deadline. In addition, the Contractor shall
ensure that the Equipment does not harm the Roadway, adjacent property, other highways,
workers, or the public.
The Contractor shall determine the design methodologies, construction methods or Equipment
necessary to complete the Work according to the Contract Documents.
A. The Contractor does not furnish sufficient skilled and experienced personnel to
complete the Project by the Substantial Completion Deadline.
B. The Contractor does not remove personnel from the Project as directed in writing by
the Department.
In the event that the Department suspends work under this Section 10.2.1 (Suspension of Work
Due to Character of Workers), the Contractor shall comply with Section 20.3 (Contractor
Responsibilities during Suspension).
The Key Personnel shall receive instructions from the Department and Department Authorized
Representatives. The Key Personnel shall promptly execute the Department’s orders or
directions, promptly perform Work as required, and promptly supply the required Materials,
Equipment, tools, labor, and incidentals.
The Contractor shall notify the Department of any proposed replacement for any Key Personnel
position. The Department shall have the right to review the qualifications and character of each
individual to be appointed to each position and to approve or disapprove use of such individual
in such position before the proposed replacement begins work on the Project. The Department
shall have the right to contact owners and/or sponsors of projects on which the proposed
individual has previously worked to verify work experience and positions held. The Contractor
shall, upon the Department’s request, provide contact information to facilitate this verification.
The Contractor shall ensure and maintain the availability of the proposed replacement.
The Contractor shall provide the Department with office and cell phone numbers and email
addresses for the Key Personnel. The Department shall have the ability to contact any Key
Personnel 24 hours per day, 7 days per week. All Key Personnel shall be immediately
accessible during the duration of their tenure as applicable to the phase of the Project and shall
be reasonably accessible throughout the Term to answer questions as needed.
11 CONTRACTOR’S COMPENSATION
11.1 Compensation for Phase 1 Work
11.1.1 Cost Principles and Limitations
The Contractor’s compensation for Professional Services undertaken in the performance of the
Phase 1 Work shall be computed as the actual paid direct labor rates for the personnel
performing the Phase 1 Work multiplied by the number of hours worked by such personnel
multiplied by the Phase 1 Multiplier Rate.
The Phase 1 Multiplier Rate includes direct labor costs, overtime payments, indirect costs
(overhead), travel, subsistence, non-salary direct costs and facilities capital cost of money.
Other actual and documented costs for the Phase 1 Work will be compensated at actual cost.
The Project Mark-up will be applied to compensation for the Phase 1 Work.
The Contractor’s compensation for the Phase 1 Work is subject to the limitations and exclusions
set forth in the remainder of this Section 11.1 (Compensation for Phase 1 Work).
The Phase 1 Multiplier Rate is subject to the limitations and exclusions set forth in Exhibit G
(Pricing Process) Part 2 (Professional Services Costs).
The Department may make DBE specific work item payments if, in the Department’s judgement,
DBEs performed Work within the invoiced period. DBE work item payments may be made by
the Department regardless of DBE invoice payment requests made by the Contractor and the
requirements of Section 8.10 (Prompt Payment) shall apply.
The Department will return to Contractor any invoices that are incomplete and/or incorrect in
any material respect for correction and resubmittal.
The Contractor shall monitor the Sub-Phase 1A expenditure and track progress of all Sub-
Phase 1A Work, and any adjustments by Change Order to the Maximum Sub-Phase 1A Prime
Compensation, calculated in accordance with Section 12 (Contract Changes).
The Contractor shall monitor the Sub-Phase 1B expenditure and track progress of all Sub-
Phase 1B Work, Project Scope changes and associated adjustments to the Maximum Sub-
Phase 1B Prime Compensation, calculated in accordance with Section 12 (Contract Changes).
The Contractor’s compensation during Sub-Phase 1B may not exceed the Maximum Sub-Phase
1B Prime Compensation approved by the Department,) unless subject to change in accordance
with Section 12.
To qualify as a FAR Participant, the Component Firm must submit an indirect cost rate schedule
(ICRS) compliant with FAR Part 31, applicable Cost Accounting Standards, and related Federal
regulations. The ICRS must be approved by either ODOT's Office of External Audits or KYTC's
External Audit Branch. As evidence of approval, the Component Firm shall provide the project
team an ICRS approval certificate or letter from ODOT or KYTC, as applicable.
FAR Participants shall maintain labor-time records in a manner that will permit, at any time
during the performance of the Phase 1 Work or at the conclusion of the Phase 1 Work, a direct
comparison of estimated labor listed in any Price Proposal that is accepted by the Department
and incorporated into a Sub-Phase 1A Change Order or Sub-Phase 1B Change Order to actual
labor expended. In accordance with FAR Part 31 the FAR Participant bears the burden of proof
to establish the allowability, allocability, and reasonableness of any costs. This applies to all
costs, including costs directly assigned to and the Work and Indirect Costs recovered through
the application of an overhead rate and/or facilities capital cost of money (FCCM) rate.
The Department may conduct interim and final Audits and/or Financial Reviews to determine the
actual, allowable costs incurred during Phase 1. In all cases, the Department will apply the cost
principles and procedures set forth in FAR Part 31, as amended from time to time, and any
other special criteria established in the PDBC. This includes additional Department policies
and/or interpretations of Federal laws and regulations, including the AASHTO Uniform Audit &
Accounting Guide, the State of Ohio Travel Regulations (Ohio Administrative Code Rule 126-1-
02), and/or the KYTC Professional Services Policies and Regulations as applicable.
In compliance with 23 U.S.C. 112(b)(2)(B), all FAR Participants that perform any Professional
Services shall submit indirect cost schedules compliant with FAR Part 31 and related Cost
Accounting Standards. ODOT does not require CPA-audited indirect cost schedules; however, if
a CPA has performed such an audit, it shall be included in the submittal package.
In the event the Department elects to establish a Lump Sum compensation method for Early
Work Packages or the Work Package(s) comprising the Phase 2 Work, such Lump Sum pricing
and compensation method shall be conducted in accordance with this Section 11 and the terms
and conditions of Exhibit G (Pricing Process). Under the Lump Sum compensation method, the
payment by the Department of a Lump Sum item shall be deemed to include complete payment
for the Work described in that item.
In the event the Department elects to establish a Guaranteed Maximum Price (GMP)
compensation method for an Early Work Package or the Work Package(s) comprising the
Phase 2 Work, the amount of the GMP will be established prior to execution of the
corresponding Change Order in accordance with Exhibit G – (Pricing Process) and Section,
each as amended in an addendum to the RFP. The GMP pricing methodology set forth in
Exhibit G – (Pricing Process) will provide for:
The Department will review each proposed current percentage completion and revise the
percentage based on the Department’s judgment of the percent completed or Work performed.
The Department may make DBE specific work item payments if, in the Department’s judgment,
DBEs performed Work within the invoiced period. DBE work item payments may be made by
the Department regardless of DBE invoice payment requests made by the Contractor and the
requirements of Section 8.10 (Prompt Payment) shall apply. The percentage of completion
accepted by the Department, multiplied by the portion of the Contract Price attributable to the
invoiced Item of Work as depicted in the approved Project Schedule, will define the gross
amount of the payment due to the Contractor for that item of Work. Each payment is
approximate, and all partial Estimates and payments are subject to correction after payment by
the Department.
The Department will return to Contractor any invoices that are incomplete and/or incorrect in
any material respect for correction and resubmittal.
Payment for Work and Materials shall not, in any way, prevent later rejection if Nonconforming
Work is discovered, nor shall payment constitute acceptance under Section 5.14 (Completion
Deadlines and Acceptance).
The Department is entitled to withhold payment for any Lump Sum or unit priced item in any
Estimate that is deficient in Material approval.
Except for Estimates generated during Project finalization, the Department will not pay an
Estimate until the Contractor certifies to the Department that the Work for which payment is
being made was performed in accordance with the Contract Documents. Certification shall be
made on forms provided by the Department.
The Department will not pay the adjusted Final Estimate until the Contractor remedies all
Nonconforming Work and accepted Work damaged by the Contractor’s operations.
Interest will be paid in accordance with ORC 126.30 (Interest on Late Payments for Goods and
Services) when warranted.
The Department will pay for the cost of approved Materials before they are incorporated in the
Work when requested by the Contractor, if the Department determines that it is not practical to
deliver the Material to the Project Site and determines that storage off the Project Site is
appropriate. Any payment for Materials manufactured for the Project and stored off the Project
Site shall be conditioned upon compliance by the Contractor with procedures satisfactory to the
Owner to establish the Owner's title to such Materials or otherwise protect the Owner's interest,
and shall include applicable insurance, storage, and transportation to the Project Site. The
Contractor shall also comply with the following specific requirements:
The storage of Materials off-site of the Project Site applies primarily for bulky Materials that are
durable in nature and represent a significant portion of the Project cost as determined by the
Department, such as aggregates, steel, and precast concrete.
The Department will pay for un-fabricated structural steel if the following requirements are met,
in addition to the specific requirements (i-v) above:
A. The Contractor has provided the Department an itemized invoice from the steel mill for
the steel for which reimbursement is requested. For Ohio steel also supply the ODOT
Office of Materials Management a copy of the itemized invoice.
B. Project structural steel design plans are complete with no forthcoming revisions.
Provide Contractor accepted shop drawings per ODOT C&MS 501.04 (Shop
Drawings), or KYTC SS 607.03 as appropriate.
C. Contractor accepted certified test data for all steel in question along with mill shipping
notices have been received by the Department. In Ohio the accepted certified test
data per ODOT C&MS 501.06 (Test Reports) shall be received by Office of Materials
Management. In Kentucky reports shall be per KYTC SS 607.03.13.
D. The steel is properly stored to allow inspection by the Department. It shall also be
properly set apart from other Material and identified as belonging to the Department.
E. The Contractor provides the Department a written statement that in accordance with
the requirements of Section 6 (Control of Materials), the Contractor is responsible for
the steel that has been paid for until the actual steel is erected and accepted in the
field.
Payment shall only be authorized after all the documentation listed above has been received by
the Department and the steel has been inspected by the Department and its Office of Materials
Management to verify that all steel listed in the itemized invoice has been received by the
fabricator and properly stored. The amount to be paid shall be equivalent to the itemized invoice
from the steel mill but shall not exceed 50% of the Contract Item price for the structural steel.
The Department will not pay delivered Materials on small warehouse items or for plant
Materials.
11.2.6 Mobilization
11.2.6.1 Description
Mobilization consists of the preparatory Work and operations including, but not limited to, those
necessary for the movement of personnel, Equipment, supplies, and incidentals to the Project
Site; for the establishment of all field offices, buildings, and other facilities necessary for Work
on the Project; for all other Work and operations that must be performed or costs incurred
before beginning the Work on the other Contract Items; and for demobilization.
11.2.6.2 Limitation
The Lump Sum amount for mobilization shall not exceed the percentage of the Contract Price
set forth in Exhibit G (Pricing Process) Part C.8 (Mobilization).
Cost for Mobilization will be established according to Exhibit G (Pricing Process) by including
the actual estimated Mobilization costs attributed to the elements of Work. These costs will be
included in the CPM Activities for which the Mobilization costs are required.
For pay adjustments based on a unit price/cost, the Contractor shall provide a unit price in the
SOV developed in accordance with Exhibit G (Pricing Process). If unit prices are used as the
basis for any portion of the Contract Price, those unit prices shall be used as the unit price/cost
component when calculating the applicable pay adjustment. For each unit priced item, the pay
adjustment shall be calculated as the difference between the unit price used as the basis for the
Contract Price and the computed adjustment to that amount multiplied by the applicable number
of units.
Pay adjustments will be paid or deducted from payments to the Contractor through the Change
Order process.
Pay adjustments associated with price fluctuation will be made according to the mechanism
shown in Exhibit W (Price Fluctuation Clauses).
The values of disincentives will be developed and agreed between the Parties during Phase 1
and the completed Lane Value Contract tables and processes for assessing disincentives will
be included as part of the Phase 2 Change Order.
12 CONTRACT CHANGES
12.1 Applicability of Section 12 Change Order Process
The following information, obligations, and duties set forth in this Section 12 (Contract Changes)
shall apply only for Construction Work.
This PDBC sets forth additional Change Orders for alternative purposes. Any Change Order
performed for one of the following purposes has its own requirements, procedures, duties,
and/or obligations contained within one of the following Sections of the PDBC.
1. For any Change Order executed for the purpose of modifying the Sub-Phase 1A
Project Scope, the Change Order shall be performed and executed in accordance with
Section 2.3.2.
2. For any Change Order executed for the purpose of progressing the PDBC from Sub-
Phase 1A to Sub-Phase 1B, the Change Order shall be executed in accordance with
Section 2.3.2.1.
3. For any Change Order executed for the purpose of modifying the Sub-Phase 1B
Project Scope, the Change Order shall be executed in accordance with Section 2.3.3.
4. For any Change Order executed for the purpose of authorizing Early Work Packages,
the Change Order shall be executed in accordance with Section 2.3.3.1.
5. For any Change Order executed for the purpose of progressing the PDBC from Sub-
Phase 1B to Phase 2, the Change Order shall be performed and executed in
accordance with Section 2.3.3.2 and Section 2.4.1.
12.2 Changes in the Work
At any time, and without invalidating this PDBC or releasing the surety, the Department
reserves the right to make, in writing, changes, revisions, or alterations in the Work when
necessary to complete the Project satisfactorily. The Contractor shall perform the Work as
revised by the Department.
If the Contractor believes that the Department directed changes, revisions, or alterations in the
Work are material in kind or nature from the Work indicated by the Contract Documents, the
Contractor may request a Change Order prior to performing the specified Work. The
Department will evaluate and determine if the request is warranted and, at its discretion,
process a Contract adjustment by Change Order as described below.
For Contract adjustments that reduce the scope of Work, the cost adjustment for the revised
Work along with the Phase 1 and Phase 2 Markup on the eliminated scope shall be deducted
from the Contract Price.
All changes in the Work shall be requested and authorized before commencing such changes
pursuant to the PDBC changes process set forth in this Article 12.
(2) The amount of the adjustment, if any, in the Contract Price; and
The Change Order document shall be prepared by the Department, after the evaluation and
approval of a validly submitted RCO, and executed by the Contractor. Once executed by the
Contractor, the Change Order will should be presented submitted to the Department to execute
and approve. Upon approval and execution by the Department, the Change Order shall
constitute a Supplemental Agreement to the PDBC and only then a Contract Document shall
become a part of the Contract Documents.
Methods used in determining adjustments to the Contract Price shall include those listed in
Section 12.7 (Changes and Extra Work Price Determination) and Exhibit I (Delay Costs).
Adjustments to the Contract Time, if any, shall be determined as set forth in Section 13 (Time
Extension to the Completion Deadlines and Payment for Excusable Delays) and Exhibit T
(Critical Path Method Progress Schedule). The Contractor shall submit RCOs requesting
changes in Contract Time separately and individually from RCOs requesting a modification in
Contract Price. RCOs requesting a change in the Contract Time and Contract Price stemming
from the same issue, should be considered as companions to one another and referenced as
such in the RCOs. The Department reserves the right to not approve and/or not consider any
RCO that is requesting both an adjustment to the Contract Time and Contract Price in the same
RCO. As set forth in Section 13 (Time Extension to the Completion Deadlines and Payment for
Excusable Delays) and in Exhibit T (Critical Path Method Progress Schedule), in order to
warrant an increase in the Contract Time, the Contractor must demonstrate (i) that the Work
affected by the change is on the Critical Path of the Project Schedule and (ii) materially
adversely impacts the Completion Dates as determined in accordance with Exhibit T (Critical
Path Method Progress Schedule).
The Contractor must provide the Department with a Notice of Potential Change Order (“NPCO”),
in accordance with Section 12.4.1 (Notice of Potential Change Order) and, if warranted a
Request for Change Order (“RCO”) upon becoming aware of any item of Work the Contractor
considers Extra Work as defined in Exhibit A (Acronyms and Definitions) or for any other item
the Contractor believes warrants a Change Order affecting either: the Contract Price or the
Contract Time. Any RC that is not subject to the EDR procedure outlined in Section 13 (Time
Extension to the Completion Deadlines and Payment for Excusable Delays) shall be submitted
within seven (7) days of the Department’s Change Event Mitigation Notice for a Change Event
Mitigation Plan as defined in Section 12.4.1.3 (Change Event Mitigation Plan), if any. Any RCO
that is subject to the EDR procedures outlined in Section 13 must. be submitted within seven (7)
days of the Departments Notice, as set forth in Section 13.4.3 (Excusable Delay Change Order).
The Contractor’s Submission of the RCO shall be considered an absolute condition precedent
to the issuance of a Change Order as a result of any item of Work the Contractor considers
Extra Work as defined in Exhibit A (Acronyms and Definitions) or for any other item the
Contractor believes warrants a Change Order impacting either: the Contract Price or the
Contract Time. Contractor’s failure to provide the RCO within the required seven (7) days of any
of the triggering events set forth herein shall be deemed a waiver by the Contractor to any claim
for a change in the Contract Price or the Contract Time associated with the underlying event
and/or underlying Extra Work associated with the NPCO that is the subject of the triggering
event(s).
The notice(s) in Section 12.4.1 (Notice of Potential Change Order) shall satisfy the initial notice
requirements as set forth in Section 18.2 for the Dispute Resolution procedures.
Notwithstanding, the Department and the Contractor agree that neither party shall pursue the
Dispute Resolution procedures in Section 18.2 (Dispute Resolution) until the Contractor has
either (i) received the Department’s written notice with respect to its decision pertaining to any
RCO or EDR pursuant to Sections 12 and 13, (ii) the Contractor has received the Department’s
decision after successfully mitigating or resolving an event as required under Section 12.4.1.1,
and/or (iii) the Contractor fails to execute a Change Order prepared by the Department or
expressly rejects a proposed Change Order. In no event shall the Dispute Resolution
Procedures begin before one of the events, (i)-(iii) has occurred.
1. the Contractor, shall provide immediate oral notification to the Department containing
sufficient details for the Department to identify the circumstance(s) or event(s)
requiring mitigation or resolution that may result in a change to the Contract
Documents and/or Work.
2. if after two (2) Working Days following the Department’s receipt of the Contractor’s
oral notification in under (1) above, the Department has not mitigated or resolved such
circumstance(s) or event(s) identified by the Contractor, the Contractor shall provide
written notice to the Department containing a sufficient description of the
circumstance(s) or event(s) and a preliminary projection of the potential impacts.
The oral and written notices made under this Section 12.4.1, shall also constitute the notices
required under Section 18.2 (Dispute Resolution).
In the event that the Department is unable to mitigate or resolve the event in accordance with
Section 12.4.1.1 (Department Mitigation/Resolution Before Written Notice) and the Contractor
has issued its written notice as stated in Section 12.4.1 (Notice of Potential Change Order), the
Department shall notify the Contractor that the Contractor may or may not be required to submit
a detailed mitigation action plan to the Department (the “Change Event Mitigation Notice”). If the
Change Event Mitigation Notice states that the Contractor is required to submit a detailed
mitigation action plan, such detailed mitigation action plan shall be submitted within seven (7)
Days of the Contractor’s receipt of the Change Event Mitigation Notice. Such mitigation action
plan shall be in accordance with Section 12.4.1.3 (Change Event Mitigation Plan).
In the event that the Department is able to resolve the circumstance(s) or event(s) before the
receipt of Contractor’s written notice, the Department may instruct the Contractor to do any or all
of the following that may apply:
1. submit a RCO pursuant to Sections 12.4 and 12.4.2 if the resolution and/or mitigation
by the Department requires a modification in the Contract Price that is not caused by
Delay Costs;
2. submit an EDR pursuant to Section 13.4 (Procedure for Requesting Delay Costs and
Completion Deadlines Alterations) requesting a modification to the Contract Time,
alone, in accordance with Section 13.4.1 (Excusable Delay Request); or
3. submit an EDR pursuant to Section 13.4 requesting a modification to the Contract
Time and a modification in the Contract Price that is caused by Delay Costs, in
accordance with Section 13.4.1 (Excusable Delay Request).
In the event that the Department has determined that the conditions or events which are the
subject of the NCPO do not warrant the issuance of a Change Order, the Contractor may elect
to proceed with the Dispute Resolution Procedures pursuant to Section 18.2 (Dispute
Resolution). The notices transmitted pursuant to Section 12.3.1 shall satisfy the notice
requirements necessary to initiate the Dispute Resolution Process set forth in Section 18.2
(Dispute Resolution). The Department may, in its sole discretion, issue a Construction Change
Directive in accordance with Section 12.5 (Construction Change Directive).
1. that Department agrees that a change in the Contract Price may have occurred, in
which case, the Contractor shall prepare an RCO in accordance with this Section 12.4
(Contract Changes) and Section 12.4.2 (RCO Contents); or
2. the Department has: (a) determined that time is of the essence and (b) there is not
ample time to determine if a change in Contract Price or increase in Contract Time
has occurred and/or is warranted, in which case the Department shall proceed under
Section 12.5 (Construction Change Directive) and issues a Construction Chance
Directive; or
3. the Department has determined that the circumstance(s) or event(s) may have
resulted in the need for: (a) a change in the Contract Time with no change in Contract
Price or (b) a change in the Contract Time with a change in the Contract Price due to
delay costs, regardless of whether or not the circumstance(s) or event(s) have
resulted in a change in the Contract Price, not caused by delay cost, in which case,
the Contractor shall submit an Excusable Delay Request in accordance with Section
13.4.1 (Excusable Delay Request); and/or
4. The Department has determined that there has not been a change in the scope of the
Work that warrants a Change Order, in which case, the Contractor may elect to
proceed with the Dispute Resolution Procedures pursuant to Section 18.2 (Dispute
Resolution), which the notices in Section 12.4.1 (Notice of Potential Change Order
(“NPCO”) shall satisfy the notice requirements of Section 18.2 (Dispute Resolution).
12.4.1.3 Change Event Mitigation Plan
If the Department elects to require the Contractor to submit a mitigation action plan in the
Department’s Change Event Notice, the Contractor shall submit such mitigation action plan
pertaining to the conditions or events that are the subject of a NPCO, Contractor’s mitigation
plan shall include the following unless instructed otherwise by the Department:
1. Include full details of the actions that the Contractor proposes to take to avoid,
mitigate, or minimize the consequences of the event and a description of how those
proposed actions will mitigate and/or minimize the effects of the event;
2. Describe any additionally resources, labor, Materials, plant, or Equipment as
applicable, that the Contractor proposes to dedicate to perform each of the proposed
actions to avoid, mitigate, or minimize the consequences of the event, which costs
must be estimated and included in the mitigation plan and may be included in any
RCO requesting a change in the Contract Price due to direct costs or EDR for a
change in the Contract Price if the event is a Category 2 Event;
3. State the time within which the Contractor will implement each of the actions
described in the proposed mitigation plan; and
4. Include any additional information reasonably requested by the Department.
The Contractor shall submit any mitigation action plan within seven (7) days of Change Event
Mitigation Notice. Upon the submission of a mitigation action plan to the Department, in
accordance with this Section 12.4.1.3 (Change Event Mitigation Plan), the Department may
reject in whole or in part the mitigation action plan. In the event the Department does reject in
whole or part of the mitigation action plan, the Contractor shall amend and resubmit the
mitigation action plan (or the part rejected) to the Department within seven (7) Days of receiving
notice of the Department’s rejection of the mitigation action plan.
If the Department accepts in whole or in part a submitted mitigation action plan, in accordance
with this Section 12.4.1.3 (Contract Mitigation Plan), then the Contractor shall act in accordance
with the accepted mitigation plan (or the accepted part of the mitigation action plan, as
applicable) in order to mitigate the effects of the event. In addition, all actions taken by the
Contractor to mitigate the effects of the event and the progress of those actions shall be
documented by the Contractor.
In the event that the Department has not responded to a submitted mitigation action plan (or a
part of it), in accordance with this Section 12.4.1.3 (Contract Mitigation Plan), within seven (7)
Days of receipt, the mitigation action plan (or part of it) shall be deemed accepted by the
Department, and the Contractor should act in accordance with Contractor’s proposed Change
Event Mitigation Plan.
1. the scope of work which describes in detail all additional or changed (or both) activities
to be authorized by a subsequent Change Order;
2. an initial cost estimate by utilizing the information and formulas specified in Section
12.8 (Changes and Extra Work Price Determination), Exhibit H (Force Account
Provisions), and Exhibit I (Delay Costs), as may be applicable, to calculate any
potential cost changes or the Detailed Cost Analysis submitted in conjunction with an
EDR request as described in Section 13.4.1.1 (Detailed Cost Analysis), if applicable;
3. an impact analysis to all Baseline Schedules affected, indicating in such analysis all
activities affected by the change, with activity numbers, durations, predecessor and
successor activities, resources, and cost, and a narrative report, if the RCO pertains to
changes in Contract Time or Contract Price caused by delay costs, which shall only be
applicable for an RCO as a result of the EDR process in Section 13.4 (Procedure for
Requesting Delay Costs and Completion Deadlines Alterations);
4. the approximate number of Days that the delay to the Critical Path of the affected
Baseline Schedule(s) was adversely impacted utilizing Exhibit T (Critical Path Method
Progress Schedule) and Section 13.4.2 (Excusable Delay Notice Analysis and
Measurement), if the RCO pertains to changes in Contract Time or Contract Price
caused by delay costs, which shall only be applicable for an RCO as a result of the
EDR process in Section 13.4 (Procedure for Requesting Delay Costs and Completion
Deadlines Alterations); and/or
5. any other supporting documentation that may be helpful or requested by the
Department.
12.4.3 Department Receipt and Procedure for RCOs
Upon the receipt of any RCO that has been submitted in accordance with Section 12 (Contract
Changes) and/or Section 13 (Time Extension To The Completion Deadlines and Payment For
Excusable Delay), except for an RCO as a result of Section 12.4.4 (Procedure for Department
Initiated RCOs), the Department shall immediately notify the Contractor of its receipt of the
RCO. After providing the Contractor notice of the Department’s receipt, the Department shall
have seven (7) Days to consider and review the RCO. On the seventh (7th) Day after the
submittal of the RCO, the Department shall notify the Contractor the Department’s acceptance
or rejection of the RCO.
If the Department notifies to the Contractor that the Department has rejected the RCO, the
Department must include a description of the basis as to its rejection. Further, upon receipt of
the notice of the rejection of the RCO, the Contractor may elect to proceed with the Dispute
Resolution Procedures pursuant to Section 18.2 (Dispute Resolution) The notices transmitted
pursuant to Section 12.3.1 shall satisfy the notice requirements of Section 18.2 (Dispute
Resolution).The Department may issue a Construction Change Directive in accordance with
Section 12.5 (Construction Change Directive).
The Contractor's signature on a Change Order shall constitute a full, final, and complete waiver
and settlement of any and all claims, demands, and causes of action that Contractor has, or
may have in the future, arising out of or relating to the Change Order and the occurrences, acts,
omissions, or events upon which the Change Order is based. No "reservation of rights" or other
attempt by Contractor to preserve, notwithstanding Contractor's signature on the Change Order,
present or future claims arising out of or relating to the Change Order (or arising out of or
relating to the cumulative effect of the Change Order in combination with other change orders)
shall be effective unless Owner and Contractor shall both agree, in a separate writing signed by
both parties contemporaneously with Contractor's execution of the Change Order, to the
specific terms, conditions, scope, and duration of such reservation of rights.
12. Any situations which, while not within one of the categories delineated above, were or
should have been reasonably anticipated by the Contractor based on the Contract
Documents or the nature of the Work.
The Contractor hereby assumes responsibility for all such matters and acknowledges and
agrees that assumption by the Contractor of responsibility for such costs and delays, and the
consequences and costs resulting therefrom, is reasonable under the circumstances of the
Contract and that whatever contingencies the Contractor included in the Contract Price or
Project Schedule constitute sufficient consideration for its acceptance and assumption of
Contractor’s risks and responsibilities as set forth herein.
Contractor shall remove or otherwise revise any Work, if not in compliance with the Contract
Documents, at the Contractor's sole cost and expense.
shall be required to track the performance of the work to be performed under the Construction
Change Directive pursuant to the force account procedures set forth in Section 12.8.2 (Force
Account) until the impacts of the Construction Change Directive are known and the procedures
and process outlined in Section 12.8.1 (Negotiated Prices) occur.
If the Department and Contractor reach an agreement regarding (1) a change in Contract Price,
if any, and/or (2) a change in Completion Dates, if any, the Contractor shall proceed to submit
an RCO in accordance with Sections 12.4 (Change Orders) and 12.4.2 (RCO Contents) and/or
an EDR in accordance with Section 13.4.1 (Excusable Delay Request); provided however, if the
Department and Contractor cannot reach an agreement regarding: a change in Contract Price
or Contract Time then the Contractor may elect to proceed with the Dispute Resolution
Procedures set forth under Section 18.2 (Dispute Resolution).
Notwithstanding anything to the contrary contained herein, any failure by the Contractor to
perform the work specified under a Construction Change Directive shall constitute a Contractor
Default under this PDBC.
Upon receipt of the Contractor’s notice, the Department will investigate the claimed potential
Differing Site Conditions. The Department will determine if Differing Site Conditions have been
encountered and notify the Contractor of the Department’s determination.
Differing site conditions are described in Section 12.7.1.3 and Section 12.7.1.4. A request for
alteration to the Contract Price/Completion Deadlines due to a Differing Site Condition as
provided in this Section 12.7.1 (Differing Site Conditions) shall be made according to the
following procedure:
1. The Department and Contractor shall comply with Section 12.7.1.1 (General
Obligation of Notice by Contractor and Department Investigation);
2. in the event that the Department determines that the Differing Site Condition (s) exists
and the Contractor believes that an adjustment in the Contract Price, due to an
increase in direct costs, the Contractor shall submit an RCO in accordance with
Section 12.4 (Change Orders) meeting the requirements listed therein; and/or
3. in the event that the Department determines that the Differing Site Condition (s) exists
and the Contractor believes that it may be entitled to an adjusted Completion Deadline
due to delays caused by the Differing Site Condition and/or additional compensation
due to Delay Costs arising from the Differing Site Condition, the Contractor may
submit an Excusable Delay Request in accordance with Section 13.4.1 (Excusable
Delay Request).
A. Subsurface or latent physical conditions at the site differing materially from those
indicated in the Contract Documents or reasonably inferred therefrom and are not
reasonably discoverable from an investigation and analysis of the site by the
Contractor meeting its Standard of Care obligations for such an investigation and
analysis, as set forth in the Contract Documents;
B. Unknown physical conditions of an unusual nature differing materially from those
ordinarily encountered and generally recognized as inherent in the Work provided for
in the Contract Documents, are encountered at the site;
C. Unknown physical conditions which are rare for the Project area and type of Project;
and
D. Unknown physical conditions which are not reasonably evident during the design by
inspection, or investigations which were performed during the design, or reasonably
should have been performed by the Contractor fulfilling its Standard of Care
obligations as set forth in the Contract Documents during or before the final design
process.
12.7.1.4 Unique Differing Site Conditions
The following are Unique Differing Site Conditions:
(1) The subsurface conditions are materially different from conditions generally recognized
as inherent in the nature of the Work in the area of the site of the Work and such
conditions adversely impact Contract Price or Contract Time to complete the Work within
the Completion Deadlines as set forth in the Contract Documents;
(2) The subsurface conditions were not reasonably discoverable by the Contractor from a
reasonable investigation and analysis of the site, including subsurface conditions, by the
Contractor in fulfilling its obligations pursuant to the Standard of Care under the Contract
Documents hereunder prior to submittal of the Contract Price Proposal; and
(3) The subsurface conditions were actually unknown to the Contractor and the Contractor -
Related Entities.
12.7.1.4.2 Historic and Archaeological Materials
If the Contractor discovers any object of potential archaeological, paleontological, or other
historic interest, all Work that could disturb said object shall immediately cease and shall not be
resumed until an investigation of the object and related deposits have been completed and
removal of articles of interest has been accomplished. Should such a deposit be discovered, the
Contractor shall notify the Department immediately upon Contractor’s discovery.
The Contractor shall be entitled to submit an RCO for an adjustment to the Contract Price
and/or an EDR for an adjustment to the Contract Time relating to differing site conditions due to
historic and archaeological materials only if all of the following conditions exist:
(1) The locations of the subsurface conditions were not described in any documents
containing indications of subsurface conditions or site conditions provided to the
Contractor;
(2) The subsurface conditions were not discoverable from a reasonable investigation and
analysis of the site by the Contractor in performing its obligations pursuant to the
Standard of Care required under the Contract Documents, including subsurface
conditions, prior to submittal of the Contract Price Proposal; and
(3) The subsurface conditions were actually unknown to the Contractor and the Contractor-
Related Entities and such conditions adversely impact the Cost or time to complete the
Work as set forth in the Contract Documents.
If the alterations or changes in quantities significantly change the character of the Work under
the PDBC, whether such alterations or changes are in themselves significant changes to the
character of the Work or by affecting other Work cause such other Work to become significantly
different in character, an adjustment, excluding anticipated profit, will be made to the PDBC
pursuant to the process set forth in Section 12.7.2.1 (Procedure for Requesting Contract
Price/Completion Deadlines Alterations).
If the alterations or changes in quantities do not significantly change the character of the Work
to be performed under the contract, the altered Work will be paid for as provided elsewhere in
the contract.
The term “Significant Change” shall be construed to apply only to the following circumstances:
A. When the character of the Work as altered differs materially in kind or nature from that
involved or included in the original proposed construction; or
B. When the product of the quantity in excess of the estimated quantity of a contract item
and the unit price is increased in excess of 125 percent or decreased below 75
percent of the original Contract quantity. Any allowance for an increase in quantity
shall apply only to that portion in excess of 125 percent of original contract item
quantity, or in case of a decrease below 75 percent, to the actual amount of work
performed.
12.7.2.1 Procedure for Requesting Contract Price/Completion Deadlines
Alterations
A request for alteration to the Contract Price/Completion Deadlines due to a Significant Change
in the character of work as provided in this Section 12.7.2 (Significant Change in the Character
of the Work) shall be made by the Contractor notifying the Department of the significant change
in the character of work set forth in this Section 12.7.2 in accordance with Section 12.4.1 (Notice
of Potential Change Order). Any change in the Contract Price or Contract Time shall occur as a
result of the procedures and processes stated in Section 12 (Contract Changes) and/or Section
13 (Time Extension To The Completion Deadlines And Payment For Excusable Delays). Any
change in the Contract Price or Contract Time shall occur as a result of the procedures and
processes stated in Section 12 (Contract Changes) and/or Section 13 (Time Extension To The
Completion Deadlines) and ;
1. Upon receipt of the Contractor’s notice, the Department shall investigate the claimed
significant change in the character of work and the Department shall determine
whether there has been a significant change in the character of work;
2. If the Department determines a material change in the character of the work did occur,
then the Department shall notify the Contractor of the Department’s determination;
3. In the event that the Department determines that a significant change in the character
of work occurred and the Contractor believes that an adjustment in the Contract Price,
due to an increase in direct costs, the Contractor shall submit an RCO in accordance
with Section 12.4 (Change Orders) meeting the requirements listed therein; and/or
4. In the event that the Department determines that a significant change in the character
of work occurred and the Contractor believes that it may be entitled to an adjusted
Completion Deadline due to delays caused by the significant change in the character
of work and/or additional compensation due to Delay Costs arising from the significant
change in the character of work, the Contractor shall submit an Excusable Delay
Request in accordance with Section 13.4.1 (Excusable Delay Request).
In the event that the Department and Contractor do not agree on the adjustment in the Contract
Price or Contract Time pursuant to Section 12.6.2.1 (Procedure for Requesting Contract
Price/Completion Deadlines Alterations) and subsequently Section 12 (Contract Changes)
and/or Section 13 (Time Extension To The Completion Deadlines And Payment For Excusable
Delays), the Department and/or the Contractor may elect to proceed with the dispute resolutions
procedures in accordance with Section 18.3.2 (Dispute Resolution).
the Contract Price or Contract Time such that the Project Schedule and Completion Deadlines
are impacted, Contractor shall notify the Department as specified in 12.4.1 (Notice of Possible
Change Order).
1. After receipt of the Contractor’s notice, the Department shall investigate the claimed
unreasonable suspension in work, and the Department shall determine whether there
has been an unreasonable suspension in work, which shall require the Department to
agree that the cost or time required for the performance of the Work has increased as
a result of such suspension and the suspension was caused by conditions beyond the
control of and not the fault of the Contractor, its suppliers, Subconsultant, or
Subcontractors at any approved tier, and not caused by Weather;
2. If the Department determines an unreasonable suspension of work did occur, then the
Department shall notify the Contractor of the Department’s determination;
3. In the event that the Department determines that an unreasonable suspension in work
occurred and the Contractor believes that an adjustment in the Contract Price, due to
an increase in direct costs, the Contractor shall submit an RCO in accordance with
Section 12.4 (Change Orders) meeting the requirements listed therein; and/or
4. In the event that the Department determines that an unreasonable suspension of work
occurred and the Contractor believes that it may be entitled to an adjusted Completion
Deadline due to delays caused by the unreasonable suspension in work and/or
additional compensation due to Delay Costs arising from the unreasonable
suspension of work, the Contractor shall submit an Excusable Delay Request in
accordance with Section 13.4.1 (Excusable Delay Request).
In the event that the Department and Contractor do not agree on the adjustment in the Contract
Price or Contract Time pursuant to Section 12.7.3.1 (Procedure for Requesting Contract
Price/Completion Deadlines Alterations) and subsequently Section 12 (Contract Changes)
and/or Section 13 (Time Extension To The Completion Deadlines And Payment For Excusable
Delays), the Department and/or the Contractor may elect to proceed with the dispute resolutions
procedures in accordance with Section 18.3.2 (Dispute Resolution).
If the Department negotiates with the Contractor but does not agree on a price adjustment, the
Department may direct the Contractor to perform all or part of the revised Work under Exhibit H
(Force Account )
When submitting the written proposal and estimated costs for revised Work or Extra Work
performed under force account provisions, the Contractor shall not be permitted to apply the
Phase Mark-Up to such estimated costs as mark-up for such revised Work or Extra Work shall
be determined in accordance with Exhibit H.
If Department directed Changes in Material result in cost savings due to a specification change,
such cost savings shall be credited to the Project by a Lump Sum adjustment to the reference
including a 15 percent markup if the originally specified Material has not been ordered. If the
Material had been ordered before the Contractor was informed of the change, the savings
markup allowed is 2.5 percent, in order to exclude profit on the original bid price ad pay only for
incurred overhead.
Such recovery schedule shall be created by the Contractor in accordance with Section 1.9(B)
and (C) of Exhibit T and shall be evaluated in accordance with Section 1.9(D) of Exhibit T.
In any event, the Contractor shall provide additional labor, Equipment, and/or Materials, work
additional shifts, and/or expedite procurement to complete the Work within the Completion
Deadlines at no additional cost to the Department.
12.8.6 Inefficiency
The Department will compensate the Contractor for inefficiency or loss of productivity resulting
from Change Orders pursuant to Section 12.4 (Change Orders), Changes and Extra Work
resulting from Section 12.8 (Changes and Extra Work Price Determination), and revisions to the
Contract occurring under Section 12.7 (Revisions to the Contract Documents).
The Department shall use the following calculation for the Measured Mile analysis:
Additional Crew Hours = (Unit Productivity Unimpacted Period - Unit Productivity Impacted
Period)/Unit Productivity Unimpacted Period x (Number of Units During Impacted Period/Unit
Productivity Impacted Period).
F. Delays due to local, state, or federally mandated quarantine restriction occurring within
the Site.
G. Delays due to civil disturbances.
H. Delays from epidemics.
I. Delays from labor strikes that are beyond the Contractor’s, Subcontractor’s, or a
Supplier’s power to settle and are not caused by improper acts or omissions of the
Contractor, Subcontractor, or a Supplier.
J. Added quantities that delay an activity on the Critical Path.
K. All other delays not the Department’s fault or responsibility, including but not limited to
a Force Majeure event as descried in Section 14 (Force Majeure Events).
13.2.2 Category 2 Events – Excusable, Compensable Delays
Category 2 Events are events that cause delays in the completion of Work on the Critical Path
that adversely impact the Completion Deadlines that are excusable and compensable that are:
(i) not the Contractor’s fault or responsibility, (ii) the Department’s fault or responsibility or (iii)
otherwise determined by judicial proceeding to be the Department’s sole responsibility or are
the fault and responsibility of a Government Entity and are listed in this Section 13.2.2, 1-9
below. Any event that is not listed in such sections shall be considered for all purposes, a
Category 1 Event. The Department will extend the Completion Deadlines with respect to a
Category 2 Event if the procedure specified in Section 13.4 (Procedure for Requesting Delay
Costs and Completion Deadlines Alteration) is met. The following are defined as Category 2
Events.
1. Delays due to revised Work as specified in Section 12.7.1 (Differing Site Conditions),
Section 12.7.2 (Significant Change in the Character of Work), or Extra Work.
2. Delays due to interference or failure by Utility owners to relocate or adjust facilities as
specified in Section 7 (Utilities and Railroads) within the Project Limits.
3. Delays due to railroad interference within the Project Limits or failure by a railroad to
adhere to the requirements of a Railroad Agreement as specified in Section 7.
4. Delays due to a Department-ordered suspension as specified in Section 12.7.3
(Unreasonable Suspension of Work).
5. Delays due to the failure by the Department to furnish the Project ROW in accordance
with the schedule for parcel availability included in the Phase 2 Change Order as
specified in Section 5.8 (Furnishing Right-of-Way).
6. Delays due to the discovery within or adjacent to the Project Site of Unknown
Regulated Materials.
7. Delays due to the discovery within or adjacent to the Project Site of a Threatened or
Endangered Species.
8. Delays due to acts of the government or a political subdivision other than the
Department.
9. Delays due to the neglect of the Department or its failure to act in a timely manner.
With respect to Category 1 Events where the Contractor is excused from performance for a
period of time and/or afforded additional time for performance, delays are measured as direct
delays to the Critical Path on the affected Baseline Schedule that impacts the Completion
Deadlines as determined in accordance with Section 13 (Time Extension to the Completion
Deadlines and Payment for Excusable Delays) and Exhibit T (Critical Path Method Progress
Schedule).
With respect to Category 2 Events for which the Contractor is excused from performance for a
period of time and/or afforded additional time for performance and granted an increase in
Contract Price, the amount of the additional compensation shall be based upon the Detailed
Cost Analysis set forth in Section 13.4.1.1 (Detailed Cost Analysis).
Without limiting the Contractor’s general duty of mitigation, Excusable Delay Events shall be
limited to the extent that the adverse effects of the Excusable Delay Events could have been
avoided by the exercise of caution, due diligence, or reasonable efforts by the Contractor or any
Contractor-Related Entity acting in accordance with the Standard of Care in all circumstances to
the extent possible. Furthermore, the mitigation of any delay, whether caused by the
Department, Contractor, third-party or an intervening event, is a shared obligation of the
Contractor pursuant to the Contract Documents. Contractor’s mitigation efforts include, but are
not limited to, re-sequencing work activities, redesigning efforts, acceleration, and continuation
of work through an otherwise planned shutdown period. The Contractor and Department must
address and develop potential mitigation efforts in a timely manner.
If the Contractor seeks relief for any costs that are covered by insurance required to be placed
under this Contract, then the Contractor shall only be entitled to seek adjustments to the
Baseline Project Schedule and not to any increase in the Contract Price; provided, however,
that nothing in this Section 13.3 (Limitations on Excusable Delays) shall be construed to
preclude the Contractor's recourse to any insurance policy or coverages.
documentation related to the occurrence of an Excusable Delay Event (the “Excusable Delay
Request”), to the Department within fourteen (14) Days following the Department’s issuance of
the Change Event Mitigation Notice in Section 12.4.1.3 event giving rise to the request, or in the
event of a delay caused by weather within fourteen (14) days of the Department’s confirmation
of the Contractor’s eligibility for a change in the Contract Time in accordance with Exhibit T
(Critical Path Method Progress Schedule), and such notice shall be accompanied by supporting
analysis, including a time analysis in accordance with Exhibit T, and documentation related to
the occurrence of an Excusable Delay Event, (the “Excusable Delay Request”). In the event the
Contractor contends believes that the Excusable Delay Event is a Category 2 Event under
Section 13.2.2 (Category 2 Events – Excusable Compensable Delays), the Contractor shall
submit a detailed cost analysis of the requested additional compensation (the “Detailed Cost
Analysis”) as a part of the Excusable Delay Request for applicable delay costs outlined in
Exhibit I (Delay Costs). The Excusable Delay Request shall only be considered by the
Department provided the Contractor initiated the performed all required actions as requires as
set forth under in Section 12.4.1 (Notice of Potential Change Order) and its subsections. If the
notice(s) required under Section 12.4.1 (Notice of Potential Change Order) are not properly
completed and submitted to the Department, the Department is under no obligation to consider
any Excusable Delay Request. The Department may, but is not obligated to, consider any EDR
submitted outside of the fourteen (14) Day timeframes listed above.
Any compensation that the Contractor may be entitled to will be calculated in accordance with
Exhibit I (Delay Costs).
1. The Department will not grant an extension of time for delays incurred from December
1 to April 30 for Construction Work unless the Contractor’s Baseline Schedule depicts
Work on the Critical Path occurring during this period.
2. The Contractor’s plea that insufficient time was specified is not a valid reason for an
extension of time.
3. The Department will relieve the Contractor from associated liquidated damages, as
specified in Section 13.7.1.1 (Liquidated Damages), if the Department extends the
Completion Deadlines under this Section 13.4 (Procedure for Requesting Delay Costs
and Completion Deadlines Alterations).
13.4.3 Department Notice
After the Department conducts its analysis in Section 13.4.2 (Excusable Delay Notice Analysis
and Measurement) the Department shall inform the Contractor within 30 Days of the
Department’s Decision in writing (the “Department Notice”). In the event that the Department
determines that the Excusable Delay Event should result in an extension to the Completion
Deadlines for the entire Project and/or the Completion Deadlines for an individual Work
Package or an increase in the Contract Price, the Department Notice shall instruct the
Contractor to submit an RCO requesting a change to the Contract Time and, if applicable, an
RCO requesting a change in Contract Price, as a result of delay costs. The Contractor must
then submit any RCO recommended in the Department Notice within seven (7) Days of receipt
of the Department Notice, in order to process any adjustment(s) based upon the Excusable
Delay Event. Any adjustment to any Completion Deadlines as a result of an Excusable Delay
Change Order, shall then have the same standing and effect as though it was the original
Completion Deadlines. The Contractor RCO required by this section shall meet all requirements
of Section 12.4 (Change Orders). To the extent required, the Contractor shall be able to
repackage and/or organize the Department’s Notice and/or Department’s Decision and the
Contractor’s EDR to meet the requirements of Section 12.4 (Change Orders).
If the Contractor fails to deliver the RCO specified in Section 12.4 (Change Orders) above within
such seven (7) Days of the required period set forth herein, the Contractor shall have
irrevocably and forever waived and released any claim or right to relief for the adverse effect
attributable to the Excusable Delay Event occurring before the date of actual delivery of an
Excusable Delay Request.
In the event the Department has determined that the Excusable Delay Event does not warrant a
Change Order, the Contractor may elect to proceed with the Dispute Resolution Procedures
pursuant to Section 18.2 (Dispute Resolution), in which case the notices in Section 12.3.1 shall
satisfy the notice requirements of Section 18.2 (Dispute Resolution). The Department may
proceed to issue a Construction Change Directive in accordance with Section 12.5
(Construction Change Directive).
In the event the Department permits the Contractor to continue the Work beyond the
Completion Deadlines, the Department will pay the Contractor for all Work performed on the
Project less any Liquidated Damages as described in Section 13.7.1.1 (Liquidated Damages).
The Department’s decision to permit the Contractor to continue and complete the Work or any
part of the Work after the Completion Deadlines, or after extensions to the Completion
Deadlines, will in no way operate as a waiver on the part of the Department of any of its rights
and remedies under the PDBC.
The Contractor further acknowledges and agrees that the damages sustained by the
Department in the event that Contractor fails to complete the Work by the Completion Deadlines
are and will be impracticable or extremely difficult to ascertain, due to the circumstances
existing as of the date of execution and delivery of this PDBC. Thus, damages arising out of the
failure by the Contractor to complete the Work by the Completion Deadlines may arise from or
include:
The Liquidated Damages payable under this Section 13.7.1.1 (Liquidated Damages) will be
payable for each Day the Completion Date exceeds the Substantial Completion Deadline,
subject to Section 13.7.
The Department may deduct the sum of Liquidated Damages from any progress payments due
to the Contractor for the performance of the Work as a result of these losses and damages as
liquidated damages. In the event that the progress payments due to the Contractor are
insufficient, the Contractor or its Surety shall pay to Department any deficiency.
The Contractor understands and agrees that any Liquidated Damages imposed on the
Contractor are not a penalty and that such sums are reasonable under the circumstances
existing as of the date of execution and delivery of this PDBC. The Contractor further
acknowledges and agrees that Liquidated Damages may be owing even though no Contractor
Default, as specified in Section 19.1.1, has occurred.
The accrual of Liquidated Damages will terminate upon the Department’s notification to the
Contractor of Substantial Completion of the Work.
The fact that the Department has agreed to accept the Liquidated Damages as compensation
for its damages associated for the Work not being completed by the Completion Deadlines shall
not preclude the Department from exercising its other rights and remedies with respect other
delays to the Critical Path in the prosecution of the Work.
The Department will adjust the Completion Deadlines or other contractually mandated dates for
delays specified in Section 13.2.1 (Category 1 Events – Excusable, Non-Compensable Delays)
and Section 13.2.2 (Category 2 Events – Excusable, Compensable Delays).
The Contractor must submit the petition to suspend the assessment of liquidated damages in
writing within thirty (30) Days of the assessment of the liquidated damages. This request to
suspend the assessment of liquidated damages must be made subsequent to the delivery of the
Continued Work Plan. The request must also include at a minimum, the Work left to be
completed, the reason(s) the Work is incomplete or on hold, as well as, methods, resources and
timelines for pursuing the same. This request must also explain in detail how the Contractor
intends to diligently pursue the completion of the Work in order to be accepted by the
Department.
1. The Contractor is diligently pursuing the remaining Work, as specified in the petition.
2. Necessary items are completed and operational to provide an appropriate level of
safety to the traveling public. These items include but are not limited to: signs,
pavement markings, guardrail, attenuators, signals and RPM’s.
If the Contractor asserts Force Majeure as an excuse for failure to perform its obligations, then
the Contractor must establish that it initiated reasonable and prudent actions to minimize the
delay or damages caused by the foreseeable events flowing from the Force Majeure event,
substantially fulfilled all non-excused obligations, and that the Department was timely notified of
the likelihood or actual occurrence of the Force Majeure event.
In the event of a Force Majeure event, the Contractor shall be entitled only to an extension of
the Contract Time associated with the Force Majeure event and not to any adjustment of the
Contract Price, as Force Majeure events are classified as Category 1 Events as described in
Section 13.2.1 (Category 1 Events – Excusable Non-Compensable Delays). Section 13 (Time
Extension to the Completion Deadlines and Payment for Excusable Delays) sets forth the terms
and conditions applicable to Contractor’s request for an extension of Contract Time associated
with a Force Majeure event.
The Contractor shall not be entitled to an adjustment in Contract Price or Contract Time for
delays associated with a Force Majeure event within the control of the Contractor. Delays
attributable to and within the control of a Subcontractor or Supplier shall be deemed to be
delays within the control of the Contractor.
Notwithstanding the foregoing, the lack of financial resources or any other financial condition
affecting Contractor shall not constitute a Force Majeure Event.
15 WEATHER
The Contractor shall not be entitled to an extension of time or additional compensation and the
Department will not allow any extension of time for weather or resulting conditions beyond those
specifically set forth herein in this Section 15 (Weather).
A Weather Day is “a Workday during which weather or seasonal conditions reduced production
by more than 50 percent on items of work on the Critical Path.”
If the Contractor believes that it has suffered from Weather Days in excess of the table found in
Section 1.4.1(E)(3)(v) of Exhibit T (Critical Path Method Progress Schedule), resulting in a need
for a potential change in the Contract Time, then the Contractor shall provide notice, in
accordance with Section 12.4.1 (Notice of Potential Change Order), to the Department of the
potential need for a change in the Contract Time as a result of weather. After providing written
notice in accordance with Section 12.4.1, the Contractor shall perform an analysis to determine
the schedule impacts due to weather per Exhibit T. The Contractor shall then proceed with the
procedures outlined in Exhibit T and submit the necessary schedules in accordance with
Section 1.8(C) of Exhibit T.
The Department will then review the timely submissions by the Contractor required by Section
1.8(C) of Exhibit T in accordance with Section 1.8(D) of Exhibit T.
In the event that the Department determines and confirms the Contractor is eligible for a change
to the Contract Time, in accordance with Exhibit T, then the Contractor shall submit an
Excusable Delay Request (EDR) and comply with the procedures outlined in Section 13 (Time
Extension to the Completion Deadlines and Payment for Excusable Delays).
In the event that the Department disputes the Contractor’s eligibility for a change in the Contract
Time, the Contractor may then elect to proceed with Dispute Resolution Procedures set forth
under Section 18.2 (Dispute Resolution).
Lane closures within the Project which are 30 days or less that are shown as part of an
accepted MOT Plan in the Contract Documents, and which are impacted by weather will be
extended for the actual Workdays lost each month. Lane closures within the Project, 31 Days or
longer that are shown as part of an accepted MOT Plan in the Contract Documents, which are
impacted by weather will be extended per Exhibit T.
The Department will not consider weekends and holidays as lost Workdays unless the
Contractor normally works those days as set forth in the Baseline Schedule or unless the
Department directs the Contractor to work those days.
Delays to the Completion Deadlines for Design Work attributable to Weather or seasonal
conditions shall not be considered as permitted.
16 INDEMNITY
16.1 Indemnifications by Contractor
16.1.1 General Provisions
The Contractor shall release, defend, indemnify and hold harmless the State of Ohio, the State
of Kentucky and its representatives, the Department, the Department’s consultants, the
Department’s attorneys, and all their respective officers, agents, and employees, their
successors and assigns, and their respective board members, council members, officers,
directors, agents and employees (collectively referred to as the "Indemnified Parties") from and
against any and all claims, causes of action, suits, judgments, investigations, legal or
administrative proceedings, and losses incurred in connection with the enforcement of this
indemnity, arising out of, relating to or resulting from the following, (each an "Indemnified
Claim"):
(1) The breach or alleged breach of any of the Contract Documents by any Contractor-
Related entity; and/or
(2) The failure or alleged failure by any Contractor-Related Entity to comply with the
governmental approvals, any applicable environmental laws or other governmental
rules (including governmental rules regarding Regulated Materials Management);
and/or
(3) Any actual or alleged patent or copyright infringement or other allegedly improper
appropriation or use of trade secrets, patents, proprietary information, know-how,
copyright rights or inventions in performance of the Work, or arising out of any use in
connection with the Project of methods, processes, designs, information, or other
items furnished or communicated to the Department or another Indemnified Party
pursuant to the Contract; provided that this indemnity shall not apply to any
infringement directly resulting from a method, process or design specifically required
by the Contract Documents and by the Department's failure to comply with specific
written instructions regarding use provided to the Department by the Contractor;
and/or
(4) The actual or alleged culpable act, error, omission, negligence, breach or
misconduct of any Contractor-Related Entity in or associated with performance of
the Work; and/or
(5) Any and all claims, actual or alleged, by any governmental entity or taxing authority
claiming taxes based on gross receipts, purchases or sales, the use of any property
or income of the Contractor or any of its Subcontractors or any of their respective
agents, officers or employees with respect to any payment for the Work made to or
earned by any Contractor-Related Entity; and/or
(6) Any and all stop notices and/or liens filed in connection with the Work, including all
expenses and attorneys', accountants' and expert witness fees and costs incurred in
discharging any stop notice or lien and any other liability to Subcontractors for failure
to pay sums due for their work or services, provided that the Department is not in
default in undisputed payments owing to the Contractor with respect to such Work;
and/or
(7) Any actual or alleged spill or release or threatened spill or release of a Regulated
Material (i) which was brought onto the Site by any Contractor-Related Entity, or (ii)
attributable to the negligence, willful misconduct, or breach of contract,
Governmental Approval or governmental rule by any Contractor-Related Entity;
and/or
(8) Any actual or alleged claim or assertion by any contractor of inconvenience,
disruption, delay or loss caused by interference by any Contractor-Related Entity
with or hindering the progress or completion of work being performed by other
contractors, or failure of any Contractor-Related Entity to cooperate reasonably with
other contractors in accordance therewith; and/or
(9) Any actual or alleged Contractor Related Entity's breach of or failure to perform an
obligation that the Department owes to a third person, including governmental
entities, under law or under any agreement between the Department and a third
person, where the Department has delegated performance of the obligation to the
Contractor under the Contract Documents or (ii) the acts or omissions of any
Contractor-Related Entity which render the Department unable to perform or abide
by an obligation that the Department owes to a third person, including governmental
entities, under any agreement between the Department and a third person, where
the agreement was expressly disclosed to the Contractor; and/or
(10) Inverse condemnation, trespass, nuisance or similar taking of or harm to real
property by reason of: (i) the failure of any Contractor-Related Entity to comply with
the Standard of Care, requirements of the Contract Documents, Project
Management Plan or governmental approvals respecting control and mitigation of
construction activities and construction impacts, (ii) the intentional misconduct or
negligence of any Contractor-Related Entity, or (iii) the actual physical entry onto or
encroachment upon another's property by any Contractor-Related Entity.
In addition to the Indemnified Parties, the Contractor will indemnify and hold harmless
municipalities, counties, public utilities, any affected railroad or railway company, and any fee
owner from whom a temporary Right-of-Way was acquired for the Project for any Indemnified
Claim set forth in Section 16.2 (Defense and Indemnification Procedures).
With respect to any Loss, damage or cost which is not of the type covered by insurance to be
provided hereunder, Contractor's indemnity obligation shall not extend to any Loss, damage or
cost to the extent that such Loss, damage or cost was caused by the active gross negligence or
willful misconduct of such Indemnified Party or its agents, servants or independent contractors
who are directly responsible to such Indemnified Party.
Such indemnities shall not inure to the benefit of an Indemnified Party so as to impose liability
on the Contractor for the active gross negligence or willful misconduct of the Department, or to
relieve the Department of liability for such active gross negligence or willful misconduct.
tendered to an insurer or if the insurer has rejected the tender) shall deliver a written notice
stating that the Contractor:
A. Accepts the tender of defense and confirms that the Indemnified Claim is subject to
full indemnification hereunder without any "reservation of rights" to deny or disclaim
full indemnification thereafter;
B. Accepts the tender of defense but with a "reservation of rights" in whole or in part; or
C. Rejects the tender of defense based on a determination that it is not required to
indemnify against the Indemnified Claim under the terms of this Contract.
16.2.5 Acceptance of Tender/Control of Defense by Contractor
If the Contractor accepts the tender of defense under Section 16.2.4, A (Tender of Defense to
Contractor), the Contractor shall have the right to select legal counsel for the Indemnified Party,
subject to reasonable approval by the Indemnified Party, and the Contractor shall otherwise
control the defense of such Indemnified Claim, including settlement, and bear the fees and
costs of defending and settling such Indemnified Claim. During such defense:
(1) The Contractor shall fully and regularly inform the Indemnified Party of the progress of
the defense and of any settlement discussions; and
(2) The Indemnified Party shall fully cooperate in said defense, provide to the Contractor
all materials and access to personnel it requests as necessary for defense,
preparation and trial and which or who are under the control of or reasonably available
to the Indemnified Party, and maintain the confidentiality of all communications
between it and the Contractor concerning such defense.
16.2.6 Control of Defense by Indemnified Party
If the Contractor responds to the tender of defense as specified in Section 16.2.4, B or Section
16.2.4, C (Tender of Defense to Contractor), the Indemnified Party shall be entitled to select its
own legal counsel and otherwise control the defense of such Indemnified Claim, including
settlement.
(1) A conflict exists between it and the Contractor which prevents or potentially prevents
the Contractor from presenting a full and effective defense;
(2) The Contractor is otherwise not providing an effective defense in connection with the
Indemnified Claim; or
(3) The Contractor lacks the financial capacity to satisfy potential liability or to provide an
effective defense.
16.2.8 Reimbursement of Expenses
If the Indemnified Party is entitled and elects to conduct its own defense pursuant hereto of an
Indemnified Claim for which it is entitled to indemnification, the Contractor shall reimburse on a
current basis all reasonable costs and expenses the Indemnified Party incurs in investigating
and defending. In the event the Indemnified Party is entitled to and elects to conduct its own
defense, then:
17 INSURANCE REQUIREMENTS
17.1 Required Insurance
Without limiting Contractor’s indemnification of the Department and the Indemnified Parties, and
prior to commencement of Work, Contractor shall obtain, at its own expense, and continuously
maintain in full force and effect, the insurance coverages specified in this Section 17. Coverage
shall be maintained through Completion of the Contract, or such longer or shorter time as may
be specifically provided in this Section 17. The Contractor may use any combination of
corporate insurance policies, project-specific policies, or a contractor controlled insurance
program (“CCIP”) provided that the selected policies comply with all of the requirements in this
Section 17, except as otherwise provided by this Section 17.
All insurance required hereunder shall be procured from insurance companies with an A.M. Best
and Company rating level of A-: VI or better and authorized or approved to do business in the
State of Ohio, or as otherwise approved by the Department. All limits of insurance set forth
below are in U.S. dollars. Each policy of insurance of the type and amounts described below
shall in a form satisfactory to the Department.
Unless otherwise required, the Contractor agrees to immediately notify the Department in
writing if the Contractor or any of its Subcontractors fails or refuses to renew its any insurances
required under this Contract. The Contractor shall notify the Department if the Contractor’s or its
Subcontractors’ policies are canceled, lapse, are terminated or modified so that any insurance
does not meet the requirements set forth in this Section 17.
The policy shall cover all property, roads, buildings, bridge structures, other structures, fixtures,
materials, supplies, foundations, pilings, machinery and Equipment that are part of or related to
the portions or elements of the Project, and the works of improvement, including permanent and
temporary works and materials, and including goods intended for incorporation into the works
located at the Project ROW, in storage or in the course of transit to the Project ROW and all
improvements that are within the Project ROW. The policy shall not cover tools or Equipment
used by any contractor to perform their work. Such tools and Equipment are the sole
responsibility of the contractor who owns or uses such tools.
(1) Any ensuing loss from faulty workmanship, Nonconforming Work, error, omission or
deficiency in design or specifications;
(2) Machinery accidents and operational testing, if applicable;
(3) Removal of debris, with a sub-limit of 25% of the loss or a sublimit of no less than
$25,000,000, and insuring the buildings, structures, machinery, Equipment,
Materials, facilities, fixtures and all other properties constituting a part of the Project;
(4) Transit, including ocean marine coverage (unless insured by the Supplier or through
a separate marine cargo policy), with sub-limits sufficient to insure the full
replacement value of any key Equipment item;
(5) Sub-limits sufficient to insure the full replacement value of any property or
Equipment stored either on or off the Site;
(6) Collapse;
(7) Terrorism;
(8) Plans, blueprints and specifications;
(9) Demolition and increased cost of construction as required by law or ordinance with a
sub-limit of no less than $20,000,000; and
(10) Soft costs expense (including costs of Governmental Approvals, mitigation costs,
attorneys' fees, and other fees and costs associated with such damage or loss or
replacement thereof). The soft cost expense sublimit may be included with the
sublimit for delay.
There shall be no coinsurance penalty provision in any such policy. Deductibles or self-insured
retentions shall be no greater than 5 percent of the total value insured at the time of loss subject
to a minimum deductible no greater than $250,000. All deductibles or self-insured retentions
shall be the responsibility of Contractor.
The policy shall provide a “severability of interests provision,” or “multiple insured’s clause” or
similar wording that the policy shall apply to each insured as if a separate policy had been
issued to each insured except as to limits.
provided to the Department, and the PML may only be used as an alternative if it is approved, in
writing, by the Department. At its option, the Department may provide a PML obtained at the
Department expense. If the Department accepts the PML so obtained, the Department may
require the Contractor to obtain coverage with a loss limit less than full replacement cost. Any
additional insurance premium shall be paid for by the Department through a Change Order. Any
reduction in insurance premium shall be credited to the Department through a deductive
Change Order.
The policy or policies shall be endorsed to remove exclusions pertaining to railroads. There
shall be no “contractors limitation” endorsements as that term is defined as of the date of this
Contract in the Glossary of Insurance and Risk Management Terms published by the
International Risk Management Institute (http://www.irmi.com/online/insurance-
glossary/default.aspx), that have not been reviewed and approved by the Department or its
representatives. There shall be no endorsement or modification of the CGL limiting the scope of
coverage for liability assumed under an insured contract.
The commercial general liability insurance coverage shall have limits of not less than
$1,000,000 per occurrence, $2,000,000 general aggregate and $2,000,000 products/completed
operations aggregate. Completed operations coverage shall extend for as long as there is any
exposure to liability under a statute of repose or any other applicable statute either through
continuous maintenance of completed operations coverage in the Contractor’s corporate
insurance program, including an endorsement providing completed operations coverage for
additional insureds, or by purchase of extended completed operations coverage for a project-
specific policy. If project-specific coverage through statutory exposure is not commercially
available, completed operations coverage shall extend for at least ten years from Completion of
the Contract. If a project-specific policy is provided, Contractor shall be the named insured and
each of the Indemnified Parties shall also be an insured as to any loss or liability arising out of
or in any way related to the Project, Project ROW, or Project Site. If Contractor’s corporate
program is used with a project-specific general aggregate limit, each of the Indemnified Parties
shall be an insured under that policy.
Additionally, Contractor shall obtain Explosion, Collapse, and Underground (XCU) coverage at
the same limits as the commercial general liability insurance policy.
Contractor’s automobile liability coverage shall have a combined single limit per policy period of
not less than $200,000,000 and may be scheduled under the excess or umbrella liability policies
to achieve the desired limit. Excess or umbrella policies shall cover “any auto” (symbol 1) or
shall be specifically endorsed to include liability coverage on an excess basis for vehicles
owned or operated by Subcontractors.
The Contractor shall require and confirm that no automobile liability policy issued to a
Subcontractor shall contain a self-insured retention exceeding $50,000 per accident unless
Such policy or policies shall include the following terms and conditions:
A. Policies shall contain a drop down feature requiring the policy to respond in the event
that any primary insurance limits are exhausted or for occurrences covered by an
umbrella policy but not covered in the underlying insurance;
B. Policies shall provide coverage at least as broad as found in the underlying primary
policies; and
C. There shall be no “contractors limitation” endorsements as described in Section 17.4,
that have not been reviewed and approved by the Indemnified Parties or their
representatives.
The Department and the Indemnified Parties shall be included as insureds on the excess policy
including coverage extension to all insureds for completed operations.
The CPL shall be obtained on an occurrence basis for a policy term inclusive of the entire
Construction Period. The CPL shall provide for a minimum 10-year coverage period, including
the Construction Period and an extended reporting period. If an occurrence-based form is not
available, coverage may be provided under a claims-made form provided that the 10 year-
coverage and claim reporting period is provided either through an extended reporting period or
through continuous maintenance of coverage with no advancement of a retroactive date that is
no later than commencement of the Work.
The CPL policy shall include coverage for investigation, removal, and remediation costs
including monitoring or disposal of contaminated soil, surface water, groundwater or other
contamination to the extent required by environmental laws caused by pollution conditions
resulting from covered operations; third-party bodily injury and property damage, provided that
the third-party property damage liability coverage includes loss of use of damaged property or of
property that has not been physically injured or destroyed, resulting from pollution conditions
caused by construction operations. The policy shall have no exclusions or limitations for loss
occurring over water including but not limited to a navigable waterway.
Coverage as required in this paragraph shall apply to sudden and non-sudden pollution
conditions resulting from the escape or release of smoke, vapors, fumes, acids, alkalis, toxic
chemicals, liquids, or gases, waste materials, or other irritants, contaminants, or pollutants. The
CPL shall also provide coverage for transportation and off-Site disposal of materials.
The Department and each of the Indemnified Parties shall also be insureds. The policy shall not
contain any provision or exclusion (including any so-called “insured versus insured” exclusion or
“cross-liability” exclusion) the effect of which would be to prevent, bar, or otherwise preclude any
insured or additional insured under the policy from making a claim which would otherwise be
covered by such policy on the grounds that the claim is brought by an insured or additional
insured against an insured or additional insured under the policy.
No self-insured retention for the Contractor or Designer shall exceed $250,000 without prior
written approval from the Department, in its good faith discretion. Coverage shall apply
specifically to professional activities performed under the Contract Documents. The policy(ies)
shall have a retroactive date consistent with the inception of the first date of design or project or
construction management activities, and no later than the date on which the RFP was issued.
The Contractor agrees to maintain this required coverage for a period of no less than five years
after Substantial Completion or to purchase an extended reporting period for no less than five
years after Substantial Completion. The Contractor shall require the Designer to agree to
maintain this coverage for a period of no less than five years after Substantial Completion or to
purchase an extended reporting period for no less than five years after Substantial Completion.
A. For claims covered by the insurance specified herein, said insurance coverage shall
be primary insurance with respect to the insureds, additional insureds, and their
respective members, directors, officers, employees, agents, and consultants, except
for coverage that by its nature cannot be written as primary. Any insurance or self-
insurance beyond that specified in this Contract that is maintained by an Indemnified
Party, their directors, officers, employees, agents, and consultants shall be excess of
such insurance and shall not contribute with it.
B. Liability insurance shall apply separately to each insured and additional insured
against whom a claim is made or suit is brought, except with respect to the limits of
the insurer’s liability. If Contractor’s liability policies do not contain the standard
Insurance Services Office separation of insureds provision, or a substantially similar
clause, such policies shall be endorsed to provide cross-liability coverage.
17.12.8 No Recourse
There shall be no recourse against the Department or the Indemnified Parties for payment of
premiums or other amounts with respect to the insurance to be provided by Contractor
hereunder.
coverage to the project site will be permitted subject to the Department approval and use of the
broadest available site-specific endorsements. No liability policy shall contain any provision or
definition that would serve to eliminate so-called “third-party-over action” claims, including any
exclusion for bodily injury to an employee of the insured or of any contractor or Subcontractor.
The Contractor shall immediately notify the Department, and thereafter keep the Department
fully informed, of any incident, potential claim, claim or other matter of which the Contractor
becomes aware that involves or could conceivably involve an Indemnified Party as a defendant.
Contractor will cooperate with the Department, and shall require its liability insurers to agree in
writing to work with the Department to assure compliance with all regarding timely response to
claims.
The Department agrees to promptly notify the Contractor of the Department’s incidents,
potential claims against the Department, and matters of which the Department is actually aware
which may give rise to a Department insurance claim or to a right of defense and
indemnification under the Contract. Delivery of any such notice will constitute a tender of the
Department’s defense of the claim to the Contractor and the insurer under any applicable
Insurance Policies, subject to the Department’s rights to control its own defense to the extent
provided in the Contract or by applicable Governmental Rules. The Department shall cooperate
with the Contractor as necessary for the Contractor to fulfill its duties hereunder, including
providing the Contractor a copy of all written materials the Department receives asserting a
claim against the Department that is subject to defense by an insurer under an Insurance Policy
or by the Contractor under the Contract.
If, in any instance, the Contractor has breached its obligations respecting insurance coverage
set forth in the Contract Documents or is unable to enforce and collect any such insurance for
failure to assert claims in accordance with the terms of the Insurance Policies or to prosecute
claims diligently, then for purposes of determining damages resulting from the breach or inability
to enforce or collect, on or determining reductions in compensation due from the Department to
the Contractor, the Contractor shall be treated as if it has elected to self-insure up to the full
amount of insurance coverage that would have been available had the Contractor performed
such obligations or not committed such failure. Nothing in this Section 17.12.11 or elsewhere in
this Section 17 shall be construed to treat Contractor as electing to self-insure where the
Contractor is unable to collect due to the bankruptcy or insolvency of any insurer which at the
time the insurance policy is written meets the rating qualifications set forth in this Section 17.
In the event that an insurer providing any of the insurance policies becomes the subject of
bankruptcy proceedings, becomes insolvent, or is the subject of an order or directive limiting its
business activities given by any Governmental Entity, including the State Department of
Insurance, the Contractor shall exercise best efforts to promptly, and at its sole cost and
expense, secure alternative coverage in compliance with the insurance requirements contained
in this Section 17 so as to avoid any lapse in insurance coverage.
If on account of the Contractor’s failure to comply with the provisions of this Section 17, the
Department is adjudged to be responsible for all or any portion of a judgment, loss or settlement
(through admission or stipulation by Contractor or court decision) that would have been covered
by insurance but for non-compliance with this Section 17, then any loss or damage it shall
sustain by reason thereof shall be borne by Contractor, and the Contractor shall immediately
pay the same to the Department, upon receipt of written demand therefor and evidence of such
loss or damage.
17.12.15 Disclaimer
The Contractor and each Subcontractor shall have the responsibility to make sure that their
insurance programs fit their particular needs, and it is their responsibility to arrange for and
secure any insurance coverage that they deem advisable, whether or not specified herein.
The Department makes no representation or warranty that the coverage, limits of liability or
other terms specified for the insurance policies to be carried pursuant to this Section 17 are
adequate to protect the Contractor against its undertakings under the Contract Documents or its
liability to any third party or preclude the Department from taking any actions as are available to
it under the Contract or otherwise at law. The Department shall not be limited to the amount of
the insurance premium not paid in the proof of any damages it may claim against the Contractor
arising out of or by reason of failure of the Contractor to provide and keep in force the insurance
policies required by and on the terms of this Section 17, but the Department shall instead be
entitled to recover the full amount of damages available.
Consideration of a Dispute and Claim in accordance with the Dispute Resolution Procedures set
forth under this Section 18.2 and the exhaustion of all the processes set forth herein with
respect to such Dispute or Claim shall be a CONDITIONS PRECEDENT to the filing of action in
the Ohio Court of Claims. Further provided, that the consideration of a Dispute or Claim in
accordance with the Dispute Resolution Procedures pertaining to the subsequent Step shall
require the exhaustion of the processes pertaining to the preceding Step.
During the pendency of any Dispute or Claim, the Contractor covenants and agrees to refrain
from contacting DDRC members, DRB members, or Department personnel assigned to
consideration of the Dispute or Claim in accordance with the Step 1, Step 2, or Step 3
procedures. Further provided, that until a Dispute or Claim has been fully considered at the
previous Step, the Contractor covenants and agrees to refrain from contacting any DDRC
member, DRB member, or Department personnel that will consider the corresponding Dispute
or Claim at the subsequent Step.
The timeframes for filing a Dispute or Claim with the DDRC, DRB, or Department will be strictly
construed and the Contractor’s failure to file a Dispute or Claim within the corresponding time
periods shall result in the waiver of the Dispute or Claim and the dismissal of the Dispute or
Claim without further consideration by the corresponding body.
The Dispute Resolution Procedures shall consist of the following levels as set forth herein:
A. Any matters that the Contract Documents expressly state are final, binding, or not
subject to Dispute resolution;
B. Any matters relating to the applicability of indemnities provided under the Contract
Documents;
C. Any Claim for injunctive relief;
D. Any Claim against an insurance company, including any Subcontractor dispute that is
covered by insurance;
E. Any Claim arising solely in tort;
F. Any Claim between or among the Contractor, the Department, and a third party in
which the third party is a necessary or appropriate party to such Dispute, including any
related Claims between the Parties arising therefrom;
G. Any Claim or Dispute that is the subject of litigation in a lawsuit filed in court to which
the Dispute Resolution Procedures established in this Section do not apply, including
any effort to interplead a Party into such a lawsuit in order to make the Dispute
Resolution Procedures established in this Section applicable;
H. Any Claim for, or Dispute based on, remedies expressly created by statute; and
I. Any Dispute that is actionable only against a Surety.
Further provided, that the Contractor acknowledges and agrees that the Contractor may not
seek recourse under the Dispute Resolution Procedures, nor shall have a Claim at Law, for any
exercise of the Department's sole discretion (or words of like import), and those oversight and
other matters with respect to the Project that result in certain rights in favor of the Department
by virtue of the Contractor's engineer's obligations resulting from its license (i.e., that inure to
the benefit of the Department rather than the Contractor).
Within seven (7) Days of receiving the Department’s written notice with respect to its decision
pertaining to any RCO or EDR pursuant to Section 12.4.1.2 and Section 13.4.3 (Excusable
Delay Change Order), respectively, should the Contractor disagree with said notice, Contractor
shall be obligated to deliver written notice (the “Contactor‘s Early Written Dispute Notice”) of its
intent to utilize the Dispute Resolution Procedures set forth herein. Contractor’s failure to submit
an Early Written Dispute Notice within such timeframe shall constitute a waiver of Contractor’s
rights with respect to such potential Dispute.
In conjunction with the evaluation of any Early Written Dispute Notice, the Department and
Contractor shall maintain records of labor, equipment, and materials used on the Work relating
to the potential Dispute or any Work made necessary by the circumstances, provided however
such records shall not constitute an acknowledgement or representation on the part of the
Department that it accepts responsibility for payment relating to the Dispute or the granting of
any extension of time with respect to the Dispute.
Within two (2) Working Days of receiving the Contractor’s Early Written Dispute Notice, the
Department will meet with the Contractor to review all pertinent information and relevant
provisions of this PDBC to resolve the issues giving rise to the Dispute. Within fourteen (14)
Days of the aforementioned meeting, the Department will issue its written Step 1 decision. If the
Step 1 decision does not resolve the corresponding Dispute to the Contractor’s satisfaction,
then the Contractor may elect to either (i) abandon the Dispute, or (ii) elect to escalate the
Dispute to Step 2.
Members of the DRB must not show or be perceived to be showing partiality or bias to either the
Contractor or the Department. A DRB member shall not have any conflict of interest which could
affect their ability to act in a disinterested and unbiased manner.
A person proposed as a member of the DRB shall submit a resume covering such member’s
applicable education and experience to the party appointing him/her. The resume shall include a
list of all DRBs on which the candidate currently serves and any projects on which the candidate
serves as a dispute resolution advisor along with meeting frequencies. A disclosure statement
shall be submitted and include, but not limited to, any of the following categories of relationships
or prior involvement in this project:
F. A contract as a consultant to the Department, the Cabinet, the Contractor, or any Sub-
Consultant or Sub-Contractor or supplier on the Project.
Category “A” and “B” relationships listed above shall disqualify a person from serving on the
DRB for this Project. The other categories listed above will be considered by the Department
and the Contractor to determine whether to accept a person as a member of the DRB. If a
prospective DRB member discloses a relationship or prior involvement in this Project listed in
other than category “A” and “B” and is considered to be highly qualified and desirable as a DRB
member, the Department and the Contractor may, by mutual agreement, approve that person to
serve as a member on the DRB.
If a DRB candidate submits a disclosure statement which fails to provide accurate and complete
disclosure of a relationship described in A through F above, the Department may disqualify that
candidate from serving on a DRB on future Department projects.
Within twenty-one (21) Days of the signing of this PDBC, the Department and Contractor shall
each obtain a written commitment from their proposed member to serve as a DRB member
along with the resume and disclosure statement. These commitments shall include a clause that
requires the first two members to immediately pursue selection of the DRB Chair. Within this
same timeframe, the Department and Contractor must also give the other party notice of the
person they have selected to serve as a DRB member. This notice shall be accompanied by the
resume and disclosure statement.
Within fourteen (14) Days of receiving the notice of selection of a DRB member, the Department
and the Contractor shall notify the other party in writing as to whether the person selected is
acceptable. Failure to give this notice within the required timeframe shall be construed to be
acceptance of that member.
If a person selected is not acceptable to the other party, the party who selected that person shall
within seven (7) Days select another person and provide to the other party a notification
accompanied by the resume and disclosure statement submitted by that person. Within seven
(7) Days written notification shall be given as to whether the person selected is acceptable.
Failure to give this notice within the required timeframe shall be construed to be acceptance of
that member.
Once the Department and the Contractor have agreed upon the first two members of the DRB
the Department and the Contractor shall immediately notify those members of their approval.
Within seven (7) Days of this notification, the Department and Contractor will each provide the
first two members with a list of not less than two (2) potential members from which the DRB
Chair will be selected. Within seven (7) Days of receipt of the list of potential members, the first
two members shall select the DRB Chair ensuring that the DRB Chair meets all the
Requirements of DRB Members set forth under Section 18.4.3 (Requirements of DRB
Members) above and give written notice to both the Department and Contractor accompanied
by that person’s resume and disclosure statement. In the event of an impasse in selection of the
DRB Chair, that member shall be selected by mutual agreement of the Department and
Contractor.
Immediately after agreement is reached on all members of the DRB, the Department,
Contractor, and the members of the DRB shall execute the DRB Three Party Agreement. The
terms and conditions of the DRB Three-Party Agreement will not modify the requirements,
terms, or conditions of this PDBC.
Service of a member of the DRB may be terminated at any time with not less than thirty (30) Days’
notice as follows:
A. The Department may terminate the service of the Department appointed member.
B. The Contractor may terminate the service of the Contractor appointed member.
C. The DRB Chair’s service may be terminated only by agreement of the other two
members.
D. Resignation of the member.
18.4.6 Dispute Review Board (DRB) Member Replacement
In the event that a vacancy on the DRB occurs, replacement members will be appointed in the
same manner as the replaced member was appointed. The selection of a replacement DRB
member shall be completed within thirty (30) Days of the creation of the vacancy. The
Department, the Contractor, and the DRB shall execute an amendment to the DRB Three Party
Agreement to reflect the change of a DRB member.
The Department and Contractor shall mutually agree upon the appropriateness of holding in-
person update status meetings or Dispute Hearing or holding such meetings virtually.
The members of the DRB will keep current on the progress of the Project by: 1) quarterly visits
to the Project, 2) keeping current files, 3) meetings with other DRB members, and 4) joint
meetings with Department and Contractor personnel. The frequency of Project visits and
meetings and content of members’ files shall be as agreed upon among the Department, the
Contractor, and members of the DRB.
The DRB Chair shall be responsible for arranging and conducting meetings, hearings, Project
visits, and drafting DRB recommendations on Claims presented to the DRB.
The DRB will not maintain an official transcript of its hearings or deliberations. The DRB
members shall perform their responsibilities impartially and independently considering the facts
and conditions related to the matters under consideration and the provisions of this PDBC.
The DRB will exist for the Term of this PDBC only and will not review Disputes or Claims on any
other project unless as otherwise agreed upon by the Department and the Contractor. If, after
Contract Completion, there are unresolved Disputes and Claims remaining, the DRB Three
Party Agreement shall remain active and in full force and effect until the Project is otherwise
administratively closed by the Department following final payment so that the DRB may continue
in operation until all unresolved Disputes and Claims are resolved or voluntarily dismissed.
A Dispute becomes a Claim when the Department representatives receive the aforementioned
written notice. The DRB will not consider a Claim until the DDRC has properly reviewed a
Dispute and issued a decision in accordance with Section 18.3 (District Dispute Resolution
Committee).
The DRB’s Operating Procedures for Dispute Resolution established by the DRB will set forth
the Step 3 (Appeal to DRB) process in detail. At a minimum, the DRB Operating Procedures will
establish both the requirements and timeframes for documentation submissions by both the
Contractor and Department, documentation exchange between the Contractor and Department,
and the hearing procedures.
The Contractor shall submit its Claims Documentation in accordance with the DRB’s Operating
Procedures. In addition to the Dispute Documentation submitted at Step 2, the Claims
Documentation shall be enhanced to include the following:
Upon submission of the Claims Documentation, the Contractor shall certify the Claim in writing
and under oath. The date the Claims Coordinator receives the certified Claims Documentation is
the date of the Department’s Receipt of the Certified Claim for the purpose of the calculation of
interest.
In the event of multiple Claims, the DRB may order that such separate Claims be considered in
a single hearing. The DRB may hold this hearing after the completion of the Project or until such
time that it is assured that all Disputes pertaining to the Project have been processed through
Steps 1 and 2 of the Dispute Resolution Process and these issues are before the DRB.
The DRB will hear the entire Claim. The DRB will hear oral presentations from the Department
and the Contractor. The DRB may, on its own initiative, request information of the Contractor or
the Department in addition to that submitted for the hearing. If either party fails to reasonably
comply with such request, the DRB may render its recommendation without such information.
Upon completion of the hearing and consideration of any additional information submitted upon
request, the DRB will render its written recommendation within fourteen (14) Days of the
hearing.
The recommendation of the DRB shall be by majority vote. The recommendation shall be a well-
reasoned decision which, at a minimum, shall include:
1. The claim number; the project number; county, route, and section number; Contractor
name; subcontractor or supplier’s name, if involved in the dispute; and the commonly
referenced name of the dispute on the cover sheet or the first page of the decision.
2. Sufficient description of the project and the claim to enable understanding by a third
party who has no knowledge of the claim or familiarity with the project.
3. The value of the claim as determined by the Contractor, if applicable.
4. The value of the claim as determined by the Department, if applicable.
5. Finding of fact and a conclusion that provides clear direction to the parties.
The DRB Chair must submit copies of the recommendation to the Contractor, the Deputy
Director of the Division of Construction Management, and the DCA.
Within three (3) days of receipt of the recommendation, either party may request a meeting of
the DRB to hear the DRB’s explanation of the recommendation. Within seven (7) days of this
request, the DRB Chair shall conduct this meeting with both the Department and the Contractor.
Within twenty-one (21) Days of receipt of the DRB’s recommendation, the Contractor must
indicate its intentions in writing to the Department and the Chair with respect to the
recommendation. The Director or designee will determine the Department’s intentions with
respect to the recommendation in writing to the Contractor and the Chair within twenty-one (21)
Days of receipt of the recommendation.
Either the Department or the Contractor may appeal a recommendation to the DRB for
reconsideration. However, reconsideration will only be allowed when there is new evidence to
present.
The recommendation of the DRB is the final step of the Department’s Dispute Resolution
Process and may not be appealed within the Department. The DRB is not bound by any offers
of settlement or findings of entitlement made during Steps 1 and 2 of the Dispute Resolution
Process.
The Department will pay interest in accordance with Section 126.30(E) of the Ohio Revised
Code on any amount found due on a Claim which is not paid within 30 Days of the Department’s
receipt of the Contractor’s certified Claims Documentation pursuant to this Section 18.4.8.
Consequential damages shall be recoverable by the Department only in the following limited
categories:
The term "consequential damages" shall mean those special, indirect, or incidental damages
that do not flow directly and immediately from an injurious act but that result indirectly from an
action or failure to act, such as revenue losses, loss of use, cost of capital, debt service, loss of
profit on related contracts, administrative costs, loss of bonding capacity, lost opportunity,
claims of taxpayers, and other indirect damage. Liabilities, costs, and losses incurred by either
party due to failure by the other to procure and maintain insurance policies required hereunder,
as well as any amounts that this PDBC expressly states are to be reimbursed from one party to
the other (including interest, late charges, fees, penalties, and similar charges), shall be
considered direct damages. This provision shall apply to limit liability under actions brought
under any theory of law, including actions in tort (including negligence) as well as in contract.
1. The Contractor shall identify clearly in all submissions pursuant to this Section 18.6.1
that portion of the Claim that involves a Subcontractor. Any Claim under this Section
18.6.1 involving Subcontractor Demands shall be considered incomplete if it is not
accompanied by such analysis and the following documents and certificates.
2. The Contractor shall include, as part of its submission pursuant to this Section 18.6.1,
a certification in a form provided by or acceptable to the Department by the
Subcontractor's officer, partner, or authorized representative with authority to bind the
Subcontractor and with direct knowledge of the facts underlying the Subcontractor’s
Demand asserting the factual and contractual basis of the Subcontractor Demand,
justification as to entitlement, and amount of money and time sought.
3. The Contractor shall also submit a certification that:
a. The Contractor has investigated the basis of the Subcontractor Demand and has
determined that all such Subcontractor claims or demands are justified as to
entitlement and amount of money and time requested, and has reviewed and
verified the adequacy of all back-up documentation;
b. The Subcontractor Demand has been prepared and submitted in accordance with
the terms of the Contract Documents and applicable Subcontracts and contains all
information required by the Contract Documents and applicable Subcontracts; and
c. The Contractor has no reason to believe and does not believe that the factual
basis for the Subcontractor Demand is falsely represented.
4. At any informal hearing on a Dispute that includes one or more Subcontractor
Demands, the Contractor shall require that each Subcontractor that is involved in the
Dispute make available an authorized representative with actual knowledge of the
facts underlying the Subcontractor Demand to assist in presenting the Dispute and to
answer questions raised by the Department's representatives. Such Subcontractor
assistance shall be limited to presenting the specific facts underlying the
Subcontractor Demand and the answering of questions raised by the Department and
Contractor's Representative.
5. Failure of the Contractor to assert timely and completely a Subcontractor Demand as
part of any Claim and on behalf of any Subcontractor or Supplier at the time of
submission of Contractor's Claims, as provided hereunder, shall constitute a release
of the Department by the Contractor on account of such Subcontractor Demand.
6. The Contractor shall require in all Subcontracts that all Subcontractors and Suppliers
of any tier:
a. Agree to submit Subcontractor Demands to the Contractor in a proper form and in
sufficient time to allow processing by the Contractor in accordance with this
Section 18.6.1;
b. Agree to be bound by the terms of this Section 18.6.1 to the extent applicable to
Subcontractor Demands;
c. Agree that, to the extent a Subcontractor Demand is involved, completion of all
steps required under this Section 18.6.1 shall be a condition precedent to pursuit
by the Subcontractor of any other remedies permitted by Law; and
d. Agree that the existence of the Dispute Resolution Procedures for Disputes
involving Subcontractor Demands shall not be deemed to create any claim, right,
or cause of action by any Subcontractor or Supplier against the Department.
Notwithstanding the foregoing, this Section 18.6.1 shall not apply to the following:
a. Any Subcontractor claim between Subcontractors and the Contractor that is not
actionable by the Contractor against the Department;
b. Any Subcontractor Demand or claim based on remedies expressly created by statute;
19 DEFAULT
19.1 Contractor Defaults
19.1.1 Events of Default by the Contractor
The Contractor shall be in breach under the Contract is PDBC upon the occurrence and failure
to cure of any one or more of the following events or conditions (“Contractor Default”):
(1) The Contractor fails to promptly begin the Work under the Contract Documents
following issuance of a Notice to Proceed authorizing such Work;
(2) The Contractor fails to perform the Work with sufficient resources to ensure the
prompt completion thereof ;
(3) The Contractor fails to perform the Work in accordance with the Contract
Documents, refuses to remove and replace rejected Materials or Nonconforming
Work, or fails to remove and replace workers as directed by the Department;
(4) The Contractor discontinues or suspends the prosecution of the Work (exclusive of
Work stoppage due to (i) termination by the Department, (ii) compliance with
stoppage requirements due to Regulated Materials, (iii) a Force Majeure Event; (iv)
suspension by the Department, or (v) nonpayment by the Department not related to
a breach by the Contractor);
(5) The Contractor fails to resume performance of Work which has been suspended or
stopped, within a reasonable time after receipt of notice from the Department to do
so or (if applicable) after cessation of the event preventing performance;
(6) The Contractor materially fails to timely observe or perform or cause to be observed
or performed any other material covenant, agreement, warranty, obligation, term or
condition required to be observed or performed by the Contractor under the Contract
Documents; provided that such actions shall not be considered a Contractor Default
if they are the direct result of the Department 's breach of its obligation to make
payments to the Contractor;
(7) The Contractor fails to obtain, provide and maintain in full force and effect any
insurance, Bonds (including the Payment Bond and Performance Bond) or
Guarantees as and when required under this PDBC for the benefit of the
Department or other relevant parties, or fails to comply with any requirement of this
PDBC pertaining to the amount, terms or coverage of the same;
(8) The Contractor makes or attempts to make or suffers a voluntary or involuntary
assignment or transfer of the Contract Documents or any right or interest therein;
(9) Subject to the Department paying the Contractor pursuant to Section 11
(Contractor’s Compensation), the Contractor fails, absent a valid Dispute, to make
payment when due for labor, Equipment or Materials in accordance with its
agreements with Subcontractors, Subconsultants and/or Suppliers and applicable
Law, fails to comply with any law or governmental approvals; or fails reasonably to
comply with the instructions of the Department consistent with the Contract
Documents;
(10) The Contractor fails to discharge or obtain a stay within 10 Days of any final
judgment(s) or order for the payment of money against it in excess of $100,000 in
the aggregate arising out of the prosecution of the Work (provided that, for purposes
hereof, posting of a bond in the amount of 125 percent of such judgment or order or
the filing of an appeal with respect to such judgment or order shall be deemed an
effective stay);
(11) The Contractor does not comply with public safety and public convenience
requirements of this PDBC or fails to correct any safety hazards promptly;
(12) The Contractor or any Major Participant shall have become insolvent, generally does
not pay its debts as they become due, admits in writing its inability to pay its debts,
or makes an assignment for the benefit of creditors;
(13) Insolvency, receivership, reorganization or bankruptcy proceedings shall have been
commenced by or against the Contractor or any Major Participant and not dismissed
within 60 Days;
(14) Any representation or warranty made by the Contractor in the Contract Documents
or in any certificate, schedule, instrument or other document delivered as part of the
Proposal or pursuant to the Contract Documents shall have been false or materially
misleading when made or becomes inaccurate in any material respect during the
Contract Term;
(15) The Contractor is a party to fraud in any way relating to the Project; or
(16) The Contractor otherwise materially fails to comply with the terms of this PDBC.
19.1.2 Right to Cure
The Department shall notify the Contractor and the Sureties of any event constituting a breach
under this PDBC before declaring a Contractor Default hereunder, after which the Sureties
and/or Contractor shall have ten (10) Days from receiving the Department’s Initial Notice to
send confirmation that the Contractor (or Sureties on behalf of the Contractor) will cure the
corresponding breach within thirty (30) Days of the date of such confirmation notice; provided
however, upon a showing of good cause by the Contractor that such cure will require more than
thirty (30) Days, the Department may elect, in its sole discretion, to extend such cure period for
additional time; provided further that, if the Department determines that a condition caused by a
Contractor Breach poses an immediate and imminent danger to public health or safety, the
Department may, without prior notice and without awaiting the expiration of any cure period,
rectify the condition at the Contractor's sole cost and expense. The Department 's good faith
determination of the existence of such danger shall be deemed conclusive in the absence of
clear and convincing evidence to the contrary.
(1) The Department may order the Contractor to suspend or discontinue the Work or
any portion of the Work;
(2) The Department may terminate this PDBC or a portion thereof;
(3) If and as directed by the Department in writing, the Contractor shall withdraw from
the Project Site; and shall remove such Materials, Equipment, tools and instruments
used by, and any debris or waste materials generated by, any Component Firm
entity in the performance of the Work;
(4) The Contractor shall deliver or cause to be delivered to the Department exclusive
possession of the Project Site and any or all of the Contractor 's facilities located on
the Project Site as well as any or all Design Documents, Construction Documents
and all other completed or partially completed drawings (including plans, elevations,
sections, details and diagrams), specifications, records, information, schedules,
samples, shop drawings and other documents, that the Department deems
necessary for completion of the Work;
(5) If the Department requests the Contractor to assign to the Department specific
Subcontracts, the Contractor shall execute such documents as may be required to
confirm the assignment of those Subcontracts to the Department and shall
terminate, at its cost, all other Subcontracts;
(6) The Department may deduct from any amounts payable by the Department to the
Contractor such amounts payable by the Contractor to the Department, including
Liquidated Damages or other damages payable to the Department under the
Contract Documents;
(7) The Department shall have the right, but not the obligation, to pay such amount
and/or perform such act as may then be required;
(8) The Department, without incurring any liability to the Contractor, shall have the rights
(i) to take the performance of all or a portion of the Work from the Contractor (either
with or without the use of the Contractor 's Materials, Equipment, tools and
instruments) and enter into an agreement with another entity for the completion of
such Work; or (ii) to use such other methods, as in the opinion of the Department,
will be required for the completion of the Project;
(9) If the Department exercises any right to perform any obligations of the Contractor, in
the exercise of such right the Department may, but is not obligated to, among other
things: (i) perform or attempt to perform, or cause to be performed, such work; (ii)
spend such sums as the Department deems necessary and reasonable to employ
and pay such architects, engineers, consultants and contractors and obtain
Materials and Equipment as may be required for the purpose of completing such
work; (iii) execute all applications, certificates and other documents as may be
required for completing the work; (iv) modify or terminate any contractual
arrangements; (v) take any and all other actions which it may in its sole discretion
consider necessary to complete the Work; and (vi) prosecute and defend any action
or proceeding incident to the Work; and/or
(10) The Department shall also have the right, but not the obligation, to require the
Contractor to comply with the obligations in Section 21.2 (Contractor Responsibilities
Upon Termination).
20 SUSPENSION OF WORK
20.1 Department Suspension for Convenience
The Department may, at any time and for any reason, by written notice, direct the Contractor to
suspend all or any part of the Work required under the Contract Documents for the period of
time that the Department deems appropriate for the convenience of the Department.
In the event that any Department ordered suspension of Work is not due to a breach of
Contractor’s obligations under this PDBC and Contractor asserts that it is otherwise entitled to
(i) reimbursement of its direct costs incurred as a result of the Department ordered suspension
of Work and/or (ii) an extension of Contract Time as a result of any Department ordered
suspension of Work, then the Contractor may, pursuant to Section 12.4.1, submit one or more
NPCOs to the Department for consideration. Thereafter, provided the Department elects to
advance any NPCO and approve an RCO or an EDR, any change in the Contract Price and/or
Contract Time due to any Department ordered suspension of Work shall be finalized in
accordance with the procedures in Section 12 (Contract Changes) and/or Section 13 (Time
Extension to the Completion Deadlines and Payment for Excusable Delays).
(1) Correct conditions unsafe for the Project personnel or general public;
(2) Comply with any Governmental Approval, Law, or otherwise carry out the
requirements of the PDBC;
(3) Carry out orders of the Department; or
(4) Comply with the NEPA Documents and other environmental requirements or
requirements for developing and implementing the Quality Management System Plan.
20.3 Contractor Responsibilities during Suspension
The Contractor shall promptly comply with any written suspension order under this Section 20.
The Contractor shall promptly recommence the Work upon receipt of written notice from the
Department directing the Contractor to resume Work. During periods that Work is suspended,
the Contractor shall continue to be responsible for the Work and shall prevent damage or injury
to the Project and other facilities in the Project vicinity, provide for drainage, obtain and maintain
compliance with all Governmental Approvals, maintain all Contractor-provided insurance and
bonds and erect necessary temporary structures, signs or other facilities required to maintain
the Project and other facilities in the Project vicinity. During any suspension period, unless
otherwise directed by the Department, the Contractor shall continue to be responsible for traffic
control in accordance with Technical Requirements Section 20 (Traffic Control) and for
maintenance during construction in accordance with Section 5.11.1 (Maintenance During
Construction). If only part of the Work is suspended, for the Work not suspended, the Contractor
shall be entitled to payment for the costs allocated thereto as set forth in the cost and resource
loaded schedule per Exhibit T (Critical Path Method Progress Schedule).
(1) The Department fails to make any undisputed payment by its due date in accordance
with the Contract;
(2) The Contractor provides written notice of such non-payment and the Department fails
to make such payment within 30 Days following receipt of the Contractor’s notice;
(3) The Contractor provides subsequent written notice that it will suspend performance of
the Work unless such payment is made within 30 Days following such subsequent
notice; and
(4) The Department fails to make such payment within 30 Days following receipt of such
subsequent notice from the Contractor.
Such right will not be available to the Contractor if there is a good faith Dispute concerning the
Contractor’s entitlement to the payment under the Contract.
b. The Design Documents and all other completed or partially completed drawings
(including plans, elevations, sections, details, and diagrams), specifications,
records, samples, information, and other property that would have been required
to be furnished to the Department if the Work had been completed.
(8) Complete performance, in accordance with the Contract Documents, of all Work not
terminated.
(9) Take all action that may be reasonably necessary, or that the Department may
direct, for the safety, protection, and preservation of:
a. The public, including public and private vehicular movement;
b. The Work; and
c. The Equipment, machinery, Materials, and property related to the Contract
Documents that is in the possession of the Contractor and in which the
Department has or may acquire an interest.
(10) As authorized by the Department in writing, use its best efforts to sell, in a manner at
the times, to the extent, and at the price or prices directed or authorized by the
Department, any property types referred to in Section 21.2(7); provided however,
that the Contractor:
a. Is not required to extend credit to any purchaser; and
b. May acquire the property under the conditions prescribed and at prices approved
by the Department.
(11) The proceeds of any transfer or disposition will be applied to reduce any payments
to be made by the Department under the Contract Documents or paid in any other
manner directed by the Department.
(12) If requested by the Department, withdraw from the portions of the Project Site
designated by the Department and remove such materials, equipment, tools and
instruments used by, and any debris or waste generated by, the Contractor and any
Subcontractor in the performance of the Work as the Department may direct.
(13) Assign and transfer to the Department all of the Contractor’s right, title and interest
in and to the following: (a) all Design Documents, completed or partially completed
drawings (including plans, elevations, sections, details and diagrams), specifications,
designs, design documents, surveys, and other documents and information
pertaining to the design or construction of the terminated Work; (b) all samples,
borings, boring logs, geotechnical data and similar data and information relating to
the terminated Work; (c) all books, records, reports, test reports, studies and other
documents of a similar nature relating to the terminated Work; and (d) all other work
product used or owned by the Contractor or any Contractor-Related Entity relating to
the terminated Work.
(14) Take other actions directed by the Department.
(1) The Contractor’s responsibility for damage to materials for which partial payment has
been made shall end when the Department certifies that those materials have been
stored in the manner and at the locations directed by the Department.
(2) The Contractor’s responsibility for damage to materials purchased by the Department
subsequent to the Notice of Termination shall end when title and delivery of those
materials has been taken by the Department.
Immediately after the Department determines that the Contractor has completed the Work
directed to be completed in accordance with the Notice of Termination and such other work as
may have been ordered to secure the Project for termination, the Contractor will not be required
to provide for continuing safety, security, and maintenance at the Site. Subsequent to the
determination that all materials have been stored in the manner and at the locations directed by
the Department, further handling of such materials shall be the responsibility of the Department.
the parties as a part of a negotiated settlement, the Department’s execution and delivery of any
settlement shall not affect any of its rights under the Contract Documents with respect to
completed Work, relieve the Contractor from its obligations with respect thereto, including
Warranties, or affect the Department’s rights under the Payment and Performance Bonds and
payment as to such completed or non-terminated Work.
(1) The Contractor’s actual reasonable out-of-pocket cost (without profit, and including
Equipment costs only to the extent permitted by Section 11 (Contractor’s
Compensation)) for all Work performed, including mobilization, demobilization, and
work done to secure the Project for termination, including reasonable overhead and
accounting for any refunds payable with respect to insurance premiums, deposits, or
similar items, as established to the Department’s satisfaction. In determining the
reasonable cost, deductions will be made for the cost of materials to be retained by
the Contractor, amounts realized by the sale of materials and for other appropriate
credits. Deductions will also be made for the cost of damaged materials. When, in the
opinion of the Department, the cost of an item of Work is excessively high due to costs
incurred to remedy or replace defective or rejected Work, the reasonable cost to be
allowed will be the estimated reasonable cost of performing that Work in compliance
with the requirements of the Contract Documents, and the excessive actual cost will
be disallowed.
(2) As profit on the actual out-of-pocket cost permitted in (1) above, a sum determined by
the Department to be fair and reasonable; provided, however, that if it appears that the
Contractor would have sustained a loss on the entire PDBC had it been completed, no
profit shall be included or allowed under this Section 21.5, and an appropriate
adjustment shall be made by reducing the amount of the settlement to reflect the
indicated rate of loss.
(3) The cost of settling and paying claims arising out of the termination of Work under
Subcontracts as provided in Section 21.2 (Contractor Responsibilities Upon
Termination), exclusive of the amounts paid or payable on account of supplies or
materials delivered or services furnished by the Subcontractor prior to the effective
date of the Notice of Termination under the Contract, which amounts shall be included
in the cost on account of which payment is made under clause (1) above.
(4) The reasonable out-of-pocket cost (including reasonable overhead) of the
preservation and protection of property incurred pursuant to Section 21.2 (9) and any
(1) All unliquidated payments for Work or materials not yet performed on or supplied to
the Project at the time of the payment, excluding payments made to or on behalf of the
Contractor applicable to the terminated portion of the PDBC;
(2) The amount of any claim which the Department may have against any Contractor-
Related Entity in connection with the PDBC;
(3) The agreed price for, or the proceeds of the sale of, any property, materials, supplies,
or other things acquired by the Contractor or sold, pursuant to the provisions of this
Section 21, and not otherwise recovered by or credited to the Department;
(4) Amounts that the Department reasonably deems advisable to retain to cover any
existing or threatened claims, Liens, and stop notices relating to the Project, including
claims by Third-Parties;
(5) The cost of repairing, replacing or otherwise correcting any Nonconforming Work; and
(6) Any amounts due or payable by the Contractor to the Department.
21.8 Partial Payments
The Department may, from time to time, under such terms and conditions as it may prescribe
and in its sole discretion, make partial payments on account against costs incurred by the
Contractor in connection with the terminated portion of the PDBC, whenever, in the opinion of
the Department, the aggregate of such payments shall be within the amount to which the
Contractor will be entitled under this Section 21. If the total of such payments is in excess of the
amount finally agreed or determined to be due under this Section 21, such excess shall be
payable by the Contractor to the Department upon demand, together with interest at a rate
equal to the average rate at the time being received from the investment of state funds, as
determined by the [State Treasurer], for the period from the date such excess payment is
received by Contractor to the date on which such excess is repaid to the Department.
21.12 No Waiver
Anything contained in the PDBC to the contrary notwithstanding, a termination under this
Section 21 shall not waive any right or claim to damages, which the Department may have, and
the Department may pursue any cause of action, which it may have at law or in equity or under
the PDBC.
If the Department exercises any termination right after the execution of any Early Work Package
Change Order or Phase 2 Change Order, the Department will have the right in its discretion to
require continued performance of the applicable Phase 2 Work and terminate only the
remaining Phase 1 Work and any other Phase 2 Work. In such event, the Contract will remain in
full force and effect only with respect to the Phase 2 Work that is not terminated by the
Department, and the Contract Price established in the applicable Early Work Package Change
Order or component Phase 2 Change Order will continue to apply to such Phase 2 Work.
22 PROJECT WARRANTIES
22.1 Contractor Project Warranties
The Contractor hereby represents and warrants to the Department that subject to the provisions
of the Contract Documents that:
1. All design and technical services for the Work furnished pursuant to the Contract
Documents shall conform to professional standards identified in the Contract
Documents and all professional principles and the Standard of Care applicable to the
design and scope of the Work, to the extent that such principles are not more
restrictive than the professional standards specifically identified in the Contract
Documents;
2. The Construction Work furnished pursuant to the Contract Documents shall be
performed in a workmanlike manner and shall conform to the standards of care and
diligence normally practiced by recognized construction firms performing construction
of a similar nature in the State;
3. Goods, materials, and equipment furnished under the Contract Documents shall be of
the quality specified or, if not specified, of good quality and, except if not otherwise
expressly set forth in the Contract Documents, when installed, shall be new;
4. The Work shall meet all requirements of the Contract Documents;
5. The specifications and/or drawings selected or prepared for use during construction
are suitable for their intended use;
6. Any work that does not meet the standards referenced in (1) through (5) above is
Nonconforming Work;
7. The Project will be free from defects (whether latent or patent) in workmanship and
materials furnished or installed by the Contractor;
8. All material and equipment incorporated into the Work will be new and free from any
and all claims, liens, and security interest of any third parties;
9. The Work will be fully and finally completed in accordance with the terms of the
Contract Documents at a cost not to exceed the Contract Price;
10. The Contractor possesses expertise in the administration, construction, management
and superintendence of projects of the type, nature, and general locality of the Project,
and will perform the Work with the care, skill and diligence of such a contractor;
11. The Contractor and its Subcontractors are financially solvent, able to pay debts as
they mature, and the financial statements and information furnished to the Owner by
Contractor present fairly the Contractor's and, if applicable, Subcontractors' respective
financial conditions, and they are possessed of sufficient working capital to complete
the Contract;
12. The Contractor is able to furnish the plant, tools, labor, materials, and equipment
necessary to complete the Work; and
13. The Contractor and its Subcontractors are qualified to perform the Work, authorized to
transact business in the jurisdictions in which the Project is located, and possesses or
have obtained and shall possess all necessary licenses, permits, and approvals
required to perform the Work.
The Contractor will promptly notify the Department of the occurrence of any event or
circumstances which renders the foregoing representations or warranties materially untrue. The
foregoing warranties are in addition to, and not in lieu of, any and all other liability imposed upon
the Contractor by law with respect to Contractor's duties, obligations and performance
hereunder. The Contractor's liability hereunder shall survive the Department's final acceptance
of and payment for the Work. All representations and warranties set forth in the Contract
Documents shall survive the final completion of the Work or the earlier termination of the
Contract. If the Department finds the materials furnished, Work performed, or the finished
product are not in reasonably close conformity with the Contract Documents and have resulted
in an unacceptable finished product, the affected Work or materials shall be removed and
replaced or otherwise corrected by and at the expense of the Contractor in accordance with the
Department’s written orders. The term “reasonably close conformity” shall not be construed as
waiving the Contractor’s responsibility to complete the Work in accordance with the Contract
Documents, plans, and specifications. For the purpose of this Section 22.1, the term
“reasonably close conformity” is intended to allow the Department to use good engineering
judgment in its determinations as to acceptance of Work that is not in strict conformity but will
provide a finished product equal to or better than that intended by the requirements of the
Contract Documents.
bear costs of correcting such rejected Work, including additional testing and inspections and
compensation for the Department made necessary thereby. If prior to the date of Substantial
Completion, the Contractor, a Subcontractor, or anyone for whom either is responsible, uses or
damages any portion of the Work, the Contractor shall cause such damage to be restored so
that the damaged portion of the Work to "like new" condition at no expense to the Department.
If at any time after the date of Substantial Completion of the Work any of the Work is found to be
not in accordance with the requirements of the Contract Documents, the Contractor shall correct
it promptly after receipt of written notice from the Department to do so unless the Department
has previously given the Contractor a written acceptance of such condition. This obligation
under this Section 22.4 shall survive acceptance of the Work under the Contract and termination
of the Contract. The Department shall give such notice promptly after discovery of the condition.
The obligations under Section 22.3 (Obligations of Contractor) shall cover any repairs and
replacements to any part of the Work or other property caused by the defective Work.
After Substantial Completion, if the Contractor fails to correct the Work that has been rejected
by the Department or fails to conform to the requirements of the Contract Documents within the
time frame determined by the Department, the Department may correct or remedy such Work.
All direct and indirect costs from the Contractor’s failure to correct the Nonconforming Work and
the Department’s correction of such Work will be the sole expense of the Contractor.
When the Contractor delivers the executed PDBC to the Department, the Contractor shall also
deliver to the Department such bonds as the Contractor may be required to furnish in
accordance with this Section 23. Upon request, the Contractor shall also provide copies of such
bonds to its subcontractors and other entities providing labor, Equipment, or Materials on the
Project.
The Contractor shall deliver the foregoing Bonds to the Department according to the following
schedule:
1. Concurrent with the execution of this PDBC in the amount equal to 100% of the Phase
1 Contract Price.
2. Concurrent with the execution of each Early Work Change Order in the amount equal
to 100% of the applicable Early Work Package Contract Price (in aggregate at any
time during Phase 1 secures the full amount of the Phase 1 Contract Price and all
Early Works Packages).
3. Concurrent with the execution of the Phase 2 Change Order in an amount equal to
100% of the Phase 2 Contract Price. This amount is the aggregate of both the amount
of the Phase 1 Contract Price and the Phase 2 Contract Price. This shall secure the
full scope of the Phase 1 Work and Phase 2 Work.
4. Following the Department’s acceptance of the Phase 1 Work, the Contractor may
request to reduce the amount secured to 100% of the Phase 2 Contract Price.
If the surety on any bond furnished by the Contractor: (1) is declared a bankrupt; (2) is placed
into receivership; (3) becomes insolvent or its right to do business is terminated in any state
where any part of the Project is located; or (4) ceases to meet the requirements of the Contract
Documents, the Contractor shall within 20 Days thereafter substitute another Bond issued by a
surety acceptable to the Department, both of which shall comply with the requirements of the
Contract Documents.
All bonds and insurance required by the Contract Documents to be purchased and maintained
by the Department or the Contractor shall be obtained from surety or insurance companies that
are duly licensed or authorized in the jurisdiction in which the Project is located to issue bonds
or insurance policies for the limits and coverages so required. Such surety and insurance
companies shall also meet such additional requirements and qualifications as may be provided
in the Contract Documents.
If notice of any change affecting the general scope of the Work or the provisions of the Contract
Documents (including, but not limited to, Contract Price or Contract Times) is required by the
provisions of any bond to be given to a surety, the giving of any such notice will be the
Contractor's responsibility. The amount of each applicable bond will be adjusted to reflect the
effect of any such change.
All Work furnished by the Contractor will be performed by or under the supervision of Persons
that hold all necessary, valid licenses to practice in the State of Ohio and Commonwealth of
Kentucky, depending where the Work is to occur, by personnel who are skilled, experienced
and competent in their respective trades or professions, who are professionally qualified to
perform the Work in accordance with the Contract Documents and who shall assume
professional responsibility for the accuracy and completeness of the Design Documents,
Construction Documents, and other documents prepared or checked by them, as and when
applicable.
The Contractor acknowledges and agrees that the award of this PDBC by the Department to the
Contractor was based, in part, on the qualifications and experience of the personnel listed in the
Proposal, and the Contractor's commitment that such individuals would be available to
undertake and perform the Work. In addition to ratifying the representations, warranties, and
covenants set forth in the “Key Personnel Commitments” attached to Exhibit D (Key Personnel
and Principal Participants), the Contractor represents, warrants and covenants that such
individuals are available for and will fulfill the roles identified for them in the Proposal in
connection with the Work. Key Personnel shall commit the amount of time to their applicable
roles as set forth in the Contract Documents.
The Contractor shall comply with, and ensure that all of its Subcontractors comply with all
applicable Laws, including but not limited to sub-sections A & B below:
A. Contractor shall ensure that it and all of its Subcontractors observe and comply with all
of the following that affect the conduct of Work on the Project, have jurisdiction or
authority over the Work, or that affect individuals engaged or employed on the Project.
1. Ohio, Kentucky, and Federal laws;
2. All local laws, ordinance and regulations;
3. All orders and decrees of authorities having jurisdiction or authority that affect
those engaged or employed on the Work or that affect the conduct of the Work;
4. Health and safety officials and regulations; and
5. ODOT Construction Safety Health Manual.
B. Comply with Federal, State, and local Laws, rules, and regulations that enumerate
unlawful employment practices.
The Contractor has complied and shall comply with the foregoing at its sole cost and without
any additional compensation or time extension on account of such compliance, regardless of
whether such compliance would require additional time for performance or additional labor,
Equipment or Materials not expressly provided for in the Contract Documents, except, and only
to the extent, of any express entitlement to seek relief hereunder.
The Phase 2 Change Order will incorporate a representation that the Contractor:
1. has evaluated the constraints affecting design and construction of the Project, as well
as the terms and conditions of the NEPA Documents, and has reasonable grounds for
believing and does believe that the Project can be designed and built within such
constraints; and
2. has conducted a reasonable investigation and otherwise examined the Site as well as
surrounding locations, and as a result of such review, inspection, examination, and
other activities the Contractor is familiar with, and has satisfied itself as to, the
character of the Site, and accepts the physical requirements of the Work, subject only
to the Contractor’s express rights and bases to seek relief under this PDBC.
24.7 Power and Authority
The Contractor has the requisite power (a) to carry on its business as now conducted or
proposed, and (b) to own its properties and assets.
The Contractor has full power, right and authority to execute and deliver the Contract
Documents and to perform each and all of the obligations of the Contractor provided for herein
and therein.
The Contractor has all requisite power to own its properties and assets and carry on its
business as now conducted or proposed to be conducted.
24.9 Authorization
The execution, delivery, and performance of this PDBC have been duly authorized by all
necessary actions of the Contractor, and, if applicable, the Contractor’s members, and will not
result in a breach or a default under the organizational documents of any such Person or any
indenture, loan, credit agreement, or other material agreement or instrument to which any such
Person is a party or by which its properties and assets may be bound or affected.
[Each]/[The] individual person executing this Contract and all other such Project related
documents, on behalf of the Contractor has been (or at the time of execution will be) duly
authorized to execute and deliver each such document on behalf of the Contractor; and the
Contract Documents, and all such other Project related documents have been (or will be) duly
executed and delivered by the Contractor.
24.11 No Breach
As of the Effective Date, no event that, with the passage of time or the giving of notice, would
constitute a breach hereunder has occurred and has not yet been cured.
24.12 No Conflicts
Neither the execution and delivery by the Contractor of this PDBC, the Contract Documents, nor
the consummation of the transactions contemplated hereby or thereby, is (or at the time of
execution will be):
1. In conflict with or has resulted or will result in a default under or a violation of the
governing instruments of the Contractor or any agreement, judgment, or decree to
which the Contractor is a party or is bound; or
2. In conflict with any Applicable Laws applicable to the Contractor that are valid and in
effect on the Effective Date.
24.13 No Violation of Law
As of the Effective Date, the Contractor is not in breach of any applicable Law that would have a
material adverse effect on the Work or the performance of any of its obligations under the
Contract Documents.
24.14 No Suits
There is no action, suit, proceeding, investigation or litigation pending and served on the
Contractor that challenges the Contractor’s authority to execute, deliver or perform, or the
validity or enforceability of, the Contract Documents, or that challenges the authority of the
Contractor’s official executing the Contract Documents; and the Contractor has disclosed to the
Department prior to the Effective Date any pending and un-served or threatened action, suit,
proceeding, investigation or litigation with respect to such matters of which the Contractor is
aware. The Contractor has no current, pending or outstanding criminal, civil, or enforcement
actions initiated by the Department, the Cabinet, the State of Ohio, or the Commonwealth of
Kentucky, and agrees that it will immediately notify the Department of any such actions.
person who has a critical influence on or substantive control over the operations of the
Contractor.
The Contractor agrees to include the above clause in each subcontract financed in whole or in
part with Federal assistance provided by FTA. It is further agreed that the clauses shall not be
modified, except to identify the subcontractor who will be subject to the provisions.
(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the
Contractor, to any person for influencing or attempting to influence an officer or
employee of any agency, a member of Congress, an officer or employee of Congress,
or an employee of a member of Congress in connection with the awarding of any
Federal contract, the making of any Federal grant, the making of any Federal loan, the
entering into of any cooperative agreement, and the extension, continuation, renewal,
amendment, or modification of any Federal contract, grant, loan, or cooperative
agreement.
(2) If any funds other than Federal appropriated funds have been paid or will be paid to
any person for influencing or attempting to influence an officer or employee of any
agency, a member of Congress, an officer or employee of Congress, or an employee
of a member of Congress in connection with this Federal contract, grant, loan, or
cooperative agreement, the Contractor shall complete and submit Standard Form-
LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions.
(3) The Contractor shall require that the language of this certification be included in the
award documents for all subawards at all tiers (including subcontracts, subgrants, and
contracts under grants, loans and cooperative agreements) and that all subrecipients
shall certify and disclose accordingly.
This certification is a material representation of fact upon which reliance was placed when this
transaction was made or entered into. Submission of this certification is a prerequisite for
making or entering into this transaction imposed by Section 1352, title 31, U.S. Code. Any
person who fails to file the required certification shall be subject to a civil penalty of not less than
$10,000 and not more than $100,000 for each such failure.
constitute a waiver of the Claim and shall bar any recovery there under. At a minimum, the
auditors shall have available to them the following documents:
Notwithstanding the foregoing, all records which relate to Claims being processed or actions
brought under the dispute resolution provisions hereof shall be retained and made available
until three years after such actions and Claims have been finally resolved. Records to be
retained include all books and other evidence bearing on the Contractor's costs and expenses
under the Contract Documents. The Contractor shall make these records and documents
available for audit and inspection by the Department and/or FHWA, at the Contractor's office,
during reasonable business times, without charge, and shall allow such Persons to make copies
of such documents (at no expense to the Contractor).
If the foregoing procedure is not followed by the Contractor, then the Department will release
versions of any document, data, or record that the Department determines to be responsive to
the request and do not violate Applicable Law, with all satisfaction and payment of such
expense(s) incurred in such determination and release being the full responsibility of the
Contractor.
In the event that the requestor asserts a right to any redacted information in the Department
Response with regard to any complete or partial document(s), data, or record(s), the
Department shall notify the Contractor of the assertion of right(s) (the “Notice of Rights”), and
from the date the Contractor receives the Notice of Rights, the Contractor shall have the
responsibility to respond to the requestor asserting that the information requested is exempt
from disclosure under Applicable Law.
In the event of litigation concerning the Department’s failure to disclose any material submitted
by the Contractor to the Department, the Department’s sole involvement will be as a stakeholder
retaining the material until otherwise ordered by a court, and the Contractor shall be fully
responsible for otherwise prosecuting or defending any action concerning the materials at its
sole expense and risk and fully responsible for paying any costs, fees, including attorney’s fees,
and civil penalties assessed against the Department for failing to disclose such documents in
accordance with the Contractor’s directions. Under no circumstances, however, will the
Department be responsible or liable to the Contractor or any other Person for the disclosure of
any such labeled materials, whether the disclosure is required by law, by court order or occurs
through inadvertence, mistake or negligence on the part of the Department. Nothing in this
Section shall modify or amend any requirement(s) and obligation(s) imposed on the Department
by the Public Records Law or other applicable Law, and the provisions of the Public Records
Law or other Laws shall control in the event of conflict between the procedures described above
and the applicable law. The Contractor is advised to contact legal counsel concerning the Ohio
Open Records Act and its application to the Contractor.
are provided for the joint use of the Contractor and the Department. The Contractor agrees, as a
requirement of the Contract, that the Escrow Documents, as updated from time to time,
constitute all the information used in the development of the Contract Price. The Contractor
acknowledges that the purpose of the Escrow Agreement and this Section 25.7 is to develop the
Contract Price through open-book negotiations and that the Contractor’s prompt and
transparent provision of the Escrow Documents is vital to the development of the Contract Price.
The Contractor also agrees that nothing in the Escrow Documents shall change or modify the
terms or conditions of the Contract Documents.
Subject to Section 25.6 (Public Records), the Department further agrees to safeguard the
Escrow Documents, and all information they contain, against disclosure to the fullest extent
permitted by law.
25.7.4 Submittal
A. The Contractor will submit the Escrow Documents in sealed containers to the
Department, which containers have been clearly marked on the outside with the
Contractor’s name, reference to the Project, and the words “Brent Spence Bridge
Corridor Project Escrow Documents”.
B. On or reasonably after the scheduled Escrow Documents Submission Date,
representatives of the Department, assisted by members of the Contractor’s staff who
are knowledgeable in how the Escrow Documents were prepared, will have examined,
organized and inventoried the Escrow Documents. This examination is to ensure that
the Escrow Documents are legible and complete. It does not include review of, and
does not constitute approval of proposed construction methods, estimating
assumptions, or interpretations of any Work Package Pricing Proposal, including this
PDBC. Such examination will not alter any condition or term of any Construction
Documents.
Timely submission of complete Escrow Documents as of the corresponding Escrow Documents
Submission Date is an essential element of the Contractor’s responsibility and a prerequisite to
the execution and delivery of this Contract by the Department.
25.7.6 Storage
The Escrow Documents will be stored at the following address:
_______________ Bank
__________________________
__________________________
Attention: _________________
Phone: ____________________
Facsimile: __________________
The Contractor will bear the cost for storing the Escrow Documents.
25.7.8 Ownership
The Escrow Documents are, and will always remain, the property of the Contractor, subject to
joint review by the Department, if applicable Department Authorized Representatives and the
Contractor, as provided herein. To the extent that any document in escrow is a Design
Document, it shall be the property of the Department.
If the Department exercises its right under Section 12 (Contract Changes) to contract with other
contractors to perform outstanding Work on the Project, the Contractor shall coordinate with
such other contractors in good faith to facilitate completion of the Project in a timely and
effective manner.
Department Authorized Representatives may inspect the certified payroll and other payroll
records. Upon completion of the Work and before receiving payment for the Final Estimate and
when required by ORC 4115.07, submit an affidavit stating that wages have been paid
according to the minimum rates specified in the Contract Documents.
26 MISCELLANEOUS
26.1 Waiver
26.1.1 No Waiver of Subsequent Rights
Either Party's waiver of any breach or failure to enforce any of the terms, covenants, conditions,
or other provisions of the Contract Documents at any time shall not in any way limit or waive
that Party's right thereafter to enforce or compel strict compliance with every term, covenant,
condition, or other provision, any course of dealing or custom of the trade notwithstanding. The
consent by one Party to any act by the other Party requiring such consent shall not be deemed
to render unnecessary the obtaining of consent to any subsequent act for which consent is
required, regardless of whether similar to the act for which consent is given.
Department's prior written approval, in the Department's sole discretion. Except and after any
Approval only, any of the foregoing actions shall be null and void ab initio and otherwise
ineffective to relieve the Contractor of its responsibility for the Work assigned or delegated.
The Contractor shall not change the legal form of its organization in a manner that adversely
affects the Department's rights, protections and remedies under the Contract Documents
without the prior written approval of the Department, in the Department's sole discretion.
The Department has the right to terminate the Contract and exercise its remedies in respect of a
Contractor event of default if the Contractor’s liability to the Authority exceeds such limitation on
liability.
Such limitation on liability applies only to damages payable by the Contractor to the Department
for non-performance under the Contract and will not apply if the Contractor abandons the
Project or to any of the following:
A. Any loss, cost or expense incurred by any Contractor team member in the
performance of the Contract or in seeking to cure or prevent any breach of the
Contract by the Contractor;
B. Any fines or penalties levied or imposed by any Governmental Agency;
C. Any claims, losses or penalties incurred by any Contractor team member to third
parties in any legal proceedings;
D. Any indemnity payment (resulting from third party claims) made by the Contractor to
any Indemnified Party;
E. Payment of any defense costs, including attorney’s fees, to, for, or on behalf of any
Indemnified Party with respect to any third-party claim;
F. Any payments made in connection with any insurance required under the Contract,
including the proceeds of such insurance and the payment of any deductible or self-
insured retention; and/or
G. Any claims, losses, penalties or settlement payments paid to the Department in
connection with any tort claim by the Department against any Contractor team
member based on gross negligence, willful misconduct or fraud.
26.4 Title and Risk of Loss
Title to the structures, improvements, fixtures, machinery, Equipment and Materials constituting
the Project will pass to Department upon incorporation in the Project or payment therefor by the
Department, whichever first occurs, free and clear of all liens, claims, security interest or
encumbrances. Except with respect to certain uninsurable events to be specified in the
Contract, the Contractor will nonetheless bear all risk of loss concerning such structures,
improvements, fixtures, machinery, Equipment and Materials until the Substantial Completion
Deadline, regardless of the extent to which the loss was insured or the availability of insurance
proceeds.
26.5 Survival
The dispute resolution provisions contained in Section 18 (Partnering and Dispute Resolution),
the warranties in Section 22 (Project Warranties), all of the indemnification provisions, and all
other provisions, which by their inherent character should survive Contract Completion or
termination of the PDBC, shall survive Contract Completion or the termination of the PDBC.
Frankfort, KY 40622
DBL Law
Covington, KY 41011
As to ODOT: Director
Columbus, OH 43223
Columbus, OH 43223
Cincinnati, OH 45202
26.8 Severability
If any clause, provision, Section or part of this PDBC is ruled invalid under Section 18
(Partnering and Dispute Resolution) or otherwise by a court of competent jurisdiction, then the
parties shall: (i) promptly meet and negotiate a substitute for such clause, provision, Section or
part, which shall, to the greatest extent legally permissible, effect the original intent of the
parties, including an equitable adjustment to the applicable compensation and Completion
Deadline(s) to account for any change in the Work resulting from such invalidated portion; and
(ii) if necessary or desirable, apply to the court or other decision maker (as applicable) which
declared such invalidity for an interpretation of the invalidated portion to guide the negotiations.
The invalidity or unenforceability of any such clause, provision, Section or part shall not affect
the validity or enforceability of the balance of this PDBC, which shall be construed and enforced
as if this PDBC did not contain such invalid or unenforceable clause, provision, Section or part.
26.12 Headings
The captions of the Sections of the Contract Documents are for convenience only and shall not
be deemed part of this Contract or considered in construing this Contract.
Wherever the word “including,” and variants, shall be deemed to be followed by the words
“without limitation”. Unless otherwise specified, lists contained in the Contract Documents
defining the Project or the Work shall not be deemed all-inclusive. “Or” means the inclusive
connotation of “or” (i.e., meaning one, some, or all of a number of possibilities). “May,” when
used in the context of a power or right exercisable by the Department (or either's designee)
means the power to exercise that right or power in its sole discretion, with no obligation to any
Contractor-Related Entity to do so. “May,” when used in all other contexts, indicates permission
by the Department for the Contractor to do (or refrain from doing) an action.
All references to time are to prevailing Eastern time. Reference to a right include any benefit,
remedy, discretion, authority, or power associated with such right.
There shall be no double counting in any calculation of any amount payable by a Party, such
that the receiving Party would receive more than owed or payable. All monetary amounts and
obligations (including use of the symbol “$”) are expressed and payable in U.S. dollars.
The fact that the Contract Documents omit or misdescribe any detail of the Work that is
otherwise necessary to carry out the intent of the Contract Documents and delivery of the
Project, or that are customarily performed, shall not relieve the Contractor from its obligation to
perform such omitted or misdescribed details as if fully and correctly set forth in the Contract
Documents, which omissions, correction of misdescriptions, or performance of those aspects
customarily performed shall not in itself be the basis for contractual relief, or other claim at law
or in equity.
26.16.3 Creation
Design Documents shall become Owner Intellectual Property upon preparation in accordance
with Section 26.14 (Ownership of Copyright Submittals). Construction Documents shall become
Owner Intellectual Property upon receipt by the Department preparation in accordance with
Section 26.14. All other submittals and other documents prepared or obtained by Contractor or
any Contractor-Related Entity in connection with the Project shall become Owner Intellectual
Property upon Contractor’s or any such Contractor-Related Entity's preparation or receipt
thereof.
The Department represents that it is exempt from all State and local taxation. As long as the
Department is exempt, the Department does not agree to pay any of these taxes. The
Contractor, not the Department, shall pay any taxes levied upon the Contractor’s net income.
Each Subcontractor shall require all lower-tier Subcontractors that provides labor on the Project
Site with whom the Subcontractor is in contract for the Work to be enrolled in and be in good
standing in the OBWC-approved DFSP prior to a lower-tier Subcontractor providing labor at the
Site.
The Department will declare a bid non-responsive and ineligible for award if the Contractor is
not enrolled and in good standing in the Ohio Bureau of Workers’ Compensation’s Drug-Free
Safety Program (DFSP) Discount Program or a similar program approved by the Bureau of
Workers’ Compensation within 8 days of the bid opening. Furthermore, the Department will
deny all requests to sublet when the Subcontractor does not comply with the provisions of this
section.
The Contractor shall not employ any person currently employed by the Department for any
Phase 1 Work. The Contractor may have other contracts with other clients (e.g., utility
companies, other units of government, or abutting land owners) whose interests may be in
conflict with the objectives of a particular Department-initiated project. It is the Contractor’s
responsibility to avoid conflicts of interest in these circumstances and to disclose them as soon
as they arise.
The Department retains title to all Department-furnished property or equipment. The Contractor
shall notify the Department of damages and/or other discrepancies discovered upon receipt of
Department-furnished property or equipment. The Contractor shall be responsible to correct
damage to Department-furnished property or equipment caused by the Contractor’s actions.
IN WITNESS WHEREOF, the Parties have executed this PDBC as of the Effective Date.
STATE OF OHIO
DEPARTMENT OF TRANSPORTATION
________________________________
Jack Marchbanks
Director of Transportation
________________________________
Date
***********************
________________________________
Attorney General
David Yost
[CONTRACTOR]
________________________________
________________________________
Name
________________________________
Title
________________________________
Date
AASHTO Uniform Audit & Accounting Guide means the guide published by AASHTIO that
includes detailed information regarding techniques for cost allocation, application of Federal
procurement regulations, and the proper treatment of operating costs incurred by organizations
for engineering and design-related services performed on various Federal, State, and Local
transportation projects.
Administrative Proposal means the proposal materials submitted by an Offeror providing the
information requested in ITO Section 6.7 (Administrative Proposal).
Affiliate means (i) any person, organization or firm that directly or indirectly, through one or
more intermediaries, controls, is controlled by, or is under common control with the Contractor
or any Principal Participant; or (ii) any organization or firm for which 10 percent or more of the
interest in such organization or firm is held directly or indirectly, beneficially or of record, by (a)
the Contractor; (b) any Principal Participant; or (c) any Affiliate under part (1) of this definition.
Alternative Technical Concept (ATC) means a concept proposed by the Contractor during the
Preconstruction Phase as further described in Technical Requirements Section 2.3 (Design
Submittals) of the PDBC.
As-Built Drawings means documents that depict the final completed Project, including all
changes from RFC Documents and data showing all items such as the electrical systems,
drainage systems, lighting systems, underground Utilities, traffic controls, intelligent
transportation system, signing placement, highway alignment and grade revisions, bridge detail
changes, bridge settlement reference elevations and joint seal measurements, typical sections,
cross sections, and all other relevant data.
As-Built Schedule has the meaning assigned in Exhibit T (Critical Path Method Progress
Schedule).
Audit or Financial Review is a formal examination of accounting systems, cost records, and
other cost presentations to verify their reasonableness, allowability, and allocability for
negotiating fees and for determining costs for Federal, Department, and Local participation and
reimbursement. Audits and Financial Reviews may include, but are not limited to, an evaluation
of the Contractor’s policies, procedures, controls, and actual performance. Objectives of Audits
and Financial Reviews include the identification and evaluation of all activities that contribute to,
or have an impact on, proposed or incurred costs under the PDBC. Audits and Financial
Reviews may include inquiries conducted electronically (by correspondence or email) and also
may involve fieldwork (the examination of financial records at the Contractor’s business offices).
Authorized Representative has the meaning set forth in ITO Section 4.2 (Authorized
Representatives and Offeror Registration).
Base Design means initially, the drawings depicting the design of the Project provided by the
Department during the RFP phase and included in the Technical Requirements, as validated by
the Contractor during Sub-Phase 1A and further developed by the Contractor during Sub-Phase
1B such that the Base Design depicts the layout of the Project included in the Phase 2 Project
Scope and used to develop the Phase 2 Change Order.
Baseline Schedule has the meaning assigned in Exhibit T (Critical Path Method Progress
Schedule) Section 1.4.1 (Interim Baseline and Baseline Schedules).
Best Management Practices or BMP has the meaning set forth in Storm Water Management
for Construction Activities: Developing Pollution Prevention Plans and Best Management
Practices (EPA Document 832 R 92 005).
Best Management Practice Plan means the documentation detailing how the Contractor
intends to conform to the requirements of Section 213 of the KYTC Standard Specifications.
Betterment means any upgrade of a utility company’s facility being relocated that is not
attributable to the Construction Work and is made solely for the benefit of and at the election of
the utility company.
Blue Book has the meaning assigned in Exhibit H (Force Account Provisions).
A. Length. The length of a bridge structure is the overall length measured along the
centerline of the roadway surface.
B. Roadway Width. The clear width measured at right angles to the longitudinal
centerline of the bridge between the bottom of curbs or guard timbers or, in the case
of multiple heights of curbs, between the bottoms of the lower risers. For curb widths
of 1 foot (0.3 m) or less, the roadway width is measured between parapets or railings.
Buildable Unit means a unit of Work that is suitable to be packaged as a Submittal because
the unit of Work is capable of being designed, reviewed, and constructed independently from
other units of Work or with clearly identified controls, constraints and assumptions governing the
interfaces with other units of Work. A Buildable Unit may be defined by a geographic area, by
types of Work or by construction stages.
Certificate of Current Cost or Pricing Data means a certificate in the form in paragraph (a) of
48 CFR 15.406-2.
Certified Test Data means test report from a manufacturer’s or an independent laboratory
approved by the Department listing actual test results of samples tested for compliance with
specified Department requirements. The Department will accept certified test data from
manufacturers’ laboratories if their products have been used satisfactorily on prior Department
contracts and their test data has been confirmed. Include a statement that the test data
furnished is representative of the material furnished to a Department project or to a supplier.
The report is identified by number or date and identifies the Department project or supplier to
which the material is shipped. Submit reports signed by a person having legal authority to act for
the manufacturer or independent laboratory.
Change Order means a written order issued by the Department to the Contractor, covering
changes to the terms and conditions, Base Design and/or contract quantities, within or beyond
the scope of the Contract and establishing the basis of payment and time adjustments for the
Work affected by the changes.
Claim means a Dispute that is not settled through Steps 1 or 2 of the Dispute Resolution
Procedures. A Dispute becomes a Claim when the Contractor submits a notice to escalate to
Step 3 of the Dispute Resolution Process.
Claims Documentation shall have the meaning assigned to such term under Section 18.4.8
(Procedures for Consideration of Disputes) of the PDBC.
Clean Hard Fill has the meaning assigned in CA-EW-20 (ODOT Beneficial Reuse Form).
Closure means that all or part of any traffic lanes, ramps, cross roads, shoulders or sidewalks
are closed or blocked, or that the use thereof is otherwise restricted.
Commencement Date means the commencement date for the performance of the Sub-Phase
1A Work, the Sub-Phase 1B Work, any Early Work Package or the Phase 2 Work which shall
be the date described as the 'Commencement Date' in the Notice to Proceed applicable to the
Work.
Commercial Quality or Grade means Materials readily available from commercial sources.
These materials require no sampling or testing as applicable to KYTC Standards and
Specifications.
Community Engagement Plan means the plan setting forth how the Contractor will support the
local community as described in Section 5.8 (Community Engagement Plan) of Exhibit E
(Technical Requirements) as may be amended in the Project Scope.
Companion Bridge means the new Bridge over the Ohio River adjacent to the Existing Brent
Spence Bridge.
Completion Deadline means the date shown in the Contract Documents upon which a
Milestone is scheduled to be achieved as such date may be extended in accordance with the
Contract Documents.
Completion of the Contract has the meaning set forth in Section 5.14.4 (Completion of the
Contract and Continuation of Contractor’s Responsibilities) of the PDBC.
Completion of the Contract Date means the date of the Department’s letter confirming
Completion of the Contract.
Completion of the Contract Deadline means the date to be established by the Parties by
which Completion of the Contract shall be achieved, which shall be a specified number of days
after the Substantial Completion Date.
Component Firm means any firm that is contemplated by the Contractor to perform Work on
the Project for or on behalf of the Contractor, including the Contractor, DBT, Principal
Participants, Major Participants, Designers, Subcontractors and Subconsultants.
Conceptual Design means design information provided by the Department including the layout
of the Project described in Section 1 (General) of Exhibit E (Technical Requirements) and LD-07
(Concept I-W Exhibit).
Construction Documents means all shop drawings, working drawings, fabrication plans,
material and hardware descriptions, specifications, construction quality control reports,
construction quality assurance reports and samples developed by the Contractor and necessary
or desirable for construction of the Project and/or the Utility Relocations included in the
Construction Work, in accordance with the Contract Documents and the Special Provisions.
Construction Period means the period beginning on the date the Department authorizes the
commencement of Construction Work per Section 5.2 (Phase 2 Preconstruction and Progress
Meetings) of the PDBC and ending on the Substantial Completion Date.
Construction Quality Management Plan (CQMP) means the Contractor’s plan to ensure
quality control and quality acceptance procedures for the Construction Work prepared in
accordance with Section 3 (Quality Management) of Exhibit E (Technical Requirements) as may
be amended in the Project Scope.
Construction Work means all Work related to the construction of the Project including
furnishing all Materials, goods, and Equipment and performing all construction, installation,
inspection, testing, and other services required to complete the fully functional Project and the
Phase 2 Work, whether temporary or permanent but excluding the Design Work. Early Work
performed during Phase 1 may include Construction Work.
Contingency means monetary set-asides by the Contractor for cost and time and duration set-
asides by the Contractor for schedule included (or proposed to be included, as the context
requires) within the Contract Price or the Project Schedule.
Consumer Price Index or CPI means the Consumer Price Index All items (BES Series ID
CUUR0000SA), as published by the United States Department of Labor. Bureau of Labor
Statistics, for which the base year is 1982-84 = 100, or if such publication ceases to be in
existence, a comparable index selected by the Department and approved by the Contractor,
acting reasonably. If such index is revised so that the base year differs from that set forth above,
the CPI shall be converted in accordance with the conversion factor published by the United
States Department of Labor, Bureau of Labor Statistics. If the Bureau of Labor Statistics
otherwise alters its method of calculating such index, the Parties shall mutually determine
appropriate adjustments in the affected index.
Contract means the PDBC (the written agreement between the Department and the Contractor
setting forth the obligations of the Parties, including, but not limited to, the performance of the
Work and the basis of payment).
Contract Completion Time means the time assigned in the Baseline Schedule accepted by the
Department to achieve Substantial Completion.
Contract Documents means the PDBC and its exhibits, general and detailed plans, Plan
notes, Standard Construction Drawings identified in the Plans, Phase Change Orders, Change
Orders, Supplemental Agreements, “Accepted” and “Accepted as Noted” Working Drawings,
and any other document designated by the Department as a Contract Document, all of which
constitute one instrument.
Contract Item (Pay Item) means a specifically described unit of Work for which a price is
provided in the Contract.
Contract Price means the amount of compensation to be paid by the Department to the
Contractor for the Phase 2 Work or for a Work Package or Buildable Unit (depending on the
context) as such amount may be modified pursuant to the Contract Documents.
Contract Time means the number of Workdays or Days, including authorized adjustments,
allowed for completion of the Project. When a specified Completion Deadline is shown in the
Contract Documents instead of the number of Workdays or Days, completion of the Project shall
occur on or before that date. Specified Completion Deadline shall be completed on or before the
day indicated even when that date is a Saturday, Sunday, or holiday.
Contractor means the individual, firm, corporation or joint venture, which may include the
Designer if qualified under the provisions of ORC 5526.04, contracting with the Department for
performance of prescribed Work, acting directly or through a duly authorized representative and
qualified under the provisions of ORC 5525.02 to 5525.09 inclusive, and any amendments
thereto.
Contractor’s Representative means the person assigned with full authority to represent and
act for the Contractor as set forth in Section 10.1.2 (Contractor’s Representative) of the PDBC.
Contractor Default has the meaning assigned in Section 19.1.1 (Events of Default by the
Contractor) of the PDBC.
Contractor Risk is a Risk Register Event in which the Contractor is not eligible for relief, as
further identified on the Risk Register.
Contractor Submittals Listing & Schedule is defined in Section 4.7 (Contractor Submittals
Listing & Schedule) of the PDBC.
Controlling Board means the State Controlling Board as defined in ORC Chapter 127.
Corrective Action means the action taken by which the Nonconforming Work is made
compliant with the Contract Documents.
Corrective Action Request means the Contractor’s plan for taking Corrective Action in respect
of Nonconforming Work, in accordance with Technical Requirements Section 3.7
(Nonconforming Work) of the PDBC.
Corrective Work Plan (CWP) means the plan described in ODOT C&MS Section 501.05.C
(Corrective Work).
Cost Accounting Standards (CAS) are issued by the Cost Accounting Standards Board
(CASB), a section of the Office of Federal Procurement Policy within the U.S. Office of
Management and Budget. The CASB has the exclusive authority to issue and amend cost
accounting standards and interpretations designed to achieve uniformity and consistency in the
cost accounting practices governing the measurement, assignment, and allocation of costs to
contracts that involve Federal funds. The CAS are codified at 48 CFR Chapter 99.
Cost Accounting System means a type of accounting system that allows for the systematic
and timely classification, recording, allocation, presentation, and interpretation of costs, either
actual or proposed, as paid or required to be paid in the performance of the applicable portion of
the Work. For each FAR Participant, the Cost Accounting System shall articulate with, and/or be
integrated with, the organization’s general ledger and financial management system. The use of
a Cost Accounting System is required by FAR Participants, as these systems provide for the
consistent allocation of costs to cost objectives (direct and indirect activities). Cost Accounting
Systems generally involve a higher level of accountability and detail than is present in simple
financial accounting systems that merely track and accumulate costs by category (expense
type), rather than by both categories and cost objectives. For specifics regarding the proper
design and maintenance of Cost Accounting Systems, see the AASHTO Uniform Audit &
Accounting Guide, Chapters 5 through 8.
Cost Model means the open and transparent model that the Contractor develops and uses with
respect to the applicable portion of the Work so that estimates and assumptions are
communicated to the Department, the Independent Cost Estimator, and the State Cost
Estimator prepared in accordance with Exhibit G (Pricing Process).
County means the designated county or counties in which the Work specified is to be done.
Critical Activities means the activities that make up the Critical Path of activities.
Critical Path means the longest path of activities in the Project Schedule that controls the time
of completion of a Milestone.
Critical Path Method (CPM) means a scheduling method that utilizes the precedence diagram
approach to calculate each activity's early dates, late dates and float values in order to establish
the Critical Path through the activity network.
Culvert means any structure not classified as a Bridge that provides an opening under the
roadway.
DBE Outreach Plan means the outreach and communication plan regarding DBE participation
described in Section 5.3 (DBE Outreach Plan) of Exhibit E (Technical Requirements) as may be
amended in the Project Scope.
DBE Performance Plan means the performance plan for achievement of DBE compliance
described in Section 5.1 (DBE Performance Plan) of Exhibit E (Technical Requirements) as may
be amended in the Project Scope.
DBT Construction Manager means the Key Personnel of that name identified in Section 2.1.2
(Key Personnel) of Exhibit E (Technical Requirements).
DBT DBE/EEO Project Plan Coordinator means the Key Personnel of that name identified in
Section 2.1.2 (Key Personnel) of Exhibit E (Technical Requirements).
DBT Design Manager means the Key Personnel of that name identified in Section 2.1.2 (Key
Personnel) of Exhibit E (Technical Requirements).
DBT Design QC Manager means the Key Personnel of that name identified in Section 2.1.2
(Key Personnel) of Exhibit E (Technical Requirements).
DBT Independent Design Quality Firm Manager means the Key Personnel of that name
identified in Section 2.1.2 (Key Personnel) of Exhibit E (Technical Requirements).
DBT Lead Bridge Superintendent means the Key Personnel of that name identified in Section
2.1.2 (Key Personnel) of Exhibit E (Technical Requirements).
DBT Lead Highway Design Engineer means the Key Personnel of that name identified in
Section 2.1.2 (Key Personnel) of Exhibit E (Technical Requirements).
DBT Lead Highway Superintendent means the Key Personnel of that name identified in
Section 2.1.2 (Key Personnel) of Exhibit E (Technical Requirements).
DBT Lead Independent Companion Bridge Engineer means the Key Personnel of that name
identified in Section 2.1.2 of Exhibit E (Technical Requirements).
DBT Lead Structural Design Engineer means the Key Personnel of that name identified in
Section 2.1.2 (Key Personnel) of Exhibit E (Technical Requirements).
DBT Project Management Plan (DBT PMP) means the plan addressing management,
administration, design, investigations, construction, environmental monitoring and compliance
described in Section 2.1 (DBT Project Management Plan) of Exhibit E (Technical
Requirements).
DBT Project Manager means the Key Personnel of that name identified in Section 2.1.2 (Key
Personnel) of Exhibit E (Technical Requirements).
Daily Force Account Record means the record prepared and signed by the Parties on a daily
basis to record labor and Equipment used on the force account Work as further described in
Exhibit H (Force Account Provisions).
Debarment Regulations means (a) Federal Executive Order no. 12549 (Feb. 18, 1986), (b)
Federal Executive Order no. 12689 (Aug. 16, 1989), (c) 31 U.S.C. § 6101 note (Section 2455,
Pub. L. 103-355, 108 Stat. 3327) and (d) 49 CFR Part 29 “Government wide Debarment and
Suspension (Non-procurement)”.
Delay Schedule has the meaning assigned in Exhibit T (Critical Path Method Progress
Schedule) Section 1.7 (Revision and Delay Schedules).
Department means the Ohio Department of Transportation and may be used interchangeably
with State or ODOT. Each reference to the Department shall be deemed to include the
Department’s Authorized Representatives.
Department-Provided Approvals means each of the Governmental Approvals for the Project
to be provided by the Department, in each case on the basis of the Base Design, as more fully
described in the Project Scope.
Department’s Decision means the Department’s decision regarding the Contractor’s request
for an extension of any Completion Deadline and/or the applicable portion of the Contract Price
due to Delay Costs in accordance with Section 13 (Time Extension To The Completion
Deadlines And Payment For Excusable Delays) of the PDBC.
Design-Build Team (DBT) means the Contractor and its Subconsultants and Subcontractors.
Design Documents means all drawings (Plans), specifications, calculations, records, reports or
other documents, including shop drawings and working drawings, prepared by the Contractor,
which may be used for design, manufacture, fabrication, installation, testing, examination and
certification of items and which give a detailed and precise representation of the configurations
and arrangements of the materials and items being constructed in connection with the Project
based on the Contract Documents.
Design Quality Management Plan (DQMP) means the Contractor’s plan describing the
internal quality control and quality assurance procedures, prepared in accordance with Section
3.3 (Design Quality Management Plan) of Exhibit E (Technical Requirements).
Design Work means all Phase 1 Work or Phase 2 Work related to the design, redesign,
engineering, or architecture of the Project, including validation of the Base Design, development
of all required Design Documents and applicable Construction Documents required by the
PDBC.
Design and Construction Work means the Design Work and Construction Work, including
those obligations of the Contractor pertaining to design and construction set forth in the Project
Scope.
Designer means the individual, firm, or corporation that the Contractor designates to prepare
the Design Document(s) and is otherwised charged with the Design Document(s) portions of the
PDBC Contract (not necessarily including Work incorporated in the preparation of Working
Drawings) who prior to such undertaking receives the written consent of the Department,
provided such individual, firm or consultant must hold a Certificate of Authorization from the
Ohio State Board of Registration for Professional Engineers and Surveyors, Kentucky Board of
Engineers and Land Surveyors and has fulfilled the Prequalification requirements under ORC
5526.04 and KRS 45A.825.
Detailed Cost Analysis means a detailed cost analysis performed by the Contractor in
accordance with Section 13.4.1.1 (Detailed Cost Analysis) of the PDBC and submitted in
conjunction with an Excusable Delay Request.
Direct Cost is any labor or non-labor cost that can be traced to a specific Project, task,
program, activity or contract (final cost objective). All direct labor costs allocable to design and
engineering contracts (regardless of the contract type, e.g., lump sum versus actual cost) shall
be properly allocated to final cost objectives, and all direct labor costs shall be included in the
direct labor base, regardless of whether the costs are billable to a client.
Director means the Director of the Ohio Department of Transportation or authorized designee.
Disadvantaged Business Enterprise (DBE) has the meaning set forth in 49 CFR Part 26.
Dispute means any Claim, dispute, disagreement or controversy between the Department and
the Contractor concerning their respective rights and obligations under the Contract Documents,
including concerning any alleged breach or failure to perform and remedies.
Dispute Documentation shall have the meaning assigned to such term under Section 18.3.3
(Dispute Documentation and Rebuttal) of the PDBC.
Dispute Resolution Coordinator shall mean the Department official given such title by the
Director.
Disputed Work means any portion of the Work that is the subject of a Dispute or Claim filed by
the Contractor in accordance with the Dispute Resolution Procedures.
Dispute Resolution Procedures means the procedures for resolving disputes set forth in
Article 18 of the PDBC.
Early Work means any Work performed pursuant to an Early Work Package.
Early Work Package NTP means the NTP issued by the Department to the Contractor
pursuant to Section 2.8.4 (Notice to Proceed for Early Work) of the PDBC.
Early Work Package means any package comprising Design Work, Construction Work or both
that is proposed (or directed) to be performed during Phase 1, subject to execution of a related
Early Work Package Change Order and issuance of an Early Work NTP including any Early
Work Packages proposed under Section 2.3.3.1 (Early Work Package Proposal) of the PDBC.
Early Work Package Change Order means a Change Order issued by the Department to the
Contractor with respect to an approved Early Work Package.
Early Work Package Contract Price means, with respect to an Early Work Package, the total
compensation payable or to be payable, to the Contractor under a Change Order for the
completion of that Early Work Package, as may be modified by any authorized cost changes
under any further Change Orders. The basis for an Early Work Package Contract Price (GMP or
Lump Sum) shall be as set out in the accepted Early Work Proposal.
Early Work Package Proposal means the Contractor's proposal for the performance of an
Early Work Package in the form required and including the information required under Section
2.3.3.1 (Early Work Package Proposal) of the PDBC.
Emergency means any unforeseen event affecting the Project, whether directly or indirectly,
which (a) causes or has the potential to cause disruption to the free flow of traffic on the Project
or a threat to the safety of the public, (b) is an immediate or imminent threat to the long term
integrity of any part of the infrastructure of the Project, to the Environment or to property
adjacent to the Project or to the Safety of the Users or the traveling public; (c) is recognized by
the Ohio Department of Public Safety as an emergency; or (d) is recognized or declared by the
Governor of the State, the Federal Emergency Management Administration (FEMA), the U.S.
Department of Homeland Security or other Governmental Entity with authority to declare an
emergency.
Encroachment Permit has the meaning assigned in the ODOT or KYTC Encroachment Permit
Manual, as applicable.
Engineered Drawings means a type of working drawing that requires the practice of
engineering as defined in ORC 4733.01(E) or KRS 322.010 (4) (a), as applicable. Examples of
Engineered Drawings include: Excavation Bracing Plans, Demolition Plans, Erection Plans,
Falsework Plans, Cofferdam Plans, Causeway Plans, Jacking and Temporary Support Plans,
Plans for Heavy Equipment on Structures, Plans for structures for Maintaining Traffic, and
Corrective Work Plans.
Environmental Consultation Management Plan (ECMP) means the Contractor’s plan for
documenting and verifying compliance with the Environmental Commitments, prepared in
accordance with the Project Scope.
Equipment means all machinery and equipment, together with the necessary supplies for
upkeep and maintenance, and also tools and apparatus necessary for the proper design,
construction, and acceptable completion of the Work.
Estimate means the estimate for payment prepared by the Contractor and approved by the
Department, prepared in accordance with Section 11.2.4 (Estimates and Payments) of the
PDBC.
Escrow Agent means the banking institution or other bonded document storage facility agreed
by the Parties to be responsible for the escrow of the Escrow Documents under the Escrow
Agreement.
Escrow Agreement means the agreement executed and delivered by the Contractor, the
Departments and the Escrow Agent pursuant to Section 25.7 (Escrow Documents) of the
PDBC.
Escrow Documents has the meaning set forth in Section 25.7.1 (General) of the PDBC.
Escrow Documents Submission Date means the date on which any Escrow Documents are
scheduled to be submitted by the Contractor to the Escrow Agent to be held pursuant to the
Escrow Agreement.
Excusable Delay Request has the meaning set forth in Section 13.4.1 (Excusable Delay
Request) of the PDBC.
Existing Brent Spence Bridge has the meaning set forth in Section 1 (General) of Exhibit E
(Technical Requirements).
Extra Work means an item of Work not provided for in the Contract as awarded but found
essential to the satisfactory completion of the Contract within its intended scope.
FAR Participant means a Component Firm that has an indirect cost rate approved by ODOT's
Office of External Audits and/or the KYTC External Audit Branch and establishes and maintains
acceptable, fully articulated Financial and Cost Accounting Systems that track, classify, and
allocate costs in accordance with the requirements of FAR Part 31 and applicable Cost
Accounting Standards.
FHWA refers to the Federal Highway Administration of the United States Department of
Transportation.
Fabricator means the individual, firm, or corporation that fabricates structural metals or
prestressed concrete members as an agent of the Contractor.
Federal Requirement means those requirements set forth in attached Exhibit N (Contract
Provisions for Federal Aid Construction Projects).
Field Design Change (FDC) means design changes initiated by the Contractor to documents
approved and Released for Construction (RFC) are completed under a Field Design Change
(FDC). FDCs are subject to quality check or review activities.
Final Design means, depending on the context: (a) the Final Design Documents, (b) the design
concepts set forth in the Final Design Documents, which shall be substantially consistent with
the Contractor’s Base Design or (c) the process of development of the Final Design Documents.
Final Design Documents means the complete final construction drawings, including plans,
profiles, cross-sections, notes, elevations, typical sections, details and diagrams, specifications,
reports, studies, calculations, electronic files, records and submittals prepared by the
Contractor, necessary or related to construction and maintenance of the Project or any portion
thereof and any utilities included in the Design Work or the Construction Work.
Final Estimate means the estimate for payment prepared by the Contractor and approved by
the Department, prepared in accordance with Section 11.2.4 (Estimates and Payments) of the
PDBC.
Final Inspection means the final inspection performed by the Department as described in
Section 5.14.2 (Final Inspection and Substantial Completion) of the PDBC.
Final Inspection Punch List means an itemized list of Construction Work identified during
Final Inspection which remains to be completed after Substantial Completion has been
achieved and before Completion of the Contract, the existence, correction, and completion of
which will have no material or adverse effect on the normal and safe use and operation of the
Project.
Financial Proposal means the financial proposal submitted by an Offeror providing the
information requested in ITO Section 6.9 (Financial Proposal).
Float means the length of time along a given network path that the actual start and finish of
activity(s) can be delayed without delaying the Substantial Completion Deadline.
FONSI means the Finding of No Significant Impact for the Project on August 9, 2012.
Force Majeure Event has the meaning assigned in Section 14 (Force Majeure Events) of the
PDBC.
Geotechnical Report means the geotechnical report to be prepared by the Contractor for Work
within the Kentucky JDM in accordance with Section 12 (Geotechnical) of Exhibit E (Technical
Requirements).
Good Faith Efforts (GFE) means efforts to achieve a DBE or goal, that by their scope,
intensity, and appropriateness to the objective, can reasonably be expected to fulfill the
requirements of the goal, in accordance with 49 CFR 26.53 and Appendix A to Part 26..
Governing Regulations means the governing regulations set forth in Section 1.2 (Governing
Regulations) of Exhibit E (Technical Requirements) as may be amended in the Project Scope.
Government Entity means any federal, state, or local government and any political subdivision
or any governmental, quasi-governmental, judicial, public, or statutory instrumentality,
administrative agency, authority, body, or entity, other than ODOT or KYTC.
Guaranteed Maximum Price or GMP means a form of pricing for any Early Work Package,
Buildable Unit or the Phase 2 Work in which, in return for delivering such Work , the Contractor
is eligible to be paid the actual allowable cost of properly performing such Work but may not
receive more than the GMP.
Guarantor means any party approved by the Department to provide a Guaranty securing
Contractor’s obligations under this PDBC.
Indemnified Parties has the meaning assigned in Section 16.1 (Indemnifications by Contractor)
of the PDBC.
Independent Design Quality Firm (IDQF) means the organization identified in Exhibit C
(Proposal Commitments).
Independent Cost Estimator (ICE) means the Independent Cost Estimator to be appointed by
the Department to validate the Pricing Proposals submitted by the Contractor.
Instructions to Offerors (ITO) means the documents, including exhibits and forms, included in
the RFP containing directions for the preparation and submittal of information by the Offerors in
response to the RFP.
Intellectual Property means any and all patents, trademarks, service marks, copyright,
database rights, moral rights, rights in a design, know-how, confidential information, and any
and all other intellectual or industrial property rights whether or not registered or capable of
registration and whether subsisting in the United States or any other part of the world, together
with all or any goodwill relating or attached to such rights, which is created, brought into
existence, acquired, used, or intended to be used by any Contractor-Related Entity for the
purposes of carrying out the Phase 1 Work or the Phase 2 Work or otherwise for the purposes
of the PDBC.
Interim Baseline Schedule has the meaning assigned in Exhibit T (Critical Path Method
Progress Schedule) Section 1.4.1 (Interim Baseline and Baseline Schedules).
Interstate Cooperative Agreement (ICA) means the document included in Exhibit Y (Interstate
Cooperative Agreement).
Jurisdictional Design & Maintenance (JDM) means the regional location, as defined within
the Contract, for which the applicable ODOT or KYTC design and construction specifications,
standards, guidance, special notes, Special Provisions, processes, manuals, technical memos,
laws, regulations, or any other guidance applies. Unless otherwise specifically identified, the
JDM shall be the state boundaries with which the Construction Work is or will be occurring.
Jurisdictional Design & Maintenance Authority (JDMA) means the authority having
jurisdiction for design and construction specifications, standards, guidance, special notes,
special provisions, processes, manuals, technical memos, laws, regulations, or any other
guidance applies. Unless otherwise identified in the Contract Documents, the JDMA shall be
ODOT or KYTC depending upon the state boundaries with which the Construction Work is or
will be occurring.
Key Personnel means those individuals named and listed in Exhibit C (Proposal Commitments)
as filling:
(a) the Key Personnel positions listed in Section 2.1.2 (Key Personnel) of Exhibit E
(Technical Requirements); and
(b) any additional Key Personnel positions not included in paragraph (a) of this definition but
offered in the Proposal Commitments, and any replacements approved in accordance
with Section 10.4 (Key Personnel) of the PDBC.
KYTC shall mean the Cabinet and may be used interchangeably with “Commonwealth” or
“Cabinet.”
KYTC Standards and Specifications means those standards and specifications designated as
originating from KYTC under Table 1-1 of Exhibit E (Technical Requirements), as the same may
be amended and updated in conjunction with an applicable Proposal.
Laboratory means the testing laboratories under the direct management of ODOT or KYTC, or
specifically contracted with ODOT or KYTC for management of the Project’s Materials. This may
include the Office of Materials Management (OMM) located at 1600 West Broad Street,
Columbus, Ohio, and the ODOT District testing facilities.
Law or Laws means (a) any statute, law, code, regulation, ordinance, rule or common law, (b)
any binding judgment (other than regarding a Claim or Dispute), (c) any binding judicial or
administrative order or decree (other than regarding a Claim or Dispute), (d) any written
directive, guideline, policy requirement or other governmental restriction (including those
resulting from the initiative or referendum process, but excluding those by the Department within
the scope of its administration of the Contract Documents) or (e) any similar form of decision of
or determination by, or any written interpretation or administration of any of the foregoing by any
Governmental Entity, in each case which is applicable to or has an impact on the Project or the
Work, whether taking effect before or after the Effective Date, including any and all Kentucky,
Ohio or federal environmental laws and regulations pertaining to the Project. “Laws,” however,
excludes Governmental Approvals.
Lead Agency has the meaning assigned in Section 3.1 of the Interstate Cooperative
Agreement Regarding the Brent Spence Bridge Corridor Project.
Lump Sum means a form of pricing and compensation for a Work Package, Buildable Unit or
the Phase 2 Work in which the Contractor agrees to perform the Work for a fixed dollar amount
that is subject to adjustment only for Change Orders, Extra Work, Excusable Compensable
Delays or other adjustments in accordance with the Contract Documents.
Maintenance of Traffic (MOT) means the maintenance of traffic on existing roads and
crossroads within the Project Right of Way to ensure access to all relevant properties during the
Work.
Maintenance of Traffic Plan means the Contractor’s plan for Maintenance of Traffic, prepared
in accordance with the Project Scope.
Major Participant means any Component Firm that a Key Personnel is employed by.
Major and Minor Items means, as applicable to KYTC Standards and Specifications, all
original Contract Items having a value of 10 percent or more of the original Contract amount,
based on the original Contract price and original estimated quantity, are major items. All
remaining items are minor items.
Materials means any materials or products specified for use in the construction of the Project
and its appurtenances.
Maximum Prime Compensation is the not-to-exceed limit of the Prime Compensation for the
Phase 1 Work under the provisions of the PDBC.
Measured Mile means an analysis comparing the productivity of Work to prove and quantify
inefficiency as further described in Section 12.8.5 (Inefficiency) of the PDBC.
Milestone means the milestone for completion of the Sub-Phase 1A Work, the milestone for
completion of the Sub-Phase 1B Work, the milestone for completion of an Early Work Package,
the milestone for opening to traffic of the Companion Bridge, the milestone for Substantial
Completion of the Work or any other milestone established in the Project Schedule as the
context requires.
Milestone Date means the date upon which each Milestone actually occurs.
Milestone Deadline means the date upon which each Milestone is scheduled to be achieved in
accordance with the Project Schedule as such dates may be extended in accordance with the
Contract Documents.
Mobilization means the Work described in Section 11.2.7 (Mobilization) of the PDBC.
Monthly Progress Report means the report the Contractor must submit to the Department
summarizing progress made the previous Month and including activities to be performed in the
following Month and as further described in the Project Scope.
Monthly Progress Update Schedule has the meaning assigned in Exhibit T (Critical Path
Method Progress Schedule) Section 1.4 (Interim, Phase 1, and Phase 2 Baseline Schedule
Requirements).
Noncompliance Events Table has the meaning set forth in Exhibit F (Noncompliance Points
System).
Noncompliance Points means the points that may be assessed by the Department for certain
Noncompliance Events, as set forth in Exhibit F (Noncompliance Points System).
Nonconformance Report (NCR) means the report pertaining to Nonconforming Work which
shall be generated by the Contractor and which may be generated by the Department in the
circumstances set forth in Section 3.7.1 (Nonconforming Work Process) of Exhibit E (Technical
Requirements).
Nonconforming Work means any Design and Construction Work that does not conform to the
requirements of the Contract Documents. Nonconforming Work shall include any unacceptable
Materials as described in Section 6.7 (Unacceptable Materials) of the PDBC.
Notice of Design Change (NDC) means design changes initiated by the Engineer of Record
(EOR) to documents approved and Released for Construction (RFC) are completed under an
NDC. NDCs are subject to quality check or review activities.
Notice of Determination means the Notice issued by the Department with respect to
Noncompliance Events as described in Exhibit F (Noncompliance Points System).
Notice of Potential Change Order (NPCO) is the potential two-step process utilized by the
Contractor, as outlined in Section 12.4.1 (Notice of Potential Change Order) of the PDBC, to
inform the Department of the existence of a circumstance(s) or event(s) that may require a
change to the Contract Documents and/or Work.
Notice of Substantial Completion means the notice delivered to the Contractor under Section
5.14.2.4 (Notice of Substantial Completion) stating that Substantial Completion of the Project
has occurred.
Notice of Work Package Substantial Completion means the notice delivered to the
Contractor under Section 5.14.2.2 (Notice of Substantial Completion of a Work Package) stating
that Substantial Completion of a Work Package has occurred.
Notice of Termination means a notice issued by the Department to terminate the PDBC
pursuant to Section 21.1 (Notice of Termination) of the PDBC.
Notice to Proceed (NTP) is a written communication from the Department to the Contractor to
start any unit or element of the Phase 1 Work, Phase 2 Work or Early Work. The Notice to
Proceed shall establish any conditions and restraints necessary for, or incident to, the
performance of the Phase 1 Work, Phase 2 Work or Early Work.
ODOT means the Ohio Department of Transportation and may be used interchangeably with
“State” or “Department.”
ODOT Standards and Specifications means those standards and specifications designated
as originating from ODOT under Table 1-1 of Exhibit E (Technical Requirements), as the same
may be amended and updated in conjunction with an applicable Proposal.
Offeror means the entity submitting a Proposal for the Project in response to the RFP.
Open Book Basis means a method in which the Contractor provides the Department, at the
Department's request, all books, records, documents, contracts, subcontracts, purchase orders,
and other data in its possession pertaining to the bidding, pricing, or performance of the PDBC,
showing the Contractor's underlying assumptions and data as to costs of the Work or services
to be provided, schedule, composition of equipment spreads, equipment rates, labor rates,
productivity, estimating factors, design and productivity allowance, Contingency and indirect
costs, risk pricing, discount rates, interest rates, inflation and deflation rates, swap and hedge
rates, insurance rates, bonding rates, letter of credit, fees, overhead, profit, and other items
reasonably required by the Department to satisfy itself as to validity or reasonableness. It also
includes review of the Contractor’s underlying project-specific accounting system and the
Department’s ability to view the Contractor’s allocation of costs within that system.
Opinion of Probable Cost (OPC) means the Contractor-generated estimate of the Contract
Price prepared in accordance with the principles set forth in Exhibit G (Pricing Process).
Organizational Conflict of Interest has the meaning set forth in ITO Section 5.3
(Organizational Conflicts of Interest).
Original Contract Work has the meaning assigned in Exhibit H (Force Account Provisions).
Overtime Premium Wages arise from the difference between an employee’s standard hourly
wage rate and the special hourly wage rate paid for time in excess of 40 hours per week.
Partnering means a collaborative process for project cooperation and communication meant to
achieve effective and efficient contract performance and completion of the Project within budget,
on schedule, safely and with requisite quality in accordance with the contract.
Payment Bonds means the payment bonds to be delivered by the Contractor to the
Department in accordance with Section 23.1 (Performance and Payment Bonds) of the PDBC.
Performance Bonds means the performance bonds to be delivered by the Contractor to the
Department in accordance with Section 23.1 (Performance and Payment Bonds) of the PDBC.
Permitting Plan means the plan to be prepared by the Contractor to determine roles and
responsibilities for permitting as described in Section 7.2 (Permitting) of Exhibit E (Technical
Requirements).
Person means any individual, firm, corporation, company, limited liability company, limited
liability partnership , joint venture, voluntary association, partnership, trust or public or private
organization, other legal entity, or combination of the foregoing.
Phase Change Order means the Sub-Phase 1A Change Order, the Sub-Phase 1B Change
Order, an Early work Change Order or the Phase 2 Change Order as the context requires.
Phase 1 or the Preconstruction Phase means the phase in which the Phase 1 Work and, if
applicable, Early Work, is performed.
Phase 1 Baseline Schedule has the meaning assigned in Exhibit T (Critical Path Method
Progress Schedule) Section 1.4.1 (Interim Baseline and Baseline Schedules).
Phase 1 Multiplier Rate means the multiplier for Professional Services undertaken in the
performance of the Phase 1 Work as set forth in Exhibit B (Contract Particulars). The Phase 1
Multiplier Rate shall include direct labor costs, overtime payments, indirect costs (overhead),
travel, subsistence, non-salary direct costs and facilities capital cost of money.
Phase 2 means the phase in which the Phase 2 Work and, if applicable, Early Work, is
performed.
Phase 2 Baseline Schedule has the meaning assigned in Exhibit T (Critical Path Method
Progress Schedule) Section 1.4.1 (Interim Baseline and Baseline Schedules).
Phase 2 Change Order means the Change Order to incorporate the Phase 2 Work that may be
issued by the Department as further described in Section 3.3 (Phase 2 Project Scope) of the
PDBC.
Phase 2 Multiplier Rate for FAR Participants means the multiplier for Professional Services
undertaken in the performance of the Phase 2 Work by FAR Participants as set forth in Exhibit
B (Contract Particulars). The Phase 2 Multiplier Rate for FAR Participants shall include direct
labor costs, overtime payments, indirect costs (overhead), travel, subsistence, non-salary direct
costs and facilities capital cost of money.
Phase 2 Multiplier Rate for Non-FAR Participants means the multiplier for Professional
Services undertaken in the performance of the Phase 2 Work by non-FAR Participants as set
forth in Exhibit B (Contract Particulars). The Phase 2 Multiplier Rate for Non-FAR Participants
shall include direct labor costs, overtime payments, indirect costs (overhead), travel,
subsistence, non-salary direct costs and facilities capital cost of money.
Phase 2 Project Scope means the Project Scope governing the Phase 2 Work which will be
agreed between the Parties during Sub-Phase 1B.
Phase 2 Work means all duties and services to be furnished and provided by the Contractor as
required by a Phase 2 Change Order, including the administrative, design, engineering, quality
control, quality assurance, relocation, procurement, legal, professional, manufacturing, supply,
installation, construction, supervision, management, testing, verification, labor, Materials,
Equipment, documentation and other efforts necessary or appropriate to achieve Completion of
the Contract except for those efforts which the Contract Documents specify will be performed by
the Department or other Persons. In certain cases the term is also used to mean the products of
the Phase 2 Work. For clarity, the Phase 2 Work does not include the Phase 1 Work.
Plans means the drawings, standard construction drawings and supplemental drawings
provided by the Department or produced by the Designer or the Designer’s Subconsultants,
approved in accordance with the PDBC, or exact reproductions thereof, that show the location,
character, dimensions, and details of the Work.
Pre-Proposal One-on-One Meeting means the meeting(s) set forth in ITO Section 2.2 (Pre-
Proposal One-on-One Meetings).
Prequalification refers to the Department’s and KYTC’s system for determining whether the
Contractor and its Subcontractors and Subconsultants meet certain minimum qualification levels
in accordance with ORC Chapters 5525 & 5526 and the rules and regulations governing
prequalification and by the Kentucky Transportation Cabinet (KYTC) in according to with
Kentucky Administrative Regulations (KAR) 603 KAR 2:015, 600 KAR 6:040, and other relevant
laws. The Department’s and KYTC’s Prequalification requirements are set out in the applicable
Consultant Prequalification Requirements and Procedures, posted on the Department’s and
KYTC’s website. Work that requires prequalification may only be performed by firms that are
prequalified for those services at the time of performance of the services.
Preventative Action Report (PAR) has the meaning set forth in Section 3.7.6 (Corrective /
Preventative Action Report) of Exhibit E (Technical Requirements).
Price Proposal means, as a component of each Work Package Proposal, the Contractor’s
written Submittal of the Project requirements together with a narrative description of the Project
and proposed Work together with a detailed schedule of requested compensations.
Prime Compensation is the monetary remuneration specified for payment by the Department
to the Contractor for acceptable elements of the Phase 1 Work.
Principal Participant means any of the following entities: (i) any joint venture, partner, or firm
holding an interest in the Contractor if the Contractor is a joint venture, partnership or other form
of unincorporated legal entity; and/or (ii) any person or firm holding (directly or indirectly) a 15%
or greater interest in the Contractor if the Contractor is a corporation, limited liability company or
other form of incorporated legal entity; or (iii) parent company or Affiliate of the Contractor or
another Principal Participant that will provide financial support to such firm (guarantor) to meet
the financial obligations of the PDBC.
Probable Maximum Loss (PML) has the meaning assigned in Section 17 (Insurance
Requirements) of the PDBC.
Procurement Point of Contact (PPC) means the authorized representative of the Offeror
identified as the sole representative for communication with the Department.
Procurement Process means the entire process by which the Department offers to outside
parties an opportunity to undertake the Project, including the RFP, beginning with the release of
the RFP and ending with the selection of the Design Build Team to design and construct the
Project.
Professional Landscape Architect means a landscape architect registered with the Ohio
Landscape Architects Board to practice landscape architecture in the State of Ohio.
Professional Services means the professional services necessary to deliver the Work,
including the design of all permanent and temporary portions of the Project, the preparation of
Working Drawings or Engineered Drawings, the practice of engineering, surveying, landscape
architecture, architectural services, estimating and risk assessment, assessment of
environmental impacts, Right-of-Way acquisition services, supervisory and administrative
personnel performing project management, superintending, preconstruction services, planning
and scheduling, safety management, purchasing, accounting, IT services, other supervisory
activities and the preparation of Claims.
Profile Grade means the trace of a vertical plane intersecting the top surface of the proposed
wearing surface, usually along the longitudinal centerline of the roadbed. Profile grade means
either elevation or gradient of such trace according to the context.
Progress Meeting means a Design Progress Meeting as defined in Section 2.2.1.4 (Design
Progress Meeting) of Exhibit E (Technical Requirements) or other Progress Meetings as
required pursuant to Section 5.2 (Phase 2 Preconstruction and Progress Meetings) of the
PDBC.
Progress Schedule means the version of the Project Schedule depicting progress of the Work
as described in Exhibit T (Critical Path Method Progress Schedule) Section 1.11 (Progress
Schedule).
a. Debarred, suspended, proposed for debarment with a final determination still pending,
declared ineligible or voluntarily excluded (as such terms are defined in any of the
Debarment Regulations) from participating in procurement or nonprocurement
transactions with the United States federal government or any department, agency or
instrumentality thereof pursuant to any of the Debarment Regulations;
b. Indicted, convicted or had a civil or administrative judgment rendered against such
Person for any of the offenses listed in any of the Debarment Regulations and no
event has occurred and no condition exists that is likely to result in the debarment or
suspension of such Person from contracting with the United States federal
government or any department, agency or instrumentality thereof;
c. Listed on the “Lists of Parties Excluded from Federal Procurement and
Nonprocurement Programs” issued by the US General Services Administration;
d. Located within, or doing business or operating from, a country or other territory subject
to a general embargo administered by the United States Office of Foreign Assets
Control (OFAC);
e. Designated on the OFAC list of 'Specially Designated Nationals';
f. Otherwise targeted under economic or financial sanctions administered by the United
Nations, OFAC or any other U.S. federal economic sanctions authority or any
divestment or sanctions program of the State of Ohio or State of Kentucky;
g. A banking institution chartered or licensed in a jurisdiction against which the United
States Secretary of the Treasury has imposed special measures under Section 311 of
the USA PATRIOT Act (Section 311);
h. Located within or is operating from a jurisdiction that has been designated as
noncooperative with international anti-money laundering principles by the Financial
Action Task Force on Money Laundering;
i. A financial institution against which the United States Secretary of the Treasury has
imposed special measures under Section 311;
j. A “senior foreign political figure” or a prohibited “foreign shell bank” within the meaning
of 31 C.F.R. Section 103.175; or
k. Any Person with whom the Department is engaged in litigation relating to performance
of contract or business practices (unless the Department has first waived (in
Department’s sole discretion) by written notice to the transferring equity holder, with a
copy to the Contractor, the prohibition on a transfer to such Person during the
continuance of the relevant litigation).
Project is the Brent Spence Bridge Corridor Project, which is the subject of this PDBC and
which is further described in Section 1 (General) of Exhibit E (Technical Requirements).
Project Float is the length of time between the End Project Milestone and the Contract
Completion Deadline.
Project Goals means the goals and objectives set forth in ITO Section 1.3 (Project Goals) and
Section 1.1 (Project Goals) of the Exhibit E (Technical Requirements).
Project Limits means points on the mainline centerline of construction where the proposed
improvement, as described in the project description on the Title Sheet (excluding incidental
construction), begins and ends.
Project Management Office (PMO) means the facility in which the Parties will co-locate as
described in Section 4.1 (Project Management Office) of Exhibit E (Technical Requirements).
Project Mark-up means the percentage mark-up applied to the Phase 1 Work and the Phase 2
Work in order to establish the applicable Contract Price as described in Exhibit G (Pricing
Process).
Project Punch List means an itemized list of Construction Work identified by Department and
Contractor staff prior to Substantial Completion that, when completed, will mean that the
Construction Work is ready for Final Inspection.
Project Right-of-Way (ROW) means the Department-acquired temporary and permanent ROW
acquired in connection by the Department as described in Section 11.1 (General Right-of-Way)
of Exhibit E (Technical Requirements), together with all additional properties acquired at the
Contractor’s request in accordance with Section 11.2 (Additional Property Request
Requirements) of Exhibit E (Technical Requirements) and other rights in real property acquired
by or granted to the Contractor pursuant to governmental resolutions or other legislation, as
such Project Right-of-Way may be adjusted from time to time in accordance with the Contract
Documents. The term specifically includes all air space, surface rights and subsurface rights
within the boundaries of the Project Right-of-Way.
Project Schedule means one or more, as applicable, of the logic-based Critical Path schedules
(the Interim Baseline Schedule, the Baseline Schedule, the Phase 1 Baseline Schedule, the
Phase 2 Baseline Schedule, the Monthly Progress Update Schedule, the Recovery Schedule,
the Weather Delay Schedule, and the As-Built Schedule) for all Work leading up to and
including Substantial Completion and Completion of the Contract, and for tracking the
performance of such Work, as the same may be revised and updated from time to time in
accordance with Exhibit T (Critical Path Method Progress Schedule).
Project Scope means the Sub-Phase 1A Project Scope, the Sub-Phase 1B Project Scope or
the Phase 2 Project Scope, as the context requires. The Project Scope describes the scope of
the Work and related Project Standards, criteria, conditions, procedures, specifications and
other provisions for the Project and/or the Utility Relocations, as such provisions may be
changed, added to, deleted or replaced pursuant to a Change Order.
Project Site means Project Right –of Way and any temporary rights or interests that the
Contractor may acquire in connection with the Project or the Utility Relocations included in the
Construction Work.
Project Standards means the standards, manuals and guidelines listed in Table 1-1 of Exhibit
E (Technical Requirements), as may be amended in the Project Scope.
Proposal Due Date means the deadline (date and time) for submission of Proposals identified
in ITO Section 1.4 (Procurement Schedule).
Provisional Sum - A fixed sum for a specific line item of Work that is included as an allowance
amount in a Phase Change Order upon agreement by the Contractor and the Department.
Provisional Sums may be used in instances when the actual price or quantity for such item of
work is unknown at the time of agreement on Phase Change Order. Where agreed as reflected
in the Risk Register, Provisional Sums may include a designation of unit pricing and the
estimated number of units making up the Provisional Sums.
Quality Assurance (QA) means all planned and systematic activities implemented to provide
confidence that the Work complies with the requirements of the Contract Documents.
Quality Assurance Plan means the Contractor’s plan for providing Quality Assurance,
prepared in accordance with the Project Scope.
Quality Check Point (QCP) has the meaning given to such term in the Project Scope.
Quality Control means all activities and techniques performed at the production level in order
to meet Contract requirements.
Quality Management System Plan (QMSP) means a plan which describes the quality program
for the Design Work, the Construction Work, and how the design and construction activities
performed by different entities will be coordinated to ensure consistency of quality, prepared in
accordance with the Project Scope.
Railroad means, depending on the context, either the right-of-way, tracks, and systems used
for rail traffic in the vicinity of the Project, or the owners and/or operators of such rail systems.
Railroad Agreement means each of the agreements between the Department and the
Railroads described at Section 7.4 (Railroad Agreements) of the PDBC and Section 10.2
(Railroad Agreement) of Exhibit E (Technical Requirements) as may be amended in the Project
Scope.
Railroad Coordination and Management Plan means the plan to be prepared by the
Contractor for railroad coordination as defined in Section 10 (Railroads) of Exhibit E (Technical
Requirements).
Records includes any document, device, or item, regardless of physical form or characteristic,
including an electronic record as defined in Section 1306.01 of the Ohio Revised Code, created
or received by the Contractor in the performance of the Phase 1 Work.
Recovery Schedule has the meaning assigned in Exhibit T (Critical Path Method Progress
Schedule) Section 1.8 (Recovery Schedule).
Registered Engineer means a Professional Engineer registered with the Ohio State Board of
Registration for Professional Engineers and Surveyors or the Kentucky Board of Engineers &
Land Surveyors to practice professional engineering in the State of Ohio or Kentucky
respectively.
Registered Surveyor means a surveyor registered with the Ohio State Board of Registration
for Professional Engineers and Surveyors or the Kentucky Board of Engineers & Land
Surveyors to practice professional surveying in the State of Ohio or Kentucky respectively.
a. Any substance, product, waste or other material of any nature whatsoever that is or
becomes listed, regulated, or addressed pursuant to any Environmental Law;
b. Any substance, product, waste or other material of any nature whatsoever that
exceeds maximum allowable concentrations for elemental metals, organic compounds
or inorganic compounds, as defined by any Environmental Law;
c. Any substance, product, waste or other material of any nature whatsoever which may
give rise to liability under clause (b) or under any statutory or common law theory
based on negligence, trespass, intentional tort, nuisance or strict liability or under any
reported decisions of a state or federal court;
Regulated Materials Management means procedures, practices and activities to address and
comply with environmental laws and environmental approvals with respect to Regulated
Materials encountered, impacted, disturbed, released, caused by or occurring in connection with
the Project, Right-of-Way or the Work, as well as investigation, characterization and remediation
of such Regulated Materials. Regulated Materials Management may include sampling, handling,
stockpiling, storing, backfilling in place, asphalt batching, recycling, dewatering, treating,
cleaning up, excavating, removing, remediating, transporting and/or disposing off-site of
Regulated Materials and otherwise managing Regulated Materials, whichever approach is
effective, most cost-efficient and authorized under applicable Law.
Regulated Materials Management Plan (RMMP) means the Contractor’s plan for Regulated
Materials Management as described in Section 7.4 (Regulated Materials) of Exhibit E (Technical
Requirements) as may be amended in the Project Scope.
Released for Construction Plans means Design Documents that have been thoroughly
checked, reviewed and sealed in accordance with the Phase 2 Project Scope and adequately
describe the Construction Work required.
Request for Change Order or RCO means a Contractor initiated request for a Change Order
pursuant to Section 12 (Contract Changes) and/or Section 13 (Time Extension To The
Completion Deadlines And Payment For Excusable Delays) of the PDBC.
Request for Proposals (RFP) Documents means the set of documents identifying the Project
and the Work to be performed and Materials to be furnished in response to which a Proposal
may be submitted by an Offeror. The RFP includes the Instructions to Offerors (ITO) and this
PDBC Contract.
Right-of-Way means a general term denoting land, property, or interest therein, usually in a
strip, acquired for or devoted to a highway.
Risk Management Plan means the Contractor’s plan for risk management for its performance
of the Phase 1 Work and the Phase 2 Work and for the Project risks owned by and allocated to,
the Contractor through the Risk Register.
Risk Register means a register incorporating a listing of risks for the Project (whether or not
allocated to the Department or the Contractor), assessments of those risks (including cost and
schedule impacts associated with the risks), an evaluation of mitigation; and allocation of
responsibility for those risks.
Road means a general term denoting a public way for purposes of vehicular travel, including the
entire area within the Right-of-Way, as defined in ORC 5501.01.
Schedule of Values (SOV) means a breakdown of the Lump Sum or GMP, as applicable, into
items of work, showing estimated quantities of Work in sufficient detail to determine testing and
Material reporting requirements per ODOT Standards and Specifications or KYTC Standards
and Specifications, as appropriate.
Service Line means (a) a Utility line, the function of which is to directly connect the
improvements on an individual property to another Utility line located off such property, which
other Utility line connects more than one such individual line to a larger system, or (b) any cable
or conduit that supplies an active feed from a Utility Owner’s facilities to activate or energize the
Department’s or a local agency’s lighting and electrical systems, traffic control systems,
communications systems and/or irrigation systems.
Signatures on Contract Documents means all signatures on Contract Documents must meet
the requirements of ODOT C&MS Section 102.06.
Signed and Sealed means the signature and seal of a licensed professional engineer on a
document indicating that the licensee takes professional responsibility for the work and, to the
best of the licensee’s knowledge and ability, the work represented in the document is accurate,
in conformance with applicable codes at the time of submission and has been prepared in
conformity with normal and customary standards of practice and with a view to the safeguarding
of life, health, property and public welfare. The licensed professional engineer certifies that the
documents have been signed and sealed in accordance with laws, rules and regulations of the
State of Ohio.
Special Provisions means additions and revisions to the Standard Specifications and
Supplemental Specifications covering conditions peculiar to the Project.
Spill Prevention Control and Countermeasures Plan or SPCC means a plan prepared by the
Contractor in accordance with the Project Scope that provides specific guidance for managing,
handling, and disposing of Regulated Materials (and all related Regulated Materials issues) that
may be encountered. The SPPC will also protect the health and safety of all on-site personnel
and the general public.
State Highway Engineer means, when referenced in KYTC specifications, the State Highway
Engineer of KYTC.
Standard of Care means the standard of care applicable to all of the Work performed under the
PDBC as defined in Section 1.7.
Standards Deviation means the Contractor requests a deviation from the Project Standards
[Governing Regulations]. The Submittal of a Standards Deviation is described in Section 1.3
(Standard Deviation Submittal Requirements) of Exhibit E (Technical Requirements) as may be
amended in the Project Scope.
State refers to the State of Ohio. or the Commonwealth , as applicable, represented by the
Director of Transportation, Secretary of the Cabinet or authorized designee.
State Cost Estimator (SCE) means the estimator appointed by the Department to develop an
engineer’s estimate prior to final pricing agreement in accordance with ORC 557.01 (State Cost
Estimator).
Storm Water Pollution Prevention Plan or SWPPP means the Contractor’s plan to address
erosion and sediment control for the Project, prepared in accordance with Section 1.2
(Governing Regulations) of Exhibit E (Technical Requirements) as may be amended in the
Project Scope.
Structures means Bridges, culverts, catch basins, drop inlets, retaining walls, cribbing,
manholes, endwalls, buildings, sewers, service pipes, underdrains, foundation drains, and other
features that may be encountered in the Work and not otherwise classed herein.
Sub-Phase 1A Project Scope means the Project Scope governing the Sub-Phase 1A Work
which will be agreed between the Parties as described in Section 2.3.1 (Pre-Sub-Phase 1A
Work) of the PDBC.
Sub-Phase 1A Proposal has the meaning set forth in Section 2.3.1 (Pre-Sub-Phase 1A Work)
of the PDBC.
Sub-Phase 1A Work means the Work to be delivered by the Contractor during Sub-Phase 1A.
Sub-Phase 1B or the Project Development Phase has the meaning set forth Section 2
(Progressive Design-Build Approach) of the PDBC.
Sub-Phase 1B Change Order means the Change Order to incorporate the Sub-Phase 1B
Work that may be issued by the Department as further described in Section 2.3.2.1 (Sub-Phase
1B: Proposal) of the PDBC.
Sub-Phase 1B Project Scope means the Project Scope governing the Sub-Phase 1B Work
which will be agreed between the Parties during Sub-Phase 1A.
Sub-Phase 1B Proposal has the meaning set forth in Section 2.3.2.1 (Sub-Phase 1B:
Proposal) of the PDBC.
Sub-Phase 1B Proposal Due Date has the meaning set forth in Exhibit B (Contract
Particulars).
Sub-Phase 1B Work means the Work to be delivered by the Contractor during Sub-Phase 1B.
Subconsultant means any person or organization to whom the Designer or Contractor has
sublet or assigned any portion of its contractual obligations for the development of Design
Documents. Any such Subconsultant must hold a Certificate of Authorization from the Ohio
State Board of Registration for Professional Engineers and has fulfilled the Prequalification
requirements under ORC 5526.04.
Subcontractor means an individual, firm, or corporation to whom the Contractor sublets part of
the Phase 1 Work or Phase 2 Work, and who is qualified under ORC 5525.02 through 5525.09
inclusive.
Subcontractor Bidding and Selection Plan means the plan prepared by the Contractor and
submitted to the Department for review and approval, defining the Contractor's approach to
subcontracting, and selecting contractors to perform that part of the Work that will not be self-
performed, that is compliant with Section 8 (Subcontracting Requirements) of the PDBC.
Submittal means all documents, data, materials, information, studies, reports, survey data,
proposals, plans, drawings, computations, specifications, estimates, codes, scientific
information, technological information, regulations, maps, Equipment, charts, schedules,
photography, exhibits, software, software source code, and documentation prepared or
developed or created or discovered for the benefit of the Department under or in connection
with the Work.
Substantial Completion means satisfaction of all the conditions as set forth in Section 5.14.2
(Final Inspection and Substantial Completion) of the PDBC, as and when confirmed by the
Department’s issuance of a certificate in accordance with the procedures and within the time
frame established in the PDBC.
Substantial Completion Date means the date that Substantial Completion has been achieved
for the entire Project.
Substantial Completion Deadline means the date shown in the Phase 2 Change Order on
which Substantial Completion is scheduled to be achieved as such date may be extended in
accordance with the Contract Documents.
Superpave Mix Design Technologist (SMDT) means an inspector qualified by the KYTC to
submit, adjust, or approve asphalt mix designs as applicable to KYTC specifications.
Superpave Plant Technologist (SPT) means an inspector qualified by the KYTC to perform
routine inspection and process control, acceptance, or verification testing on asphalt mixtures as
applicable to KYTC specifications.
Supplement means a list of requirements for fabrication plants, methods of test, or other
miscellaneous requirements that are maintained on file by the Department.
Supplemental Agreement means a written agreement executed by the Contractor and by the
Department covering necessary alterations to the PDBC.
Supplier means any Person not performing work at or on the Site which supplies machinery,
Equipment, Materials, hardware, software, systems or any other appurtenance to the Project to
the Contractor or any Subcontractor in connection with the performance of the Work. Persons
who merely transport, pick up, deliver or carry materials, personnel, parts or Equipment or any
other items or persons to or from the Site shall not be deemed to be performing Work at the
Site.
Surety means the corporation, partnership, or individual, other than the Contractor, executing a
bond furnished by the Contractor.
Technical Proposal means the technical proposal submitted by an Offeror providing the
information requested in ITO Section 6.8 (Technical Proposal).
Term means the period identified in Section 1.5 (Term) of the PDBC.
Total Float means the amount of time that any given activity or logically connected sequence of
activities shown on the Project Schedule may be delayed before it delays occurrence of either
the Substantial Completion Date or the Completion of the Contract Date. Such Total Float is
generally identified as the difference between the early start date and late start date or early
completion date and late completion date for each of the activities shown on the Project
Schedule.
Traffic Management Plan means the Contractor’s plan for temporary traffic control prepared in
accordance with Section 21 (Maintenance of Traffic) of Exhibit E (Technical Requirements) and
providing information to the public on traffic information and access pursuant to Section 21
(Maintenance of Traffic) of Exhibit E (Technical Requirements) as may be amended in the
Project Scope.
User(s) means the registered owner of a vehicle traveling on the Project of any portion thereof.
Utility or utility means and includes poles, plants, lines, trenches, bridges, tunnels, pipelines,
and any other system for furnishing, producing, generating, transmitting or distributing power,
electricity, communications, telecommunications, water, gas, oil, petroleum products, coal or
other mineral slurry, steam, heat, light, chemicals, air, sewage, drainage not connected with a
highway drainage system, irrigation, or another substance. The term “utility” also includes a
system for furnishing transportation of goods or persons by means of railway, tramway,
cableway, conveyor, flume, canal, tunnel, pipeline, or a similar means. The term “Utility” or
“utility” excludes (a) storm water facilities providing drainage for the Project Right of Way, (b)
street lights and traffic signals and (c) ITS (intelligent transportation systems) and IVHS
(intelligent vehicle highway systems) facilities. The necessary appurtenances to each Utility
Owner Project shall be considered part of such Utility. Without limitation, any Service Line
connecting directly to a Utility shall be considered an appurtenance to that Utility, regardless of
the ownership of such Service Line.
Utility Owner means the owner or operator of any Utility (including both privately held and
publicly held entities, cooperative Utilities, and municipalities and other governmental agencies
(including, without limitation, the Department)).
Utility Owner Project means the design and construction by or at the direction of a Utility
Owner (including by the Contractor) of a new Utility other than as part of a Utility Adjustment.
Utility Relocation Work means (a) the work associated with Utility Relocation, including the
coordination, design, design review, permitting, construction, inspection, maintenance of
records, installation, manufacture, supply, testing inspection, adjustments (including all
appurtenances), and otherwise required by the Contract Documents, including all labor,
Materials, Equipment supplies, utilities and subcontracted services provided or to be provided
by the Contractor and/or the Utility Owners; and (b) any reimbursement of Utility Owners that is
the Contractor’s responsibility pursuant to Section 7 (Utilities and Railroads) of the PDBC.
Warranty means any warranty made by the Contractor in Section 22 (Project Warranties).
Warranty Work means Work performed by the Contractor to rectify a warranty defect.
Weather Day has the meaning set forth in Section 15 (Weather) of the PDBC.
Weather Delay Schedule has the meaning assigned in Exhibit T (Critical Path Method
Progress Schedule) Section 1.8 (Weather Delay Schedules).
Work means the entire completed design and construction of the various separately identifiable
parts thereof required to be performed or furnished under the Contract Documents that
comprise the Project or any portion thereof. Work includes and is the result of performing or
furnishing Professional Services and construction required by the Contract Documents and
includes the Phase 1 Work, any Early Work and the Phase 2 Work. Work includes Utility
Relocation Work and Warranty Work.
Work Breakdown Level or Level 3 means a schedule level that includes each Buildable Unit
as further described in Exhibit T (Critical Path Method Progress Schedule).
Work Element Level or Level 4 means a schedule level that includes each element of the
Work as further described in Exhibit T (Critical Path Method Progress).
Work Limits means the extreme limits of the Contractor’s responsibility on the Project,
including all temporary and incidental construction, with the exception of work zone traffic
control devices required for maintenance of traffic.
Work Package means the package attached to the applicable Change Order, following
acceptance by the Department of a Proposal, defining the Work and any changes to the
Contract Documents necessary to define the responsibilities of the Parties. A Work Package
may be the Sub-Phase 1A Work Package, the Sub-Phase 1B Work Package, an Early Work
Package or the package attached to the Phase 2 Change Order .
Work Package Proposal means a proposal prepared by the Contractor in a form approved by
the Department containing the Contractor’s Price Proposal, proposed scope of Work and other
matters as may be directed by the Department. A Work Package Proposal may be any of the
Sub-Phase 1A Proposal, the Sub-Phase 1B Proposal, an Early Work Proposal or the Phase 2
Proposal as further described in Section 2 (Progressive Design Build Approach) of the PDBC.
Working Day means any day that is not a Saturday, Sunday or other day on which (a) the
Department is officially closed for business, (b) banks located in New York City are required or
authorized by Law or executed order to close, or (c) the New York Stock Exchange is closed.
Work Breakdown Level means a hierarchical and organizational level that breaks the Design
and Construction Work into discrete elements, as described in Exhibit T (Critical Path Method
Progress Schedule). Each descending WBS level represents an increasingly detailed
description of elements comprising the Work with a clearly identifiable linkage between the
Work Breakdown Level and Project Schedule activities.
Working Drawings means Contractor submitted Design Document drawings for Work, not
otherwise defined in the Contract Documents, and requiring Department acceptance. Examples
of Working Drawings include Engineered Drawings, installation plans, certified drawings, and
any other supplementary plans or similar data that the Contractor is required to submit for
acceptance.
Worksite Traffic Supervisor (WTS) means the staff member or members employed and
identified by the Contractor that is a staff member other than the superintendent to implement
the Traffic Management Plan, monitor the safety and mobility of the entire work zone, and
correcting Temporary Traffic Control (TTC) deficiencies for the entire work zone.
EXHIBIT E
TECHNICAL REQUIREMENTS
ODOT PID 116649 | KYTC PROJECT ITEM NO. 6-17
ODOT CONSTRUCTION PROJECT 23-3000
TABLE OF CONTENTS
1. GENERAL ....................................................................................................................................... 1
1.1 Project Goals ............................................................................................................................... 2
1.2 Governing Regulations ................................................................................................................ 3
1.3 Standards Deviation Submittal Requirements .............................................................................. 9
1.4 Design Criteria ........................................................................................................................... 10
1.5 Airway/Highway Clearance for Airports and Heliports ................................................................ 12
1.6 Compatibility Requirement ......................................................................................................... 12
1.7 Video Monitoring........................................................................................................................ 12
1.8 Naming Conventions ................................................................................................................. 13
1.9 Drawing Format ......................................................................................................................... 13
7. ENVIRONMENTAL ........................................................................................................................ 62
7.1 Environmental Commitments ..................................................................................................... 62
7.2 Permitting .................................................................................................................................. 62
7.3 Mussel Relocation ..................................................................................................................... 63
7.4 Regulated Materials ................................................................................................................... 63
7.5 Cultural Resources .................................................................................................................... 64
7.6 Noise ......................................................................................................................................... 64
7.7 Submittals.................................................................................................................................. 65
9. UTILITIES ...................................................................................................................................... 69
9.1 General Utilities ......................................................................................................................... 69
9.2 Administrative Requirements ..................................................................................................... 70
9.3 Contractor Responsibilities in Ohio ............................................................................................ 71
9.4 Contractor Responsibilities in Kentucky ..................................................................................... 78
9.5 Utility Adjustment and Relocation Team .................................................................................... 80
9.6 Protection of Utilities .................................................................................................................. 81
9.7 Acquisition of Replacement Utility Property Interests ................................................................. 81
9.8 Submittals.................................................................................................................................. 82
LIST OF TABLES
Table 1-1: Standards and References ................................................................................................... 4
Table 1-2: Design Designation, Design Criteria and Maintaining Agencies .......................................... 11
Table 2-2: Submittal Durations and Print Requirements for Sub-Phase 1A Base Design Reviews ...... 31
Table 2-3: Submittal Durations and Print Requirements for Sub-Phase 1B and Phase 2 Reviews....... 33
Table 2-4: Submittal Durations and Print Requirements for RFC Submittals ........................................ 34
Table 13-1: Building Demolition and Reconstruction Submittals Table ............................................... 108
LIST OF FIGURES
Figure 1-1: Brent Spence Bridge Corridor Implementation Phasing ....................................................... 1
Figure 9-2: Utility Flowchart – New and Relocated Public Facilities ..................................................... 73
Figure 9-3: Utility Flowchart – New and Relocated Private Facilities .................................................... 74
1. GENERAL
The Brent Spence Bridge (BSB) corridor consists of 7.8 total miles of I-71 and I-75 located within
portions of Ohio and Kentucky. This corridor is located within the Greater Cincinnati/Northern Kentucky
region and is a major route for regional and local mobility. Regionally, the BSB carries both I-71 and I-
75 traffic over the Ohio River and connects to I-74, I-275, and US-50. The corridor is also one of the
busiest trucking routes in the United States, connecting Michigan to Florida via I-75. The BSB corridor
also facilitates local travel by providing access to downtown Cincinnati in Hamilton County, Ohio and
Covington in Kenton County, Kentucky.
The Brent Spence Bridge (BSB) corridor was split into three phases as depicted in Figure 1-1 (Brent
Spence Bridge Corridor Implementation Phasing) below. The Brent Spence Bridge Corridor Project
(PID 116649) (the Project), or Phase III, will construct approximately five miles of I-71/I-75 in Kentucky
and one mile of I-75 in Ohio and a new Companion Bridge over the Ohio River just to the west of the
existing Brent Spence Bridge and rehabilitate the existing Brent Spence Bridge. Design of Phase I
(ODOT PID 114161) and Phase II (ODOT PID 113361) are occurring under separate contracts.
Through value engineering workshops and continued studies, the Department is moving forward with
Concept I-W as the Conceptual Design for the Project. Reference Information Documents (RID) provide
additional information regarding Concept I-W and are identified throughout these Technical
Requirements. The Contractor shall use LD-07 (Concept I-W Corridor Exhibit) as a basis for the
development and validation of the Base Design. Additional geometric modifications and Alternative
Technical Concepts that meet project goals, environmental commitments, and local government
expectations can be evaluated during Sub-Phase 1A. Limits for the entire BSB corridor are shown in
the RIDs. The Project Limits encompass Phase III only, as graphically depicted in Figure 1-1 (Brent
Spence Bridge Corridor Implementation Phasing).
B. Build the Project with a context sensitive design that fits within the community;
C. Maximize the public investment in the Project by minimizing the footprint;
D. Minimize the footprint of the interstate system to maximize potential developable space;
E. Improve neighborhood connectivity across the interstate;
F. Minimize traffic disruption during construction, with minimal detours or diversion of traffic to local
streets;
G. Provide opportunities for Workforce Development and DBE utilization;
H. Provide strong aesthetic value along the Project corridor;
I. Achieve effective project delivery;
J. Minimize physical intrusion and impact;
K. Create best environmental outcomes;
L. Design for sustained quality of life;
M. Improve the local road aesthetics when crossing the interstate; and
N. Open the new Companion Bridge to traffic by July 15, 2029.
Contractor shall perform the Work in accordance with the most current version of each Project
Standard or reference listed in Table 1-1 (Standards and References) at the time Notice to Proceed is
given for Sub-Phase 1A.
Any standards, manuals and guidelines that are not included within the definition of Governing
Regulations shall subject to the Department’s approval prior to use. Any manuals or documents other
than those reflected herein or in the PDBC require Department approval before use in the Work. The
Contractor shall obtain advance prior written approval from Department, for any Standards Deviation
from the Governing Regulations, in addition to complying with all requirements regarding requested
Standards Deviations set forth in Section 1.3 (Standards Deviation Submittal Requirements).
Table 1-1: Standards and References
Author/Agency Title
Ohio
Author/Agency Title
City of Cincinnati Stormwater Management Rules and Regulations, Stormwater Management Utility (SMU)
Kentucky
KYTC Standard Drawings 2020 (includes Headwall Supplement) and Active Sepias 2020
Author/Agency Title
AASHTO Guide for the Planning, Design, and Operation of Pedestrian Facilities
Author/Agency Title
AASHTO Standard Specifications for Highway Bridges, 17th Edition (for checking HS20 load only)
Guide Manual for Condition Evaluation and Load and Resistance Factor (LRFD) Highway
AASHTO
Bridges, 3rd Edition with 2019 interim revisions
Guide Design Specifications for Bridge Temporary Works, 1995 with 2020 interim
AASHTO
revisions
AASHTO Geometric Design of Highways and Streets, 7th Edition
Author/Agency Title
CSXT CSX Design and Construction Standard Specifications for Pipeline Occupancies
FHWA HEC 15 Design of Roadside Channels with Flexible Linings, Third Edition
NFPA Standard for the Installation of Lightning Protection Systems, NFPA 780
Author/Agency Title
The Contractor shall clearly identify each individual portion of the Standards Deviation proposal that is a
proposed change to the Project Standards and the Contract Documents. Submit one electronic copy
(PDF format) of each Standards Deviation to the Department.
Each Standards Deviation submittal must contain and clearly depict the following information applicable
to the Deviation:
A. Description: Provide a detailed description of the Standards Deviation including specifications
and conceptual drawings.
B. Deviation: Reference all the specific section(s) in the Contract Documents which are
inconsistent with the proposed Deviation, provide an explanation of the nature of these
deviations from the referenced section, and a request for approval of such deviations. Provide
proposed language for the referenced section that is in keeping with the Standards Deviation
which can be seamlessly incorporated into the Contract Documents. Seamless incorporation
will be at the determination of the Department.
C. Usage: A description of where and how the Standards Deviation would be used on the Project.
D. Traffic and Safety Impacts: A discussion of the impacts the Standards Deviation will have on
vehicular, pedestrian, and cyclist traffic and safety, including an operational analysis, if relevant.
E. Maintenance of Traffic Impacts: A discussion of the impacts the Standards Deviation will have
on maintenance of traffic during construction.
F. Environmental Impacts: A discussion of how the Standards Deviation is in accordance with the
approved project Environmental Document and will meet environmental commitments and not
cause increased community impacts.
G. ROW Impacts.
H. Utilities: A discussion of utility (public and private) impacts.
I. Maintenance: A discussion of the long-term maintenance impacts of the proposed Deviation.
J. History: A detailed description of other projects on which the proposed Standards Deviation has
been used; including contact information (name, title, phone number, address, and email) for
project owners that can confirm Deviation implementation.
K. Inspection: Any additional testing and inspection requirements during construction and during
the expected life of the installation.
L. Costs: A discussion of cost savings of the proposed Standards Deviation.
Functional classifications, design speeds, legal speeds, and maintaining agency of roadways that are
designed and constructed as part of this Project or will be crossed by a new bridge or other structure as
part of this Project are provided in Table 1-2 (Design Designation, Design Criteria and Maintaining
Agencies) as a basis for the specific design criteria to be submitted by the Contractor. The specific
design criteria shall follow the standards and specifications set forth in Section 1.2 (Governing
Regulations) unless a design exception is approved by the Federal Highway Administration (FHWA). A
draft version of the LD-10 (Design Exceptions) listing current design exceptions is provided with the
RIDs, see further information regarding design exceptions in Section 15 (Roadway).
The Project design speeds for all facilities shall meet or exceed the minimum design speeds as shown
in Table 1.2. The existing legal/posted speeds are to remain the same on all existing facilities. The
terrain for the project is rolling. A schematic of the design speeds is shown in LD-09 (Concept I-W
Design and Legal Speeds Exhibit (from 12th Street to north end of Project)).
The Contractor shall cause all Design and Construction Work on city streets to comply with the
applicable local agency standards. If the local agency does not have a Standard Construction Drawing,
applicable ODOT or KYTC Standard Construction Drawings shall apply.
Legal/
Design
Functional Posted Maintaining
Roadway Other Designations Speed
Classification Speed Agency
(MPH)
(MPH)
W. 3rd Street Urban Principal Arterial 25 25 City of Cincinnati
Upon Completion of the Contract, the Contractor shall remove the camera equipment and provide
archive data encompassing the duration of the Project to the Department. Format of archive data must
be acceptable to the Department.
The Contractor shall be responsible for producing at minimum six professional-quality video vignettes
per year highlighting Project operations. The Contractor shall obtain Department Approval of the timing
and content for each vignette. These videos shall be 30 seconds to two minutes long.
The Contractor shall include video monitoring in the Opinion of Probable Cost (OPC).
All sheets north of the north ends of the Companion and Existing Brent Spence Bridges shall follow
ODOT naming standards found in ODOT’s CADD Engineering Standards Manual.
All sheets north of the north ends of the Companion and Existing Brent Spence Bridge shall follow
ODOT drawing format requirements found in ODOT’s CADD Engineering Standards Manual.
2. PROJECT MANAGEMENT
2.1 DBT Project Management Plan
2.1.1 Purpose and Format of the DBT PMP
In accordance with the requirements of the Project, develop and implement a written DBT Project
Management Plan (DBT PMP) for all elements of the Project, including, but not limited to, management,
administration, design, Internal organization systems, document management, communication plan,
investigations, construction, environmental monitoring, and compliance.
The PMPs shall be consistent with ISO principles (ISO 9001:2000 Quality Management Systems-
Requirements; ISO 9004:2000 Quality Management Systems - Guidelines for Performance
Improvement; ISO 9000:2000 Quality Management Systems- Fundamentals and Vocabulary;
ISO:19011:2004 Guidelines for Quality and/or Environmental Management Systems Auditing; ISO
14001:2004 Environmental Management Systems-Specifications with Guidance for Use).
Engage the Department in the DBT PMP development process to facilitate the process and ensure
understanding. The Department’s participation in the development of the DBT PMP does not waive the
Contractor’s responsibility for the quality of the Work, nor does it ascribe any responsibility to the
Department for the Work. Further, this involvement does not preclude subsequent rejection of the DBT
PMP by the Department.
The Department will audit and monitor the activities described in the DBT PMP to assess the
Contractor’s performance. All commitments and requirements contained in the DBT PMP shall be
verifiable.
The implemented DBT PMP shall accomplish the following functions and objectives:
A. Successfully deliver the Project within the accepted Project Schedule; and
B. Construct a high-quality Project that meets the requirements of the Contract Documents.
The DBT PMP must delineate how the Contractor will ensure all disciplines, aspects and elements of
the Work will comply with the requirements of the Contract Documents and all materials incorporated
into the Work will perform satisfactorily for the purpose intended and conform to the Contract
requirements. The general outline and the minimum content of the DBT PMP is described below and in
Section 2.1.2 (Key Personnel) through Section 2.1.8 (Utilities Plan).
2.1.1.1 DBT Management Plan
A. The purpose of the DBT Management Plan is to provide the Department with a clear view of the
project management approach undertaken by the Contractor for all aspects of the Project. It
shall clearly identify responsibilities and procedures for each Project management activity and
demonstrate a thorough understanding of the Project requirements.
B. The DBT Management Plan shall reference and consider all other PMPs and link their
relevance to each other and to the management approach.
C. The DBT Management Plan is an umbrella document that describes the Contractor’s
managerial approach, strategy, and quality procedures to design and build the Project and
achieve all requirements of the PDBC. The DBT Management Plan shall include an organization
chart outlining the basic structure of the Contractor’s Project organization including well defined
roles for the design and construction; sub-organizations (such as consulting, subcontractors,
suppliers) and a description of the roles; relationship with the Contractor, Designer,
Subconsultant, Subcontractor, and third parties; organizational chart with responsibilities,
professional qualifications, and Work to be accomplished by each member of the management
team and each sub-organization, including identified subcontractors and suppliers.
D. The DBT Management Plan shall describe how all PMPs fit within the overall quality
management system, responsibilities for developing and maintaining the plans and the schedule
for implementation.
E. The DBT Management Plan shall address the Contractor’s schedule and procedures for
preparation of amendments and submission of amendments to any part of the PDBC.
F. The DBT Management Plan shall be linked to the QMSP in Section 3 (Quality Management).
2.1.2 Key Personnel
Describe the roles of those involved in project management and the interactions between them.
The project management organization of the Contractor must include the following:
A. An organizational chart for each phase of the Project (Sub-Phase 1A, Sub-Phase 1B and Phase
2) showing lines of authority and reporting responsibilities for all Project disciplines.
B. The name, position, qualifications, duties, responsibilities, and authorities of each person
proposed for a project management function, including the following minimum named persons:
1. DBT Project Manager.
2. DBT Design Manager.
3. DBT Design QC Manager (See Section 2.1.2.3 (Other DBT Lead Personnel Requirements)).
4. DBT Lead Structural Design Engineer.
5. DBT Lead Highway Design Engineer.
6. DBT Lead Independent Companion Bridge Engineer.
7. DBT Independent Design Quality Firm (IDQF) Manager.
8. DBT Construction Manager.
9. DBT Lead Bridge Superintendent.
10. DBT Lead Highway Superintendent.
11. DBT Diversity and Inclusion Manager.
2.1.2.1 Duties and Experience Requirements
A. DBT Project Manager:
1. Ultimately responsible for the Contractor’s performance and ensures that personnel and
other resources are made available. Responsible for all aspects of the Project, including, but
not limited to, overall design, environmental compliance, construction, quality management,
and contract administration.
2. Shall have at least 15 years of design-build experience managing the design and
construction of major highways, interstate-to-interstate interchanges, or navigable river
bridge structures, with preference for both. The DBT Project Manager shall be assigned to
the Project full time and meet the co-location requirements in accordance with Section 4
(Co-Location Facilities for Contractor and Department Forces).
B. DBT Design Manager:
1. Responsible for ensuring overall Project design is completed and all design requirements are
met for the Project, inclusive of all structures and structural elements (bridge substructures
and superstructures, retaining walls) and roadway items (alignment, drainage, pavement,
lighting, traffic signals, maintenance of traffic, etc.).
2. Shall have at least 15 years of recent experience, experience with integrated project delivery
preferred, managing the design of major projects, and with complex maintenance of traffic
design experience. The DBT Design Manager must be a licensed professional engineer in
the State of Ohio and Commonwealth of Kentucky or be able to obtain licensure by award of
Contract. The Design Manager shall be assigned to the Project full time and meet the co-
location requirements in accordance with Section 4 (Co-Location Facilities for Contractor
and Department Forces).
C. DBT Lead Structural Design Engineer:
1. Actively manages and serves as point of contact for all structural designs. Responsible to
ensure that all requirements of the design for all structural elements on the Project, including
bridges, box culverts, walls, and foundations are met.
2. Shall have at least 15 years of recent similar experience. They must be a licensed
professional engineer in the State of Ohio and Commonwealth of Kentucky or be able to
obtain licensure by award of Contract. The DBT Lead Structural Design Engineer shall meet
the co-location requirements in accordance with Section 4 (Co-Location Facilities for
Contractor and Department Forces).
D. DBT Lead Highway Design Engineer:
1. Responsible for ensuring all highway geometric, drainage and traffic components on the
Project are completed and all design requirements are met.
2. Shall have at least 15 years of recent similar experience. They must be a registered
professional engineer in the State of Ohio and Commonwealth of Kentucky or be able to
obtain licensure by award of contract. The DBT Lead Highway Design Engineer shall meet
the co-location requirements in accordance with Section 4 (Co-Location Facilities for
Contractor and Department Forces).
E. DBT Lead Independent Companion Bridge Engineer:
1. Responsible for the independent design check of the Companion Bridge. Must be employed
by a qualified, independent professional firm selected and subcontracted to the DBT,
independent of the original bridge design for the Project.
2. Shall have at least 10 years of experience in the design and review of complex bridges for
major highway projects of similar size and complexity. They must be a registered
professional engineer in the State of Ohio and Commonwealth of Kentucky or be able to
obtain licensure by award of contract. The DBT Lead Independent Companion Bridge
Engineer shall meet the co-location requirements in accordance with Section 4 (Co-Location
Facilities for Contractor and Department Forces).
The Contractor shall document within the DBT PMP the Contractor management’s commitments
through processes and descriptions of the quality policies and objectives that will be implemented
throughout its organization The policies shall demonstrate the Contractor’s senior management’s
commitment to implement and continually improve the quality management system for the Work.
The Department will partner with the Contractor to establish a format within the ECMS and grant
needed access for the Contractor’s personnel to assist in the management of the site. The
Department’s ECMS will be the official project record for the Project.
Describe the means by which records established to provide evidence of conformity to requirements
and the effective operation of the quality program are identified, stored, protected, readily retrieved,
retained according to the Department’s Record Retention Policy, and disposed of.
Describe the procedures for meeting documentation requirements and document control of all Design
Documents.
As part of the DBT PMP the Document Control plan shall document correspondence distribution and
submittal requirements. Contractor shall provide copies of all correspondence between the Contractor
and other agencies, including cities, Government Agencies, Railroads, and Utility Owners, to the
Department via the Department’s ECMS at the time of submittal to the applicable agency.
DBT Document Control Plan shall include collection, retaining, and uploading to the Department’s
ECMS, within five Working Days of the activity to which the document pertains, the following, all of
which shall be in a format acceptable to the Department:
A. Evidence that all required activities have been performed.
B. Type, number, and results of all current quality management activities, including reviews,
verifications, audits, Nonconformances, Corrections, Opportunities For Improvement, Corrective
Actions, Preventive Actions and monitoring of Work performance and progress.
C. Documentation used and created by the IDQF for review of design submittals, including all
Design Documents included with interim and final design submittals, review comments, and
disposition of comments.
D. Engineered, Shop and Working drawings.
E. Minutes of all Contractor and IDQF meetings (distribute draft minutes within 48 hours).
F. For railroad and utility work, documentation of the design as well as documentation of utility and
railroad personnel on-site performing Work, including inspection and flagging. The documents
shall be maintained separately for each individual utility and railroad facility.
G. Any other document not listed above provided by the Contractor.
The Document Control Plan shall be linked to the QMSP in Section 3 (Quality Management).
2.1.4 Quality Planning
Plan, develop, and document in the DBT PMP the processes needed to deliver the Work in accordance
with the requirements of the Contract Documents, including but not limited to the following and Section
3 (Quality Management):
A. Geotechnical investigations and testing.
B. Field survey verification. The Contractor shall be responsible for the cost and repair of any
damage to survey monuments caused by the Work within a duration agreed to by the
Department.
C. Control of monitoring and measurement devices, to ensure that tools, gages, instruments, and
other measuring and testing devices used in activities affecting quality are properly maintained,
controlled, calibrated, certified, and adjusted at specified periods to maintain accuracy within
necessary limits.
D. Design planning, to establish the responsibilities, checks, reviews, timing, procedure, or
reference standard, and resulting records for all design submittals.
E. Design requirements definition, to ensure that all users have the current and complete set of
requirements applicable to their work.
F. Deviations from the requirements of the Contract Documents, to ensure that general or specific
Deviations from requirements occur only with the Department’s approval.
G. Validation of computer programs and checking of inputs.
H. Cross-discipline reviews, to ensure consistency and prevention of coordination errors.
I. Conformance checking, to ensure the right requirements are being utilized.
J. Fitness for use reviews, to ensure that Work will meet generally implied expectations.
K. Accuracy checking, to ensure requirements are designed right.
L. Style checking, to ensure compliance with appearance needs, i.e., CADD, file type, spelling, etc.
per Section 1.9 (Drawing Format).
M. Constructability reviews, to ensure the functionality, accessibility, and maintainability of the
Work.
N. Over-the-shoulder reviews.
O. Scope checking to verify the completeness of submittals.
The Contractor shall include methods, processes, and procedures to ensure compliance with final
environmental commitments for the Project. It should be noted that these may require specific
performance measures for compliance.
Contractor shall include the use of the SWPPP Track pursuant to ODOT SS832 as part of the process
and procedures. The Contractor shall include separate bid item codes for KYTC and ODOT.
6. Information to stakeholders about events in the area that may be affected by construction
activities.
J. Linkage to other PMPs and the QMSP.
2.1.8 Utilities Plan
The Utilities Plan will define the utility coordination, adjustment, and relocation activities during the
design and construction of the Project and will address:
A. The roles and responsibilities of the Contractor, the Department, and Utility companies/owners.
B. Utility agency coordination plans and process.
C. The Utility Relocation and adjustment process.
D. Applicable guidelines, laws, and regulation.
E. The application of prior rights and cost allocations.
F. The utility easement acquisition process, if required.
G. Utility agreements including KYTC Memorandum of Understanding (“MOU”) and/or the
development of Project specific utility relocation agreements.
H. Relocations and adjustments of utility facilities included in the Contractor’s Contract.
I. Relocations and adjustments of utility facilities performed by the utility company/owner or their
contractor.
J. The coordination with the Contractor, the Department, KYTC, Utilities, Utilities’ designers, and
contractors.
K. The identification and resolution of utility conflicts and interdisciplinary coordination.
L. The development and maintenance of a Utility tracking report.
M. The process for revising utility plan and estimates.
N. The process of payment of utility company progress and final billings by the Department and
KYTC, to be further coordinated after Sub-Phase 1A NTP.
O. The process for close out of utility relocations and processing as-builts, and if required land
use permit applications.
P. Identify monitoring and recording requirements.
Q. On-going monitoring and compliance records tracking system.
R. The roles and responsibilities related to Contractor provided MOT services for utilities and/or
their contractors.
S. Regularly updated impact on project schedule.
T. Reporting and documentation mechanism.
U. Linkage to other relevant PMPs and the QMSP.
2.1.9 Overall DBT Organization Plan
The Contractor shall describe the design and construction organizational arrangements it intends to
implement. The organizational arrangements described should clearly identify responsibilities and
reporting lines of staff, particularly relating to Key Personnel. The Contractor shall include an
organization chart and communication protocol graphic (11-by-17 inch) illustrating the Proposer’s Key
Personnel and their prospective roles and responsibilities, as well as other principal participants and
any known Subcontractors having a material role in the Project’s design Work, design check Work, and
construction Work.
The Contractor shall describe the interrelationships and interfaces between each discipline within the
Offeror’s organization (e.g., design, design check, shop drawing preparation and review, construction,
and quality management).
The Overall DBT Organization Plan shall also describe the interrelationships and interfaces between
the Contractor’s organization, the Department and other governmental agencies, utility owners,
stakeholders, businesses, the public and other contractors working in the vicinity and impacted by the
construction of the Project. This description shall also, at a minimum, address the following activities:
A. Reviews of plans and permits;
B. Progress, workshop, partnering and utility coordination meetings; and
C. Construction, engineering and inspection activities.
2.1.10 Construction Management Plan
The Contract shall provide a Construction Management Plan, which may include relevant material
submitted with its Proposal and submit it to the Department for review and comment. The Construction
Management Plan shall provide how well the Contractor understands and is organized to manage
construction, construction quality control and the tools that will be implemented to provide seamless
interaction with the Department for the construction of a quality Project; provides how the progress of
the construction work is reported to the Department and for control of the Work; provides how
nonconformance issues in construction will be resolved; provides the method of updating the Baseline
Schedule; provides how the work will be progressed in coordination with other agencies; provides the
methods of maintaining detours and evaluates how the interaction with the Department’s construction
inspection professional engineering firm and the materials testing firm/laboratory will occur and how this
will contribute to the construction management and quality of the Project.
At the Department’s sole discretion, the Department may approve portions of the DBT PMP to allow
certain Work (e.g., design) to proceed as defined by the applicable portion of the DBT PMP.
2.1.11.2 DBT PMP Approval
Submit a draft DBT PMP of all the Management Plans listed in Table 2-1 (DBT PMP Component
Management Plans). then allow 15 Working Days for the Department to approve or reject initial DBT
PMP submittals. For subsequent revisions to the DBT PMP, the Department requires 10 Working Days
to approve or reject the submittal. Submit each DBT PMP revision after the approved to the Department
during a submittal meeting, in which the Contractor shall provide an overview of the DBT PMP revision.
Project meetings will include the Contractor, the Department, and other active participants requested by
the Department. Other active participants may include representatives from the Cities of Cincinnati,
Covington, Ft. Wright, and Ft. Mitchell.
maintenance of all future OPCs, including design and construction cost and Project
Schedule estimates. This meeting will also establish the plan to communicate changes in
scope, quantity, risk, and other information required to affirm a consistent foundation for cost
and schedule estimation. This initial meeting will be led by the Department.
2. Attendees:
a. Department’s Project staff, Department’s Office of Estimating Staff, the ICE, the DBT
Project Manager, Design Manager, Superintendents, and other parties defined by the
Department and Contractor.
3. Agenda:
a. Review the methods and procedures related to the Project Schedule and overall project
progress.
b. Introduction of the Contractor’s Schedule team’s qualified personnel that will develop
and update the project schedule, including BIM 4D and 5D components if the DBT PMP
plans incorporate them into the project.
c. Content, format, and submittal requirements for schedules and reports.
d. Schedule for other concurrent work under Department’s separate contracts and
coordination with other work and personnel.
e. Review time required for submittals and resubmittals.
f. Review time required for RFIs, Change Orders, Government Entity reviews and
approvals, and project logistics.
g. Requirements for tests and inspections by independent testing and inspecting agencies.
h. Time required for mobilization and demobilization.
i. List of Contract activities to be included in schedule and their associated naming
conventions.
j. Procedures for updating schedule.
k. Proposed structure and assumptions for the Cost Model and establish input standards
for the formulation of future cost estimates.
l. Software limitations, if any.
4. Minutes:
a. The Contractor will record and distribute meeting minutes.
B. Monthly Cost and Schedule Update Review Meetings:
1. Contractor shall schedule, attend, and actively participate in cost and schedule working
group meetings with the Department and the ICE to review cost estimate organization,
break-down, reconciliation of OPC and cost estimates. The Contractor shall lead the
Monthly Cost and Schedule Update Review Meetings.
2.2.4 Design Progress Meeting
A. Department will schedule regular Design Progress Meetings to determine the progress of the
development of the Design Work. These meetings will start two weeks after the post award
scope meeting. The meetings will occur once a week at a minimum and as required to
accomplish design tasks.
B. Attendees:
1. Design Progress Meetings shall be attended by:
a. Department and Department’s Consultants;
b. DBT’s Key Personnel, at a minimum;
c. Major Subcontractors as applicable; and
d. Others as directed by Department.
C. Agenda:
1. The Contractor shall be responsible for developing the meeting agendas. The purpose of
the meetings is to discuss significant items that could affect the completion of the
Construction Drawings and Specifications and have a major impact of the quality, cost, and
overall schedule for the Work. The agenda shall be submitted to Department a minimum of
48 hours prior to the meeting.
D. Minutes:
1. The Contractor will record and distribute meeting minutes. Meeting minutes shall be
distributed no later than three Working Days after such meeting is held.
2.2.5 Project Coordination and Logistics Meetings
A. Schedule and administer as needed support, coordination and logistics meetings among
stakeholders affected by the Work. Stakeholders include Contractor and all applicable
Subcontractors, the Department and when applicable representatives of Government Entities
affected by or having jurisdiction over the Work. Contractor shall coordinate with stakeholders to
allow for their reasonable review prior to finalizing the Base Design, Cost, and Schedule
Submittals. Incorporate all logistical and coordination topics into the Project Schedule to allow
for at least 10 Working Days’ notice of review.
B. Agenda to include design criteria, limits of work, design alternatives considered, reasons that
given alternatives were either discarded or adopted, or specific topics requested by the
Department or stakeholders.
C. Minutes:
1. The Contractor will record and distribute meeting minutes.
Conduct over-the-shoulder reviews in the Project Management Office (PMO) and in the presence of the
design personnel, with the intent of minimizing disruption of ongoing Design Work. The IDQF Manager,
design staff, and the Department will jointly determine the materials to be compiled for each review.
Formal assembly and submittal of drawings or other documents will not be required; however, the
Contractor is encouraged to provide informal submittals to facilitate reviews. The over-the-shoulder
review may be of progress prints, computer images, draft documents, working calculations, draft
specifications or reports, or other Design Documents. If mutually agreed upon for specific review items,
the over-the-shoulder review may be facilitated by the transfer of electronic files. The IDQF shall
document the outcome of each over-the-shoulder review. It shall be the Contractor’s responsibility to
confirm whether comments made are in conformance with the Contract Documents.
Schedule a submittal meeting with the IDQF to present the Base Design Submittal. Notify other
agencies, (i.e., FHWA, City(s), Railroads, and Utilities as applicable to the submittal) including the
Department, at least 10 Working Days in advance of submittal meeting and attend meeting. At
submittal meeting, provide an overview of the submittal, including a summary of all included
information. Submittals with missing information will not be accepted. The submittal and timeframe by
which it is submitted shall be in accordance with PDBC Section 4.8 (Department Review of Contractor
Submittals).
Provide a complete review of all Design Documents with each formal IDQF review to ensure Contract
Document requirements and design criteria are being met, including any calculations by the Lead
Independent Companion Bridge Engineer (ICBE) for the Companion Bridge design submittals. The
IDQF Manager is not allowed to release any design submittal that does not meet Contract Document
requirements or was not developed in accordance with the DBT PMP. The IDQF does not have the
authority to waive Contract Document requirements. In addition, the IDQF Manager will verify there are
no conflicts between the Buildable Units being reviewed. All deviations from these requirements must
be noted and corrected.
Upon IDQF approval and verification that a design submittal is in compliance with the Contract
Documents, the Contractor must submit Design Documents including the IDQF quality certification to all
applicable agencies requiring review and upload electronic copies to the Department’s ECMS.
Submittal requirements, beyond those stated in the Contract Documents, to agencies other than the
Department shall be determined by and complied with by the Contractor.
Use the durations listed in Table 2-2 (Submittal Durations and Print Requirements for Sub-Phase 1A
Base Design Reviews) in the Project Schedule for Sub-Phase 1A Base Design and reviews as follows.
The Contractor shall submit an electronic searchable version (in PDF format that is Bluebeam
compatible) along with full size and half size plans in accordance with ODOT’s CADD Engineering
Standards Manual and KYTC’s CADD Standards and Table 2-2 (Submittal Durations and Print
Requirements for Sub-Phase 1A Base Design Reviews) simultaneously to the parties indicated in Table
2-2 (Submittal Durations and Print Requirements for Sub-Phase 1A Base Design Reviews) below.
Table 2-2: Submittal Durations and Print Requirements for Sub-Phase 1A Base Design Reviews
Review times begin upon receipt of submittal following IDQF approval and the Working Day following
the date on which the submittal is made. The Project work schedule for the Preconstruction Phase is a
five-day workweek with each Working Day ending at 5 pm. Submittals made after 5 pm will be counted
as submitted on the following Working Day. The Department will not provide formal review of design
submittals; however, design submittals are subject to Department audit over the course of design
development. Department design audits may be limited to scope compliance; however, the depth,
magnitude, type, and timing of the Department’s audit of design submittals will be at the Department’s
sole discretion. As necessary, schedule comment resolution meetings with the Department to resolve
comments received as a result of the Department audit.
The IDQF Manager must prepare and distribute minutes of each submittal and comment resolution
meeting and shall ensure that all review comments are addressed by the Contractor and verified by the
IDQF. Base Design Submittal shall include a written disposition of all comments made during formal
interim design submittals.
2. Ensure that recommendations identify impacts to long term maintenance and operations
and any specialty inspection that may be required;
3. Ensure that recommendations identify all impacts to previously approved federal, state, and
local environmental approvals;
4. Clearly identify and explain techniques, means and methods, phasing, scoping, or other
items that result in the reduction of cost or schedule;
5. Clearly quantify rough order of magnitude (ROM) cost and schedule implications for each
ATC;
6. Provide a list of ATCs developed and reviewed with the Department and identify ATCs that
will be carried forward into the Base Design Submittal and Sub-Phase 1B and Phase 2;
7. Contractor to perform an iterative process not to exceed 60 Working Days from submittal of
the draft ATC and innovation plan to accept ideas to address goals listed in Section 1.1
(Project Goals), improve Project quality, reduce cost, shorten schedule; and
8. During the ATC process, creativity and an objective problem-solving approach that addresses
Project Goals, is an expectation of the Contractor in the Work in this Sub-Phase 1A.
E. Continuous updates to OPC’s necessary to support the ATCs and innovation process;
F. Final ATCs and innovation plan, due 30 days after Department’s comments on last OPC update
and included in the Sub-Phase 1B Proposal;
G. Continuous updates to the Project schedule necessary to support the OPC;
H. Base Design Submittal quantities with appropriate item codes per state; and
I. An overall schematic of all Buildable Units.
2.3.3 Sub-Phase 1B and Phase 2 Design Submittals
Schedule a submittal meeting with the IDQF to present each Interim and Final design submittal. Notify
other agencies, (i.e., FHWA, City(s), Railroads, and Utilities as applicable to the submittal) including the
Department, in advance of each submittal meeting and attend each meeting. At submittal meetings,
provide an overview of the submittal, including a summary of all included information. Submittals with
missing information will not be accepted.
Provide a complete review of all Design Documents with each formal IDQF review to ensure Contract
Document requirements and design criteria are being met, including any calculations by the Lead
Independent Companion Bridge Engineer for the Companion Bridge design submittals. The IDQF
Manager is not allowed to release any design submittal that does not meet Contract Document
requirements or was not developed in accordance with the DBT PMP. The IDQF does not have the
authority to waive Contract Document requirements. In addition, the IDQF Manager will verify there are
no conflicts between the Buildable Units being reviewed and any previously approved designs. All
deviations from these requirements must be noted and corrected.
Upon IDQF approval and verification that a design submittal is in compliance with the Contract
Documents, the IDQF must submit Design Documents to all applicable agencies requiring review and
upload electronic copies to the Department’s document management system. Submittal requirements,
beyond those stated in the Contract Documents, to agencies other than the Department shall be
determined by and complied with by the Contractor.
Use the durations listed in Table 2-3 (Submittal Durations and Print Requirements for Sub-Phase 1B
and Phase 2 Reviews) in the Project Schedule for Sub-Phase 1B and Phase 2 reviews and
comments/approvals as follows. The Contractor shall submit an electronic searchable version (in PDF
format that is Bluebeam compatible) along with full size and half size plans in accordance with ODOT’s
CADD Engineering Standards Manual and KYTC’s CADD Standards and Table 2-3 (Submittal
Durations and Print Requirements for Sub-Phase 1B and Phase 2 Reviews) simultaneously to the
parties indicated in Table 2-3 (Submittal Durations and Print Requirements for Sub-Phase 1B and
Phase 2 Reviews) below.
Table 2-3: Submittal Durations and Print Requirements for Sub-Phase 1B and Phase 2 Reviews
Review times begin upon receipt of submittal following IDQF approval and the following Working Day
the submittal is made. The Project work schedule for the Preconstruction Phase is a five-day workweek
with each Working Day ending at 5 pm. Submittals made after 5pm will be counted as submitted on the
following Working Day. The Department will not provide formal review of design submittals; however,
design submittals are subject to Department audit over the course of design development. Department
design audits may be limited to scope compliance; however, the depth, magnitude, type, and timing of
the Department’s audit of design submittals will be at the Department’s sole discretion. As necessary,
schedule comment resolution meetings with the Department to resolve comments received as a result
of the Department audit.
The IDQF Manager must prepare and distribute minutes of each submittal and comment resolution
meeting and shall ensure that all review comments are addressed by the Contractor and verified by the
IDQF. Submittals shall include a written disposition of all comments made during formal design
submittals.
The IDQF must verify compliance with all Contract Document requirements and design procedures and
verify that all comments from final reviews have been resolved. If upon IDQF review it is determined
that it is questionable as to whether comments received from the Department or other agencies have
been resolved or addressed appropriately, the IDQF Manager may consult with the commenter to
resolve such comments.
The IDQF Manager must sign and stamp the Design Documents “Released for Construction” after the
following requirements have been met:
A. All IDQF, Department, and other agency comments and Nonconformances have been resolved.
B. Design Documents have been designed in accordance with the requirements of the Contract
Documents and are consistent with the overall design.
C. Design Documents have been checked in accordance with the DQMP.
D. All identified deviations have been approved by the Department.
E. Design Documents have been Signed and Sealed by the Engineer of Record.
F. Design Documents for the independent quality check must be Signed and Sealed by the Lead
Independent Companion Bridge Engineer.
Provide detailed quantity estimates and ODOT and KYTC standard bid codes for all Work that requires
quality sampling or testing and all materials subject to price adjustments (e.g., structural steel). Be
consistent with the units used to determine frequency of sampling and testing. For example, if the
number of compaction tests to be taken is based on a specific number of cubic yards of embankment,
then the quantity estimate must also be in cubic yards. Quantities may be provided after Design
Documents are Released for Construction; however, provided quantities prior to any construction
commencing for the Work covered by the applicable Released for Construction Documents.
For all design changes requiring calculations, the Designer, and Design QC Engineer shall conduct a
documented check of all calculations. All design changes requiring alteration of design documents
released for construction shall undergo all review and certification procedures included for the original
design documents in the Design Quality Management Plan.
If a design change takes place after sign-off of the Released for Construction Plans, the Contractor
shall prepare a Notice of Design Change (NDC) and submit it to the Department for review and
comment. The NDC shall describe the change; identify and provide the Buildable Unit Plans,
Specifications, calculations, and other documents impacted by the change; explain the reason for the
change; list other Buildable Unit that will be impacted by the change; and describe the impacts to the
Project Schedule, if any.
In all cases, the DBT IDQF Manager must certify in writing that the field design change:
A. Has been designed in accordance with Contract Document requirements.
B. Has been checked in accordance with the DQMP.
C. Has been reviewed by the IDQF.
2.3.8 As-Built Submittals
Produce As-Built Documents as the Project progresses and as each Buildable Unit is completed, within
60 Workdays of Buildable Unit completion Prepare As-Built Documents in conformance with ODOT and
KYTC plan formats described in applicable standards and submit them in both hardcopy and electronic
(PDF, TIFF, and CADD) format, including MicroStation and Open Roads Designer (ORD) files,
conforming to ODOT and KYTC CADD standards. See Section 8.4.F (Design and Preconstruction
Survey) for KYTC As-Built survey requirements. As-Built Documents shall include quantities for the
Work associated with each Buildable Unit.
Group quantities in accordance with the Location and Design Manual, Volume 3, Section 1307, and
provide them in Microsoft Excel or similar tabular format, as approved by the Department. Provide
instructions with each table of quantities, providing information that enables Department personnel to
properly identify all quantities.
Prepare formal As-Built submittals for each Buildable Unit that incorporate all updates to the Released
for Construction Documents including any design changes, actual field as-built changes, actual survey
info; and up-to-date copies of all other Design Documents including Project reports, calculations, design
files, etc. These submittals must include an overall schematic of all Buildable Units.
Utility relocations performed by others, in conjunction with the Project (e.g., telecom, gas, private
electric, other private utilities), do not need to be incorporated in the As-Built CADD files and plan
sheets, however, the utility relocation plans must be included as an attachment to the As-Built
submittal.
The IDQF will review and verify As-Built Documents for compliance with the Contract Documents prior
to submittal to the Department.
The review of As-Built Documents will be performed by the Department with Contractor participation. All
As-Built Buildable Unit submittals must be submitted as noted in Table 2-5 (Project Management
Submittals Tables), as a condition of Completion of the Contract or as a condition of Final payment per
PDBC Section 5.14.3 (Final Payment).
2.4 Submittals
Unless otherwise indicated, submit all Submittals in both electronic format and hardcopy format.
Acceptable electronic formats include Microsoft Word, Microsoft Excel, or Adobe Acrobat (.PDF) files,
unless otherwise indicated. At a minimum, the Contractor shall submit the following to the Department:
3. QUALITY MANAGEMENT
3.1 General
The Contractor is responsible for the quality of the Work, including the Work and products of the
Designer, Subcontractors, Subconsultants, fabricators, suppliers, and vendors.
12. Explain the corrective action process for workmanship related quality issues in order to
minimize the recurrence of such errors and quality problems.
Provide an organizational chart in the Design Quality Management Plan identifying key Designer and
Subconsultant design management personnel. Include a description of responsibilities, qualifications,
and authority of the key design management personnel and the organizational interfaces between other
engineering groups disciplines which undertake the Design Work. The Design Quality Management
Plan must address all phases and aspects of the Design Work.
The Design Quality Management Plan must, at a minimum, include or reference detailed quality system
procedures and process flow charts for the following processes:
A. Design and computer input and output review;
B. Verification of design inputs that incorporate on-Site measurements and/or inspections;
C. Design verification to ensure that design input requirements have been met;
D. Design validation to ensure that the final product is capable of meeting its intended use;
E. Design changes;
F. Control of non-compliant product;
G. Compliance with design certification requirements;
H. Design subcontractor quality assessment and procurement;
I. External quality audits of design subcontractors;
J. Internal quality audits;
K. Corrective actions;
L. Document management;
M. Control of records;
N. Interaction with design checking teams, including independent design checkers; and
O. Any mandatory documented procedures in addition to the foregoing.
At a minimum, the above-listed procedures and flow charts must document who will do the work, what
they will do, and what evidence is generated that they have done the work correctly. Provide a
declaration with each submittal from the DBT Design Quality Manager that the Design followed the
quality process and complies with the Design Quality Management Plan and any applicable
independent design check certifications. The Design Quality Management Plan shall be linked to other
relevant PMPs and the QMSP.
The IDQF shall not have any responsibility for, and shall remain independent from, all production
activities for Design Work. All written or documented communications (including all notices,
notifications, correspondence, meeting minutes, data, reports, transmittals, and emails) between the
IDQF and the Contractor relating to the IDQF’s responsibilities in connection with the Project shall be
copied to the Department. In the event the IDQF determines that the Design Work (or any portion
thereof) is not in accordance with the Contract, the DBT Design Manager and DBT Construction
Manager shall not have the authority to over-rule the IDQF’s determination.
The Contractor cannot terminate or seek the termination or removal of any IDQF personnel performing
quality functions or with a judgment in the quality of the Design Work without the expressed written
permission of the Department.
The DBT Lead Independent Companion Bridge Engineer must have authority independent of and be
equivalent (or higher) authority than the DBT Design Manager.
The Contractor cannot terminate or seek the termination or removal of the Lead Independent
Companion Bridge Engineer without the expressed written permission of the Department.
Provide a Construction Quality Management Plan that contains an organizational chart identifying key
construction management personnel. Include a description of the responsibilities, qualifications, and
authority of the above personnel and the organizational interfaces between construction and other
disciplines, including design, environmental management, and traffic management. Include all phases
and aspects of the Work, including design and construction, in the Construction Quality Management
Plan.
The Construction Quality Management Plan must, at a minimum, include or reference detailed quality
system procedures and process flow charts for the following processes that the Contractor will be
responsible for compliance with the Project Standards:
A. Construction safety audits:
1. Compliance with the Department’s inspection, testing, and monitoring.
B. Inspection, sampling and testing for Ohio Work required by C&MS 611 and SS840.
C. Field measurements and surveys.
D. Materials identification and traceability including (Information provided by Contractor):
1. Material sources.
2. Mill certifications.
3. Buy America certifications.
4. General material certifications.
5. Test data certifications.
6. Mix designs.
E. Subcontractors’ quality assessment and procurement.
F. Procurement monitoring compliant with the Subcontractor Bidding and Selection Plan.
G. External quality audits of Subcontractors.
H. Internal quality audits.
I. Control of non-compliant product and process of addressing non-compliance by both Contractor
and Subcontractors.
J. Corrective Action Plan and process for addressing corrective actions to address and prevent the
recurrence of Nonconforming Work as defined in Section 3.7 (Nonconforming Work).
K. Document management (Contractor for documents they produce/provide).
L. Control of records (Contractor for what they produce/supply).
M. Any mandatory documented procedures in addition to the foregoing.
At a minimum, document who does the work, what they do, and what evidence is generated that they
have done the work correctly in the foregoing procedures and flow charts.
Integrate the Departments quality assurance specifications, process, and durations into the
Construction Quality Management Plan.
Upload all Quality Documentation to the Department’s chosen document management software and
systems within 10 Working Days for access by the Department.
Integrate the Departments fabricator specifications, process, and duration into the Construction Quality
Management Plan.
all information required by the Department. The Contractor shall rectify or otherwise address the
Nonconforming Work as described in the NCR, subject to the Department’s acceptance, in a manner
that allows each NCR to be closed within the period identified in the NCR, but in any event no later than
the Substantial Completion Deadline, or as otherwise stated in the PDBC Section 5.9 (Unauthorized
and Nonconforming Work).
Notwithstanding that Nonconforming Work has not yet occurred, a potential NCR shall be initiated
whenever any of the following apply:
A. An internal or external audit finding shows that a process or procedure in the PMP is not clearly
documented.
B. It has been discovered that the applicable reviews, testing, or inspections related to the Work
may not have been followed and the Project Documents or records are incomplete or
inconclusive.
C. Work of a similar nature or Work subject to similar processes has been discovered to be
Nonconforming Work and the root cause has not yet been established.
D. Work is in a state prior to reaching final completion condition such that modification would
require its destruction or otherwise require unplanned Work to occur to correct the condition to
make the Work conform to the requirements of the Agreement or to conform with other design
discipline elements. These fixed points include:
1. Upon transmittal of a Buildable Unit Submittal.
2. Any other point in time where Work has a distinct transition into a new and subsequent
stage, form, or time period. For example, substructure Construction Work is progressing,
and superstructure Release for Construction plans are submitted after substructure
Construction Work begins.
An NCR or potential NCR shall be initiated with respect to any of the following types of Work:
A. PMP, including conformance to stated process and procedures
B. Design Work at or after the Released for Construction Submittal, including associated Field
Design Change, Notice of Design Change, and Shop Drawings and their associated revisions
C. Construction Work including maintenance during construction
Wherever this Section 3.7 refers to Contractor actions and obligations with respect to each NCR, this
shall be deemed to include Contractor actions and obligations with respect to each potential NCR, and
the same processes and procedures specified herein for NCRs shall be followed for potential NCRs.
Where the disposition of an NCR is set to submit/re-submit for periodic or re-occurring Submittals, the
accepted remedy shall have been implemented prior to the next periodic Submittal or subsequent stage
of Submittal and in accordance with PDBC Section 5.9 (Unauthorized and Nonconforming Work) and
with PDBC Exhibit F (Noncompliance Points System).
Where the disposition of an NCR is set to “redesign” for a post-RFC Design Work Submittal and the
remedy requires the Design Work to be modified prior to construction beginning, the Contractor shall
issue the associated Field Design Change or Notice of Design Change.
shall address whether the performance by personnel responsible for the relevant activities may be a
primary or contributing cause of the systemic Nonconforming Work. In such case, remedial action shall
include additional training, additional personnel, or the replacement of personnel or Subcontractors
from the activity or Project. Where the Department does not accept the PAR, the Contractor shall revise
and resubmit the PAR via the ECMS system. Upon the Department acceptance of a PAR, the CAR
shall be closed. The Contractor’s failure to provide or address the Department’s comments shall be
handled in accordance with PDBC Section 5.9 (Unauthorized and Nonconforming Work). The
Contractor’s failure to submit, implement, or comply with the accepted PAR shall result in the issuance
of a Noncompliance Event in accordance with PDBC Exhibit F (Noncompliance Points System).
The independent design check requirement shall be separate from, and in addition to, the Contractor’s
required quality management procedures. The use of an Independent Bridge Engineer is not required
for report submittals unless noted otherwise elsewhere in the Contract Documents.
A. Design Assessment Requirements: Design assessment shall be the review of general
compliance with the requirements of Section 18 (Structures) taking into consideration the
proposed method of construction, and shall at a minimum cover the following areas:
1. Loads.
2. Applicable laws and standards.
3. Methods of analysis.
3.9 Submittals
Submit submittals under this Section 3.9, a non-exhaustive list of which is set forth in Table 3-1 (Quality
Management Submittals Table), in electronic format in accordance with the schedule set forth below.
Acceptable electronic formats include PDF and current versions of Microsoft Word and Microsoft Excel,
unless otherwise indicated. At a minimum, the Contractor shall submit the following to the Department:
Although located in the same facility as the Contractor , Department staff and consultant advisor
personnel workspaces shall be adjacent to the extent possible. If the facility has multiple floors, the
Department and consultant advisor workspaces should be placed together on its own floor while
Contractor workspaces shall be located on a separate floor.
The PMO shall be established with a short-term lease (with a maximum initial term of one-year) with the
option to extend for the term of the Project on a month-to-month basis. If PDBC Section 21
(Termination for Convenience) is initiated by the Department the short-term lease shall be allowed to
expire or shall be terminated.
The following personnel, at a minimum, shall be in the PMO during the Preconstruction Work (Sub-
Phase 1A) for weekly progress meetings:
A. DBT Construction Manager
B. DBT Design QC Manager
C. IDQF Manager
D. Lead Structural Design Engineer
E. Lead Highway Design Engineer
F. Lead Independent Companion Bridge Engineer
G. DBT Diversity and Inclusion Manager
Although considered beneficial by the Department, it is left to the discretion of the Contractor as to
whether detailed design production activities of the Project are located at the PMO. If any portion of the
Design Work is not accomplished at the PMO, it is expected that the Key Personnel and design
discipline leads shall be responsible for all necessary coordination at the PMO.
It is required that all design reviews, Contractor’s design discipline (subject area) meetings called for by
the Contract Documents, and all coordination and other activities requiring Department’s consultation
be held in the PMO unless otherwise mutually agreed.
The following personnel, at a minimum, shall be co-located in the PMO for Preconstruction Work (Sub-
Phase 1B) per percentages/week listed below:
A. DBT Project Manager (100%)
B. DBT Design Manager (100%)
C. IDQF Manager (100%)
D. Lead Independent Companion Bridge Engineer (20%)
E. DBT Construction Manager (20%)
F. Lead Structural Design Engineer (20%)
G. Lead Highway Design Engineer (20%)
H. DBT Diversity and Inclusion Manager (20%)
I. DBT Design QC Manager (20%)
The following personnel, at a minimum, shall be co-located in the PMO for Final Design and
Construction Work (Phase 2) per percentages/week listed below:
A. DBT Project Manager (100%)
B. DBT Design Manager (100%)
C. DBT Construction Manager (100%)
D. DBT Utilities/Rail/City Coordinator (80%)
E. IDQF Manager (100%)
F. Public Information Point of Contact (60%)
G. Lead Bridge Superintendent (100%)
H. Lead Highway Superintendent (100%)
I. DBT Diversity and Inclusion Manager (60%)
J. Lead Independent Companion Bridge Engineer (60% until 100% of the Companion Bridge
Released for Construction Plans are accepted)
K. Lead Structural Design Engineer (20% until 80% of the structural Released for Construction
Plans are accepted)
L. Lead Highway Design Engineer (20% until 80% of the roadway Released for Construction Plans
are accepted)
M. DBT Design QC Manager (20% until 80% of the Released for Construction Plans are accepted)
The Contractor shall coordinate to ensure at a minimum one of the following Key Personnel is in the
PMO during the work week during Phase 2: DBT Project Manager, DBT Design Manager, and DBT
Construction Manager.
In Phase 2 of the Project, it is anticipated that construction field offices will be necessary in both Ohio
and Kentucky. The Ohio construction field office may be separate from or combined with the PMO.
Equipment and network requirements for the field office(s) will be coordinated prior to the Phase 2
Change Order.
After the Design Work of the Project is complete, the Contractor may elect to reduce the size of the
PMO provided sufficient office space remains for the required Contractor’s and Department’s
managerial, construction, and environmental compliance personnel.
In addition to the requirements of ODOT Construction and Materials Specifications Item 619, within two
weeks after NTP, the Contractor shall schedule a meeting with the Department to coordinate plans for
the interim and/or permanent PMO and possible construction field office(s), including integration,
accommodation, and incorporation of Department’s requirements. Contractor shall provide the following
items and features for the required office space and facilities for Department forces within 30 days after
Notice to Proceed.
The Contractor shall provide maintenance for all items provided by the Contractor. The Contractor is
responsible for determining office requirements to accommodate the Contractor’s staff.
A. New Office furniture for the entire office space:
1. Two copier, printer, and scanner systems per the specifications listed below. The Contractor
shall provide paper and printing supplies and maintenance for all specified equipment.
Contractor shall provide maintenance within 24 hours of Department notification of
equipment use disruption.
2. Contractor to provide telephone service for KYTC and Consultant Advisors as required for
the PMO to function as a typical design office with minimal delays in service or ability to
complete Work.
3. All rooms, cubicles, and conference rooms shall be capable of having network jacks
installed for use by the Department.
4. The Contractor will obtain and pay for two separate internet connections for Contractor,
KYTC, and Consultant Advisors, each with secure 1Gbps (“Gigabit internet”) broadband
internet service and wi-fi connectivity, capable of providing simultaneous service to at least
30 staff at a minimum. The Contractor will provide the necessary network equipment and
communication circuits to connect the PMO to the Department network. The DBT will install
network drops in the office cubicles, conference room, and public meeting room.
B. For Security purposes the Contractor will provide and maintain their own internet connectivity,
wired network and Wi-Fi network. The Contractor shall provide a second Wi-Fi network for
KYTC and Consultant Advisors.
C. The Contractor shall provide two licensed copies of Primavera (P6) for KYTC and the
appropriate contract management software compatible with the Department’s project document
management system.
D. Office space for the Department’s staff that has, at a minimum, the following:
1. 12 offices (100 square feet, each enclosed office space with individual locking door, one
desk, office chair, folding table, bookcase, and two side chairs);
2. 18 cubicles (80 square feet each) and an appropriate number of desks, chairs, and filing
cabinets;
3. An enclosed conference room (600 square feet) with doors, provided with:
a. A computer projector and minimum 7-foot-wide screen;
b. Folding Office Chairs (10);
service dumpster (at least 5 cubic yards), landscaping, and the removal of snow and ice,
including the supply and application of de-icing or ice melting agents, from parking areas and
walks in a timely manner to ensure safe passage to and from the PMO.
DBE firms can be added to the DBE Performance Plan at any time; however, the Contractor shall follow
the contract process for termination, reduction, and replacement of a DBE firm as set forth in PDBC
Section 8.5 (Substitution of Subcontractors) and Exhibit L (Disadvantaged Business Enterprise (DBE)
Performance Plan and Good Faith Efforts). This process requires pre-approval by the Department. The
DBE Performance Plan shall be updated on a rolling basis and submitted monthly to the Department for
approval. At a minimum, the following information shall be included in the monthly submittal to the
Department:
A. A comprehensive list of subcontract packages to be set aside or made available for DBE
participation. Each subcontract packages shall set forth the type of work available including
applicable NAICS codes for the Work, the timeframe the subcontract would be entered into, and
when the subcontract work would be performed. Subcontract packages shall be added or
subtracted from the DBE Performance Plan on a rolling basis, as opportunities are identified
and/or filled;
B. A list of DBEs committed on the Project including the following:
1. Names and addresses of certified DBE firms committed;
2. A description of the work that each DBE will perform. To count toward meeting a goal, each
DBE firm must be certified in a North American Industry Classification System (NAICS) code
applicable to the kind of work the firm would perform on the contract;
3. Whether the DBE firms being used to meet the goal will be utilized as a subcontractor, regular
dealer, manufacturer, consultant, or other capacity;
4. The dollar amount of the participation of each DBE firm used to meet the DBE goal;
5. Written documentation of the bidder/offeror’s commitment to use a DBE subcontractor
whose participation it submits to meet a contract goal; and
6. Written confirmation from each listed DBE firm that it is participating in the contract in the
kind and amount of work provided in the prime contractor’s commitment.
C. A list of the names, position, and qualifications of each individual on the Contractor’ team who
will be responsible for DBE utilization and commitments; and
D. A statement providing Contractor shall make good faith efforts throughout the life of the Project
to identify and carve out potential subcontracting packages for DBE participation.
The Contractor shall Submit an updated and revised DBE Performance Plan per PDBC Section 2
(Progressive Design-Build Approach) and PDBC Section 4 (Design Requirements and Submittals) with
the Sub-Phase 1B Proposal and Phase 2 Proposal.
The Contractor is responsible for ensuring the DBE goal is tracked in real time throughout the life of the
Project shall submit a monthly report to the Department outlining goal attainment and commitments to
date and maintain a project dashboard with daily updates. The Contractor is responsible for ensuring
the DBE firms committed to the Project are properly certified as a DBE in Ohio, Kentucky, or Indiana
pursuant to the relevant reciprocity agreements and have received the proper NAICS codes for the
work performed in order for the work to count toward meeting a goal.
The DBE Goal Attainment and Tracking Plan shall include, at a minimum, the following components:
A. Explanation of the Contractor’s methodology for tracking the Project DBE goal in real time. This
tracking should include:
1. Commitments and negotiations with each DBE firm along with a copy of the DBE’s quotation
for Work;
The Contractor shall submit an updated and revised DBE Goal Attainment and Tracking Plan per
PDBC Section 2 (Progressive Design-Build Approach) and PDBC Section 4 (Design Requirements and
Submittals) with the Sub-Phase 1B Proposal and Phase 2 Proposal.
The DBE Outreach Plan shall include creating and maintaining a database of all contacts, inquiries, and
identified potential DBE firms. This database shall contain, at a minimum, the company name, date of
initial inquiry, date of every inquiry after, how the inquiries were made (phone, email, etc.), nature of
potential viable work to be performed, efforts made by the Diversity and Inclusion Manager, contact
information, and whether the business is ultimately included in the Project. If a company is not being
considered for the Project, the reasons must be documented along with proof that the company was
notified of the decision including feedback so the firm can learn for future projects.
The DBE Outreach Plan shall set forth the names, position, and qualifications of each individual on the
Contractor who will be responsible for DBE outreach and communication.
The Contractor shall Submit an updated and revised DBE Outreach Plan per PDBC Section 2
(Progressive Design-Build Approach) and PDBC Section 4 (Design Requirements and Submittals) with
the Sub-Phase 1B Proposal and Phase 2 Proposal.
will enable long term viability for future construction-related projects. A DBE Development Plan may
include but not limited to opportunities to assist DBE firms in overcoming challenges to participate on
the Project by utilizing small business assistance resources to help with bonding, insurance, loans,
access to capital, DBE certification, prequalification, etc, as approved by the Department. The DBE
Development Plan may also present strategies to mentor or create opportunities for mentorships with
DBE firms.
The DBE Development Plan shall include the Diversity and Inclusion Manager’s assistance in the
company’s ongoing understanding of contracting with the Department. The Contractor shall Submit
updated and revised DBE Development Plan per PDBC Section 2 (Progressive Design-Build Approach)
and PDBC Section 4 (Design Requirements and Submittals) with the Sub-Phase 1B Proposal and
Phase 2 Proposal.
D. Prompt Payment:
1. The Contractor shall set forth its methodology for ensuring payment is promptly made to
each subcontractor working on the Project in accordance with all State and Federal
requirements.
2. As part of this methodology, the Contractor shall ensure each subcontractor affirms receipt
of payment when received.
3. The Contractor shall identify the method by which it will track and communicate payments
and receipt of payments to each subcontractor.
4. The Contractor shall also identify the process for addressing prompt payment violations,
which may include mediation, sanctions, and withholding payment.
5. The Contractor shall provide a list of the names, position, and qualifications of each
individual on the Contractor’s team who will be monitoring prompt payment.
The DBT shall Submit updated and revised Compliance Plan per PDBC Section 2 (Progressive Design-
Build Approach) and PDBC Section 4 (Design Requirements and Submittals) with the Sub-Phase 1B
Proposal and Phase 2 Proposal.
The Contractor shall provide a list of the names, position, and qualifications of each individual on the
Contractor’s team who will be assisting with the OJT Performance Plan.
The Contractor shall Submit updated and revised On the Job Training Performance Plan per PDBC
Section 2 (Progressive Design-Build Approach) and PDBC Section 4 (Design Requirements and
Submittals) with the Sub-Phase 1B Proposal and Phase 2 Proposal.
The Workforce Development Plan shall include the Diversity and Inclusion Manager’s assistance in
working on the Project. The Contractor shall Submit updated and revised Workforce Development Plan
per PDBC Section 2 (Progressive Design-Build Approach) and PDBC Section 4 (Design Requirements
and Submittals) with the Sub-Phase 1B Proposal and Phase 2 Proposal.
The Contractor shall Submit updated and revised Community Engagement Plan per PDBC Section 2
(Progressive Design-Build Approach) and PDBC Section 4 (Design Requirements and Submittals) with
the Sub-Phase 1B Proposal and Phase 2 Proposal.
5.9 Submittals
Submittals under this Section 5.9, a non-exhaustive list of, shall be submitted in electronic format in
accordance with the schedule set in Section 2.1.11 (PMP Submittal), Table 2-1 (DBT PMP Component
Management Plans). Acceptable electronic formats include PDF and current versions of Microsoft Word
and Microsoft Excel, unless otherwise indicated.
The Department will be responsible for disseminating all public information and communications.
The Contractor shall work with the Department to achieve the following public information and
community relations goals:
A. Support the successful delivery of the Project by presenting the Project in a positive light to the
public.
B. Provide information to individuals and entities directly affected by construction in a proactive,
responsive, and complete manner.
C. Reinforce positive Department relationships with associated agencies, individuals, and
community and business groups.
The Contractor shall support the Department with public outreach and communication as requested.
This may include meeting attendance and development of reader-friendly graphics, presentations, or
summaries during Preconstruction (Phase 1) and Final Design and Construction (Phase 2).
7. ENVIRONMENTAL
An Environmental Assessment (EA) (EN-01, EN-02) was prepared for the BSB Corridor Project, and a
Finding of No Significant Impact (FONSI) (EN-03) was approved by FHWA on August 9, 2012. FHWA
approved reevaluations of the EA on February 11, 2015 (EN-04) and March 15, 2018 (EN-05). The
Department is currently developing a supplemental EA that assesses and documents revised impacts,
policy updates, project changes, and coordination that has occurred since the 2012 EA/FONSI. This
Section 7 describes the environmental commitments and requirements of the Project in accordance
with the 2012 EA/FONSI, reevaluations, and supplemental EA.
7.2 Permitting
The Contractor shall coordinate with the Department to determine roles and responsibilities for
permitting. The Contractor shall update (add, remove, and refine) the information provided in PC-01
(Project Permitting Requirements) based on permitting needs as the Project progresses. The
Contractor shall prepare a Permitting Plan that identifies timelines, required information, and
approval/signature cycles for each permit.
Anticipated federal permits include U.S. Army Corps of Engineers (USACE) Section 408, USACE
Individual Section 404, USACE Section 10, U.S. Coast Guard (USCG) Section 9, and Federal
Emergency Management Agency (FEMA) Conditional Letter of Map Revision (CLOMR)/Letter of Map
Revision (LOMR). For the USCG Section 9 permit initial coordination, Contractor shall refer to PC-02
(USCG Coordination and Correspondence) and PC-03 (Brent Spence Bridge Section 9 Project
Initiation Request).
Anticipated state and local permits in both Ohio and Kentucky include Section 401 Water Quality,
Stream Construction Permit, Floodplain/Floodway, and National Pollutant Discharge Elimination
System (NPDES).
If permits other than those described above are required, the Contractor shall include them in the
Permitting Plan.
The Contractor shall initiate coordination with permitting agencies in accordance with the approved
Permitting Plan.
Regulated Materials or contaminated areas encountered during the Design and Construction Work are
the responsibility of the Contractor to identify and take the appropriate steps to coordinate with ODOT
and KYTC for disposal in accordance with all applicable laws and regulations. A summary of regulated
materials studies and commitments made for the Project is provided in EN-15. Prior Environmental Site
Assessment studies conducted for the Project are provided in EN-16 through EN-25.
The Contractor shall prepare a Regulated Materials Management Plan (RMMP) that provides specific
guidance for managing, handling, and disposing of regulated materials that may be encountered within
the Right-of-Way and for protecting the health and safety of all on-site personnel and the public in
accordance with all applicable local, state and federal regulations. The RMMP shall list specific sites
and define procedures for managing both known and unknown regulated materials encountered during
the design and construction of the Project.
Once properties are acquired and the plans have advanced to the necessary detail, the Contractor shall
perform a Regulated Materials inspection on buildings, bridges, and other structures to be demolished
by the Contractor. If asbestos containing materials are identified on any bridge or other structures that
are proposed to be demolished and/or renovated, the Contractor shall perform asbestos abatement.
The Contractor shall follow all applicable local, state, and federal requirements for handling and
disposing of Regulated Materials identified during inspections (i.e., lead paint, fluorescent lightbulbs,
etc.) The inspection/notification to regulatory agencies/abatement shall be conducted prior to demolition
and/or renovation activities.
Once acquired, the Contractor shall coordinate with the Department and the property owner to
incorporate mitigation activities at Longworth Hall (EN-12, EN-13, EN-14) into the Project Schedule and
OPC.
When the construction plans are advanced to sufficient detail, the Contractor shall coordinate with
ODOT to provide the State Historic Preservation Officer and the Section 106 Consulting Parties in Ohio
the opportunity to review and comment on the plans.
7.5.3 Archaeology
The Contractor shall have the pavement for the parking lots of the Kenton County Administration
Offices stripped, and the Department shall perform a Phase I Archaeology Survey.
A Contractor archaeologist or geoarchaeologist shall monitor and/or review soil and geotechnical
borings conducted in the Ohio River bottom area for evidence of buried archaeological deposits and/or
undisturbed original landforms. If either are determined to be present, the Contractor shall design and
implement an archaeological testing strategy for the horizontal and vertical footprint of the bridge
supports and construction work limits.
7.6 Noise
In accordance with the KYTC Noise Analysis and Abatement Policy, the Contractor shall hold A Noise
Abatement Public Meeting and conduct surveys with benefited receptors at each location where noise
barriers were identified in the supplemental EA.
7.7 Submittals
Submittals under this Section 7.7, a non-exhaustive list of which is set forth in Table 7-1 (Environmental
Submittals Table), shall be submitted in electronic format in accordance with the schedule set forth
below. Acceptable electronic formats include PDF and current versions of Microsoft Word and Microsoft
Excel, unless otherwise indicated.
The Contractor shall review the environmental commitments for the BSB Corridor Project and
incorporate additional studies/field work, mitigation, and measures in the Project Schedule.
Table 7-1: Environmental Submittals Table
8.1 General
Contractor shall provide surveying services for the duration of the Project to support all aspects of
design, permitting, mobilization, preconstruction, construction, inspection, commissioning, activation,
and closeout. This includes confirming the dimensions, orientations, and locations of property lines,
roadways, highways, ramps, bridges, sidewalks, landscaping, curb & gutter, buildings, structures,
utilities & infrastructure, interior features, exterior features, topography, paving, striping, signage, street
lighting, traffic signals & equipment. Contractor shall reference SU-01 (Project Monumentation Control),
SU-02 (KYTC Summary of Project Datum Conversions), SU-03 (KYTC Survey Aerial Triangulation),
SU-04 (Survey Report 2046-337 Preliminary), SU-05 (Control Notes), SU-06 (Control
Coordinates.xlsx), SU-07 (Control Coordinates), SU-08 (HAM-75-1.15_PID113361 Survey Report), and
SU-09 (HAM-75-0022 Centerline Resolution and Boundary Resolution), and SU-10(116649 Mapping
and Survey Quality Control Report) for prior survey information performed by the Department.
systems.
Monuments located Ohio identified in Kentucky survey report (SU-04) will require scaling using the
project scale factor for ground projection. The monumentation information listed in SU-04 is Ohio South
Zone grid.
The Department will provide the Contractor with the following Survey-Related Data as part of the RIDs:
A. Survey Baseline Control Data;
B. Right-of-Way/Highway Boundary Geometry;
C. Survey/Photogrammetric Base Mapping Planimetrics;
D. Survey/ Photogrammetric Digital Terrain Model; and
E. Record Plans.
The Contractor shall document all forms of data verification. If the Contractor identifies any
discrepancy, the discrepancy shall be reported in writing to the Department for review. The Department
will respond to the discrepancy within 10 Working Days.
8.5 Submittals
Submittals under this Section 8.5, a non-exhaustive list of which is set forth in Table 8-1 (Survey and
Mapping Submittals Table) below, shall be submitted in electronic format in accordance with the
schedule set forth below. Acceptable electronic formats include PDF and current versions of Microsoft
Word and Microsoft Excel, unless otherwise indicated.
Table 8-1: Survey and Mapping Submittals Table
9. UTILITIES
The utilities requirements described in this Section 9 are in addition to requirements within Section 1.2
(Governing Regulations) and Section 153.64 of the Ohio Revised Code and incorporated Kentucky
requirements.
The Department will make all determinations of compensable rights related to utility facility design,
relocation, modification, and construction during Sub-Phase 1B.
Any Utility Relocation Work (including protection work) shall be consistent with the Utility’s reasonable,
written specifications, standards of practice, and construction methods, as well as any applicable
Department and City permit requirements. Details regarding the Contractor’s plan for utility coordination
and relocations shall be addressed in the PMP Utilities Plan prepared by the Contractor for the Project.
Contractor and Department shall meet with Duke Energy to review west end substation site and the
previous remediation work complete by Duke Energy (See UT-10 (Duke Energy West End Existing
Conditions)). Contractor shall anticipate separate utility meeting with Duke Energy for Sub-Phase 1A.
Contractor shall prepare utility meeting agendas and provide copies of the meeting minutes to the
Department for the Project files within one week following the respective meeting.
The Contractor is responsible for maintaining and updating the Utilities Impacts Matrix to reflect the
project design and construction. The Utility Impact Matrix shall be updated by the Contractor as
necessary during the course of plan development. The Contractor shall make its updated matrix
available to affected utility owners and the Department.
A meeting at or near the time of the Base Design review shall be held between the Contractor, the
Department and the Utility Owners to determine if any significant Utility Relocations can be eliminated
or mitigated. Notify the Department five Working Days in advance of the meeting.
Only those Utilities immediately affected by the Construction Work shall be subject to Utility Relocation,
unless directed otherwise by the Department. If the Contractor desires the temporary or permanent
adjustment of any Utility for its sole benefit, the Contractor shall provide a Standards Deviation (See
Section 1.3 (Standards Deviation Submittal Requirements)) request itemizing differences from the
Utility Relocations identified in the Conceptual Design for Department review.
The Contractor should follow recommendations of the Duke Energy Allowable Utility Loading
requirements within the proposed Project Limits. The Contractor is directed to UT-05 (Duke Energy
Allowable Utility Loading Memo) for further information. The Contractor shall provide horizontal offsets
within the Design Submittals to define the allowable distance for equipment to be placed and
construction activities adjacent to Duke Energy. The Contractor shall maintain access to all Duke
Energy facilities for maintenance of operations.
both parties. If a utility owner rejects any design work, the Contractor shall immediately notify the
Department, in writing, of the grounds for rejection and suggestions for correcting the problem. The
Contractor shall correct the design and resubmit to the utility owner for review. This compliance review
shall take no more than 10 Working Days. The Contractor shall be responsible for discovering and
addressing additional utility conflicts that arise as a result of chosen substructure unit locations;
retaining wall construction; building demolition; roadway and pavement construction; excavation and
embankment limits; Contractor selected construction means and methods; and other construction.
9.3.7.2 Utility Relocation Plans Prepared by the Utility Owner
When the utility owner prepares a utility facility relocation plan, the Department and the Contractor will
review the design and/or permit application to ensure that the relocation does not interfere with other
proposed construction activities, including relocations of other utility facilities. This review shall be
completed no later than 10 Working Days after its submission, unless a different time-period is
expressly agreed to by both parties. The Contractor shall compile and provide written review comments
to the Department and the utility owner. The Contractor shall be responsible for coordination with the
Utility Owner to ensure that all Department comments to the Utility Owner are adequately addressed in
the design and construction of the Project, including, any modification, re-approval by the Utility Owner
and re-submittal to the Department as necessary to obtain approval.
9.3.7.3 Design Documents
Each proposed Utility Relocation shall be shown in the Base Design Documents, regardless of whether
the Utility Relocation plans are prepared by the Contractor or by the Utility Owner. Contractor shall
provide casing as specified in accordance with the Ohio Real Estate Manual on the Project, where
applicable. Contractor shall review Utility relocation plans meet the casing requirement.
9.3.7.4 Certain Requirements for Underground Utilities
9.3.7.4.1 Duke Energy Work
A. Work in vicinity of Duke Energy buried gas lines for Parcel 2 (RW-02 denotes the parcel as 2),
for locations refer to UT-05 (Duke Energy Allowable Utility Loading Memo).
B. Gas Regulating Station:
1. Stay-in-Place deck forms shall be used to construct the bridge deck in this area.
2. All temporary personnel walkways to access the construction area shall have a solid face
using:
a. Plywood.
b. Portable Concrete Barrier (PCB) shall be placed around the above ground facility.
c. Bottom of all new bridge beams shall be at least 6 feet above the top of the existing gas
structure.
d. Drilled foundations and/or shoring shall be used on Ramp A (northbound CD Road to
northbound 71) around the existing gas facility and gas main.
C. Temporary or permanent fill not allowed in the vicinity of Duke Energy buried gas and electric
lines for Parcel 2 and Parcel 4. Contractor to refer to RW-02 (ODOT Final Right-of-Way
Tracings) for parcel locations.
D. Work in vicinity of Duke Energy buried gas lines located in Parcel 2, maximum allowable
construction loads shall be based on American Petroleum Institute 1102 Steel Pipelines
Crossing Railroads and Highways. Duke Energy will not allow stresses from loading to exceed
60% Specified Minimum Yield Strength (SMYS) of the steel pipe. The Contractor will need to
coordinate equipment loading and crossing locations with Duke Energy. Based on loading
calculations, mitigation strategies such as timber matting or air bridging may be required.
E. Work in vicinity of Duke Energy buried 138k transmission Parcel 4, maximum allowable
construction loads shall be based on API 1102 Steel Pipelines Crossing and Highways. Duke
Energy will not allow stresses from loading to exceed 60% Specified Minimum Yield Strength
(SMYS) of the steel pipe. The Contractor will need to coordinate equipment loading and
crossing locations with Duke Energy. Based on loading calculations, mitigation strategies such
as timber matting or air bridging may be required.
F. The minimum offset of construction and vehicle loads from the precast vault structure on August
St. shall be in accordance with the following:
1. Live loads and construction loads on or immediately adjacent to the vault are not to exceed
HS20.
2. For construction loads exceeding HS20, the 1V:1H zone of influence method shall be used
to determine allowable placement. Based on this method, construction and live loads
exceeding HS20 shall be restricted to a minimum of 10-feet-8-inches from the outer limits of
the precast vault structure.
9.3.8 Changes to the Utility Work
Once Utility Relocation Work has begun, the Contractor shall not make any changes to the Project
design, which would necessitate an additional Utility Relocation. Contractor shall refer to PDBC Section
7 (Utilities and Railroads).
Where the Contractor is responsible for the performance of utility work, in order to maintain the service
continuity of the Utility Owner’s facilities to the extent practicable during that performance of work, the
Contractor, at its cost, shall:
A. Keep the Utility Owner fully informed of schedules, including coordinating with the Utility Owner
regarding their design, construction and inspection of utility work performed by the Contractor;
B. Keep the Utility Owner fully informed of changes that affect their facilities; and
C. Keep the Utility Owner involved in making the decisions that affect their facilities, so the Utility
Owner can provide uninterrupted service to its customers or be subject to the least interruption
practicable.
All the Utility Owner’s facilities shall remain fully operational during all phases of Project construction,
except as specifically allowed and approved by the Utility Owner. The Contractor is responsible for
maintaining public utility facilities throughout construction, which includes all necessary temporary
bypass provisions.
The Contractor shall ensure that all utilities remain operational during all phases of Project construction
to the greatest extent practicable.
KYTC comments to the Utility Owner are adequately addressed in the design and construction of the
Project, including, any modification, re-approval by the Utility Owner and re-submittal to KYTC as
necessary to obtain approval.
9.4.4.3 Design Documents
Each proposed Utility Relocation shall be shown in the Base Design Documents, regardless of whether
the Utility Relocation plans are prepared by the Contractor or by the Utility Owner. Contractor shall
provide casing as specified in accordance with the KYTC Utilities and Rails Guidance Manual on the
Project, where applicable. Contractor shall review Utility relocation plans meet the casing requirement.
9.4.4.4 Kentucky Utility Agreement Submittals
Each Utility Relocation shall be addressed in a Utility Agreement prepared jointly by KYTC and
Contractor and the Utility Owner. The Utility Agreement will be developed per KYTC Utility coordination
process. The Contractor shall coordinate with the Utility Owner to prepare all components of each Utility
Agreement. Completion of the review and approval process for the applicable Utility Agreement, as well
as issuance of any required KYTC approvals, shall be required before the start of construction for the
affected Utility Relocation Work.
The Department has the authority to approve the placement of Utilities within Project Right-of-Way. As
detailed in the Report, Utility Relocation concepts consistent with Utility Owner and Project Goals and
objectives for the Project have been explored. Further, it has been determined that each respective
Utility Relocation can be accommodated in an acceptable manner to said companies and agencies. It
shall be the responsibility of the Contractor to work with the Utility Owner to prepare all required
documentation to be included with each subsequent Utility Agreement submittal.
The Contractor’s obligations regarding reimbursement to Utility Owners in Kentucky for all costs of
Utility Relocation Work shall be as set forth in the Utility Agreements prepared for the Project by the
Contractor and in conformance with KYTC’s Utility Guidance Manual and Kentucky State Statutes.
The Contractor shall arrange for the Utility Owner to execute each Utility Agreement and subsequent
encroachment permit required to do the work on the Project. All Utility Relocations covered by the same
initial Utility Agreement may be addressed in a single Encroachment Permit. Please refer to the KYTC
Encroachment Permit Manual for additional information. In general, the Utility Agreement package
required for each Utility Relocation shall include:
A. Encroachment Permit Application (KYTC, and/or local government agency);
B. Utility Agreement (executed between the Contractor or Department and the Utility Owner);
C. Utility Relocation Plans and Specifications as referenced in the Utility Agreement;
D. Roadway Plans and Profile and/or Structure Plans and cross-sections clearly indicating existing
and proposed Utility location. For Utilities deemed acceptable to remain in place by the Utility
Owner and the Contractor, the location of the Utility, both horizontally and vertically, along with
any special construction requirements or protection needed to prevent damage to the facility
during construction of the Project, must be clearly defined;
E. Utility Relocation cost estimate as defined in the Utility Agreement including definition and
separation of any betterment proposed; and
F. Complete Utility Agreement packages as described herein or as directed by KYTC. Once review
and comment is complete, copies shall be returned to the Contractor and Utility Owner for their
use. The number of Utility Agreement packages will be defined by the Utility Coordination
process.
9.4.4.5 Certain Requirements for Underground Utilities
9.4.5 Changes to the Utility Work
Once Utility Relocation Work has begun, the Contractor shall not make any changes to the Project
design, which would necessitate an additional Utility Relocation. Contractor shall refer to PDBC Section
7 (Utilities and Railroads).
Where the Contractor is responsible for the performance of utility work, in order to maintain the service
continuity of the Utility Owner’s facilities to the extent practicable during that performance of work, the
Contractor, at its cost, shall:
A. Keep the Utility Owner fully informed of schedules, including coordinating with the Utility Owner
regarding their design, construction and inspection of utility work performed by the Contractor;
B. Keep the Utility Owner fully informed of changes that affect their facilities; and
C. Keep the Utility Owner involved in making the decisions that affect their facilities, so the Utility
Owner can provide uninterrupted service to its customers or be subject to the least interruption
practicable.
All the Utility Owner’s facilities shall remain fully operational during all phases of Project construction,
except as specifically allowed and approved by the Utility Owner. The Contractor is responsible for
maintaining public utility facilities throughout construction, which includes all necessary temporary
bypass provisions.
The Contractor shall ensure that all utilities remain operational during all phases of Project construction
to the greatest extent practicable.
The Contractor shall perform work in a manner that will cause the least reasonable inconvenience to
the Utility Owner and those being served by the Utility Owner. Existing, adjusted, or new utility facilities
that are to remain within the Right-of-Way of the Project shall be properly protected by the Contractor to
prevent disturbance or damage resulting from Project construction operations. If the Contractor
encounters a previously unknown utility that requires adjustment, they shall not interfere with the utility
but shall take the proper precautions to protect the facility or take appropriate actions, per the PDBC, to
coordinate the adjustment of the facilities.
9.6.1 Existing Utility Facilities that Cannot Be Impacted by the Proposed Work
Several existing utility facilities have been identified by their respective owners as unable to be
relocated or modified in any fashion as a result of the proposed construction. Currently known facilities
falling into this category are identified in UT-04 (Concept I-W Utility Matrix).
In Kentucky, the Contractor shall be responsible for working with each Utility Owner for acquiring any
Replacement Utility Property Interests that are necessary for its Utility Relocations. The Contractor shall
have the following responsibilities for each acquisition:
A. The Contractor shall coordinate with and provide all Project information needed to each Utility
Owner as necessary for the Utility Owner to identify any Replacement Utility Property Interests
required for its Utility Relocations.
B. If the Contractor and/or Contractor subcontractors assists a Utility Owner in acquiring a
Replacement Utility Property Interest, the Contractor shall ensure that the following
requirements are met:
1. The files and records must be kept separate and apart from all acquisition files and records
for the Project Right-of-Way; and
2. The items used in acquisition of Replacement Utility Property Interests (e.g., appraisals,
written evaluations, and owner contact reports) must be separate from the purchase of the
Project Right-of-Way.
9.8 Submittals
Submittals under this Section 9.8, a non-exhaustive list of which is set forth in Table 9-1 (Utilities
Submittals Table), shall be submitted in electronic format in accordance with the schedule set forth
below. Acceptable electronic formats include PDF and current versions of Microsoft Word and Microsoft
Excel, unless otherwise indicated.
Table 9-1: Utilities Submittals Table
For Number of Copies
Acceptance, Reference
Submittal Submittal Schedule
Approval, or Section
Submittal Hardcopy Electronic
10. RAILROADS
This Section 10 defines the criteria required for the Project to accommodate Railroads crossing the
Project Right-of-Way. Contractor is responsible for coordination with all Railroads that may be impacted
by the Work. The following provisions described in this Section 10 are in addition to the Section 1.2
(Governing Regulations) of this document.
CSX Transportation, Inc. (CSXT) owns the existing tracks that cross the Project Right-of-Way under I-
71/I-75 between West 3rd Street and West Pete Rose Way. Where the Project crosses or affects
Railroad Right-of-Way, operations, or facilities, the Contractor shall coordinate the Work with the
Railroad, and Department, as appropriate. The Department will provide railroad contact information to
Contractor.
ODOT is acquiring the abandoned railroad track property from the Central Railroad Company of
Indiana that cross the Project Right-of Way under I-71/I-75 between West 3rd Street and West Pete
Rose Way. A Railroad agreement is not anticipated to be required with the acquisition of the property.
Details regarding the Contractor’s plan for railroad coordination shall be addressed in a Railroad
Coordination and Management Plan prepared by the Contractor for the Project. The plan shall include
plan submittal requirements, Contractor approach to meeting the Railroad agreement requirements,
railroad communication plan, and reporting procedures.
Contractor shall design the Work affecting Railroads following Good Industry Practice, such as FHWA
Railroad-Highway Grade Crossing Handbook, AREMA, and MUTCD, and incorporating the usual and
customary design standards and operating requirements of Railroad(s) that has an agreement with the
Department. However, for purposes of this Section, wherever a conflict arises between any details in
the design standards and operating requirements, the criteria as required by the Railroad shall govern.
Construction details and specifications shall conform to the Standard Specifications and the rules,
regulations, and requirements of the Railroads, including those related to safety, fall protection, and
protective equipment. Contractor will develop Unique Special Provisions for the Protection of Railway
Interest. Contractor shall coordinate with Railroads to finalize the Unique Special Provisions and
comply with the finalized special provisions.
shall comply with all requirements contained in the Railroad PE Agreement, which compliance is
included as part of the Work. Contractor shall coordinate with ODOT, Railroads, and develop Base
Design to finalize the Railroad Construction Agreement prior to Early Work and Phase 2 Work.
Contractor shall include railroad coordination and railroad construction agreement as activities within
the project schedule. See PDBC Exhibit T (Critical Path Method Progress Schedule).
C. CSXT Standard Clearance Matrix and CSXT Clearance Diagram – This document includes
clearance considerations for the temporary platform and any other proposed temporary
features; and
D. Specification Section 34 11 26.13 – Ballast - Ballast used for track owned or operated by CSXT
shall be provided from an approved CSXT ballast supplier and meet CSXT ballast material
requirements.
10.3.2 CSXT Coordination Requirement
The Coordination requirements for working with CSXT are as follows:
A. It is anticipated that more complex submittals and those requiring coordination or input from
CSXT field staff will require multiple weeks of review. CSXT and their representatives will make
every effort to work with the Contractor to meet the proposed schedule. The Contractor shall
develop a submittal schedule for CSXT review and approval per Section 10.4.2 (Railroad
Project Schedule) to assist in planning for and accommodating this Project’s schedule.
B. The Contractor shall prepare site-specific work plans for review and approval by CSXT before
commencing work when any part of the equipment used in conducting the work is within 25 feet
of the live tracks.
C. The Contractor shall submit site-specific work plans covering all work that is within 25 feet of
any track or work that has the potential to foul the track. The potential to foul is as any work
having the possibility of impacting CSXT property or operations and defined as one or more of
the following:
1. Any activity where access onto CSXT property is required.
2. Any activity where work is being performed on CSXT Right-of-Way.
3. Any excavation work adjacent to tracks or facilities, within the Theoretical Railroad Live
Load Influence Zone, or where the active earth pressure zone extends within the railroad
operational right-of-way.
4. The use of any equipment where, if tipped and laid flat in any direction (360 degrees) about
its center pin, can encroach within 25 feet of the nearest track centerline. This is based upon
the proposed location of the equipment during use and may be a function of the equipment
boom length. Hoisting equipment with the potential to foul the track must satisfy the 150
percent factor of safety requirement for lifting capacities.
5. Any work where the scatter of debris, or other materials has the potential to encroach within
25 feet of the nearest track centerline.
6. Any work where significant vibration forces may be induced upon the track structure or
existing structures located under, over, or adjacent to the track structure.
7. Any other work which poses the potential to disrupt rail operations, threaten the safety of
railroad employees, or otherwise negatively impact the railroad operational right-of-way, as
determined by CSXT.
D. Railroad Flagging
1. It is anticipated the cost of the Railroad Flagging provided by CSXT will be included in a
separate agreement between CSXT and the Department.
2. Contractor shall arrange with the Railroad for railroad flagging as required in accordance
with the Railroad Agreement and PDBC. Contractor shall provide at a minimum monthly
report to Department on usage of a railroad flagman and field construction inspectors (FCI).
3. It should be anticipated that Railroad Flaggers will not be available between November 15th
to January 15th of any calendar year.
E. Contractor shall perform ongoing coordination of their design and construction with the railroad
throughout the Project. The Contractor shall provide a current schedule on a monthly basis
including anticipated dates of the following items:
1. Construction Submittals requiring railroad review and approval prior to beginning
construction (per the Railroad PE and Construction Agreements).
2. Construction start and end dates for work that may create an impact to the rail
facility/operations.
3. Anticipated dates and duration for flaggers.
4. Anticipated dates and duration for potential outage request.
5. Any other milestones that may impact railroad facilities or operations.
The Contractor shall initiate any railroad coordination meetings needed to ensure that the technical
design and physical construction concerns are addressed on plans involving the railroad(s). The
Contractor shall notify the Department at least two Working Days in advance of any meeting with the
railroad(s). A Department representative will attempt to attend all railroad coordination meetings. The
Contractor shall maintain railroad meeting notes and promptly distribute to all meeting attendees, the
Department’s Project Engineer, and the State and/or District Railroad Coordinator. The Contractor shall
proactively keep the Department’s Project Engineer and the State and/or District Railroad Coordinator
aware of all railroad coordination information and/or issues through regular status reports.
Contractor shall complete Final Plans for the Railroad protection. The Plans shall contain points
labelling the location of the minimum horizontal and vertical clearance between the bridge and the
adjacent Railroad tracks. The Plans shall also include details providing the bottom of footing and top of
rail elevation and distance from centerline of track to nearest footing.
time to address comments with the railroad. Railroad agreement will indicate railroad review time is 30
days.
Contractor to Submit a detailed separate railroad construction schedule lookahead schedule for the
duration of the Project clearly indicating the time periods while Contractor will be working on and
around CSX right-of-way. As the work progresses, this schedule shall be updated monthly and
resubmitted as necessary to reflect changes in work sequence, duration, and method.
10.5 Submittals
Submittals under this Section 10.5, a non-exhaustive list of which is set forth in Table 10-1 (Railroads
Submittals Table) below, shall be submitted in electronic format in accordance with the schedule set
forth below. Acceptable electronic formats include PDF and current versions of Microsoft Word and
Microsoft Excel, unless otherwise indicated.
11. RIGHT-OF-WAY
11.1 General Right-of-Way
The Department will acquire all temporary and permanent Project Right-of-Way to encompass the
proposed Project Limits shown in RW-01 (KYTC Right of Way Plans) and RW-02 (ODOT Final Right-
of-Way Plan Tracings). RW-01 and RW-02 indicates the existing Project Right-of-Way lines and any
permanent and/or temporary easements being acquired by ODOT and KYTC for the Project.
The Right-of-Way access date is indicated in RW-06 (Right-of-Way Availability Table), which the
Contractor shall include in the Progress Schedule. The Department will provide written notification to
the Contractor when each required parcel is available and of any applicable access restrictions. The
Contractor shall not access any parcel until such written notification is provided.
Through the right-of-way acquisition process, the Department has or intends to make site specific
commitments to property owners. A draft of these commitments and Contractor requirements are
included in GN-03 (Project Commitments). GN-03 commitment includes requirement for the Contractor
to prepare Right-of-Way plans for the final location of the bridge piers on parcel 9.
If the Contractor determines during the Preconstruction Phase (Phase 1) that additional Right-of-Way is
required in order to deliver the Project, the Contractor shall prepare Preliminary and Final Right-of-Way
plans for use by the Department to acquire any necessary additional property (see Section 11.2
(Additional Property Request Requirements) herein).
Temporary easements being acquired by the Department for the Project are to be used in project
construction activities, as described in RW-02 (ODOT Final Right-of-Way Plan Tracings). Contractor
will be provided access to each temporary easement for a 36-month duration, beginning on the date on
which physical Work commences within the temporary easement site. Physical Work does not include
survey or soil boring activities. All Work that necessitates the use of the temporary easements shall be
completed within the temporary easement access duration. The Contractor will not be granted access
to the temporary easement sites after the temporary easement access duration. Under no
circumstances are temporary easements to be used for storage of material or equipment by the
Contractor unless otherwise noted.
The Contractor will be provided access to each parcel identified in RW-05 (KYTC Acquisition Status
Report) as the parcel title is cleared. The access date is indicated in RW-06 (Right-of-Way Availability
Table), which the Contractor shall include in the Progress Schedule. The Department will provide
written notification to the Contractor when each required parcel is available and of any applicable
access restrictions. The Contractor shall not access any parcel until such written notification is
provided.
The Department will acquire all Right-of-Way and easements as shown on the KYTC Final Right-of-
Way Plans (RW-01) by the dates shown in RW-05 (Right-of-Way Acquisition Status Report). The
Project has sufficient Right-of-Way to perpetually maintain the permanent features of the Project as
shown on the Final Right-of-Way Plans. See Section 13 (Building Demolition and Reconstruction) for
additional information. The Department will provide commitments to property owners that must be
incorporated in design and construction. Contractor requirements will be included in RW-07
(Communicating All Promises Report (CAP)).
If the Contractor determines additional Right-of-Way is required during Phase I (Preconstruction), the
Contractor shall prepare Preliminary and Final Right-of-Way plans for use by the Department to acquire
any necessary property.
The Contractor shall follow ODOT’s Real Estate Manual. Contractor to prepare Preliminary and Final
Right-of-Way Plans for Department approval prior to Acquisition beginning. The Final Right-of-Way
Plans will include legal descriptions, closure calculations, and Final Right of Way plans. ODOT will
provide acquisition services and provide acquisition status reports to the Contractor. After ODOT
approval of the Final Right-of- Way Plans, the Department and Contractor shall coordinate and agree
upon clearance dates listed in RW-03 (ODOT Right-of-Way Action Plan) and RW-06 (Right-of-Way
Availability Table).
The Contractor shall follow KYTC Highway Design and Right-of-Way Manual requirements to prepare
Preliminary and Final Right-of-Way Plans for Department approval prior to acquisition beginning. The
Final Right-of-Way Plans shall include plan sheets, profiles, cross sections, Right-of-Way Summary,
Strip Map, and legal descriptions. KYTC will provide acquisition services and provide acquisition status
reports to the Contractor. After KYTC approval of the Final Right-of- Way Plans, the Department and
Contractor shall coordinate and agree upon clearance dates listed in RW-05 (KYTC Acquisition Status
Report) and RW-06 (Right-of-Way Availability Table).
11.5 Submittals
Submittals under this Section 11.5, a non-exhaustive list of which is set forth in Table 11-1 (Right of
Way Submittals Table) below, shall be submitted in electronic format. Acceptable electronic formats
include PDF, current versions of Microsoft Work, or Microsoft Excel files, unless otherwise indicated. At
a minimum, the Contractor shall submit the following to the Department:
Table 11-1: Right of Way Submittals Table
12. GEOTECHNICAL
12.1 General
This Section 12 describes the requirements for geotechnical investigations, analysis, and design.
Significant geotechnical data exists within the project limits. Incorporate the existing geotechnical
information into the development of final geotechnical studies for Sub-Phase 1A and Sub-Phase 1B
development. In some instances, the existing borehole and laboratory testing information may be
sufficient to complete design activities. The Department and Contractor will work cooperatively to utilize
existing information as much as practical.
Draft geotechnical reports are to be submitted as part of the Sub-Phase 1A development. The
Department will review the reports and provide comments as part of the Sub-Phase 1A review.
Notify the Department in the event of a conflict between the standards set forth in Section 1.2
(Governing Regulations) relating to geotechnical analysis and design. Provide the reason for the
conflict and recommend for Department approval which standard should govern and why per Section
1.3 (Standards Deviation Submittal Requirements).
12.2.1.1 Ohio Standards
This section shall apply to Work within Ohio’s JDM.
Complete and submit all geotechnical design and geotechnical explorations performed by the
Contractor to Department in accordance with the LRFD method.
Prepare Geotechnical Exploration Reports, including foundation reports, as defined in the ODOT Bridge
Design Manual (BDM) and the ODOT Specifications for Geotechnical Exploration (SGE) for each
structure. Perform geotechnical design methodology as outlined in the Geotechnical Design Manual.
Geotechnical reports must include all engineering analyses and design recommendations for each
structure, wall, or roadway as appropriate.
12.2.1.2 Kentucky Standards
This section shall apply to Work within Kentucky’s JDM.
Complete and submit all geotechnical design and geotechnical explorations performed by the
Contractor to Department in accordance with the KYTC Geotechnical Guidance Manual and current
Transmittal Memoranda.
Produce and submit a Foundation Analysis and Design Report for each structure and Roadway
Geotechnical Report(s) that include all engineering analyses and design recommendations.
12.2.2 Meetings
Schedule and facilitate meetings related to geotechnical Project Work prior to commencement of field
exploration activities. The following meetings are required:
A. Geotechnical investigation plan review meeting: Schedule and facilitate a meeting with
Department to review the Contractor’s proposed subsurface investigation plan for geotechnical
borings.. Schedule this meeting after reviewing the geotechnical information provided, but at
least one week prior to Contractor requesting approval to commence with geotechnical
exploration operations. These meetings may be held for various sections of the Project. A
meeting may be waived with prior approval of the Department but at a minimum the Contractor’s
proposed subsurface investigation plan for supplemental geotechnical data must be submitted
for review and approval. Comments must be resolved one week prior to Contractor requesting
approval to commence with geotechnical exploration operations.
B. River crossing foundation concepts meeting: Schedule and facilitate a meeting with the
Department to review the Contractor’s proposed river bridge foundation design and proposed
pre-design load testing (if used). Discuss potential or intended means and methods for
foundation construction and their impact on the foundation design.
C. Meeting to discuss the subsurface investigation plan submittal schedule and expectations.
12.2.3 Permits/Authorizations Related to Geotechnical Investigation and
Materials
Obtain all necessary permits and/or authorizations required to perform geotechnical site investigations
or other geotechnical services for the Project, including Utility clearance, property access, and roadway
safety and traffic control.
Perform necessary notifications and obtain all necessary approvals and Deviations needed for
installation of environmental wells as defined by the Standards.
The DBT’s geotechnical personnel responsible for the installation and monitoring of instrumentation
such as inclinometers, piezometers, settlement indicating devices, standard penetration testing, etc.
must have a minimum of two years of experience with the specific type of instrumentation they will be
operating.
12.2.4.1 Approval
Replace any Geotechnical Engineer that does not meet the qualification or registration requirements in
Section 2.1.2.3 (Other DBT Lead Personnel Requirements).
Information provided below takes precedence over similar design requirements in AASHTO LRFD.
Where no information is provided, refer to the ODOT and KYTC geotechnical guidelines, KYTC special
notes, and then to AASHTO LRFD.
Project development timelines may place obtaining geotechnical information on the critical path for plan
development. Thus, to aid in expeditated geotechnical delivery, develop detailed design memos for
each wall, bridge, noise wall and roadway as appropriate in a Buildable Unit rather than developing one
large geotechnical report.
Selectively locate subsurface explorations on the basis of field observations, and design
considerations. Location of explorations shall be as topography, site conditions, soil conditions, and
design factors dictate.
Thoroughly review all available existing geotechnical information prior to developing the subsurface
exploration program for the Project or portion of the Project. Provide test borings, laboratory testing and
geotechnical analyses as necessary to supplement the archive geotechnical data for the new proposed
work to meet the requirements of the ODOT Specifications for Geotechnical Exploration, the ODOT
Geotechnical Design Manual, all ODOT Geotechnical Bulletins as well as the Kentucky Geotechnical
Guidance Manual and current Transmittal Memoranda. Incorporate archive geotechnical borings as
well as newly obtained geotechnical information available into the final design, individual geotechnical
reports, and geotechnical drawing submittals. Obtain Department acceptance of the boring and
laboratory program prior to commencement of each. Contractor to convert archive boring locations to
current project stationing.
During planning of the geotechnical program, provide the Department a subsurface investigation plan in
PDF and KML format, complying with ODOT and/or KYTC requirements as appropriate. Illustrate
archive borings on the proposed subsurface investigation plans in addition to the proposed borings.
Field work can begin following Department acceptance of the boring program. The boring program can
be specific to a portion of the Project.
Soil and groundwater conditions are only known at the exploration locations at the time of the
explorations.
It is the responsibility of the Contractor to perform soil surveys, soil borings, geotechnical investigations,
and appropriate analysis, including global stability, to produce a feasible concept for the Project.
Wherever vibration-producing activities could affect a structure, building, sewer, or utility, the Contractor
shall prepare a Vibration Monitoring and Control Plan to address the potential impacts to nearby
receptors due to construction or demolition activities associated with this Project. The term “receptor”
includes buildings, structures, utilities, utility service connections, occupants, and sensitive
operations/processes for which construction impacts or Work above recommended vibration limits may
be detrimental. The plan shall include ground vibration threshold limits.
The monitoring plan shall address how the Contractor intends to complete vibration-related activities
and meet the following minimum requirements:
A. Develop a list of all anticipated vibration producing activities and where and when they are
expected to occur;
B. Develop a list of all potentially impacted receptors from these activities;
C. Provide a vibration susceptibility analysis for each identified receptor, and establish a vibration
control limit to preclude damage, including threshold damage, to each of the identified receptors
and include in a susceptibility study;
D. Provide a plan for notifying the public of potential vibration impacts, responsible Project
personnel, receptors requiring precondition surveys, and vibration monitoring activities;
E. Monitor construction related ground movement and vibrations at the nearest and most critical
receptor(s), and notify Department in writing through the ECMS system immediately if
established vibration limits are exceeded;
F. Provide instrumentation locations, monitoring procedures, and a description of the monitoring
devices and/or manufacturers’ brochures in the submitted Sub-Phase 1A and Sub-Phase 1B
plan set;
G. Access any sensitive community or business operations that may be affected by ground
movements and vibrations per Section 7 (Environmental);
H. Provide recommendations for vibration-limiting methods to meet the established maximum safe
vibration levels;
I. Develop Sewer Condition Reports;
J. Develop Structures and Pavement Reports; and
K. Develop Building Condition Reports.
List of receptors shall include:
A. Existing Bridge foundation elements
B. Utilities, including storm and sanitary sewers
C. Storage tanks
D. Buildings
E. Newly constructed elements
F. Existing structures within zone of influence of vibration producing activities
The Contractor construction monitoring plan shall detail the proposed program of instrumentation and
monitoring, set monitoring frequency, assess the impacts to existing structures and utilities, establish
threshold values of the monitored parameters, and describe the response plan that will be implemented
when threshold parameters are exceeded. Construction monitoring of the Bridge shall include vertical,
horizontal, and tilt movements and vibration of bridge piers in sufficient locations as to determine
adequate performance and safety of the Bridge and its foundations during construction.
The Contractor shall ensure that the instrumentation can be read remotely, and that data shall be
uploaded to a website provided by the Contractor, and which shall be accessible remotely by both the
Contractor and the Department. Remote-access functionality shall include the ability to extract data and
to isolate an individual monitoring point or multiple points. The presentation system shall include the
functionality to modify the extents and scale of data plotting such that arbitrary views are available.
The Contractor shall provide weekly construction instrumentation monitoring reports to the Department.
Monitoring reports shall be interpretive in nature, and shall enumerate any corrections applied to the
data including, but not limited to any notification measures taken regarding data. The weekly reports
shall include clear and explicit statements of exceedances of any pre-determined threshold values. The
Contractor shall maintain the instrumentation and monitor the measurements during and after
construction up to Completion of the Contract.
12.3.4.1 Vibration Susceptibility Study
Contractor shall prepare a Susceptibility Study to assess each building, structure, Utility, Utility Service
Line, and other receptors with sensitive operations/processes and occupants in the survey area defined
below and determine its susceptibility to disruption by vibration-producing Work. “Disruption” includes
both cosmetic cracking (threshold damage) and impacts on sensitive equipment and its operation.
Categorize the susceptibility of each building to cracking during Work as high, moderate, or low as
defined below. Susceptibility to cracking is the threshold of cosmetic cracking, which is:
A. Threshold damage (e.g., opening of old cracks and formation of new plaster cracks, dislodging
of loose structural particles such as loose bricks from chimneys)
B. Architectural or minor damage that is superficial and does not affect the strength of the structure
(e.g., broken windows, loose or fallen plaster, hairline cracks in masonry)
As part of the Susceptibility Study, determine whether there are sensitive operations or equipment
nearby, such as hospitals, computerized industries or banks, and industrial machinery. Include a list of
buildings with sensitive equipment or procedures in the Susceptibility Study. The Susceptibility Study
will include the three items listed below, which will be provided to Department as part of the Vibration
Monitoring and Control Plan.
12.3.4.1.1 Anticipated Vibration-producing Activities
Identify locations where moderate to heavy construction activities will occur that are capable of
producing vibrations that may cause damage, interference, or annoyance to receptors. Heavy activities
include operations such as blasting, pile-driving, dynamic compaction, and percussive demolition.
Moderate construction activities include operations such as vibratory compaction and heavy equipment
operation. Present locations on a plan sheet or map that shows in-place topography, including nearby
structures and buildings.
12.3.4.2 Potentially Impacted Receptors
Produce a map that includes the potential receptors established. Identify receptors by type of
construction, size, material, address (if applicable), and owner. Identify all receptors in the survey area
and categorize them as high, medium, or low susceptibility. The survey area is defined as the area
including:
A. All buildings and structures within a distance at which vibrations of 0.1 inch per second or
greater will occur from construction activities and/or contributing structures within historic
districts or individually listed properties listed in or eligible for the National Register of Historic
Places within 140 feet of proposed construction work.
B. Any building that has sensitive operations or Utility that may be affected by vibration-producing
activities.
12.3.4.3 Establish Vibration Limits
Establish safe vibration levels that preclude damage to structures. Use these safe vibration levels as
vibration limits for the Contract. Set separate levels for each receptor, if desired, but the limits may not
be less stringent than those set forth in the OSM Alternative Blasting Level Criteria (Modified from
Figure B1, RI 8507U.S. Bureau of Mines). Express the vibration criteria in peak particle velocity (PPV)
with units of inches per second (ips).
The Contractor will coordinate with the Department to notify each household, institutional operator,
Utility Owner, structure owners, and business establishment identified as receptors in accordance with
Section 12.3.4 (Geotechnical Instrumentation and Construction Vibration Monitoring Plan). Notify each
contact via a registered letter at least three weeks prior to the survey. Obtain confirmation of receipt of
notification letter. Include the following at a minimum in the letter:
A. Explanation of the potential for producing vibrations;
B. Steps the Contractor will take to avoid potential damage from those vibrations;
C. Name and telephone number of a contact person to respond to any questions or concerns;
D. Description of the pre-construction survey, including probable dates that the survey will be
conducted. Provide at least two dates;
The full spatial extent of the Contractor pre-construction condition survey necessarily depends upon the
Contractor’s design and proposed means and methods of construction. In its preparation for the pre-
construction survey, the Contractor shall be responsible for predicting anticipated vibration and
settlement effects at various offset distances from the Project Limits, and for ensuring that the pre-
construction condition survey encompasses at a minimum all properties within areas that are identified
by the Contractor to be potentially prone to: (i) ground vibration levels, expressed as resultant peak
particle velocity, in excess of 0.10 inches per second or greater; and (ii) predicted ground settlements of
greater than 0.25 inches. In addition, the spatial extent of the pre-construction condition survey shall be
integrated with the Contractor’s implementation of its strategy for conformance with the Environmental
Commitments related to the protection of cultural resources (see Section 7 (Environmental)). This
strategy shall include properties within designated historic districts.
The Contractor shall submit to the Department the records and photographic and video documentation
of the pre-construction condition survey, which shall be signed and stamped by a Professional
Engineers registered in the State of Ohio and Commonwealth of Kentucky. Submit the records prior to
commencement of construction with the affected area.
12.3.5.2 Post-Construction Condition Survey
The Contractor shall conduct a post-construction condition survey of the zone and properties covered
by the pre-construction conditions survey (see Section 12.3.5.1 (Pre-Construction Condition Survey)
herein). The post-construction condition survey shall be performed by the Contractor at Substantial
Completion, and it shall compare the post-construction conditions with the conditions recorded in the
pre-construction condition survey. The location and scope of the post-construction condition survey
shall match those of the pre-construction condition survey. The survey shall provide information on
whether the specific receptors have been damaged due to Construction Work and shall detail the
extent of damage to each impacted receptor.
The complete documentation of the post-construction survey, describing the comparison with the
preconstruction conditions and signed by a Professional Engineer registered in the State of Ohio and
Commonwealth of Kentucky, shall be submitted to the Department.
Damage identified in the Post-Construction Condition Survey that was not present in the Pre-
Construction Survey shall be repaired by the Contractor to a condition approved by the Department.
person in possession by such means as are reasonably available not less than 48 hours or more than
30 Days prior to the date of such entry.
Provide final boring plans in electronic format for incorporation into the ODOT Geotechnical Data
Management System (GeoMS). All new boring data obtained for the project is to be compliant with the
Data Interchange for Geotechnical and Geoenvironmental Specialists (DIGGS) standard as outlined in
Section 701 of the Specifications for Geotechnical Exploration.
12.3.6.2 Geotechnical Exploration Reports
All geotechnical design and explorations performed by the Contractor shall be completed and submitted
to ODOT in a Geotechnical Exploration Report(s) following the guidelines of Section 700 of the SGE.
The Contractor shall combine all new geotechnical exploration and historical information in accordance
with the SGE. In lieu of one large report for the project, geotechnical reports can be submitted per
structure (wall or bridge) or Buildable Unit.
12.3.6.3 Subgrade Stabilization
Use the geotechnical information gathered by the Contractor, and applicable existing geotechnical
information provided to design and construct subgrades below pavements per the Standards.
12.3.6.4 Soil Slope Stabilization
Use the geotechnical information gathered by the Contractor, and applicable existing geotechnical
information provided to design and construct embankments and slope stabilizations per the ODOT
Standards.
Perform all subsurface explorations, including sampling and laboratory testing, in accordance with the
latest KYTC Geotechnical Manual and Transmittal Memoranda, AASHTO standards, and ASTM
standards. Perform all laboratory testing at a KYTC pre-qualified geotechnical testing laboratory per
KYTC methods.
For all subsurface explorations performed by the Contractor, the Contractor shall secure an access
permit from the appropriate agency, if required, which may require the preparation of an equipment
access plan, description of equipment types, a plan of the test locations, etc. The Contractor shall
adhere to all traffic control requirements when taking samples on existing roadways. A traffic control
plan may be required. The Contractor shall not enter any private property without permission from the
private property owner. The selected Contractor may enter any State of Kentucky property in the
Project Limits at any time, however, parcels not yet purchased by the State of Kentucky or Contractor
for this Project may not be accessible without specific permission from the property owner.
12.3.7.2 Geotechnical Exploration Reports
Submit a Geotechnical Report (or reports), prepared by the DBT's Geotechnical Engineer of Record,
presenting the results of all investigations, design recommendations and analyses calculations. The
DBT's Geotechnical Engineer of Record shall review the applicability of the available geotechnical
information provided by the Department to the Contractor's design. The review shall be documented in
the Geotechnical Report(s). Subsurface explorations refer to geotechnical borings, cone penetration
tests, geophysical methods, and other in-situ testing methods; and laboratory tests conducted to
support the analysis and design of subgrades, embankments, fills, bridges, walls, and culverts.
12.3.7.3 Subgrade Stabilization
Use the geotechnical information gathered by the Contractor, and applicable existing geotechnical
information provided to design and construct subgrades below pavements per the Standards and
directives provided by KYTC during the Sub-Phase 1A design development.
12.3.7.4 Soil Slope Stabilization
Use the geotechnical information gathered by the Contractor, and applicable existing geotechnical
information provided to design and construct embankments and slope stabilizations per the KYTC
Standards.
The Contractor is responsible for analysis and design of soil slopes. Reinforce slopes steeper than two
to one (2:1). Slopes two to one (2H:1V) or flatter may require stabilization improvements such as rock
embankment, shear keys, reinforcement, or other measures depending on soil conditions and shall
follow KYTC manuals, standard specifications, and special notes.
The Contractor is responsible for analysis and design of cut slopes. A rockfall analysis along with
assumed parameters may be required for review by the Department, depending on conditions. If
required, the analysis shall follow KYTC manuals, Standard Specifications, and Special Notes.
12.4 Submittals
Submit submittals under this Section 12.4, a non-exhaustive list of which is set forth in Table 12-1
(Geotechnical Submittals Table), in electronic format in accordance with the schedule set forth below.
Acceptable electronic formats include PDF and current versions of Microsoft Word and Microsoft Excel,
unless otherwise indicated. At a minimum, the Contractor shall submit the following to the Department:
All existing features encountered on the building removal parcels within permanent and temporary
easement limits not otherwise designated in the Contract Documents as to remain for salvage or for
reuse shall be removed and disposed of, except as directed by the Department, including but not
limited to pavements, sidewalks, driveways, minor structures and obstructions, fencing, pipes, drainage
structures, railing steps, debris, vehicles, Regulated Materials, and underground storage tanks. The
Contractor shall ensure that all improvements associated with each demolished building/property are
removed including all abandoned personal property found within or outside the building, and that only a
bare grass lot remains, unless otherwise specified in the Contract Documents. The burning of
buildings/building material is forbidden. The use of explosives is forbidden.
Backfill all cavities created from building demolition with structural backfill conforming to ODOT and/or
KYTC standards.
Building Demolition and Removal Plans shall be signed by a Professional Engineer registered in the
State of Ohio or Commonwealth of Kentucky and submitted to the Department for review and written
comment.
13.2.1 ARTIMIS
The Contractor shall demolish the existing ARTIMIS building following relocation and connection of all
ITS infrastructure in accordance with Section 20.5 (Intelligent Transportation System (ITS)). In addition
to requirements within this Section 13, the Contractor shall remove all pavement and fencing on the
property.
13.2.9 Utilities
Building Demolition and Removal Plans shall address any service utility connections that will be
required to be capped or removed due to demolition. The discontinued and capped utilities shall be in
accordance with the requirements of the utility companies or the Department. The Contractor shall
coordinate the removal of all utility services and pay all utility disconnect fees. For additional
information, see Section 9 (Utilities).
The critical historic elements that should be salvaged and recreated on the newly reconfigured east
façade, include the historic brick, coping stones, limestone window sills, limestone and brick pilaster
elements and rusticated blocks. Key decorative architectural elements such as the brick pilasters,
pilaster capitals, arches and roof-line corbelling, window eyebrows and limestone pilaster bases should
be documented, catalogued, and carefully salvaged and cleaned for reinstallation on the reconfigured
façade. Façade elements should be stored in a manner to prevent exposure to the weather and
extreme temperature.
The original brick coursing is a running bond with interlocking header courses which should be
recreated. The new wall should be laid up as a monolithic fully parged masonry wall like the original
and not be installed as a brick veneer. If possible, the backup masonry should be the same or similar in
density and size to the original to maintain the historic structural and thermal/moisture behavior of the
existing wall. Some areas of the existing walls to remain near the new wall on the south and north sides
will need to be rebuilt in order to fully integrate the new masonry wall.
Based on the age of the structure, the mortar is likely lime-based mortar with no portland cement. The
new mortar should be as close to the original as possible in make up with no portland cement. The
existing historic mortar should be tested per ASTM C1324 Standard Test Method for Examination and
Analysis of Hardened Masonry Mortar to assist in the selection of replacement and pointing mortar for
the sections of the wall to remain.
Chemical analysis of the historic mortar should be performed to determine the mortar make up of lime
aggregate and sand. The goal is to recreate the structural strength and vapor permeability of the
original wall to prevent freeze-thaw damage.
The Contractor shall utilize the resources available through the Ohio State Historic Preservation Office
(SHPO) website https://www.ohiohistory.org/preserving-ohio/state-historic-preservation-office/services-
fees/ that provides listings of companies which have met federal professional qualification requirements
and the following services:
A. Archaeology Consultants List
B. History / Architecture Consultants List
C. Choosing an Archaeology Consultant
D. Choosing a History / Architecture Consultant
13.3.4 Additional Qualifications
In completion of the Work, the Contractor shall meet the following requirements unless authorities
having jurisdiction supersede requirements of specialists:
A. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to
those indicated for this Work and with a record of successful in-service performance, as well as
sufficient production capacity to produce required units. As applicable, procure products from
manufacturers able to meet qualification requirements, warranty requirements, and technical or
factory-authorized service representative requirements.
B. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for
this Work and with a record of successful in-service performance, as well as sufficient
production capacity to produce required units.
C. Installer Qualifications: A firm or individual experienced in installing, erecting, applying, or
assembling work similar in material, design, and extent to that indicated for this Work, whose
work has resulted in construction with a record of successful in-service performance.
D. Specialists: Certain Specification Sections require that specific construction activities be
performed by entities who are recognized experts in those operations. Specialists will satisfy
qualification requirements indicated and engage in the activities indicated.
13.3.5 Design Development
The Contractor shall perform a detailed field investigation of the exterior and interior of the building in
coordination with the owner and prepare a report summarizing the findings which will be used as a
basis of design.
As part of Sub-Phase 1A, the Contractor will develop drawings to 50% completion, develop necessary
specifications, and estimate costs to complete the work as part the Project’s Opinion of Probable Costs.
During Sub-Phase 1B, the Contractor will develop final plans to 100% completion, prepare a list of
necessary permits to be obtained, and include costs as part of the development of the GMP.
Phase 2 work will include the necessary permitting, demolition, and reconstruction work required.
13.4 Submittals
Submittals under this Section 13.4, a non-exhaustive list of which is set forth in Table 13-1 (Building
Demolition and Reconstruction Submittals Table), shall be submitted in both hardcopy and electronic
format in accordance with the schedule set forth below. Acceptable electronic formats include PDF and
current versions of Microsoft Word and Microsoft Excel, unless otherwise indicated. At a minimum, the
Contractor shall submit the following to the Department:
Table 13-1: Building Demolition and Reconstruction Submittals Table
For Number of Copies
Acceptance, Reference
Submittal Submittal Schedule
Approval, or Hardcopy Electronic Section
Submittal
Building As Defined in the DBT
Demolition and Submittal N/A 1 Design Submittal Plan and 13.1
Removal Plan Base Design Submittal
14. PAVEMENTS
The Contractor shall construct, maintain, and rehabilitate roadway pavements within the Project Limits
in accordance with Section 1.2 (Governing Regulations) and using Good Industry Practices.
Additional Project specific design criteria and pavement types will be coordinated and communicated
during the Sub-Phase 1A Scope Meeting per Section 2 (Project Management).
Ohio has completed the subsurface exploration and has designed the pavements including subgrade
treatment. Completed final pavement designs are shown in the RIDs PA-01 (Ohio Pavement Type
Selection), PA-02 (Ohio Pavement Section), and PA-03 (Ohio Pavement Requirements). Contractor
shall follow PA-01 (Ohio Pavement Type Selection), PA-02 (Ohio Pavement Section), and PA-03 (Ohio
Pavement Requirements). The Department will not accept modifications to the Ohio pavement type
selection.
Requirements for smoothness and temporary pavement design can be found in Section 1.2 (Governing
Regulations).
KYTC, prior to contract award, will provide base pavement designs for both asphalt and concrete
pavements based on an assumed CBR.
During the Proof-of-Concept Phase, the Contractor shall validate the assumed soil conditions and
coordinate with the Department on any adjustments needed to the base pavement designs including
subgrade treatments. The Contractor may also submit modified equivalent pavement designs to KYTC
for consideration. Modified equivalent pavement designs shall be in accordance with Section 1.2
(Governing Regulations) and supported by documentation of cost and/or time savings. All interstate
and ramp shoulders shall match the mainline driving lane thickness for any modified equivalent
pavement design proposed by the Contractor. The determination of final pavement design(s) will be at
the sole discretion of the Department. Once the Department directs the final pavement designs, the
Contractor shall prepare a Pavement Design Memorandum for KYTC documenting this decision.
Pavement smoothness requirements are per KYTC Standard Specification Section 410 (Asphalt
Pavement Ride Quality Category A) and Section 501 (Portland Cement Concrete Pavement Category
A). Pavement smoothness requirements shall apply to all pavement structure transition areas between
asphalt, concrete, approach slabs and structures for this project.
Special pavement performance aspects or appropriate treatments for reaches of the Project may be
required as part of the environmental commitments for the project or identified through ATC
development.
15. ROADWAY
The Contractor shall design and construct all roadways and associated roadway items including
earthwork, pavements, curbs, pedestrian facilities, driveways, barriers, fence, incidentals, and other
roadside items in accordance with Section 1.2 (Governing Regulations), Table 1-2 (Design Designation,
Design Criteria and Maintaining Agencies), and Design Year forecasted certified traffic volumes which
will be provided by the Department, and requirements within this Section 15.
The Contractor shall develop a Base Design that meets the intent of Concept I-W provided in LD-07
(Concept I-W Corridor Exhibit). The Department has coordinated with local communities and provided
many new active transportation connections in the project limits, many of which cross at or near ramp
terminals. The Contractor shall implement traffic calming measures at locations where drivers are
transitioning from a free flow facility to the local street network, with increased emphasis at active
transportation facility crossings. Additional geometric modifications that meet Project Goals can be
evaluated during Sub-Phase 1A. Additional information is provided for the Contractor to establish Base
Design Plans:
A. LD-01 (Concept I-W_Final Design Summary Report)
B. LD-02 (Kentucky_PAVR Alternative I)
C. LD-03 (Ohio_PAVR Alternative I
D. LD-04 (BSB Smart PDF)
E. LD-05 (BSB IMS)
F. LD-06 (BSB Addendum)
G. LD-07 (Concept I-W Corridor Exhibit)
H. LD-08 (Concept I-W Multimodal Exhibit)
I. LD-09 (Concept I-W Design and Legal Speeds Exhibit (from 12th Street to north end of Project))
J. LD-10 (Draft Design Exceptions)
K. LD-11 (BSB IMS Addendum 2 (Concept I-W) – to be provided
The Department is currently coordinating several design exceptions that will be provided to the
Contractor once approved. Draft design exceptions are provided in LD-10. If additional design
exceptions are identified during Preconstruction Phase (Sub-Phase 1A and/or Sub-Phase 1B) and Final
Design and Construction Phase 2, the Contractor shall prepare the design exceptions for the
Department review. The Department will coordinate and obtain any approvals necessary from FHWA.
Contractor shall include local street repair plans based on the local detours and haul routes coordinated
with Department and local agencies to be further detailed and agreed between the Parties as part of
the Sub-Phase 1A Project Scope. Additional Project specific design criteria will be coordinated and
established during the Post Award Scope Meeting per Section 2 (Project Management).
15.1 Submittals
The Contractor shall submit detailed Base Design plans per ODOT and KYTC requirements and
supporting calculations for review. See Section 2 (Project Management) for Base Design submittal
requirements.
16. DRAINAGE
16.1 General
The Contractor shall conduct all work necessary to design and document design criteria for the
stormwater management facilities for the Project. Elements of work shall include the following:
A. Prepare a Hydraulic Report for the Project in accordance with the Section 1.2 (Governing
Regulations).
B. Pavement drainage systems for both the permanent Project facilities and the temporary
construction conditions. This includes existing detention facilities.
C. Temporary sedimentation and erosion control measures.
D. Runoff treatment and or detention facilities as required to meet Section 1.2 (Governing
Regulations) and the permit commitments for the Project.
E. Maintenance of existing off-site flows that pass through the Project area.
F. New Subsurface drainage systems or Underdrains shall be designed, and design coordinated
with the storm sewer design.
G. Hold meetings and coordinate the design as required with the ODOT and KYTC hydraulics,
maintenance, and environmental staff, the Cincinnati Metropolitan Sewer District (MSD),
Sanitary District No. 1 (SD1), and local public agency (LPA) staff.
H. Compliance with local drainage ordinances.
The stormwater system along the interstate in Ohio will be completely replaced with this Project. ODOT
has committed that the new stormwater system will be removed from the existing MSD combined sewer
system. See Section 17 (Sanitary and Combined Sewers) for additional technical requirements and
information.
The existing stormwater system along the interstate in Kentucky utilizes the Willow Run Combined
Sanitary/Stormwater system through Covington. KYTC has committed that the new stormwater system
will be removed from the existing Willow Run system with the new construction and create an
independent system and outfall. See Section 17 (Sanitary and Combined Sewers) for additional
technical requirements for the Willow Run Combined Sanitary/ Sewer System.
The design of drainage systems shall include reconfiguration of the existing drainage systems within
the Project Limits, and design of new and reconfigured storm drainage systems as required by the
performance requirements as defined in this Section 16. The existing storm sewer systems will be
completely replaced unless approved by the Department based on condition assessment completed by
the Contractor. Contractor shall prepare existing asset condition surveys for stormwater, culverts, and
cross drains as part of the Sub-Phase 1A Work. If Contractor, proposes to re-use existing storm sewer
systems and additional fill is placed, the Contractor shall prepare storm drain joint deflection
calculations and evaluation of safety using Section 12 (Geotechnical), “Buried Structures and Tunnel
Liners” of the AASTO LRFD Bridge Design Specifications for Department review. Contractor shall
design in accordance with ODOT SS 837 and SS 899 for Pipe Liner and KYTC Specification 701.03.
The Contractor shall provide facilities compatible with existing drainage systems and all applicable
municipal drainage plans or systems in adjacent properties. The Contractor shall preserve existing
drainage patterns wherever possible, other than the separation of the interstate stormwater and Willow
Run Sanitary as stated above.
The Contractor shall coordinate this work with Utility and Railroad Owners to design and construct
drainage conveyance utility crossings to meet the respective requirements.
the system needed to meet hydraulic capacity requirements per MSD and ODOT Governing
Regulations.
16.4 Culverts
The Contractor shall be responsible for video inspecting all culverts and cross-drain pipes within the
limits of the Project. The Contractor shall note within the Base Design plans to retain, modify, protect
ends with headwalls, or abandon the existing cross-drains and culverts as required to match revised
roadway sections.
All proposed modifications to cross-drains and culverts in the Project area shall be checked and/or
sized for capacity, and the results shall be included in the Contractor’s design calculations in the Base
Design Submittal. All culvert designs and capacity checks shall be performed in accordance with the
Section 1.2 (Governing Regulations).
As stated in L&D Volume 2, Sections 1112 and 1115, post-construction BMPs are not required if all
runoff is collected in a combined sewer provided design flow to the combined sewer meet the
requirements of maintaining agency. Drainage areas contributory to combined sewers shall not be
credited toward Project treatment percentages for quantity or quality.
The ODOT drainage will require Quality BMP. The Contractor will need to maximize the vegetated BMP
(biofilter and filter stripes) and then offsite mitigation will be required. Contractor will need to coordinate
with OEPA. Coordination has already started with OEPA to get preapproval.
For Kentucky side of the Project BMP design requirements will follow the Section 1.2 (Governing
Regulations), unless directed by KYTC where special considerations may be needed.
16.8 Utilities
The stormwater design must accommodate existing utilities.
Cincinnati MSD is the local stormwater authority for Ohio with responsibility for managing and
implementing the local erosion control protection and sediment control ordinance and floodplain
ordinance.
SD1 is the local stormwater authority for temporary erosion control measures shall be in accordance
with KYTC Drainage Manual, Project permits, and applicable Specifications.
from through deck drains or bridge scuppers. The roadway drainage design shall include the bridge
approach drains to intercept gutter flow at each end of the bridge. Stormwater flowing toward the bridge
shall be intercepted upstream from the approach slab. Bridge drainage shall be collected at the gutter
lines (toe of parapet) by scuppers. Over-the-side drainage is not permitted. The Contractor will be
required to perform all necessary hydraulic calculations per Section 1.2 (Governing Regulations).
drains shall be located at the outer edges of shoulders, or in medians or gore areas. Culverts and
cross- drains isolated from convenient maintenance and inspection access shall be provided with
achievable maintenance and inspection access at one end of the pipe.
Maintenance access adjacent to the sedimentation pools of ponds and vaults shall include a working
area suitable for the loading and maneuvering of sediment disposal equipment and trucks.
Maintenance access roads shall be designed to be compatible with maintenance equipment.
The United States Army Corps of Engineers (ACOE) HEC-RAS Water Surface Profile Program should
be used for performing the hydraulic analyses for the river crossing bridge. Hydraulic and scour
analyses shall also be required. Scour analysis shall be completed for both the existing Brent Spence
Bridge and the new Ohio River bridge.
Hydraulic analysis shall be required for temporary construction conditions creating a scenario worse
than the model developed for permitting. Scour analysis shall also be completed for the temporary
construction condition.
The Cincinnati Metropolitan Sewer District and the Kentucky Sanitary District No. 1 have both identified
the potential need for the development of a Conditional Letter of Map Revision (CLOMR) and Letter of
Map Revision (LOMR). The Contractor will be responsible for performing the CLOMR and LOMR as
part of the permitting process (See Section 7.2 (Permitting)).
Contractor shall develop the Base Design plans for separation of sanitary and storm sewers within the
Project Limits to develop an OPC.
Interstate 71/75 currently crosses a portion of this existing combined sanitary/stormwater sewer
between 9th Street and 4th Street in Covington. The Contractor may design to avoid relocation of this
system in this area as was done with the original interstate construction and subsequent highway
improvements. During Sub-Phase 1A, the Contractor will however need to evaluate whether it is more
cost effective to relocate through this area. A potential concept to relocate is shown in SS-04 (Willow
Run Storm Water Separation Study).
KYTC has further committed to SD1 and the City of Covington to reconstruct and upsize the existing
sanitary/combined sewer system to 120 inches between St. Anthony Elizabeth Hospital and 9th Street.
plans, and details for coordination with ODOT, KYTC, MSD, and SD1. The drainage design report shall
contain the drainage design criteria for the Project. The proposed drainage systems shall not introduce
new connections to the existing combined sewer pipes nor increase the flow to the existing CSO
drainage networks. Where drainage patterns will or must be changed from existing patterns, the
Contractor shall be responsible for coordinating existing drainage patterns with the sewer districts
during Sub-Phase 1A.
Design requirements for the proposed pump station shall be coordinated with ACOE and SD1 and will
need included in the 408 permit. The Contractor shall obtain approval for final design from these two
agencies along with Department concurrence.
17.5 Submittals
Submittals under this Section 17.5, a non-exhaustive list of which is set forth in Table 17-1 (Sanitary
and Combined Sewers Submittals Table), shall be submitted in electronic format in accordance with the
schedule set forth below. Acceptable electronic formats include PDF and current versions of Microsoft
Word and Microsoft Excel, unless otherwise indicated.
18. STRUCTURES
18.1 General
This Section 18 describes overall requirements for temporary and permanent Structures required of this
Project. Applicable requirements for each individual Structure shall be determined and implemented
based on whether the Structure is:
A. Owned or will be owned by KYTC;
B. Owned or will be owned by ODOT; or
C. A specific structure as described in this Section 18, including the Companion Bridge and the
existing Brent Spence Bridge.
The Contractor shall provide structural analysis and design, and develop and produce structural plans,
calculations, specifications, and Submittals for each Structure in accordance with and to a level of
completion required by this Section 18, government regulations, and the Contract Documents.
The Contractor shall coordinate with the Department on providing a Structural Health Monitoring
System on the Companion Bridge. The system design, supply, and installation Work will be further
coordinated with the Department in Sub-Phase 1A.
For structural components not addressed by the standards listed in Section 1.2 (Governing
Regulations), submit for Department Approval other guidelines or specifications that reflect currently
accepted industry practice prior to use.
18.2.2 Meetings
Schedule and facilitate meetings related to structural Project Work. The following meetings are
required:
18.2.2.1 Structure Type Study Base Design Concept Meetings
Group and combine Structures into Buildable Units as acceptable to the Department. Schedule and
facilitate a minimum of one meeting per Buildable Unit with the Department to discuss proposed
structure type design concepts for each Structure in the package. Discuss alternatives reviewed by the
Contractor (Refer to Section 2.3.1.2 (Base Design Submittal)), Contractor preferred alternative, and
reasons for preferred alternative. See Section 18.3.2 (Structure Type Base Design Submittal) for
additional structure type Base Design requirements.
Lead Independent Companion Bridge Engineer and the ICBE designated staff shall be invited to
participate in all meetings discussing the Companion Bridge.
D. Hydraulic information:
1. Design flood years and stage elevations
2. Minimum freeboard at applicable flood stages
3. Backwater at applicable flood stages
4. Relevant flood insurance studies
5. Other agency requirements including DNR, Coast Guard, Corps of Engineers as applicable
E. Risk:
1. Risk items
2. Risk level
3. Risk mitigation strategies
F. ROW/easements:
1. Existing ROW and easements
2. ROW needs
3. Temporary easement needs
4. Permanent easement needs
G. Design and construction costs
H. Bridge Phasing Plan and Maintenance of traffic/traffic control
I. Existing structures:
1. Status during construction staging (full or partial demolition)
2. Anticipated demolition methods
18.3.2 Structure Type Base Design Submittal
Complete Structure Type Base Design for all structures to a minimum level defined in the Sub-Phase
1A Scope Meeting and Sub-Phase 1A Work.
E. For all steel splices, 50 percent of the splice bolts need to be installed prior to unhooking girder
from crane unless designed by the EOR for less and included in the plans.
F. Straddle Bents:
1. Minimum of three independent steel girder I-Beams;
2. Shall be redundant;
3. Post-tensioning is not preferred;
4. Each steel girder to be supported on pier with a bearing; and
5. Annual/bi-annual in-service condition inspection access shall be considered in design. See
Section 18.3.3.1.N (General – All Bridges).
G. Concrete Deck and Vertical Concrete Bridge Railing Reinforcement:
1. Mainline interstate bridges and system to system ramp bridges:
a. Stainless Steel.
b. Chromium Type CS.
2. Local street bridges:
a. Galvanized.
H. Concrete Substructure Reinforcement:
1. Concrete straddle bents:
a. Chromium Type CS.
b. Stainless Steel.
2. Other:
a. Galvanized.
I. Concrete mix design (refer to ST-07 and ST-08):
1. Include macro-synthetic fibers (1-inch minimum to 2.5-inch maximum) at a dosage rate of 4-
pounds per cubic yard.
2. Approved corrosion inhibitor.
J. A minimum vertical clearance as published by the affected railroads shall be maintained over
railroad lines at all times.
K. Bridge mounted PCB attached to new bridge decks is not preferred.
L. Holes will not be permitted to be drilled into the face of the substructure units to support the
structure during jacking operations.
M. All concrete sealing shall be epoxy-urethane and limits shall be per the BDM sections 306.1.2
and 309.2.1.
N. Annual/bi-annual in-service condition inspection access shall be accommodated, and a plan for
inspection shall be provided for each structure by the Contractor.
O. Bridge Load Ratings for each structure shall be per BDM section 900.
P. Provide lifting locations to accommodate jacking and temporary support at all bearing locations.
Q. Design all superstructures to accommodate a future deck replacement while maintaining traffic
for the number of lanes agreed upon during Sub-Phase 1A.
R. Elastomeric troughs are to be placed under all bridge deck expansion joints.
18.3.3.2 Structure Type Limitations
A. Fracture Critical Elements in the substructure and/or superstructure shall not be allowed in their
final condition.
B. Prestressed concrete box beams are not permitted.
C. Post tensioned I-beams are not permitted.
D. Segmental construction is not preferred.
E. Prestressed concrete girders shall be ODOT standards (Std Dwg PSID-1-19) or have a
minimum web thickness of 8 inches.
F. Truss type bridges are not permitted.
G. Non-redundant designs are not permitted in the final configuration.
H. 3-Sided structures used as tunnels traffic conduits for traffic purposes are not allowed.
18.3.3.3 Local Bridge Commitments
Contractor shall refer to Section 19 (Aesthetics and Enhancements), AE-01 (Aesthetic Design
Guidelines), AE-04 (Draft Aesthetic Design Checklist PID 116649) and ST-06 (BSB Local Street Bridge
Cross Sections).
Form Liner shall be used on both sides of the bridge railings when sidewalks and/or shared use path is
adjacent to the bridge railing.
18.3.3.4 Existing Structure Identification
The following existing bridges shown in Table 18-1 (Existing Ohio Bridges) are located within the
anticipated project limits. These structures may or may not require modification or replacement as part
of the Work, depending upon the requirements of the Base Design as developed by the Contractor. All
dimensions are approximate. Contractor is responsible for field measuring critical bridge dimensions.
Existing plans are available.
Table 18-1: Existing Ohio Bridges
Facility Carried by Year Structure Deck
SFN Feature Intersected
Structure Built Length Width
3107787 IR 71 OHIO RIVER BRENT SPENCE 1963 1736.5 94
3108872 IR75 RAMP TO SR264 USR50EB; US50EB TO 2ND ST 1998 264.6 32.8
3108821 IR75 off Rmp CLOSD CLOSED-CENTRAL AVENUE 2000 161.3 32.8
3109062 I-75 7TH ST. GEST ST WITHIN IR R/W 1963 245 35.2
The Department will consider precast concrete cantilevered retaining walls supported on cast-in-place
or deep foundations as appropriate, for this Project. The structural thickness of any precast concrete
retaining wall stems shall be a minimum of 10 inches. The reinforcement clearance on all precast
elements utilized in cantilevered retaining walls shall be 2 inches to each face of the element. The
minimum reinforcement clearance does not include the aesthetic treatment thickness.
All retaining walls, whether temporary or permanent, shall be designed to limit the top of wall deflection
to be less than 1 percent of the exposed wall height, excepted as noted further in these Technical
Requirements. Walls supporting structures, utilities, and pavement, shall be designed to limit top of wall
movement as to prevent damage to the adjacent structure or pavement (applies to both the permanent
and temporary condition). The Contractor will be responsible for repairs to adjacent facilities that occurs
due to excess wall deflection.
Prefabricated modular retaining walls (gravity or reinforced) may be utilized on local streets but cannot
be incorporated on the ODOT interstate mainline or ramps. Local street segmental walls shall use wet-
cast retaining wall blocks. The Contractor shall coordinate the pattern and color of the blocks
comprising any segmental wall with the City of Cincinnati prior to selection of the wall. Design and
construction of all segmental block walls shall follow the most current version Supplemental
Specification 870. Prequalification of the proposed modular block system(s) as outlined in SS870 is a
contract requirement for use on the project.
Retaining walls have been identified as required in several locations for project geometry. Refer to ST-
04 (Concept I-W Retaining Wall List Plan). All retaining walls shall receive aesthetic treatment. See
Section 19 (Aesthetics and Enhancements). In addition, the top of all walls shall receive a smooth
coping in the same manner as that outlined in SS 840 for MSE walls. The coping shall extend beyond
the aesthetic surface treatment a minimum of 1 inch. The aesthetic treatment shall include a relief of at
least 1.5 inches beyond the structural thickness.
Retaining walls supporting bridge abutments are considered retaining walls and shall receive the same
aesthetic treatment as walls away from the bridge structures. Wing walls for bridges and culverts shall
also receive aesthetic treatment. Walls adjacent to each other but of different type (i.e., CIP next to
MSE) shall use the same coping thickness and aesthetic treatment such that the walls visually appear
to be the same type. The use of self-consolidating concrete will be considered by the Department.
Provide aesthetic treatment for the retaining walls with a minimum relief of 1.5 inches beyond the
required structural thickness of the wall. The environmental commitments for the project will determine
the general aesthetic pattern to be incorporated. A single aesthetic pattern (same form liner
manufacturer and product specification) shall be utilized for all walls on the project, regardless of the
wall type. Mixing of form liner patterns, while still providing the same general appearance, is prohibited.
This does not apply to prefabricated modular block walls.
Provide permanent graffiti protection for permanent retaining walls. Epoxy seal all walls from 1 foot
below the permanent ground line in front of the wall, the entire wall facing and 6 inches below the
coping/cap on the back side of the retaining wall. Seal the wall with 17778 Light Neutral sealer, unless
otherwise noted in the environmental commitments. Apply permanent graffiti protection from 1 foot
below the groundline in front of the wall to the top of the wall coping/cap.
Retaining walls shall be designed so that no additional loading from the wall is applied to existing storm
or sanitary conduits crossing.
18.3.3.7.2 Soldier Pile and Lagging Walls (cantilevered and anchored)
Design of cantilevered solider pile and lagging retaining walls shall follow the guidelines outlined in
Specification for Design of Cantilever Soldier Pile Walls as provided by on the Office of Geotechnical
Engineering web site. The wall design shall be analysed using a p-y method (L-pile) of analyses.
Provide the design calculations, along with all appropriate models, in the geotechnical report.
All retaining wall components (including ground anchors, reinforcing straps, porous backfill, etc.) shall
remain within the permanent public R/W or permanent underground easement. All ground anchors and
reinforcing straps shall be a minimum of 5 feet below subgrade.
Design, construct, and test temporary and permanent ground anchors per Supplemental Specification
866. Provide double corrosion protection for all permanent ground anchors.
Perform at least two extended creep tests for each design factored design load (FDL) and at each wall
location utilizing permanent ground anchors. Performance test the first production anchor at each wall
location. Additional performance testing is required for each FDL and wall location. All anchor testing
shall utilize a load cell in conjunction with hydraulic jack, hydraulic pump and pressure gauges needed
to accurately. Provide all testing equipment per SS 866.
Incorporate a permanent cast-in-place facing for any permanent soldier pile and lagging (SPL) wall.
The structural thickness of the cast-in-place facing thickness shall be at least 10 inches. Include the
fractured fin aesthetic treatment on the cast-in-place facing as well as a coping. Horizontal construction
joints are prohibited for all cast-in-place facings.
Temporary hardwood lagging for all soldier pile walls shall be installed in a top-down manner such that
no more than 3 feet of unsupported exposed at any given time. Excavation for placement of the
temporary wood lagging shall be performed in such a manner that the lagging has full-contact with the
excavated face. Any voids behind the lagging shall be backfilled with No. 57 crushed carbonate stone
as directed by the Engineer. Reduce the unsupported height of the excavation as necessary to prevent
caving and sloughing of the soil between the soldier piles. Provide a 0.25 to 0.875 inch horizontal gap
between adjacent lagging boards to permit drainage.
Cover the entire surface of the hardwood lagging with geocomposite drainage board. The
geocomposite drainage board shall meet the requirements of Item 518 Prefabricated Geocomposite
Drain.
Incorporate a permanent cast-in-place facing for any permanent soldier pile and lagging (SPL) wall.
The structural thickness of the cast-in-place facing thickness shall be at least 10 inches. Include the
fractured fin aesthetic treatment on the cast-in-place facing as well as a coping. Horizontal construction
joints are prohibited for all cast-in-place facings.
Soldier piles can be installed using continuous flight auger methods. The Department will consider
construction of the drilled shafts for the installation of the soldier piles utilizing continuous flight auger
(CFA) methods. Use of CFA methods is considered an alternative to Item 524 - Drilled Shafts, for
soldier pile installation. The Contractor shall submit the CFA installation plan in lieu of the drilled shaft
installation. The CFA installation plan shall include the provisions outlined in Item 524. With the use of
CFA methods, the entire drilled shaft excavation from the design tip elevation to the ground elevation at
the time if drilling is to be backfilled with LSM/grout. The continuous flight augers must be hollow, and
continuous to induce placement of the LSM/grout under pressure at the bottom of the drilled
excavation. Once the design shaft tip elevation is reached, place the LSM/grout to the elevations shown
in the project plans by pumping. A minimum 10 feet of pressure head must be maintained during
casting of the shaft. Provide a calibrated, automated inline monitoring system to document the quantity
of grout/LSM placed in the drilled excavation. Submit the flowmeter documentation for each drilled shaft
to the Engineer the day after shaft casting. Immediately re-drill any shaft (do not place soldier beam) in
which the amount of LSM utilized is less than the theoretical volume.
Provide proof of inline flowmeter calibration with the CFA installation plan. The inline flow meter must
have been calibrated by an independent third party within 12 months of the CFA construction date. The
cost of the inline monitoring system is incidental to the cost of the drilled shaft. No additional
compensation will be permitted for shafts re-drilled when the inline flowmeter indicates the initial LSM
volume was less than the theoretical volume.
When utilizing a CFA installation method, provide testing of the LSM/grout mix samples by an
independent testing lab. Quality control cubes or 3-by-6-inch (or larger) cylinders are acceptable. The
Department will obtain 3-by-6-inch cylinders for every fifth set of cubes or cylinders as quality
assurance samples. The cost for providing cube samples and testing is incidental to the drilled shaft
cost.
The Contractor proposing to utilize CFA methods of drilled shaft installation must be ODOT prequalified
and have demonstrated five previous projects in which continuous flight augers were successfully
utilized for soldier pile installation. Include the previous project information, location, year, and
reference contact with the CFA installation plan.
During construction and operation of all temporary retaining walls, the Contractor shall install
monuments on maximum 25-foot intervals along the length of the wall. Each wall shall have minimum
of three monitoring points regardless of length. The monitoring points shall be evenly spaced along the
length of each wall. The Contractor is to survey the top of wall at least weekly during operation. The
survey monitoring shall include the station, offset and elevation of each monitoring point as well as the
coordinates (latitude, longitude) of each point. Provide the Engineer a weekly summary spreadsheet of
the monitoring data and indicate the differences between individual readings as well as the total
movement from the baseline reading. Damage to adjacent pavement, structures, utilities, etc. as well as
voids created by wall movement shall be repaired by the Contractor at no additional cost to the
Department.
Temporary MSE walls shall not be utilized at angles less than 45 degrees to the supporting phase line.
18.3.3.8 Noise Barrier – Ohio
This Section 18.3.3.8 is not used. No Noise Barriers are within the State of Ohio limits.
1. Epoxy.
2. Stainless.
3. Hot dip galvanized.
4. Continuous galvanized.
5. Chromium Type CS in the top mat with chromium Type CM in the bottom mat.
C. Lightweight concrete is not permitted except as otherwise noted in this scope.
D. Bituminous type wearing surfaces are not permitted.
18.3.4.3 Superstructures
A. A minimum of four girder/beam lines for girder/beam bridges shall be required. Three
girders/beams are permitted for single lane ramps and for bridges under part-width construction
but shall be designed for additional future wearing surface load as directed per KYTC.
B. Joints shall be sealed from bridge deck surface drainage. Drainage troughs shall be provided for
open-type joints that accept bridge deck drainage, such as finger joints.
C. Stay-in-place (SIP) deck forms are permitted, when needed. Design shall be adjusted for the
additional load from material in the troughs of the SIP forms.
D. The number of joints shall be minimized, and necessary joints shall be located at end
substructures.
E. Superstructures shall lend preference toward integral end bents, then semi-integral end bents.
F. Bridge design shall include conduit for the full barrier length, junction boxes at 200-foot
maximum spacing along bridge barriers, and junction box Type A at the ends of bridge.
18.3.4.4 Substructures
A. Substructures shall use reinforced concrete designs.
B. Internal forms shall be removed for hollow piers and where bottom of voids for hollow piers do
not extend below the groundline.
C. Straddle bents shall be permitted where necessary with a minimum of three independent steel
beams. Straddle bents shall not contain fracture critical members or requiring post-tensioning.
D. Substructures that rest directly on soil behind MSE walls shall not be permitted.
E. Substructures that utilize spread footings on soil shall not be permitted.
18.3.4.5 Foundations
Select and design bridge foundations that are deep foundations or spread footings founded on
competent bedrock. See Section 12 (Geotechnical) for additional requirements and information. Deep
foundations are required for bridge abutments located within MSE walls.
18.3.4.6 Existing Structure Identification
The existing bridges in Table 18-3 (Existing Kentucky Bridges) are located within the anticipated project
limits. These structures may or may not be receiving work based upon the specified scope and the
extents of the Contractor’s design plans. All dimensions are approximate. Contractor is responsible for
field measuring critical bridge dimensions. Existing plans are available.
059B00044R I-75 US25, KY1120, (11TH, 12th, LEWIS) 1960 684.1 54.0
059B00087N I-75 RAMP PIKE ST-ON RMP TO I-75N 1993 85.0 26.0
059B00088N I-75 RAMP 9TH ST (I-75NB) RAMP 'G' 1993 159.0 25.9
059B00039N 5TH ST/SB I75 RAMP 4TH ST RAMP TO SB I-75 1963 62.0 62.0
059B00041N PED. OP AT 5TH ST NB I75 EXT RMP TO 5TH STREET 1968 149.0 0.0
anticipated. See Section 7 (Environmental) Appendix EN-08 (Ohio Noise Analysis Report), EN-26 (KY
Traffic Noise Impact Analysis North), and EN-27(KY Traffic Noise Assessment South).
permit over the Companion bridge. Files shall include all the current rating vehicles required for load
rating by both ODOT and KYTC. The Contractor shall have a discussion with both KYTC and ODOT to
ensure the rating tool will include features and vehicles that are required from both states.
18.3.5.6 Precast Deck
Full depth precast panels combined with a rigid overlay shall be allowed to be used for the Companion
Bridge. To ensure durability, transverse post-tensioning may be used for both Cable Stayed and Arch
bridge types. Longitudinal post-tensioning of the precast deck may be used for the Arch bridge. For the
Cable Stayed option the horizontal cable thrust may be utilized to ensure post-tensioning of the precast
deck in the longitudinal direction. For either structure type Contractor is to design for zero tensile
stresses in the deck for all loadings acting on the structures.
18.3.5.7 Type of Rebar in the Deck
The Companion bridge deck, precast or cast-in-place shall be designed and constructed using only the
following types of reinforcing bars:
A. Stainless steel reinforcing bars.
B. Type CS chromium bars.
The decision should be made with the Owner based on a cost/benefit analysis prepared by the
Contractor, and availability of each type to meet project schedule.
18.3.5.8 Barge Impact Study
The Companion bridge supports shall be designed to resist vessel collision. The methodology to be
used to determine the magnitude and application of vessel impact forces should be in accordance with
the 2020 American Association of State Highway and Transportation Officials (AASHTO) LRFD Bridge
Design Specifications (9th Edition) Article 3.14. As stated in the AASHTO LRFD Specifications, the
AASHTO “Guide Specifications and Commentary for Vessel Collision Design of Highway Bridges” may
be used as an additional source of information for the determination of vessel impact parameters.
18.3.5.9 Coast Guard Requirements
Cable stayed and arch bridge shall provide a minimum low steel elevation of 532 feet NAVD88 between
the two river piers. Contractor shall coordinate with the Department to establish the minimum
acceptable navigational clearance with the USCG. Contractor to refer to PC-02 (USCG Coordination
Correspondence), ST-03 (BSB USCG Coordination Summary), and PC-03 (Brent Spence Bridge
Section 9 Project Initiation Request).
18.3.5.10 Independent Companion Bridge Review Requirements
Companion bridge has been determined to be either a Cable Stayed structure or Arch type structure,
hence either option is considered a complex signature bridge. Therefore, a design review (with
independent design computations) will be performed by the Independent Companion Bridge Engineer
(ICBE). The ICBE shall be selected as a fully independent firm that:
A. Will use an independent structure software at least as sophisticated as that used by the Design
Engineer of Record; and
B. Will utilize only information provided by the Design Engineer of Record as part of their official
sequenced submittals and will have no access to the designer’s calculations.
The ICBE will participate as part of the project team beginning with the development of design criteria.
Department expects that the ICBE, DBT Design Manager, and DBT Lead Structure Design Engineer
will generally resolve issues where they may initially differ as the project progresses through Sub-
Phase 1A OTS reviews, Base Design, Sub-Phase 1B Scope development, and Phase 2 Final Design
and Construction. The Contractor shall have the ICBE seal a statement agreeing with the overall design
provided by the DBT Design Manager and Lead Structure Design Engineer.
18.3.5.11 Tower Configuration
Tower configuration for the Companion bridge shall be established as part of the aesthetic study for the
project.
No elevators shall be included in the Companion bridge towers. Access inside the towers for installation
and inspection shall be provided using a combination of ladders installed in the inner walls and rest
areas.
18.3.5.12 Access for Biannual Bridge Inspection
The Companion Bridge shall be designed with inspection in mind:
A. The Cable Stayed option of the Companion bridge shall include tie-offs for inspectors to hook
safety gear along the fascia girders and all floor beams and on the exterior of the towers.
B. The Arch option of the Companion bridge shall provide for the ability of the inspectors to climb
and access the interior of the steel arch ribs and ties.
18.3.5.13 NEPA Commitments
The following information is included in EN-28 (Environmental Commitments):
A. The highest point of the bridge shall be at least 300 feet +/- above the Normal Pool Elevation of
the Ohio River (EL. 456.36’ NAVD88).
B. The highest point of the bridge shall be less than 420 feet +/- above the Normal Pool Elevation
of the Ohio River (EL. 456.36' NAVD88).
C. The Minimum Provided Underclearance shall be no lower than that provided by the existing
Brent Spence Bridge. The lowest point in the companion bridge shall be at elevation 532’
NAVD88.
D. The bridge main span shall provide sufficient length to ensure that substructure units are
outside of the main span piers of the existing Brent Spence Bridge.
E. If a double deck design is provided, a 25-foot minimum vertical clearance shall be provided
above the bottom deck roadway surface.
18.3.5.14 Cofferdam Design
Hydrograph is provided based on USCG river elevation records. Contractor and Department shall get
together during the progressive design-build process to review and determine the required cofferdam
elevation up to which the Department will be responsible. Contractor to refer to ST-05 (BSB Companion
Bridge Hydrograph).
18.4 Submittals
Submittals under this Section 18.4, a non-exhaustive list of which is set forth in Table 18-5 (Structures
Submittals Table), shall be submitted in both electronic format and hardcopy format in accordance with
the schedule set forth below. Unless otherwise indicated, acceptable electronic formats include PDF
and current versions of Microsoft Word and Microsoft Excel, unless otherwise indicated.
(Structure Type Base Design Submittal), discussed in Structure Type Base Design meetings, and to
receive Department Approval. At a minimum, the Contractor shall submit the following to the
Department:
Table 18-5: Structures Submittals Table
Aesthetic Design Guidelines (AE-01) were established as part of the prior NEPA effort completed in
2012 under ODOT PID 75119. In addition, an Aesthetic Design Checklist (AE-02) has been developed
for Phases I and II of the corridor. A Draft Aesthetic Design Checklist (AE-04) has been developed for
Phase III in Ohio. Conceptual Aesthetic Design Guidelines for Phase III in Kentucky are under
development. The final Ohio Phase III Aesthetics Design Checklist and Conceptual Kentucky Aesthetic
Design Guidelines will be provided to the Contractor for inclusion in the Base Design.
The Aesthetics Committee and the Department are coordinating additional aesthetics requirements for
the existing and Companion Bridges. Lighting enhancements will likely be required for the Companion
Bridge.
The aesthetic process will follow ODOT’s current Aesthetic Design Guidelines and KYTC’s current
aesthetic guidance. The Contractor will coordinate with the Department, the Aesthetic Committee,
subsets of the Aesthetic Committee, and the cities of Fort Wright and Fort Mitchell to finalize aesthetic
details to be included in the Base Design.
The Contractor shall coordinate with the Department to develop a landscape development plan per the
Aesthetic Design Checklist and Conceptual Aesthetic Design Guidelines.
20.2 Signing
The Contractor shall design all permanent signage for the Project according to Section 1.2 (Governing
Regulations). The development of signing plans shall start with the Concept I-W Conceptual Signing
Plan provided in LD-01 (Concept I-W Final Design Summary Report). All modified and relocated
signage must be new. All proposed overhead sign supports shall be of new construction and the
Contractor will be required to replace all existing sign structures within the Project Limits.
The Contractor, Department, and KYTC shall meet with local agencies, as necessary, to discuss,
define signing design criteria, and review signing plans. The Contractor shall schedule two or more
concept meetings to present to the Department the inventory of existing signing and pavement
markings for the Project and the proposed permanent signing and pavement markings. The Contractor
shall document the resolutions of issues in a correspondence file, including meeting minutes and
memoranda for the record. The Contractor shall document meetings with other local agencies to define
criteria as required. The Contractor shall submit conceptual signing plans as part of the Base Design
Submittal.
Contractor shall provide design of proposed temporary and permanent traffic signals for the Project as
part of the Base Design Submittal. Traffic data for use in the design of signalized intersections will be
provided in LD-11 (BSB IMS Addendum 2 (Concept I-W)). At a minimum the Base Design Submittal
shall include:
A. Recommendations for signal timing (during construction as well as final configuration);
B. Type of detection to be used (radar, video, loops);
C. Proprietary item approvals;
D. Conceptual MOT;
E. Signal plan sheets with signal support locations;
F. Signal heads;
G. Signal cabinet locations;
H. Detector locations;
All signals should have remote communications per the owner’s standards. The Contractor shall also
coordinate with all agencies, power companies, and Department to provide appropriate design
methods, procedures, plan preparation, analysis methodology, equipment specifications, and
construction requirements. Contractor shall coordinate power service locations with the power
companies and Department.
A Draft Aesthetic Design Checklist (AE-04) has been developed for Phase III in Ohio and Conceptual
Aesthetic Design Guidelines for Phase III in Kentucky are under development. Contractor shall design
signals for aesthetics requirements.
20.4 Lighting
The Contractor shall design a roadway lighting system for all roadways within the Project Limits. This
would include design of a complete and functional lighting system that integrates utility service,
foundations, poles, luminaires, support and support hardware, service equipment, conduits, conductors,
boxes, grounding components, commissioning, and testing. The Contractor shall coordinate with all
agencies, power companies, and Department to provide appropriate design methods, procedures, plan
preparation, analysis methodology, equipment specifications, and construction requirements.
Contractor shall also coordinate power service locations with the power companies and Department.
The Contractor shall coordinate pad size and locations with the power companies. The street lighting
systems shall be metered separately from the traffic signals and accent lighting. Lighting circuits shall
also be separated based on ownership. The ownership of the lighting should be the agency that
maintains the roadway being illuminated. All new luminaires shall be designed with LED and shall meet
the requirements stated in Section 1.2 (Governing Regulations).
Companion Bridge shall be lighted in accordance with FAA requirements for obstruction marking. The
Contractor shall provide all temporary aviation obstruction lighting required by the FAA during
construction including on cranes, structures, or any other objects more than 200 feet above water or
ground. FAA lighting design criteria will be coordinated during Sub-Phase 1A. See Section 1.5
(Airway/Highway Clearance for Airports and Heliports) for FAA permit coordination.
A Draft Aesthetic Design Checklist (AE-04) has been developed for Phase III in Ohio and Conceptual
Aesthetic Design Guidelines for Phase III in Kentucky are under development. Contractor shall design
lighting for aesthetics requirements.
Lighting over the navigation channel shall conform with USCG requirements, as provided for the in
USCG Bridge Permit Application Guide, USCG Bridge Lighting Manual, and as listed in 33 CFR Part
118 for fixed bridges. The Contractor shall determine navigation channel lighting requirements with the
USCG for both the companion bridge and any modifications required to the existing Brent Spence
Bridge. The Contractor shall take into account the existing navigational lighting on the existing Brent
Spence Bridge and work with the USCG to provide appropriate lighting of piers. In addition, any
modifications to the existing Brent Spence Bridge navigational lighting shall be as approved by the
USCG for both directions of traffic. The Contractor shall maintain navigational lighting as required by
the USCG on the existing Brent Spence Bridge for the replacement of its bridge deck. Power supply for
the Navigation lighting may be combined with the obstruction lighting (FAA) circuits but shall not be
made part of the aesthetic lighting circuit and shall be provided on its own dedicated, separately
metered circuit.
offers an opportunity to utilize newer ITS technologies and applications. The TRIMARC TMC is located
in Louisville at 901 W. Main Street Louisville, KY. 40202. The ODOT TMC main fiber is connected to
the ARTIMIS building located at 508 W. 3rd St., Cincinnati, OH. The Contractor shall locate and design
a utility vault, either above ground or buried, to house the ARTIMIS equipment. The utility vault shall be
temperature controlled, have vehicle access, and doors large enough to get equipment in and out (36
inches wide, standard height door at a minimum). All access to the vault shall be secure via normal lock
and key design. The design of the vault shall include details to supply power to a 200-amp breaker
panel. The vault shall be at least 10-foot square. All of the existing fiber from the ARTIMIS facility needs
to be terminated in the new vault. ODOT shall have the ability to run new communications to the vault,
so a conduit system to an outside manhole will be required. Four, 4-inch conduits shall be provided. ITS
connectivity must be maintained, and relocation of ITS infrastructure must be completed prior to
demolition. For existing ARTIMIS building plans see EX-18 through EX-25.
The design and construction of all ITS and components shall meet the requirements of CFR 940 and
provide functionality, connectivity, and compatibility with Central Software in the respective TMC
(TRIMARC for Kentucky, OKI Regional ITS, and ODOT Statewide TMC) with considerable thought
included in the design for durability, ease of maintenance, safety, and aesthetics.
20.6 Submittals
Submittals are defined within Section 1.2 (Governing Regulations) and Section 2 (Project
Management). Contractor shall provide traffic control plans and calculations in the Base Design
Submittal.
freeways, ramps, and local streets. The schedule shall take into consideration snow and ice
operations from December 1 through March 31. Lane shifts, restrictions, and closures may not
be approved if they adversely affect snow removal operations.
B. Discussion of sequence of operations and MOT procedures, identifying all long-term lane
closures and all complete directional roadway closures (short-term or long-term). Long-term
shall mean any closures greater than 24 hours.
C. Plans at an appropriate scale showing the Work area, tapers, temporary pavement and/or
structures, signs, locations of typical sections, locations of construction access points, and
references to applicable standard construction drawings (SCDs).
D. Typical sections including lane widths, pavement markings, drums, portable barriers, limiting
stations, barrier and shoulder offsets, work area, and drop-offs.
E. Detour plans and alternative route plans identifying anticipated improvements. The Contractor
may need to provide additional lanes along mainline and ramps along the detour/alternate
routes used to bypass the construction area.
F. Temporary local street closures and detour routes.
G. Temporary pedestrian and bicycle detour routes.
H. Haul routes.
I. Information and guidance for signing and detour routes, including color-coded definitions of
detour routes.
J. Summary of traffic modelling with anticipated level of service due to lane closures and detour
routes.
K. Summary of anticipated locations and durations of variable message signs and boards.
L. Outline of the IMP and TMP requirements. The TMP will require a Worksite Traffic Supervisor
(WTS). The WTS shall be certified in the state where Work being supervised is being
performed. The IMP will require a Contractor TIM contact.
M. Opinion of Probable Costs for MOT, TMP, and IMP items.
N. The disincentives required by the Department consistent with the requirements of PDBC Exhibit
S (Lane Value Contract).
O. List of signals that could be impacted during each phase of construction.
P. Evaluate MOT drainage (ODOT) and temporary drainage structures (KYTC). Provide MOT or
temporary drainage culverts and/or drainage structures as needed to avoid disruption of existing
drainage flow patterns. Provide temporary drainage items on the MOT plans and drainage
calculations per ODOT Location and Design Manual Volume 2 and KYTC Drainage Manual.
Q. Prior to shifting traffic to the existing shoulders or to the opposite bound of the freeway via
temporary crossovers, replace existing drainage structure covers where traffic is driving over the
covers with temporary bolt down drainage structure covers. Prior to shifting traffic to proposed
shoulders provide temporary bolt down drainage structure covers on proposed drainage
structures where traffic is driving over the final phase proposed covers. Final proposed covers to
be added after traffic is shifted.
21.4 Submittals
Submittals under this Section 21.4, a non-exhaustive list of which is set forth in Table 21-1
(Maintenance of Traffic Submittals Table), shall be submitted in electronic format in accordance with
the schedule set forth below. Acceptable electronic formats include PDF and current versions of
Microsoft Word and Microsoft Excel, unless otherwise indicated.
Table 21-1: Maintenance of Traffic Submittals Table
January 3, 2023
LIST OF EXHIBITS
EXHIBIT A: ACRONYMS AND DEFINITIONS1
The Maximum Sub-Phase 1A Prime Compensation amount subject to adjustment for Change
Orders as set forth in PDBC Section 11.1.3 (Compensation for the Sub-Phase 1A Work) is
$30,000,000.
The Maximum Sub-Phase 1B Prime Compensation amount subject to adjustment for Change
Orders as set forth in PDBC Section 11.1.4 (Compensation for the Sub-Phase 1B Work) is
$200,000,000.
The Sub-Phase 1B Proposal shall be submitted no later than 230 Days2 after the Sub-Phase 1A
NTP (the “Sub-Phase 1B Proposal Due Date”).
The Phase 2 Proposal shall be submitted no later than 390 Days3 after the Sub-Phase 1B NTP
(the “Phase 2 Proposal Due Date”).
The target date for the Companion Bridge Opening Deadline is July 15, 2029.
The target date for the Substantial Completion Deadline is September 15, 2030.
The Project Mark-up percentage as specified in Exhibit G (Pricing Process) shall be [●] %4.
The amount of liquidated damages to be deducted for each Day by which the Substantial
Completion Date exceeds the Substantial Completion Deadline, subject to PDBC Section 13.7
(Failure to Complete On Time) shall be $37,000.
1.1 Certain of the Contractor’s failures to perform and breaches of its contractual obligations
under the Contract Documents constitute Noncompliance Events (NCEs) that may result in the
assessment of Noncompliance Points. Table F-1 (Noncompliance Events Table) identifies each
Noncompliance Event, the points assessed per event and the NCE Cure Period available to the
Contractor for each Noncompliance Event. Noncompliance Points are a system to measure the
Contractor’s performance and trigger the remedies set forth or referenced in this Exhibit F.
2.1.1 The Contractor shall provide an electronic database, which the Contractor shall utilize in
connection with the Noncompliance Points system. Upon the occurrence of any Noncompliance
Event specified in Table F-1 (Noncompliance Events Table), the Contractor shall enter such
Noncompliance Event into the electronic database in real time upon discovery or being made
aware of the discovery but no later than 12:00 noon the next Working Day (once the Contractor
is aware of or is made aware of the occurrence) if the occurrence takes place after normal
business hours. The format and design of the electronic database shall provide the Contractor,
and the Department the ability to make full or partial entries and edits to any existing entry. At a
minimum, each electronic database entry by the Contractor shall:
(a) Include a description of the Noncompliance Event in reasonable detail;
(b) Identify the reference number and headings and sub-headings assigned to the
Noncompliance Event in Table F-1 (Noncompliance Events Table);
(c) Identify the Project location (if applicable);
(d) Identify the date and exact time of occurrence;
(e) Identify the applicable response date and time, if any;
(f) Indicate the applicable NCE Cure Period, if any, as set forth in Table F-1
(Noncompliance Events Table);
(g) Indicate status of cure, whether the item is open or cured by the Contractor, rejected by
the Department, or disputed by the Contractor; and
(h) Indicate the date and exact time of cure (if any).
2.1.2 In cases of dispute of entries, the Department may edit or enter comments to the
Contractor entries at any time. If the Contractor disagrees with the Department’s entries, the
changes or entries inserted by the Department must remain in place, subject to the provisions
regarding Dispute Resolution in Section 5 (Provisions Regarding Dispute Resolution).
2.1.3 The Department may provide to the Contractor a “Notice of Determination” via the
electronic database or in writing. A Notice of Determination may:
(a) make a determination of occurrence of a Noncompliance Event;
(b) make a determination of whether a Noncompliance Event was cured during the
applicable NCE Cure Period;
If the Department identifies any Noncompliance Points to be assessed the Department will
provide the "Notice of Determination" in writing to the Contractor.
If the Department believes there has occurred any Noncompliance Event which the Contractor
is not aware of, the Department may deliver to the Contractor a Notice Noncompliance Event.
2.3.1 The Contractor shall cure each Noncompliance Event by the end of the NCE Cure
Period for each such Noncompliance Event set forth in Table F-1 (Noncompliance Events
Table). The start of the NCE Cure Period shall be determined according to the “Assessment
Category” shown in Table F-1 (Noncompliance Events Table).
2.3.2 For each “Category A” Noncompliance Event, the NCE Cure Period shall start not later
than the date and time of delivery by the Department of a Notice of Noncompliance Event to the
Contractor.
2.3.3 For each “Category B” Noncompliance Event, the NCE Cure Period shall start upon the
earlier of: (i) the date and time the Contractor first obtained knowledge of the Noncompliance
Event or (ii) the date and time the Contractor received notice thereof by any third party.
2.4.1 When the Contractor determines that it has completed cure of any Noncompliance
Event, the Contractor shall enter in the electronic database a record that it has completed the
cure, a brief description of the cure, and any modifications needed to the DBT PMP to avoid
future similar Noncompliance Events.
2.4.2 Upon the Contractor’s determination that it has completed the cure, the Department shall
have the right, but not the obligation, to inspect to verify completion of the cure. If satisfied that
the Noncompliance Event is fully cured, The Department will deliver to the Contractor a Notice
of Determination with its acceptance or rejection of the cure. If the Department issues a Notice
of Determination with its acceptance of a cure, the cure is effective as of the date of the
Contractor’s notice of cure.
2.4.3 Subject to the time restrictions in this Section 2, The Department may reject the
Contractor’s notice of cure if the Department determines that the Contractor has not fully cured
the Noncompliance Event or if the Department cannot determine whether the Contractor has
fully cured the Noncompliance Event. Upon making this determination, the Department will
deliver a Notice of Determination to the Contractor rejecting the cure. Any Dispute regarding
rejection of cure shall be resolved according to the Dispute Resolution procedures in Section 5
(Provisions Regarding Dispute Resolution).
Noncompliance Points in accordance with Table F-1 (Noncompliance Events Table), subject to
the following:
(a) For each Noncompliance Event for which an NCE Cure Period is identified in the Table
F-1 (Noncompliance Events Table) (Category A or B), that is not a late, incomplete or
defective Submittal, provided that the Noncompliance Event is not cured,
Noncompliance Points shall first be assessed at the end of the first NCE Cure Period.
(b) For each Noncompliance Event for which a NCE Cure Period is identified in Table F-1
(Noncompliance Events Table) (Category A or B) that is a late, incomplete, or defective
Submittal, Noncompliance Points shall first be assessed at the date of expiration of the
time period required by the Contract Documents for the Submittal plus the applicable
NCE Cure Period.
(c) If a Noncompliance Event for which an NCE Cure Period is provided in Table F-1
(Noncompliance Events Table) (Category A or B) is not fully cured within the applicable
NCE Cure Period then continuation of such Noncompliance Event beyond such NCE
Cure Period shall be treated as a new and separate Noncompliance Event. Additionally,
(i) a new cure period equal to the NCE Cure Period set forth in Table F-1
(Noncompliance Events Table) shall apply upon expiration of the NCE Cure Period, and
(ii) if applicable, additional Noncompliance Charges shall be assessed against the
Contractor in accordance with Section 6 (Noncompliance Charges) and deducted from
the amounts due to the Contractor under this PDBC.
(d) The Department may, but is not obligated to, assess fewer than the maximum number of
Noncompliance Points for any Noncompliance Event.
(e) The Department shall not be entitled to assess Noncompliance Points under more than
one category for any event or circumstance that is a breach or failure. Where a single
act or omission gives rise to more than one breach or failure, it shall be treated as a
single breach or failure for the purpose of assessing Noncompliance Points, and the
highest amount of Noncompliance Points under the relevant breaches or failures shall
apply.
4.1 The provisions of this Section 4 apply to a Noncompliance Event identified in Table F-1
(Noncompliance Events Table) that is directly attributable to a Force Majeure Event.
4.3 For the avoidance of doubt, for any Noncompliance Event directly attributable to a Force
Majeure Event where the Contractor is unable to comply with a requirement of the Contract
Documents due to an ongoing Force Majeure Event, then solely during the period that such
Force Majeure Event prevents compliance with such requirement, no Noncompliance Points or
Noncompliance Charges will be assessed for such Noncompliance Event and the Contractor
shall be excused from performance of the underlying requirement.
5.1 The Contractor may object to the assessment of Noncompliance Points or the starting
point for or duration of the NCE Cure Period respecting any Noncompliance Event by delivering
to the Department Notice of such objection not later than seven Days after The Department
delivers its Notice of Determination.
5.2 If the Contractor gives timely notice of objection and the Parties are unable to reach
agreement on any matter in Dispute within ten days of such objection, either Party may refer the
matter for resolution according to the procedures for resolving Disputes in the Contract
Documents, including Facilitated Partnering and Dispute Resolution Procedures.
6. Noncompliance Charges
6.1 Upon assessment of the 10th Noncompliance Point pursuant to Section 3 (Assessment
of Noncompliance Points) and upon assessment of each subsequent 10th Noncompliance Point
pursuant to Section 3 (Assessment of Noncompliance Points), the Department shall be entitled
to immediate and automatic Noncompliance Charges from the Contractor in an amount equal to
$50,000 (such amount calculated at a rate of $5,000 per Noncompliance Point).
Noncompliance NCE
No. of Assessment
Ref. Main Heading Sub-heading Events Table Cure
Points Category
Failure to: Period
Comply with the
reporting requirements
or any requirement of
the DBE Performance
Contracting Comply with
Plan in accordance with
5 and Labor DBE Reporting 2 B 5 Days
Section 5.1 (DBE
Practices Requirements
Performance Plan) of
Exhibit E (Technical
Requirements) and
Exhibit L of the PDBC.
Report compliance
with, or to comply with
the reporting
Federal requirements of, any of
30
6 Reporting Reporting the Federal 2 B
Days
Requirements Requirements, as
required by the
Contract Documents,
including Exhibit N.
Comply with any of the
reporting, recording
keeping, or
documentation
requirements, including
DB Contractor
monthly and annual 14
7 Reporting Reporting 1 B
reporting, or any Days
Requirements
Subcontractor reporting
requirements, as
required by and in
accordance with the
Contract Documents.
Maintain and update
the complete
Maintain and Stormwater Pollution
Environmental
8 Update Prevention Plan 2 A 7 Days
Compliance
SWPPP (SWPPP) as required
by Exhibit E (Technical
Requirements).
Notify The Department
of Regulated Materials
Notify the or a Recognized
Environmental Department of Environmental
9 2 B 1 Day
Compliance Regulated Condition as set forth in
Materials Section 5.13.6
(Regulated Materials)
of the PDBC.
Noncompliance NCE
No. of Assessment
Ref. Main Heading Sub-heading Events Table Cure
Points Category
Failure to: Period
Perform a permanent
repair to a hazardous
defect in accordance
Maintenance Ensure Timely Defect
with Section 5.11
10 during Hazard Repair 3 B Repair
(Damage to the Work
Construction of Defect Period
and Maintenance
During Construction) of
the PDBC.
Comply with any
specific traffic control
construction
requirements for local
Comply with access, detours, local
Traffic traffic control approvals, markings
11 2 B 1 Day
Management construction and signing, utility cuts,
requirements hauling Equipment,
final clean up and
stockpiles, as required
by the Contract
Documents.
No later than 15 Days after Sub-Phase 1A NTP, the Contractor shall convene, attend, and
actively participate in a meeting to discuss and develop an initial approach to costing the Project
with the Department and the Independent Cost Estimator (ICE). The purpose of this meeting is
to establish the baseline Cost Model structure, input standards, and assumptions for the
formulation and ongoing updates and maintenance of all future Opinions of Probable Cost
(OPC’s), including design and construction cost and Project Schedule estimates. This meeting
will also establish the plan to communicate changes in scope, quantity, risk, and other
information required to affirm a consistent foundation for cost and schedule estimation.
No later than 60 Days after the initial approach to cost meeting, the Contractor shall document
and submit to the Department the description and assumptions for the work elements that
communicate the estimating practices, processes and format to be developed on an Open Book
Basis for each Price Proposal (“Estimating Methodology Report”) and the proposed Cost Model.
1. General
(a) An Opinion of Probable Cost (OPC) is a Contractor-generated accounting and
estimation of all cost and schedule for a Price Proposal. An OPC may contemplate
Design Work, Construction Work, related Professional Services, or any combination
thereof.
(b) The Contractor shall maintain an OPC(s) for each Price Proposal unless and until each
Price Proposal is agreed and executed.
(c) The Department will maintain an accounting and estimation of all cost and schedule (the
“Department's Estimate”) for each Price Proposal and the overall Project. The
Department will engage the State Cost Estimator (SCE) to develop the Department's
Estimate.
(d) At a minimum, the Contractor shall generate and maintain an OPC for the following:
(i) The overall project at the end of Sub-Phase 1A
(ii) Sub-Phase 1B Work
(iii) Any proposed Early Work Package
(iv) Phase 2 Work
(v) Any proposed Buildable Units in Phase 2
(ii) The cost of Materials shall include freight, delivery, unloading, storage charges,
taxes, normal wastage allowance in accordance with Good Industry Practice and
all Supplier discounts;
(iii) Except as otherwise expressly permitted under this PDBC in the case of an Early
Work Package, the OPC or Price Proposal shall utilize the Project Mark-up to
calculate the Contract Price to complete the Work. Costs included in the Project
Mark-up shall not be included in the reasonably estimated costs prepared in
accordance with Part C (Basis for Establishing Price) of this Exhibit G;
(iv) The Contractor shall prepare its OPC or Price Proposal on the basis described in
the Cost Model or as otherwise directed by the Department or agreed by the
Parties;
(v) An OPC or Price Proposal for the whole of the Phase 2 Work shall incorporate, as
a separate line item, the Contract Price for any Price Proposal for which a Change
Order has been executed prior to preparation of that OPC;
(vi) The Contractor shall list indirect costs for each item in a separate list and the
Department will review and approve the list of costs at each OPC;
(vii) The OPC or Price Proposal shall be produced under an Open Book Basis;
(viii) The OPC or Price Proposal shall be supported in sufficient detail to be used in
preparing budgets based on sub-trades, combinations of sub-trades, building
systems, and Subcontractor bid packages in accordance with the approved
Subcontractor Bidding and Selection Plan. Lump sum estimates are not
acceptable;
(ix) The OPC or Price Proposal shall be consistent with the then-current Project
Schedule incorporating the Phase 2 Work as part of an integrated and cohesive
cost and schedule build-up for the Phase 2 Work. The OPC or Price Proposal shall
clearly delineate Work assumed to be self- performed by the Contractor, Work to
be performed by a Subcontractor that is an Affiliate and Work assumed to be
performed by a Subcontractor that is not an Affiliate, consistent with PDBC Section
8.2 (Limitation on Subcontracted Work);
(x) The Contractor shall obtain such number of quotes from potential Subcontractors
as is contemplated under the approved Subcontractor Bidding and Selection Plan.
This information shall be provided with each OPC and Price Proposal and the
Contractor shall require its potential Subcontractors to share their information,
quotes, scope of work bid, and product or services data with the Department and
the ICE. Where the approved Subcontractor Bidding and Selection Plan does not
contemplate obtaining quotes from potential Subcontractors, the Contractor shall
provide the estimate for the applicable scope of work and supporting data, which
shall include data from recent quotes obtained for equivalent scopes of work,
products or services on other projects;
(xi) Any Contingency amounts included in the OPC or Price Proposal shall be fully
identified and delineated so that they are included as an express and transparent
amount, consistent with the risk allocation, risk mitigation and qualitative and
quantitative analysis under the then current Risk Register. Contingency amounts
included in the OPC or Price Proposal shall be entirely amounts necessary to
address risks allocated to the Contractor and shall not include any amounts that
may be held by the Department for risks allocated to the Department. All
Contingency amounts shall be allocated to specific Contractor risks;
(xii) No OPC or Price Proposal shall include cost items already included in the other
Price Proposals or Contract Prices, items expressly retained by the Department, or
items not required by the Department; and
(xiii) Each OPC and Price Proposal shall be independently prepared by the Contractor
but in coordination with the Department and the ICE.
(f) Each OPC or Price Proposal submitted by the Contractor shall contain the following
elements in the following order:
(i) A summary memorandum consisting of a narrative summary of the cost estimate
that includes:
(A) A summary of costing activities since the previous OPC or Price Proposal
submittal;
(B) Changes subsequent to the previous OPC or Price Proposal submittal and
reasons for the changes;
(C) Responses to the Department's comments on the previous OPC or Price
Proposal submittal;
(D) A list of proposed Materials to be installed and the procurement status for
each (including Supplier selection activities);
(E) A list of critical or long lead Materials;
(F) A list of proposed Subcontracts with the procurement status for each
(including Subcontractor selection activities);
(G) The current Contingency value and the approach to determining the value;
and
(H) A cost summary table.
(ii) An updated Cost Model (including a completed Schedule of Values) showing a line
item cost breakdown;
(iii) A list of all assumptions, clarifications, and exclusions that the Contractor used to
determine the OPC or Price Proposal;
(iv) Detailed description of any allowances, performance incentives or risk sharing
arrangements proposed by the Contractor;
(v) A breakdown of Contractor Contingencies including escalation of Materials and
goods, Contractor risks, and scope gap/exclusions not included in the direct costs
and providing clear referencing to the Risk Register;
(vi) The most recent proposed updated Project Schedule;
(vii) A certification from the Contractor that all costs included in the OPC or Price
Proposal (as applicable) are allowable in accordance with the cost principles in 2
CFR part 200 subpart E, and the OPC or Price Proposal (as applicable) does not
include any costs which are expressly unallowable under applicable cost principles
of 2 CFR part 200 subpart E; and
3. Schedule of Values
(a) Each Schedule of Values required to be prepared in accordance with this Contract shall:
(i) Be coordinated with and consistent with the draft updated Project Schedule; and
(ii) Provide an estimated quantity of items to the Department for each element of Work
in accordance with Department or KYTC standard bid item codes whenever
possible. Where Department or KYTC standard bid items are not available, provide
an explanation of non-standard items. The Department will provide unique item
names and codes for these items.
1. General
Each OPC or Price Proposal shall be based on the reasonably estimated actual cost of
completing the associated Work. The Contract Price for any Work Package shall equal:
Project Mark-up includes profit, general and administrative costs, and any costs not specifically
included in the reasonably estimated cost of Work.
Reasonably estimated cost of Work shall equal the sum of the cost components set forth in
items 2 through 9 below.
Costs for Professional Services undertaken in the performance of the Phase 1 Work shall be the
actual direct labor rates multiplied by the number of hours estimated to be worked multiplied by
the Phase 1 Multiplier Rate shown in Exhibit B (Contract Particulars).
Costs for Professional Services undertaken in the performance of the Phase 2 Work by
personnel and entities that meet the definition of FAR Participants shall be the actual direct
labor rates multiplied by the number of hours estimated to be worked multiplied by the Phase 2
Multiplier Rate for FAR Participants.
Costs for Professional Services undertaken in the performance of the Phase 2 Work by
personnel and entities that do not meet the definition of FAR Participants shall be the actual
direct labor rates multiplied by the number of hours estimated to be worked multiplied by the
Phase 2 Multiplier Rate for Non-FAR Participants.
3.1 General
Construction labor costs will be based on the wages and fringe benefits currently in effect for
each estimated hour the Work is performed by all labor employed in the Work and all foremen in
direct charge of the specific operation. “Fringe benefits” are the actual costs paid to, or on behalf
of, workmen by reason of health and welfare benefits, pension fund benefits, or other benefits,
when such amounts are required by prevailing wage laws or by a collective bargaining
agreement or other employment contracts generally applicable to the classes of labor employed
on the Project.
Construction labor cost will also include the following payroll taxes and legally required
insurances:
(a) Social Security Tax
(b) Medicare Tax
4. Material Costs
Costs for Material will be included at fair market value at the time of the estimate. Material costs
will include applicable taxes, loading, unloading, freight charges, and storage for Materials the
Contractor uses in the Work.
Costs for owned or rented Equipment necessary to complete the Work will be included at
established rates given in the Equipment Watch Cost Recovery (formerly Rental Rate Blue
Book), by Equipment Watch, a division of Penton Business Media, Inc. No mark-up will be
applied to Equipment costs.
The Contractor shall perform, if requested by the Department, a buy-rent analysis and the
aggregate rental amounts (exclusive of all installation, maintenance, dismantling, removal,
transportation, and delivery costs) for any one piece of Equipment cannot exceed 80 percent of
the purchase price (at the time it is placed in service) during the rental period of the Equipment
used for this Project. Estimated Equipment costs shall include delivery, installation,
maintenance, consumables (e.g., fuel, oil, lube, tires), dismantling, removal, and transportation,
6. Indirect Costs
Indirect costs will be included at actual estimated costs for bonds, insurance, licenses, permits,
taxes and fees, personnel vehicles, co-located offices, and field offices. No costs that are
covered in other areas will be included in indirect costs. General and administrative costs that
are not specifically attributable to the Project are included in the Project Mark-up and will not be
considered indirect costs.
7. Subcontracted Work
Subject to the Subcontractor Bidding and Selection Plan, costs for subcontracted Work that is
competitively procured will be included at the amount of the selected Subcontractor’s bid.
Costs for subcontracted Work that is not competitively procured will be included in accordance
with this Part C – Basis for Establishing Price. Only one Project Markup will be included,
regardless of the number of tiers.
8. Mobilization
Cost for mobilization will be included at the actual estimated costs for the elements of Work
included in mobilization, but under no circumstances shall the total exceed 2.5 percent of the
Price Proposal for an Early Work Package or the Phase 2 Work.
9. Risk Contingency
Risk contingency cost for those elements of risk that are specifically assigned to the Contractor
will be calculated and included in accordance with PDBC Section 2.6 (Risk Identification, Pricing
and Assignment).
The Department may direct the Contractor to perform revised Work including Extra Work under
force account. The Contractor shall submit a written proposal and estimated costs for the Work,
including the planned Equipment, Materials, labor, and a work schedule.
The Department will pay the Contractor as specified in this Exhibit H as full compensation for
performing the force account Work. The markups included in this Exhibit H shall be all-inclusive
and the Contractor shall not be eligible to receive the Project Mark-up for force account Work.
The Contractor and the Department will document the labor and Equipment used on the force
account Work on a Daily Force Account Record. At the end of each Workday, the Contractor
and the Department will compare and sign the Daily Force Account Record. The Department
will make no force account payment before the Contractor submits an itemized statement of the
costs for the applicable force account Work.
The Department will examine and, if found to be acceptable, approve all rates and costs
submitted by the Contractor.
The Contractor shall provide the following content in itemized statements for all force account
Work:
a. Name, classification, date, daily hours, total hours, rate, and amount for all labor.
b. Designation, dates, daily hours, total hours of actual operation and idle time, Blue Book
rate with reference or category, and amount for each unit of Equipment and the
applicable Blue Book hourly operating cost for each unit of Equipment and invoices for
all rental Equipment. The designation includes the manufacturer’s name or trademark,
model number, and year of manufacture.
c. Quantities of materials and prices.
d. Transportation charges on materials, free on board (F.O.B.) at the Project Site.
e. Cost of workers’ compensation insurance premiums, all applicable insurance premiums,
unemployment insurance contributions, and social security tax and fees or dues required
by a collective bargaining agreement. Express each of these items of cost as a
percentage of payroll, except fees or dues, which should be expressed as a cost per
hour.
f. Documentation of the following:
(1) For surveying or design work in accordance with Part 9 (Professional and
Specialized Work) of this Exhibit H the Contractor shall provide:
i. Documentation for all work performed by the Designer and any Subconsultants
that provided services. Documentation shall consist of records of all Actual
Allowable Costs broken down as direct labor charges, indirect costs (overhead),
non-salary direct costs and facilities capital cost of money. In addition, the
Department will pay a profit of 12 percent of the sum of direct labor costs plus
overhead. The Department will not pay an additional percent markup to the
Contractor on these costs.
ii. “Actual Allowable Costs” are incurred costs based on the cost principles and
procedures set forth in Part 31 of the Federal Acquisition Regulation (Codified at
48 CFR Part 31), the State of Ohio Travel Regulations (Ohio Administrative Code
Rule 126-1-02), and the AASHTO Uniform Audit and Accounting Guide, all as
amended from time to time.
(2) For all surveying, professional, or similar specialized Work not normally part of a
Design-Build contract as set forth in Part 9 (Professional and Specialized Work) of
this Exhibit H, the Contractor shall provide documentation showing payment to a firm
hired by the Contractor.
g. If Materials are taken from Contractor’s stock and original receipted invoices for the
materials and transportation charges do not exist, the Contractor shall provide an
affidavit and certify all of the following:
(1) The Materials were taken from the Contractor’s stock.
(2) The quantity shown was actually used for the force account Work.
(3) The price and transportation costs represent the actual cost to the Contractor.
h. Documentation showing payment to trucking firms and owner-operators. The Contractor
shall submit documentation showing owner-operations status. When the trucking is
subject to prevailing wage, the Contractor shall submit payroll and Equipment usage
records according to Parts 1.a, 1.b, and 1.e (General) of this Exhibit H.
i. The Contractor shall provide “receipted invoices” for all costs substantiated by an
invoice.
If only part of the expenditure represented by an invoice is applicable to force account work, or if
the invoice represents expenditure for more than one item of work, clearly indicate the actual
amount of expenditure applicable to each item of work.
2. Labor
The Department will pay the wages and fringe benefits currently in effect for each hour the Work
is performed by all labor employed in the Work and all foremen in direct charge of the specific
operation. The Department will pay an additional 38 percent markup on these wages and
benefits. “Fringe benefits” are the actual costs paid to, or on behalf of, workmen by reason of
health and welfare benefits, pension fund benefits, or other benefits, when such amounts are
required by prevailing wage laws or by a collective bargaining agreement or other employment
contracts generally applicable to the classes of labor employed on the Project.
The Department will pay the actual itemized cost, without markup, of the following payroll taxes
and legally required insurances:
a. Social Security Tax.
b. Medicare Tax.
c. Ohio Workers’ Compensation Premiums.
d. State and Federal Unemployment Insurance.
e. Longshore and Harborworkers’ Compensation Insurance for work from a barge or ship,
or unloading material from a barge or ship.
The Contractor shall provide itemized statements in addition to the documentation requirements
for all labor including the name, classification, date, daily hours, total hours, rate, and amount. If
any person is paid more than the one rate, a separate listing shall be made for that person for
each rate paid. The Contractor shall provide itemized statements for Ohio Workers’
Compensation insurance premiums, all applicable insurance premiums, State and Federal
Unemployment Insurance contributions, and Social Security Tax and fees or dues required by a
collective bargaining agreement. Express each of these items of cost as a percentage of payroll,
except fees or dues, which shall be expressed as a cost per hour.
Instead of itemizing the cost of Social Security Tax, Ohio Workers’ Compensation, and State
and Federal Unemployment Insurance, the Contractor may elect to receive as compensation for
these payroll taxes and premiums, an amount equal to 22 percent of the paid wages. If the
Contractor pays fringes directly to the worker in lieu of paying into a fringe benefit program, then
the Department will treat these fringe payments as paid wages when calculating the allowed 22
percent compensation.
The Department will pay, without markup, the actual itemized cost of fees and dues paid to
labor unions or to business associations when they are based on payroll hours and required by
a collective bargaining agreement.
The Department will not pay for wages or benefits for personnel connected with the Contractor’s
forces above the classification of foreman that have only general supervisory responsibility for
the force account Work.
If the foreman or timekeeper is employed partly on force account Work and partly on other
Work, the Contractor shall prorate the number of hours between the force and non-force
account Work according to the number of people on each task as shown on payrolls.
The Department will pay the prevailing wage and fringe rates that apply to the Project for the
classifications required for Extra Work. The Contractor shall provide payroll records for pay
rates higher than the prevailing wages and establish that the higher than prevailing rates are
paid for original scope of Work excluding the force account Work (the “Original Contract Work”).
The Department will pay for foremen and time keepers not covered by prevailing wages not
more than the salaried rate they receive when engaged in Original Contract Work.
The Department will pay actual costs for subsistence and travel allowances when such
payments are required by the collective bargaining agreement or other employment contracts
applicable to the classes of labor employed on the Project. The Department will not pay a
percent markup on these costs.
3. Materials
The Department will pay the Contractor’s actual invoice costs, including applicable taxes and
actual freight charges, for Department approved materials the Contractor uses in force account
Work. The Department will pay an additional 15 percent markup on these costs.
Freight or hauling costs charged to the Contractor and not included in unit prices shall be
itemized and supported by invoices. The cost of owned or rented Equipment used to haul
materials to the Project Site is not part of the Materials cost. Such Equipment, when used for
hauling Materials, shall be listed under cost of Equipment.
The Contractor shall provide itemized statements in addition to the documentation requirements
for all Equipment including the quantity and price of each Material and transportation charges
free on board (F.O.B.) at the Project Site. Attach invoices to support the quantities of Materials
used, unit prices paid and transportation charges. If the Contractor uses Materials from the
Contractor’s stock and original receipted invoices for the Materials and transportation charges
do not exist, the Department and the Contractor will agree on a price that represents the actual
cost to the Contractor. Provide an affidavit and certify all of the following:
a. The Materials were taken from the Contractor’s stock.
b. The quantity shown was actually used for the force account Work.
c. The price and transportation costs represent the actual cost to the Contractor.
The Contractor shall not incorporate Materials into the Work without a price agreement.
4. Construction Equipment
a. General
The Department will pay the Contractor’s costs for Equipment the Department deems necessary
to perform the force account Work for the time directed by the Department or until the
Contractor completes the force account Work, whichever happens first. The Department will pay
the Contractor the established rates for Equipment only during the hours that it is operated,
except as otherwise allowed elsewhere in the Contract Documents. The Department will pay for
non-operating hours at the idle Equipment rate as specified in Part 4.c (Hourly Idle Equipment
Rate) of this Exhibit H. The Contractor shall report Equipment hours to the nearest 1/2 hour.
The established Equipment rates in this Exhibit H include compensation for overhead and profit
except as otherwise specified.
The Department will pay for use of Contractor-owned Equipment the Department approves for
force account Work at established rates. The Department will pay the rates, as modified in Part
4.b (Hourly Owned Equipment Rates) of this Exhibit H, given in the Equipment Watch Cost
Recovery (formerly Rental Rate Blue Book), by EquipmentWatch, a division of Penton Business
Media, Inc.
The Contractor shall provide, and the Department will confirm, the manufacturer’s ratings and
manufacturer-approved modifications required to classify Equipment for rental rate
determination. For Equipment with no direct power unit, use a unit of at least the minimum
recommended manufacturer’s rating.
The Department will not pay rental for small tools or Equipment that show a daily rate less than
$5.00 or for unlisted Equipment that has a value of less than $400.
Tool trucks will be allowed for compensation if they are used at the location where force account
Work is performed. Only the tools used from the tool truck will be allowed for compensation.
Tools in the tool truck that are not used in the force account Work will not be compensated. A
tool trailer that remains at the Contractor’s office or yard will not be compensated under force
account Work. Tool trailers that are taken to the location where the force account Work is
performed will be allowed for compensation along with the tools used on the force account Work
that we
Traffic control devices used in Maintenance of Traffic and owned by the Contractor shall be
considered as owned Equipment. Allowed rates for common traffic control devices and concrete
barrier that are not listed in the Blue Book will be as determined by the Department.
The Contractor shall use Department-approved Equipment in good working condition and
providing normal output or production. The Department may reject Equipment not in good
working condition or not properly sized for efficient performance of the Work.
For each piece of Equipment used, whether owned or rented, provide the Department with the
following information:
(1) Manufacturer’s name or trademark.
(2) Equipment type.
(3) Year of manufacture.
(4) Model number.
(5) Type of fuel used.
(6) Horsepower rating.
(7) Attachments required, together with their size or capacity.
(8) All further information necessary to determine the proper rate.
(9) Dates, daily hours, total hours of actual operation and idle time.
(10) Blue Book rate with reference or category.
(11) Amount.
(12) Applicable Blue Book hourly operating cost.
(13) Invoices for all rental Equipment.
The base rate for the machine and attachments represents the major cost of Equipment
ownership, such as depreciation, interest, taxes, insurance, storage, and major repairs. The
hourly operating rate represents the major costs of Equipment operation, such as fuel and oil
lubrication, field repairs, tires, expendable parts, and supplies.
For all Equipment used on force account Work, determine, and have the Department confirm,
the hourly owned Equipment rates as follows:
Where:
• HOER = Hourly owned Equipment rate
• RAF = Regional adjustment factor shown in the Blue Book
• ARA = Age rate adjustment factor shown in the Blue Book
• R = Current Blue Book monthly rate
• HOC = Estimated hourly operating cost shown in the Blue Book
However, compensation for Equipment normally used on a 24 hours per day basis will not
exceed the monthly rate plus adjustments and operating costs.
The rate adjustment factor assigned to any attachment will be the yearly factor as determined
for the base Equipment.
When multiple attachments are included with the rental Equipment, only the attachment having
the highest rental rate will be eligible for payment, provided that the attachment has been
approved by the Department as being necessary to the force account Work.
When a piece of owned Equipment is not listed in the Blue Book, use the rate for similar
Equipment found in the Blue Book or, if no similar Equipment is listed, use 6 percent of the
purchase price as the monthly rate (R) and add the hourly operating rate found in the Blue Book
for similar Equipment of the same horsepower.
For Equipment brought to the Project Site exclusively for force account Work and on the Project
Site for less than a month, multiply the monthly rate (R) by the factor listed in Table H-1 below:
TABLE H-1
Working Hours Factor
The term “Working Hours,” as used in Table H-1, includes only those hours the Equipment is
actually in operation performing force account Work; apply the factor, as determined above, to
these actual working hours only. Calculate compensation for any idle time according to Part 4.c
(Hourly Idle Equipment Rate) of this Exhibit H without application of the factor.
The Department will pay as working Equipment for the entire Workday, Equipment used
intermittently during the Workday. The following criteria qualify for intermittently used
Equipment:
(1) Equipment dedicated to the force account Work exclusively all day and not used on
other Work.
(2) Equipment works before and after the intermittent idle period and its total working time
during the Workday is at least two hours.
Equipment that is captive to the force account Work (i.e. it must remain at the location of the
force account Work), but does not qualify for intermittently used owned Equipment, is paid as
idle Equipment according to Part 4.c (Hourly Idle Equipment Rate) of this Exhibit H for the time it
is not working.
For Equipment that is in operational condition, on the Project Site, and necessary for force
account Work, but is idle, the Department will pay an hourly idle Equipment rate. The procedure
to determine the hourly idle Equipment rate for Contractor owned Equipment is as follows:
Where:
• HIER = Hourly idle Equipment rate.
▪ RAF = Regional adjustment factor shown in the Blue Book.
▪ ARA = Age rate adjustment factor shown in the Blue Book.
▪ R = Current Blue Book monthly rate.
If rented Equipment necessary for force account Work is idle, the Department will pay the
Contractor for the actual invoiced rates prorated for the duration of the idle period. The actual
invoiced rates must be reasonably in line with the Blue Book rates and approved by the
Department. The Department will pay a 15 percent markup for overhead and profit for the actual
invoiced rates during the idle period.
The Department will not pay idle owned Equipment costs for more than eight hours in a 24-hour
day or 40 hours in a week.
The Department may order specific Equipment to the Project Site up to five Days before its
planned usage. If this Equipment is not used for other Work, the Department will pay for it as
idle Equipment until used.
The Department will pay for the cost of idle owned or rented Equipment if the force account
Work is suspended at the Department’s direction. The Department will not pay the cost of idle
Equipment if the force account Work is suspended by the Contractor for the Contractor’s own
reasons.
The Department will only pay for the number of Calendar Days during the existence of a
Department-directed force account Work suspension. The Department will not compensate the
Contractor for days during a Department-instructed suspension of the force account work that
the Department determined were lost to weather.
The Department will only pay for Equipment physically located at the Project Site that was
received to prosecute the scheduled Work during the period of a Department-instructed
suspension of the force account Work.
Compensation for idle Equipment will stop at the completion of the force account Work or at the
end of the suspension of the force account Work.
d. Rented Equipment
The Department will pay a 15 percent markup for overhead and profit for all rented Equipment,
its corresponding Blue Book hourly operating costs, and State and Local sales taxes.
(1) Equipment Rented Solely for Force Account Work
If the Contractor rents or leases Equipment from a third party exclusively for force
account Work, the Department will pay the actual invoiced amount. The actual invoiced
rates must be reasonably in line with the Blue Book and approved by the Department.
The Department will pay a 15 percent markup for overhead and profit for all rented
Equipment paid for by the actual invoices. Add the Blue Book hourly operating cost to
the marked up actual invoiced rates.
(2) Equipment Rented for Original Contract Work, but Used for Force Account Work
If the Contractor uses rented Equipment currently on the Project Site for Original
Contract Work to perform force account Work, then determine the hourly outside-rented
Equipment rate as follows:
The Department will not compensate for rental rates that exceed the Blue Book rates unless
approved in advance of the Work by the Department.
e. Moving of Equipment
The Department will also pay for the time required to move needed Equipment to the location of
the force account Work and to return it to its original location. The Department will pay for
loading and transportation costs instead of moving time if Equipment is moved by means other
than its own power. Moving time back to the original location or loading and transportation costs
will not be allowed if the Equipment is used at the location of the force account Work on contract
items or related Work.
The Department will consider the actual cost of transferring the Equipment to the Project Site
and returning it to the original location as an additional expense and pay for it as specified, for
Equipment moved on the Project Site exclusively for force account Work.
The Department will confirm the original location of the Equipment before the Contractor moves
and uses it for force account Work.
If the Equipment is transported by a common carrier, the allowance is the invoiced amount paid
for the freight plus 15 percent. However, if the Contractor’s forces transport the Equipment, the
allowable compensation will be Blue Book rate of the hauling unit and hourly Blue Book
operating cost plus the driver’s wages and the cost of loading and unloading the Equipment
calculated according to Part 2 (Labor) of this Exhibit H.
5. Foreman’s Transportation
The Department will pay the Blue Book rate for every hour the foreman’s truck is at the location
of the force account Work or moving to or from the Project Site. This rate includes Equipment
cost, fuel and lubricants, overhead, profit, and mobile phone or two-way radios.
6. Subcontract Work
For Work performed by an approved Subcontractor, the Department will pay an amount to cover
administrative costs of 8 percent on the first $10,000 of Work and 5 percent for Work in excess
of $10,000 as provided in Part 2 (Labor) of this Exhibit H through Part 5 (Foreman’s
Transportation) of this Exhibit H. No additional mark-up is allowed for Work of a sub-
subcontractor or trucking services employed by a Subcontractor.
Not Used.
8. Trucking
a. Trucking firms and owner operators not subject to prevailing wage will be paid at the
invoiced cost plus 8 percent on the first $10,000 of trucking and 5 percent for trucking in
excess of $10,000 to cover administrative costs.
b. Trucking that is subject to the prevailing wage law will be compensated according to the
following parts of this Exhibit H: Part 1 (General), Part 2 (Labor), Part 4 (Construction
Equipment), Part 6 (Subcontract Work), and Part 10 (Payment for Force Account Work).
The Contractor shall provide documentation showing payment to trucking firms and owner-operators
and owner-operations status. When the trucking is subject to prevailing wage, the Contractor shall
submit payroll and Equipment usage records according to Part 2 (Labor) of this Exhibit H and Part 4
(Construction Equipment) of this Exhibit H.
Professional and specialized Work will be paid for according to the following:
a. The following Work, when performed by the Designer or its subconsultants, is paid as set
forth in Part 1.f (General) of this Exhibit H.
(1) Design costs.
(2) Surveying costs.
b. The following Work, when performed by a firm other than the Designer or its
subconsultants, is paid at the reasonable and fair market invoiced cost plus a 5 percent
markup. The markup is limited to $10,000 for all the Work performed by the firm.
(1) Specialized Work that is not part of the Original Contract Work and is not normally
subject to prevailing wage.
(2) Installation, periodic maintenance, and removal of traffic control devices under
ODOT C&MS Item 614 performed by a traffic control service or rental company,
provided the workers are not on the Project Site full-time. Maintenance of Traffic
services performed by LEO.
(3) Other professional or specialized Work not contemplated at the time of submittal of a
Work Package Proposal.
The Contractor shall provide documentation showing payment for professional and specialized
Work.
The Contractor shall submit an analysis of estimated cost prepared in accordance with this
Exhibit H for force account Work. Attach an original affidavit to the analysis stating:
“Labor rates shown are the actual rates paid for labor, unit prices for Materials and rates for
owned and rented Equipment have been estimated on the basis they are not in excess of those
charged in the area in which the Work will be performed.”
The Department will process an Estimated Cost of Force Account (ECFA) if the amount of the
force account Work is likely to be greater than $100,000 and is expected to take more than two
weeks to complete. The Department will process an Actual Cost of Force Account (ACFA) to
make any necessary adjustment between the ECFA and the final itemized costs for the force
account Work.
For force account Work estimated to be less than $100,000 and anticipated to require less than
two weeks to perform, the Department will process an Actual Cost of Force Account (ACFA) at
the conclusion of the Work.
The Contractor shall submit biweekly itemized statement of costs prepared from the Daily Force
Account Records to the Department as the Work is being performed. The Department will
process estimates as the force account Work is performed. Payment will only be made upon
receipt of the Contractor’s itemized statement of costs.
Upon conclusion of the Work performed by an ECFA or Work performed by an ACFA the
Contractor shall submit an itemized statement of the actual costs prepared from the Daily Force
Account Record and utilizing the Department’s electronic template titled “Electronic Force
Account.” Submit a compact disk (CD), labeled with the Contractor’s name and the project
number, and a hard copy of the “Electronic Force Account.” The “Electronic Force Account”
template can be downloaded from the following website:
www.dot.state.oh.us/divisions/constructionmgt/admin/pages/default.aspx
The Department may approve an alternative electronic template provided all calculations and
printouts are equivalent to those generated by the “Electronic Force Account” template.
The Contractor shall attach an original affidavit to the hard copy stating:
“The name, classification, total hours worked and rates paid each person listed on the Summary
of Actual Cost are substantiated by actual records of persons employed on the force account
work. All unit prices for Materials and rates for owned and rented Equipment listed on the
Summary of Actual Costs are substantiated by actual records of Materials and Equipment
actually used in performance of the force account Work and the price of any owned Equipment
not previously agreed upon does not exceed prices charged for similar Equipment in the area in
which the Work was performed.”
Daily Force Account Records signed by both the Department and Contractor will govern over
other Department and Contractor records subject to the following:
a. When the Contractor is subject to a Union Contract that requires a minimum number of
paid hours, the compensation will be for the verified contract minimum hours.
In the event the Contractor declines to sign the Daily Force Account Record, the Department’s
records shall govern. Any resulting dispute must be pursued in accordance with PDBC Section
18 (Partnering and Dispute Resolution).
If the Department agrees that it has caused a delay, the Department will pay for the costs
specified in this Exhibit I as allowed by PDBC Section 13 (Time Extension to the Completion
Deadlines and Payment for Excusable Delays), unless these costs have been previously paid
as listed in PDBC Section 12.8.1 (Negotiated Prices) or Exhibit H (Force Account Provisions).
Such payment constitutes full compensation for any and all delay costs.
The Department will make no payment for delays occurring during the period from December 1
to April 30 unless the Contractor’s approved progress schedule depicts Work on the Critical
Path occurring throughout this period.
The Department will not pay for delay costs until the Contractor submits an itemized statement
of those costs. Provide the content specified in Exhibit H (Force Account Provisions), for the
applicable items in this statement and as follows:
a. Proof of cost of superintendent, or other project staff salaries, wages, and payroll taxes
and insurance.
b. Proof of cost of office rent, utilities, land rent, and office supplies.
c. Proof of escalated cost for labor and Material.
d. Proof of Material storage costs.
a. Extended Labor
The Contractor shall compute labor costs during delays as specified in Part 2 (Labor) of
Exhibit H for all non-salaried personnel remaining on the Project as required under
collective bargaining agreements or for other Department-approved reasons.
b. Escalated Labor
To receive payment for escalated labor costs, demonstrate that the Department-caused
delay forced the Work to be performed during a period when labor costs were higher
than planned at the time of Submittal of each Work Package Proposal. Provide adequate
support documentation for the costs, allowances, and benefits specified in Part 2 (Labor)
of Exhibit H. The Department will pay wages and fringes with a 20 percent mark-up to
cover administrative costs.
The Department will pay the Contractor according to Part 4.c (Hourly Idle Equipment
Rate) of Exhibit H for idle Equipment, other than small tools, that must remain on the
Project during the delays. The Department will pay the Contractor’s transportation costs
to remove and return Equipment not required on the Project during the delays. No other
Equipment costs are recoverable as a result of delay.
The Department will pay the Contractor for increased Material costs or material storage
costs due to the delay. Obtain the Department’s approval before storing Materials due to
a delay. Payment will be based upon the accepted quantity of Work performed during
the period for which escalated costs have been approved. The Department will pay
increased Material costs with an 8 percent mark-up to cover administrative costs and
any Material waste inherent to the Work.
e. Field Overhead
The Department will pay field overhead costs for the Contractor or any Subcontractor
which include the cost of supervision, field office and office supplies, and utilities for
which payment is not provided for in Part 2.f (Home Office Overhead) of this Exhibit I,
during a delay period provided all of the following criteria are met:
(1) The Contractor has incurred an excusable, compensable delay that delays the Work
at least 10 Days beyond the original Completion Date. These days are cumulative
throughout the Term.
(2) The delay for which payment of field overhead is sought is due to delays defined in
the following numbered subsections of PDBC Section 13.2.2 (Category 2 Events –
Excusable, Compensable Delays):
• 2. (Delays due to utility interference);
• 3. (Delays due to railroad interference);
• 4. (Delays due to a Department-ordered suspension); and
• 9. (Delays due to the neglect of the Department or its failure to act in a timely
manner).
(3) The delay for which payment of field overhead is sought is due to delays due to
revised Work as specified in PDBC Section 12 (Contract Changes).
The Department will pay the salary and fringes plus a 5 percent markup for the field
personnel included as part of the Contract Price build-up that are on the Project Site
during the delay period.
The Contractor’s or Subcontractor’s field office costs include field office trailers, tool
trailers, office Equipment rental, temporary toilets, and other incidental facilities and
supplies. The Contractor shall compute these costs on a Day basis. Owned trailers are
paid at the Blue Book rate. Rented trailers are paid at the invoiced cost plus a 15 percent
markup. Rented office space, toilets, and office Equipment are allowed a 5 percent
markup. Purchased office supplies are allowed a 5 percent markup.
Office utilities include, but are not limited to, telephone, electric, water, and natural gas.
Compute these costs on a Day basis and allow a 5 percent markup.
The Department will pay the Contractor for home office overhead, unabsorbed home
office overhead, extended home office overhead, and all other overhead costs for which
payment is not provided for in Part e (Field Overhead) of this Exhibit I, including
overhead costs that would otherwise be calculated using the Eichleay formula or some
other apportionment formula, provided all of the following criteria are met:
(1) The Contractor has incurred an excusable, compensable delay that delays the Work
at least 10 Days beyond the original Completion Deadline. These days are
cumulative throughout the Project.
(2) The delay for which payment of home office overhead is sought is only due to delays
defined in the following numbered subsections of PDBC Section 13.2.2 (Category 2
Events – Excusable, Compensable Delays):
• 2. (Delays due to utility interference);
• 3. (Delays due to railroad interference);
• 4. (Delays due to a Department-ordered suspension); and
• 9. (Delays due to the neglect of the Department or its failure to act in a timely
manner).
Any Subcontractor that has approved C-92’s for subcontracted work totaling
$10,000,000 or more is eligible for reimbursement of home office overhead provided the
criteria set forth in Part f, subsections (1) and (2) (Home Office Overhead) of this Exhibit
I are met.
Payment will be made for every eligible day beyond the original Completion Date at the
rate determined by Part f , Sub-part () (Home Office Overhead Daily Rate) of this Exhibit
I.
Payment for eligible days occurring during an unanticipated construction period will be
calculated in accordance with this Part f, Sub-part (ii) (Home Office Overhead Payment
for an Unanticipated Construction Period) of this Exhibit I.
Payment for eligible days occurring during an unanticipated winter period will be
calculated in accordance with this Part f, Sub-part (iii) (Home Office Overhead Payment
for an Unanticipated Winter Period) of this Exhibit I.
Calculate the home office overhead daily rate using the following formula:
Where:
• A = Original Contract Price
• B = Contract duration in Days
• C = 0.02
• Daily HOOP = Home office overhead daily rate
Contract duration term, B, includes every Day from the execution of the Phase 2
Change Order, to the original Contract Completion Date.
Calculate the home office overhead payment for an unanticipated construction period
occurring between May 1 and November 30 using the following formula:
Where:
• D = Sum of all excusable, compensable delays in Days minus the sum (in
Days) of all delays due to following numbered subsections of PDBC Section
13.2.2 (Category 2 Events – Excusable, Compensable Delays):
o 1. (Delays due to Revised Work); and
o 8. (Delays due to acts of the government or political subdivisions other
than the Department).
• Daily HOOP = Daily home office overhead rate.
• CP HOOP = Home office overhead payment for an unanticipated
construction period occurring between May 1 and November 30.
The Contractor shall calculate the payment for home office overhead for an
unanticipated winter period occurring between December 1 and April 30 using the
following formula:
Where:
• D = Sum of all excusable, compensable delays in Days minus the sum (in
Days) of all delays due to following numbered subsections of PDBC Section
13.2.2 (Category 2 Events – Excusable, Compensable Delays):
o 1. (Delays due to Revised Work); and
o 8. (Delays due to acts of the government or political subdivisions other
than the Department).
• E = Sum of all excusable, compensable delays in Days plus the sum of all
excusable, non-compensable delays in Days.
• F = 151 for a non-leap year or 152 for a leap year.
• Daily HOOP = Daily home office overhead rate.
• WP HOOP = Home office overhead payment for an unanticipated winter
period occurring between December 1 and April 30.
Payment for Home Office Overhead for an unanticipated winter period will not be
made when the value of the remaining Work is below the lesser of $500,000.00 or 10
percent of the estimated final Contract Price.
The Contractor shall calculate the total home office overhead payment using the
following formula:
Where:
• CP HOOP = Home office overhead payment for an unanticipated
construction period occurring between May 1 and November 30
• WP HOOP = Home office overhead payment for an unanticipated winter
period occurring between December 1 and April 30
• Total HOOP = Total home office overhead payment
The Department will pay costs for subsistence and travel allowances for labor that must
remain on the Project Site during the delays, when such payments are required by the
collective bargaining agreement or other employment contracts applicable to the classes
of labor employed on the project. Overnight lodging will be reimbursed if the person is at
a location greater than forty-five miles from their residence up to a maximum of $106 per
day. Meals and incidental expenses will be reimbursed up to a maximum of $56 per day.
The Department will not pay a percent markup on these costs.
The provisions in this Exhibit J shall apply to any Contract Items in a Work Package that are to
be compensated under unit prices.
For items in a Work Package with unit prices (if any), the Department will measure the
quantities of Work and calculate payments based on the method of measurement and basis of
payment provisions provided in the ODOT C&MS or KYTC SS. When the following units of
measure are specified, the Department will measure quantities as described below unless
otherwise specified in the Contract Documents. The accuracy of individual pay item Estimate
payments will be one decimal more accurate than the unit of measure denoted for the pay item.
The Department will monitor the quantities of Work and may verify invoice requests based on
the method of measurement and basis of payment provisions provided in these Specifications.
When the following units of measure are specified, the Department will monitor quantities as
described below in Ohio unless otherwise specified in the Contract Documents. In Kentucky
follow the SS.
Lump Sum. Not measured. Describes payment as reimbursement for all resources necessary
to complete the Work. When a complete structure or structural unit is specified as the unit of
measurement, the unit will include all necessary fittings and accessories.
Foot (Meter). Measured parallel to the longitudinal base or foundation upon which items are
placed, or along the longitudinal surface of the item. Measured vertically to the nearest 0.1 foot
(0.01 m), with a minimum vertical measurement of 1 foot (0.10 m), at each unit.
Square Yard or Square Foot (Square Meter). Measured by a two-dimensional area method on
the surface of the item.
Cubic Yard (Cubic Meter). Measured by a three-dimensional volume method. Measure all
“loose material” or material “measured in the vehicle” by the cubic yard (cubic meter). Haul
material “measured in the vehicle” in approved vehicles and measure in the vehicle at the point
of delivery. For this purpose, use approved vehicles of any type or size satisfactory to the
Department, provided the vehicle’s bed is of such type that the actual contents are readily and
accurately determined. Unless all approved vehicles on a job are of uniform capacity, each
approved vehicle must bear a legible identification mark indicating the specific approved
capacity. The Inspector may reject all loads not hauled in such approved vehicles.
Cubic Yard (Cubic Meter) for Asphalt Concrete. Measure as specified in C&MS 401.21.
Acre (Hectare). Measured by a two-dimensional area method on the surface to the nearest 0.1
acre (0.05 ha).
For Work on a tonnage basis, file with the Department receipted freight bills for railroad
shipments and certified weight-bills when Materials are received by any other method, showing
the actual tonnage used. For Work on a volume basis, itemize evidence of the volume used.
Gallon (Liter). Measured by actual item liquid volume. The Department will measure the
following materials by the gallon (liter) at the following temperatures:
Temperatures Items
Measure tank car outage of asphalt material at its destination before any material has been
removed from the tank car according to Supplement 1060.
Convert the net weight of asphalt material shipments to gallons (liters) at the specified pay
temperature according to Supplement 1060.
Convert the gallons (liters) at the measured temperature to gallons (liters) of asphalt material at
the specified pay temperature according to Supplement 1060.
Thousand Board Feet, MBF (Cubic Meter). Measure timber by MBF (cubic meter) actually
incorporated in the structure. Base the measurement on nominal widths, thicknesses, and the
extreme length of each piece.
Standard Manufactured Items. When standard manufactured items are specified such as
fence, wire, plates, rolled shapes, pipe conduit, etc., and these items are identified by size, unit
weight, section dimensions, etc., such identification will be to nominal weights or dimensions set
by the industry.
For Work that is priced using unit priced Contract Items, the Department may increase or
decrease unit priced item quantities and may alter the Work as necessary to complete the
Project. The Department will make appropriate adjustments according to PDBC Section 12.7.2
For unit priced items the term “significant change” is defined as follows:
1. When the character of the Work as altered differs materially in kind or nature from that
involved or included in the Contract Documents; or
2. When the product of the quantity in excess of the estimated quantity of a unit priced
Contract Item and the unit price exceeds $100,000.
After the determination of final quantities for unit priced Contract Items, the Department will
adjust the unit prices for the affected unit priced Contract Item by multiplying the unit price by
the factor obtained from Table J-1.
TABLE J-1
25 1.08 57 1.33
26 to 27 1.09 58 1.35
28 to 29 1.10 59 1.36
30 to 31 1.11 60 1.38
32 to 33 1.12 61 1.39
34 to 35 1.13 62 1.41
36 1.14 63 1.43
37 to 38 1.15 64 1.44
39 1.16 65 1.46
40 to 41 1.17 66 1.49
42 1.18 67 1.51
43 1.19 68 1.53
44 to 45 1.20 69 1.56
46 1.21 70 1.58
47 1.22 71 1.61
48 1.23 72 1.64
49 1.24 73 1.68
50 1.25 74 1.71
51 1.26 75 1.75
52 1.27 76 1.79
53 1.28 77 1.84
54 1.29 78 1.89
55 1.31 79 1.94
When a change does not qualify as a significant change or a quantity underrun, the change is
considered a minor change. The Department will pay for minor changes in the Work at the
applicable unit price for the Contract Item. Table J-1 is not applicable to Lump Sum Contract
Items.
3. Eliminated Items
The Department may partially or completely eliminate Contract Items, or may eliminate portions
of the Work described in the Base Design.
The Department will only make an adjustment to compensate the Contractor for the reasonable
cost incurred in preparation to perform significantly changed Work according to the provisions in
this Exhibit J for significant changes in the character of the Work as defined in Part 2 (Significant
Changes in the Character of the Work (Unit Priced Items)) or Work completely eliminated prior
to the date of the Department’s written order to significantly change or completely eliminate the
Work. The adjustment will be determined according to the provisions in this Exhibit J under the
provisions of Part 4 (Compensation for Altered Quantities) and PDBC Section 12 (Contract
Changes). Such payment will not exceed the price of the Contract Item.
The Department will not seek a savings for maintaining traffic, Mobilization, and construction
layout stakes items for eliminated Contract Items, unless there is a significant change.
If the quantities of unit priced items vary from the quantities in the Contract, the Department will
make payment at the original Contract unit prices for the agreed quantities of Work.
A. If a portion of the Work is eliminated in accordance with Part 3 (Eliminated Items) or the
contract is terminated in accordance with PDBC Section 21 (Termination for
The DBE Performance Plan included with the Offeror’s Proposal submitted in response to the
ITO provided initial percentages for use during Phase 1. An updated DBE Performance Plan
shall be submitted by the Contractor to the Department at the execution of the Contract (Sub-
Phase 1A) and each Change Order for Sub-Phase 1B, Early Work Packages, and Phase 2. The
DBE Performance Plan shall set forth specific information demonstrating how the Contractor will
achieve the DBE goal. By submitting a DBE Performance Plan, the Contractor is affirming that
they will be using the DBE firms identified in the Performance Plan to meet the DBE contract
goal.
DBE AFFIRMATION
The DBT shall ensure the DBE firms being utilized to meet the DBE goal affirm their
participation in the Project prior to submittal of any Work Package Proposal. The contract dollar
amount(s) and/or DBE firm(s) included in the DBT’s DBE Performance Plan must match the
contract dollar amount(s) and/or DBE firm(s) included on the DBE Affirmation Form(s). If the
contract dollar amount(s) and/or DBE firm(s) do not match, the DBT shall utilize the Request to
Terminate/Substitute DBE Form located at
http://Transportation.ohio.gov/Divisions/ODI/SDBE/Pages/Resources.aspx and submit for
review and approval by the Office of Small & Disadvantaged Business Enterprise within five (5)
calendar days of the Work Package Proposal submittal.
In the event a DBE firm fails to confirm the information contained in the DBE Affirmation Form
within five calendar days of Work Package Proposal submittal, the DBT shall submit a Request
to Terminate/Substitute DBE Form, as set forth herein. The Request to Terminate/Substitute
DBE Form shall be submitted within five (5) calendar days after Work Package Proposal
submittal. The DBT shall include as its reason for termination the DBE firm’s failure to provide a
timely affirmation and should include all efforts the DBT made to obtain the affirmation from the
DBE firm and shall attach proof of these efforts, if available. If the DBT intends to replace the
DBE Firm, it shall include the replacement firm’s information on the form. In the event the DBT
is unable to affirm a DBE firm included in its original DBE Performance Plan at Work Package
Proposal submission and it results in a goal shortfall, Good Faith Efforts (GFE’s) must be
submitted by the fifth calendar day after Work Package Proposal submittal. All GFE
documentation submitted for consideration should demonstrate the efforts the DBT made prior
to the time of Work Package Proposal submission to secure sufficient DBE participation on the
project to meet the DBE goal although the DBT was unable to do so. A DBE firm’s failure to
timely confirm information contained in the DBE Affirmation Form will be considered as good
cause to terminate the DBE firm and will also be considered a part of the Contractor’s Good
Faith Efforts in meeting the goal.
In the event that the DBE contract goal established by ODOT is not met, the DBT shall
demonstrate that it made adequate good faith efforts to meet the goal, even though it did not
succeed in obtaining enough DBE participation to do so.
If the DBT does not meet the goal at Work Package Proposal submittal, the DBT shall submit its
Good Faith Efforts (GFE’s) documentation within five (5) calendar days of Work Package
Proposal submittal. Submission of DBE Affirmation(s) with additional participation sufficient to
the meet the DBE contract goal does not cure the DBT’s failure to meet the goal at bid time or
eliminate the DBT’s responsibility of submitting GFE’s within five (5) calendar days of the Work
Package Proposal submittal.
The DBT shall demonstrate its GFE’s by submitting the following information within five (5)
calendar days after the Work Package Proposal submittal:
1. All written quotes received from certified DBE firms;
2. All written (including email) communications between the Contractor and DBE firms;
3. All written solicitations to DBE firms, even if unsuccessful;
4. Copies of each non-DBE quote when a non-DBE was selected over a DBE for work on
the contract; and
5. Phone logs of communications with DBE firms.
The DBT shall utilize the Pre-Bid GFE Template to document their GFE’s. This template and
supporting documentation shall be sent along with any DBE Affirmation Forms within five (5)
calendar days of Work Package Proposal submittal. ODOT has provided Good Faith Efforts
Guidance located at:
http://www.dot.state.oh.us/Divisions/ODI/SDBE/DBE%20Goal%20Forms/Contractors%20Good
%20Faith%20Efforts%20Guidelines.pdf.
All other Contractors shall submit documentation of GFE’s if notified that the information is
required in order for ODOT to complete its bid assessment. Contractors shall have five (5)
calendar days from the date of notification to submit all required GFE documentation.
Notification will be by phone or email.
ODOT shall utilize the guidance set forth in 49 CFR §26.53 Appendix A in determining whether
the DBT has made adequate good faith efforts to meet the goal.
ADMINISTRATIVE RECONSIDERATION
ODOT will review the GFE documentation and issue a written determination on whether
adequate GFE’s have been demonstrated prior to contract award. If ODOT determines that the
DBT has failed to demonstrate adequate GFE’s to meet the goal, the DBT will have an
opportunity for administrative reconsideration prior to the contract being awarded.
As part of this reconsideration, the DBT may provide written documentation or argument
concerning the issue of whether it met the goal or made adequate good faith efforts to do so.
Such written documentation or argument must be provided to ODOT, attention to the Office of
Chief Legal Counsel, 1980 West Broad Street, MS 1500, Columbus, Ohio 43223 (with copy to
the Office of Contract Sales, MS 4110), within two (2) business days of ODOT’s written
determination that GFE’s were not adequately demonstrated. The DBT may also include in their
written documentation a request for an in person meeting to discuss the issue of whether it met
the goal or made adequate good faith efforts to do so. ODOT’s Office of Chief Legal Counsel
will respond to the Contractor within five (5) business days of receiving written documentation or
holding the in-person meeting.
ODOT will send the DBT a written decision on reconsideration explaining the basis for finding
that the DBT did or did not meet the goal or make adequate good faith efforts to do so. The
result of the reconsideration process is not administratively appealable to the United States
Department of Transportation.
By submitting a DBE Performance Plan, the DBT is committing to use the DBE firms identified
in the plan. The DBT shall utilize the specific DBEs listed in the DBE Performance Plan to
perform the Work and supply the Materials for which each is listed unless the DBT obtains
written consent as provided in this paragraph. In order to request termination or substitution of a
DBE firm, the DBT shall utilize the Request to Terminate/Substitute DBE Form located at
http://Transportation.ohio.gov/Divisions/ODI/SDBE/Pages/Resources.aspx.
This termination/replacement procedure applies only to DBE firms or the amount of work being
utilized to meet the goal.
Without ODOT’s written consent to terminate/replace a DBE firm being utilized to meet the goal,
the Contractor shall not be entitled to any payment for DBE listed work or material unless it is
performed or supplied by the listed DBE.
GOOD CAUSE
ODOT may provide written consent to terminate a DBE only if it agrees, for reasons stated in a
concurrence document, that the DBT has good cause to terminate the DBE firm.
For purposes of this paragraph, good cause to terminate a DBE includes the following
circumstances:
1. The listed DBE firm fails or refuses to provide the required DBE Affirmation Form or to
execute a written contract;
2. The listed DBE firm fails or refuses to perform the work of its subcontract in a manner
consistent with normal industry standards. Provided, however, that good cause does not
exist if the failure or refusal of the DBE firm to perform its work on the subcontract results
from the bad faith or discriminatory action of the awarded contractor;
3. The listed DBE firm fails or refuses to meet the awarded contractor's reasonable,
nondiscriminatory bond requirements;
4. The listed DBE firm becomes bankrupt, insolvent, or exhibits credit unworthiness;
5. The listed DBE firm is ineligible to work on public works projects because of suspension
and debarment proceedings pursuant 2 CFR Parts 180, 215 and 1200 or applicable
state law;
6. ODOT has determined that the listed DBE firm is not a responsible contractor;
7. The listed DBE firm voluntarily withdraws from the project and provides to you written
notice of its withdrawal;
8. The listed DBE is ineligible to receive DBE credit for the type of work required;
9. A DBE owner dies or becomes disabled with the result that the listed DBE contractor is
unable to complete its work on the contract; and
10. Other documented good cause that ODOT determines compels the termination of the
DBE firm. Provided, that good cause does not exist if the awarded contractor seeks to
terminate a DBE it relied upon to obtain the contract so that the awarded contractor can
self-perform the work for which the DBE contractor was engaged or so that the awarded
contractor can substitute another DBE or non-DBE contractor after contract award.
REPLACEMENT
When a DBE firm is terminated or fails to complete its work on the contract for any reason the
DBT must make GFEs to find another DBE firm to replace the original DBE. These GFEs shall
be directed at finding another DBE to perform at least the same amount of work under the
contract as the DBE that was terminated, to the extent needed to meet the contract goal. The
GFEs shall be documented by the DBT. If ODOT requests documentation under this provision,
the DBT shall submit the documentation within seven (7) calendar days, which may be
extended for an additional seven (7) calendar days if necessary at the request of the contractor,
and ODOT shall provide a written determination to the contractor stating whether GFEs have
been demonstrated.
ADDITION
In the event additional DBE participation is required beyond the originally approved DBE
Performance Plan for each Phase, the DBT shall utilize the DBE Affirmation Form located at
http://Transportation.ohio.gov/Divisions/ODI/SDBE/Pages/Resources.aspx.The executed DBE
Affirmation Form will be utilized as written confirmation from each DBE firm that it is participating
in the contract in the kind and amount of work on the project and shall be submitted with the
monthly DBE Performance Plan.
Before transmitting to ODOT its request to terminate and/or substitute a DBE firm, the DBT
must give notice in writing to the DBE firm, with a copy to ODOT, of its intent to request to
terminate and/or substitute, and the reason(s) for the request.
The DBT must give the DBE five calendar days to respond to the notice, advising ODOT and
the DBT of the reasons, if any, why it objects to the proposed termination of its subcontract and
why ODOT should not approve the DBT's action. If required in a particular case as a matter of
public necessity (e.g., safety), ODOT may provide a response period shorter than five days.
The DBT shall make available upon request a copy of all DBE subcontracts. The DBT shall
ensure that all subcontracts or agreements with DBEs require that the subcontract and all lower
tier subcontractors be performed in accordance with this Exhibit L.
Approval of a DBE Performance Plan does not ensure approval of C-92 Requests to Sublet nor
does approval of a DBE Performance Plan indicate that the DBE goal has been met. ODOT will
monitor goal attainment throughout the life of the project. It is the responsibility of the DBT to
advise ODOT of any changes to the DBE Performance plan throughout the life of the project.
The DBE goal of a project is stated as a percentage of the contract. In the event the contract
amount increases or decreases, the actual dollar amount of the DBE goal for the project may
increase or decrease accordingly.
POST-BID
Failure by the DBT to carry out the requirements of this Exhibit L, including the submission of
adequate good faith efforts to meet the goal for a project, is a material breach of the contract
and may result in the issuance of sanctions as follows:
• 1st Tier: Letter of Reprimand.
• 2nd Tier: Damages equivalent to the DBE shortfall.
• 3rd Tier: If a pattern of paying damages persists or the DBT has falsified,
misrepresented or withheld information, ODOT can pursue other remedies available by
law including suspension, revocation, and/or debarment.
Factors to be considered in issuing sanctions may include, but are not limited to the following:
• The magnitude and the type of offense.
• The degree of the DBT’s culpability.
• Any steps taken to rectify.
• The DBT’s record of performance on other projects including, but not limited to:
o Annual DBE participation;
The DBT may meet a Disadvantaged Business Enterprise (DBE) contract goal using DBE
trucking firms, but only when such firms perform a commercially useful function (CUF). The DBT
must not include a DBE trucking firm on its DBE Performance Plan if it is aware that the firm will
not be performing a CUF. Even if a DBE trucking firm will be performing a CUF, the dollar
amount of trucking services it provides may not be fully countable towards the DBE contract
goal. When including a DBE trucking firm that will be performing a CUF on its DBE Performance
Plan, the DBT must only include the portion of the dollar amount of which it is aware will count
towards the DBE contract goal.
The DBT is responsible for performing any Good Faith Efforts (GFEs) that may be necessary if
it includes, in good faith, a DBE trucking firm on its DBE Performance Plan and the DBT
becomes aware (or is made aware) that the DBE trucking firm is not performing a CUF or that
the trucking services provided by the DBE trucking firm are not countable to the extent
previously believed.
When a DBE trucking firm performs a CUF, the dollar amount of trucking services it provides
counts towards the DBE contract goal only in instances meeting at least one of the following
criteria:
• It provides trucking services using trucks it owns, properly insures, and operates using
drivers it employs (i.e., that are not 1099 “employees”/independent contractors).
It provides trucking services with trucks that are leased on a long-term basis (i.e., one year or
more) from a non-DBE truck leasing company, properly insured, and operated by drivers it
employs.
The dollar amount of trucking services provided using leased trucks will only be countable in
cases where all the following circumstances apply:
• The DBE trucking firm’s lease indicates that the DBE trucking firm has exclusive use of
and control over the leased truck(s), including responsibility for maintenance and
insurance. This does not preclude the leased truck(s) from working for others during the
term of the lease with the DBE trucking firm’s consent, as long as the lease gives the
DBE trucking firm absolute priority for use of the leased truck(s).
• The leased trucks display the DBE trucking firm’s name and federal identification
number.
• The leased truck(s), when onsite, carry a copy of the lease agreement.
In order to ensure the DBT is monitoring DBE trucking/hauling operations on projects with
federal funding, the DBT must complete monthly DBE Trucking Disclosure Affidavits
(“Affidavits”). An Affidavit must be completed for all DBE trucking/hauling operations, regardless
of whether the work is counting towards a DBE contract goal. The Affidavit will be completed by
the DBT and emailed to the designated Compliance Officer (CO) by the 10th of each month.
This information will be used to affirm DBE and non-DBE trucking utilized by each DBE firm
performing those duties during the previous month.
ODOT will monitor trucking with the following requirements for all ODOT-let projects:
1. The DBT will be required to provide a master list of trucks for all anticipated DBE
trucking firms to the CO within seven days of executing the changed order for Phase 2 of
the contract.
Note: If no DBE trucking is anticipated on a project, the DBT will complete the “No
Anticipated DBE Trucking Affidavit” and submit it to the CO within seven days of the
execution of the change order for Phase 2 of the contract. If DBE trucking/hauling does
occur, the DBT must notify the CO within seven days of the DBE trucking activity. The
DBT will then complete the monthly Affidavits as required below.
2. The CO will email the Affidavit to the DBT, along with the Pre-Construction
documentation. The DBT will be required to complete the Affidavit disclosing the DBE
trucking operations during the previous month. The Prime will return the Affidavit by the
10th day of each month (if the 10th day falls on a weekend, the deadline moves to the
following Monday).
3. Trucking will continue to be monitored at project sites by construction field staff and the
COs.
Failure by the DBT to follow the DBE Trucking Disclosure Affidavit requirements may result in
the issuance of sanctions as follows:
• 1st Level Occurrence: The Administrator for the Office of Civil Rights Compliance, under
the Division of Opportunity, Diversity & Inclusion (ODI), will issue a Letter of Reprimand
to the DBT (applies if there is a failure to submit the Affidavits and/or the Affidavits are
not submitted timely; if the DBT completes the No Anticipated DBE Trucking Affidavit,
utilizes DBE trucking and does not notify the CO within seven days of the activity).
• 2nd Level Occurrence: ODI may withhold an estimate in the amount due to the DBE
trucking firm(s) that the Affidavit was not submitted for (applies if there is a failure to
submit the Affidavits and/or the Affidavits are not submitted timely; if the DBT completes
the No Anticipated DBE Trucking Affidavit, utilizes DBE trucking and does not notify the
CO within seven days of the activity).
• 3rd Level Occurrence: If a pattern of not submitting the Affidavit(s) persists or the DBT
has falsified, misrepresented or withheld information, ODOT can pursue other remedies
available by law including suspension, revocation, and/or debarment.
Factors to be considered in issuing sanctions may include, but are not limited to the following:
• The DBT’s past project practices;
• The magnitude and the type of offense;
• The degree of the DBT’s culpability;
• Any steps taken to rectify;
• The DBT’s record of performance on other projects; and
• The number of times the DBT has been previously sanctioned by ODOT.
The DBE MSV Directory is available within the Ohio Unified DBE Directory at
http://www.dot.state.oh.us/Divisions/ODI/SDBE/Pages/DBE-Directory.aspx (select MSV only).
The DBT may meet a Disadvantaged Business Enterprise (DBE) contract goal using DBE
MSVs. The dollar amount of materials or supplies purchased from a DBE MSV will usually not
be fully countable towards the DBE contract goal. When including a DBE MSV on its DBE
Performance Plan, the DBT must only include the portion of the dollar amount of which it is
aware will count towards the DBE contract goal.
The DBT is responsible for performing any Good Faith Efforts (GFEs) that may be necessary if
it includes, in good faith, a DBE MSV on its DBE Performance Plan and the DBT becomes
aware (or is made aware) that the materials or supplies purchased from the DBE MSV are not
countable to the extent previously believed.
The DBT must seek information from DBE MSVs to allow it to be sufficiently informed about the
nature of the transaction and which scenario listed below applies. The DBT must document this
information on the DBE Affirmation Form:
https://www.transportation.ohio.gov/wps/portal/gov/odot/programs/business-economic-
opportunity/dbe/dbe-resources/pn-013-affirmation)
o Is certified in the correct (wholesale or retail) NAICS code(s) for the item(s);
o Is certified in the correct MSV descriptor(s) for the item(s), if located in Ohio;
o Is certified in the correct trucking NAICS code(s); and
o Does not drop-ship the item(s).
• The purchase price of materials and supplies obtained from a DBE MSV but not in
accordance with any of the above scenarios is not countable, but the fees or
commissions charged by the DBE MSV are countable if the DBE MSV:
o Is certified in NAICS code 425120 Wholesale Trade Agents and Brokers; and
o Convincingly explains how the Selected/Awarded DBT benefits by transacting
business with it rather than directly with the non-DBE vendor from which the DBE
MSV is re-selling.
All credit toward DBE goals is conditional. Actual credit will be determined based upon invoices,
receipts, and/or transportation documents/bills of lading, which must be submitted to ODOT as
they are received throughout the course of the project.
The required contract provisions for federal-aid construction contracts (contained in Form
FHWA 1273 revised July 2022 and located here) are hereby incorporated by reference as if
rewritten herein. Form FHWA-1273 shall be physically incorporated in all contracts,
subcontracts and lower-tier subcontracts (excluding purchase orders, rental agreements and
other agreement for supplies or services related to a construction contract). The Contractor shall
be responsible for ensuring that the FHWA-1273 is physically incorporated into all lower-tier
subcontracts.
Failure by the Contractor to include the provisions of FHWA-1273 in their contract or in their
lower-tier subcontracts may result in the issuance of sanctions as follows:
• 1st Tier: Letter of Reprimand.
• 2nd Tier: Damages equivalent to the daily liquidated damages amount found in C&MS
Section 108.07 for each incident of non-compliance.
• 3rd Tier: If a pattern of paying damages persists or the Contractor has falsified,
misrepresented or withheld information, ODOT can pursue other remedies available by
law including suspension, revocation, and/or debarment.
Factors to be considered in issuing sanctions may include, but are not limited to the following:
• The magnitude and the type of offense;
• The degree of the Contractor’s culpability;
• Any steps taken to rectify;
• The Contractor’s record of performance on other projects; and
• The number of times the Contractor has been previously sanctioned by ODOT.
Utilization goals applicable to the project, expressed in percentages, for minority and female
participation for each construction craft can be found in the Technical Requirements. These
goals are based on 2020 census data and represent the area, per craft, minority and female
availability pool.
• Census Availability Percentages for minority and female workers by craft per county
(applicable to project):
o http://www.dot.state.oh.us/Divisions/ContractAdmin/Contracts/Construction/CensusF
orAllCounties.xlsx.
o http://www.dot.state.oh.us/Divisions/ContractAdmin/Contracts/Construction/CensusF
orAllCounties.pdf.
• Statewide utilization obligations/ goals for minority workers by county (applicable to
each project).
• Statewide utilization obligation/ goal for female workers is 6.9 percent and applies the
same for each county.
• Source: US Department of Labor’s, Office of Federal Contract Compliance Programs,
Technical Assistance Guide for Construction Contractors (pp. 126 – 127).
o Construction Contractors Technical Assistance Guide (dol.gov).
SMSA Counties:
OH Butler.
SMSA Counties:
OH Champaign; OH Clark.
The New Hire Definition for the purposes of on-the-job training and workforce utilization
is as follows:
An individual who has a break in service (not on an employer’s payroll) for a period of 12
months or longer and the person affected is not a salaried employee but belongs to a union
craft. Individuals compensated for training or incidental work which does not cause a break in
unemployment compensation, i.e., paid by voucher check or petty cash, are considered new
hires if the individual’s break in service is 12 months or longer.
The time frame for a new hire shall be associated with the first project worked for the DBT
regardless of whether it is public or private. When reporting a newly hired employee, the DBT
shall identify that employee as a new hire on that specific project only. Subsequent work,
barring a break in service of 12 months or more, would not qualify the employee as a new hire
for the DBT.
Compliance: The DBT's compliance shall be based on the implementation of affirmative action
obligations required by the specifications set forth in 23 CFR Part 230, and its good faith efforts
to meet these obligations. The hours of minority and female employment and training must be
substantially uniform throughout the length of the contract, and in each trade, and the DBT shall
make a good faith effort to employ minorities and females on its project. The transfer of minority
or female employees or trainees from Contractor to Contractor or from project to project for the
sole purpose of meeting the affirmative action obligations shall be a violation of the contract and
regulations in 23 CFR Part 230. The good faith efforts put forth by the DBT will be measured
against the total work hours performed.
Under FHWA, ODOT is the authority tasked with ensuring that the DBT adheres to the
aforementioned regulations. In addition to complying with the Required Contract Provisions, the
DBT shall provide immediate written notification to ODOT when referral practices of the union(s)
with which the DBT has a collective bargaining agreement impede the company's efforts to
meet its equal opportunity obligations.
Requirements for affirmative action obligations governing OFCCP contract compliance reviews
are those listed in the Federal Register for the Economic Area.
The Ohio Department of Development (ODOD), Minority Business Division, is responsible for
ensuring state contractors implement and adhere to the State of Ohio’s affirmative action
program pursuant to Ohio Administrative Code (OAC) 123: Chapters 123:2-3-01 through 123:2-
3-07. Specifically, this unit’s responsibilities includes the issuance of certificates of compliance
under ORC 9.47 and 153.08, conducting project site visits, and compliance reviews (desk
audits) to ensure contractors utilize minorities and women in the construction trades, and
maintain a working environment free of discrimination, harassment, and intimidation. The ODOD
may perform contract compliance reviews on contractors involved with state or state assisted
projects. Requirements for affirmative action obligations governing ODOD contract compliance
reviews are those listed in OAC 123:2-3-02, for the Metropolitan Statistical Area in which a
project is located.
The DBT and all subcontractors regardless on the number of employees or the state
contract amount are required to submit monthly utilization reports (Input Form 29) to the
Ohio Department of Development covering the contractor’s total workforce within the
state of Ohio (private sector and public sector projects). The reports must be filed
electronically by the 10th of each month, beginning with the contract award and
continuing until the DBT or subcontractor completes performance of the contract, as set
forth in OAC 123:2-9-01.
I-29 monthly reports must be submitted via the Ohio Business Gateway portal:
https://ohio.gov/wps/portal/gov/site/business/resources/ohio-business-gateway / Ohio
Business Gateway | Ohio.gov | Official Website of the State of Ohio.
I-29 reports are used by ODOT to create monthly utilization work hour reports to monitor
adherence to on-the-job training requirements and workforce diversity requirements. The DBT
and all subcontractors shall provide monthly utilization work hour reports for the DBT's or
subcontractor's total workforce within the state of Ohio to the compliance officer of the
contracting agency (ODOT). The DBT's or subcontractor's failure to submit a monthly utilization
work hour report shall be a basis for invoking any of the sanctions set forth in rule 123:2-7-01 of
the Ohio Administrative Code.
ODOT will monitor the progress toward meeting these goals throughout the life of the project.
The totality of the project workforce hours (including the various trades utilized) must be met
and complied with by the DBT and all subcontractors. ODOT will monitor compliance utilizing an
agreed upon process that meets the following requirements:
1) Present quarterly reports showing the percentage of female and minority workers hired
by the DBT and Subcontractors on the project;
2) If female and/or minority workforce goals at not being met, the DBT must demonstrate
Good Faith Efforts were made to meet the goal. Good Faith Efforts must be submitted
within 30 days of Substantial Completion. for approval.
3) The Department will determine whether the Good Faith Efforts are acceptable within 10
days of receiving the checklist from the DBT and will inform the DBT of the decision.
The DBT shall adhere to all requirements of the OJT Program as set forth in the most recent
version of the ODOT On the Job Training Program Plan located at the link below, and
incorporated in its entirety herein by reference.
http://www.dot.state.oh.us/Divisions/ODI/SDBE/OJTDocs/OJT%20Program%20Plan.pdf
The Department monitors the payments made by the Contractor and Subcontractors for
compliance with this Exhibit Q, ORC 4113.61, Section 8.10 (Prompt Payment) of the PDBC and,
for federally funded contracts, 49 CFR 26.29. To facilitate this monitoring, the Department
requires the Contractor to report their remitted payments to specified Subcontractors, and
Subcontractors to report their remitted payments to specified lower-tier Subcontractors, as
follows.
• The Contractor must report remitted payments to subcontractors (DBE and non-DBE),
suppliers (DBE only, unless the supplier sublets to a lower-tier DBE firm), and trucking
firms (DBE only, unless the trucking firm sublets to a lower-tier DBE firm) (collectively,
Subcontractors).
The Contractor must report remitted payments to Subcontractors within 10 calendar days of
each payment it receives from the Department. Each Subcontractor must report remitted
payments to Lower-tier Subcontractors within 10 calendar days of receipt of each payment
received from the Contractor. Payers must report return of retainage (and/or other amounts
withheld) within 10 calendar days of release to the payee.
The payer (whether Prime Contractor or Subcontractor) must report the following information:
1.) The name of the payee;
2.) The dollar amount of the payment to the payee;
3.) The date the payee was paid; and
4.) The retainage or other amount withheld (if any), and the reason for the withholding (if
other than for retainage).
Payment reporting(s) must be both gross (i.e., the amount owed without factoring in retainage
and/or other amounts being withheld) and net. The payer must report its return of retainage
(and/or other amounts withheld) in separate, standalone payment entries (i.e., without being
commingled with a payment for work performed or materials supplied).
Payees must verify each payment reported by a payer within 10 calendar days of the payment
being reported by the payer. This verification includes whether the payment was received, and if
so, whether it was as expected or not.
The Contractor must include the above prompt payment and reporting requirements in all
Subcontractor (DBE and non-DBE), supplier (DBE only, unless the supplier sublets to a lower-
tier DBE firm), and trucking firm (DBE only, unless the trucking firm sublets to a lower-tier DBE
firm) agreements that it enters into and further require that all such subcontractors include the
same prompt payment and reporting obligation in their lower-tier Subcontractor (DBE and non-
DBE), supplier (DBE only), and trucking firm (DBE only) agreements.
Note: Payments made to non-DBE suppliers and trucking firms need not be reported. However,
as required in C&MS 107.21 and in accordance with ORC 4113.61, contractors are required to
make payment to each subcontractor and supplier within 10 calendar days after receipt of
payment from the Department for work performed or materials delivered or incorporated into the
project—this requirement includes non-DBE suppliers and trucking firms. If a contractor does
not comply with this requirement, penalties in accordance with ORC 4113.61 may apply.
Suggested language for the federal-aid Contractor to include in its subcontractor agreements:
As a Subcontractor, supplier* and/or trucking firm*, you (the payee) must verify receipt of
payments from the Contractor. You must verify each payment within 10 calendar days of the
payment being reported by the Contractor. This verification includes whether the payment
was received, and if so, whether it was as expected or not. Furthermore, you must report
payments to your lower-tier Subcontractors (DBE and non-DBE), suppliers (DBE only), and
trucking firms (DBE only). The payment data reported must include any retainage (and/or
other amounts) withheld and any previously withheld amounts released. You must report
payments within 10 calendar days of receipt of each payment received from the Contractor.
You must also report return of retainage (and/or other amounts withheld) within 10 calendar
days of release to the payee. Your payees must then verify each payment reported by you
(the payer) within 10 calendar days of the payment being reported. Your lower-tier
Subcontractor (DBE and non-DBE), supplier (DBE only), and trucking firm (DBE only) sub
agreements must include this prompt payment and reporting obligation.
Suggested language for the subcontractor to include in its lower-tier sub agreements:
As a lower-tier subcontractor (DBE or non-DBE), supplier (except non-DBE) and/or trucking
firm (except non-DBE), you (the payee) must verify receipt of payments from the payer (i.e.,
the maker of this sub agreement with you). Payees must verify each payment reported by
the payer within 10 days of the payment being reported. This verification includes whether
the payment was received, and if so, whether it was as expected or not.
PROMPT PAYMENT
Failure by the Contractor to follow Prompt Payment requirements may result in the issuance of
sanctions listed below. The Contractor may also receive the below sanctions if any of their
Subcontractors fail to follow Prompt Payment requirements.
• 1st Level Occurrence: The Department will issue a Letter of Reprimand to the Contractor
(applies if there is a failure to report payments and/or failure to timely pay
subcontractor(s)).
• 2nd Level Occurrence: The Department may withhold an estimate in the amount due to
the subcontractor(s) that was not reported or paid (applies if there is a failure to report
payments and/or failure to timely pay subcontractor(s)).
o If a Contractor receives a 1st Level Occurrence reprimand for a project, all
subsequent Prompt Payment violations on that project (same or different
subcontractor) may result in withholding. In this situation, no 1st Level Occurrence
reprimand letters will be sent.
• 3rd Level Occurrence: The Contractor may be required to pay interest in the amount of
18 percent per annum of the payment due, beginning on the eleventh day following the
receipt of payment from the owner and ending on the date of full payment of the
payment due plus interest (applies if a pattern of not paying subcontractor(s) persists or
the Contractor has falsified, misrepresented or withheld information, ODOT can pursue
other remedies available by law including suspension, revocation and/or debarment).
Factors to be considered in issuing sanctions may include, but are not limited to the following:
• The Contractor’s past project practices;
• The magnitude and the type of offense;
• The degree of the Contractor’s culpability;
• Any steps taken to rectify;
• The Contractor’s record of performance on other projects; and
• The number of times the Contractor has been previously sanctioned by ODOT.
RETURN OF RETAINAGE
Failure by the Contractor to follow Return of Retainage requirements may result in the issuance of
sanctions listed below. The Contractor may also receive the below sanctions if any of their
Subcontractors fail to follow Return of Retainage requirements.
• 1st Level Occurrence: The Department will issue a Letter of Reprimand to the Contractor
(applies if there is a failure to report retainage being held and/or failure to timely return
retainage).
• 2nd Level Occurrence: The Department may withhold an estimate in the amount of
retainage due to the subcontractor(s) (applies if there is a failure to report retainage
being held and/or failure to timely return retainage).
Factors to be considered in issuing sanctions may include, but are not limited to the following:
• The Contractor’s past project practices;
• The magnitude and the type of offense;
• The degree of the Contractor’s culpability;
• Any steps taken to rectify;
• The Contractor’s record of performance on other projects; and
• The number of times the Contractor has been previously sanctioned by ODOT.
http://www.dot.state.oh.us/Divisions/ConstructionMgt/Pages/Partnering.aspx.
B. Initial Partnering Session
Every attempt shall be made to hold an Initial Partnering Session prior to beginning the Work
and separately from the Preconstruction Meeting. This session shall be no later than one month
after the Preconstruction Meeting. With reference to the applicable provisions of the Technical
Requirements, identify and invite all Stakeholders necessary to make the Project successful
including utility companies, other transportation entities (i.e., railroads), community leaders, all
Project participants including Subcontractors. The Parties shall develop the Partnering agenda
with the Department and facilitator before holding the Initial Partnering Session.
During the Initial Partnering Session the Parties will collaborate to:
1. Develop Partnering teams consisting of Department and Contractor senior personnel
and Project personnel.
2. Identify and develop a consensus on Project Goals consistent with the contractual
obligations, including specific goals concerning safety, quality, schedule, and budget.
3. Decide on how the teams will measure progress on Project Goals.
4. Identify any potential risks to the project’s success, mitigation strategies and an
implementation plan for appropriate strategies.
5. Define key issues, project concerns, joint expectations, roles of key partnership leaders,
lines of decision making authority, and share relevant information to help determine the
scope of the Partnering efforts.
6. Identify any opportunities for Project enhancement, enhancement strategies, and a
specific action plan for implementing strategies.
7. Develop a communication protocol to enhance communication on the Project.
8. Develop an issue identification and resolution process that identifies and attempts to
resolve issues at the level closest to the Work. The issue identification and resolution
process will develop all the necessary steps for issue elevation as contemplated under
Section 18.2.4 (Step 1: Mitigation and On-Site Determination) of the PDBC.
C. Partnering Update Sessions
Hold quarterly Partnering update sessions, unless the frequency is otherwise determined by the
Parties, to maintain open communication and evaluate the Partnering relationship on the
Project. Identify Partnering successes and possible areas of improvement. Identify and invite all
stakeholders necessary to make the session successful including utility companies, other
transportation entities (i.e., railroads), community leaders, all project participants including
subcontractors.
D. Partnering Monitoring
Monitor the progress of the Partnering relationship based on the goals decided during the Initial
Partnering Session. On-line surveys of project participants will be used to monitor goals
progress and help identify issues as they arise. The Contractor shall complete the survey prior
to every Partnering Update Session and determine with the Department and facilitator whether
more frequent evaluations are necessary. The on-line surveys will be consistent with the
Department’s Partnering Project Rating Form which is located on the Division of Construction
Management’s Partnering website:
http://www.dot.state.oh.us/Divisions/ConstructionMgt/Pages/Partnering.aspx.
E. Compensation
1. Submission for Compensation. The facilitator shall submit to the Contractor actual
invoice costs.
2. Facilitator Compensation. After review and verification by the Contractor and
Department of the facilitator’s submission for compensation, the Contractor shall pay the
facilitator the fees earned.
3. Contractor Reimbursement. The Department and the Contractor shall bear the costs and
expenses of the facilitator and venue equally.
The facilitator chosen by the Department and the Contractor shall be compensated at a
maximum rate of $3,500 for the Initial Partnering Session. The facilitator shall be compensated
at a maximum rate of $1,500 for the Partnering Update Sessions.
The maximum session rates above shall be considered full compensation for venue cost, on-
site time, travel expenses, transportation, lodging, and incidentals, or portion thereof that the
facilitator is at an authorized meeting.
F. Basis of Payment
The Department will furnish the following item with an amount in the Proposal:
The fixed amount shown in the Proposal is included in the Total Bid Amount. This fixed amount
is 50 percent of the Department’s estimate of the total cost of all Partnering Update Sessions
and facilitator expenses
The payments due will be deducted from the item. If the Department’s costs of the Facilitated
Partnering item exceed the fixed amount, the Department will continue to pay its share of the
actual invoice costs of the item by processing a change order.
The Department will not pay a percent mark-up on these costs. The Department will make
partial payments according to C&MS 109.09. This item is exempt from the non-performance
table found in C&MS 104.02.
A “Non-Chargeable Lane Closure” is: (i) a Lane Closure for which the minimum number of lanes
and movements to be maintained during the Construction Work are observed, as described in
Section E (Minimum Number of Lanes and Allowable Lane and Roadway Closures) below, or
(ii) a Lane Closure required due to Incidents or Emergencies that are not attributable to, could
not have been avoided by or are not exacerbated by the actions of the Contractor, and only to
the extent necessary to remediate the Incident or Emergency. No Payment deductions /
disincentives shall be assessed for a Non-Chargeable Lane Closure.
A “Chargeable Lane Closure” is any Lane Closure that is not a Non-Chargeable Lane Closure,
regardless of whether the Department has approved the Lane Closure.
Except for Lane Closures required due to Incidents or Emergencies, advance written notice of
any Lane Closure must be provided to the Department as provided in the Contract Documents.
Except for Lane Closures required due to Incidents or Emergencies, all Lane Closures shall be
pursuant to a TCP submitted to the Department for approval 10 Days in advance of the Lane
Closure.
Lane Closures shall comply with the approved Traffic Management Plan and an approved TCP.
No Lane Closure will be permitted unless the Contractor can demonstrate that the Lane Closure
will provide clear benefit to the progress of the Work. When simultaneous requests for traffic
control are received from the Contractor, adjacent projects, and/or Government Entities, the
Department will give priority to the closure request submitted first. For Lane Closures on a non-
Department controlled facility, the Contractor shall obtain approval from the applicable
Government Entity in addition to approval from the Department. The Contractor shall coordinate
Lane Closures that may affect crossing Department facilities with appropriate Department
Project staff, as needed, to ensure that no conflicts occur.
The Contractor shall consider the safety of workers and the traveling public as the primary factor
when determining the appropriate time to implement a Lane Closure.
The Contractor shall be assessed a payment disincentive as designated in Table S-1 (Payment
Disincentives for Unauthorized Lane Use Closures) for each unit of time a Critical Lane/Ramp is
closed by the Contractor’s action while not otherwise permitted by the Contract Documents. The
payment disincentive will be for any Lane Closures caused by the Contractor during times and
locations not specifically permitted by the Contract Documents.
Unauthorized Lane Use Payment disincentives shall be assessed for (i) Full Roadway Closures,
or (ii) Lane Closures that result in less than the minimum number of lanes that must be
maintained as described in Section D (Lane Value Disincentives) and that occur during a
Holiday, a Special Event, or the Peak Period. For purposes of this Exhibit S, a “Full Roadway
Closure” means a Lane Closure that has no lanes or shoulders available to traffic in one or both
directions of travel. The disincentives for Unauthorized Lane Use Closures are set forth below in
Table S-1 (Payment Disincentives for Unauthorized Lane Use Closures) for the applicable
number of lanes that are closed below the minimum number of lanes required to be kept open
set forth in Section E (Minimum Number of Lanes and Allowable Lane and Roadway Closures).
TABLE S-1: PAYMENT DISINCENTIVES FOR UNAUTHORIZED LANE USE CLOSURES
Full Roadway Lane Closure resulting in less than
Closure minimum number of Lanes
The Contractor shall be assessed disincentive as designated in Table S-2 (Lane Value Contract
Table) below for each unit of time the described Critical Lane/Ramp is restricted from full use by
the traveling public within the restricted time period. The payment disincentives will be assessed
for all restrictions of Critical Work defined as having the designated sections open to
unrestricted traffic as shown in the table, or the entire Project if not otherwise listed.
Unrestricted traffic is defined as all traffic lanes being available for use with specified striping
and safety features in place.
The disincentives for Lane Value Closures are set forth below in in Table S-2 (Lane Value
Contract Table) for the applicable number of lanes that are closed below the minimum number
of lanes required to be kept open as set forth in Section E (Minimum Number of Lanes and
Allowable Lane and Roadway Closures) of this Exhibit S.
The minimum number of lanes and movements to be maintained after issuance of Construction
NTP are listed below. [Insert minimum requirements].
F. Crossing Streets
G. Holidays
The following are “Holidays” for the purpose of this Exhibit S. The Department has the right,
without liability, to lengthen, shorten, or otherwise modify these Holidays as actual, or expected,
traffic conditions may warrant.
• New Year’s Eve and New Year’s Day (12:00pm on December 31 through 10:00pm on
January 1).
• Easter Holiday Weekend (12:00pm on Friday through 10:00pm on Sunday).
• Memorial Day Weekend (12:00pm on Friday through 10:00pm on Monday).
• Independence Day (12:00pm on July 3 through 12:00pm on July 5).
• Labor Day Weekend (12:00pm on Friday through 10:00pm on Monday).
• Thanksgiving Holiday (12:00pm on Wednesday through 10:00pm on Sunday).
• Christmas Day (12:00pm on December 24 through 10:00pm on December 25).
• Total Solar Eclipse per ODOT Traffic Engineering Manual Section 642-6.
• Major events (to be defined in the Phase 2 Change Order).
5Definitions of the peak period during which during which Unauthorized Lane Use payment deductions
shall apply and the off-peak period(s) during which Lane Value payment deductions shall apply will be
based upon impacts to traffic determined in accordance with the findings of the conceptual MOT Plan.
Phase 1 Work. The schedule shall incorporate past feedback from Department
and include recommended Milestones and Completion Deadlines no later than
the specified Contract Completion Time.
iv. The Contractor shall provide a draft Phase 1 Baseline Schedule within 80 Days
of the Department’s acceptance of the Interim Schedule. The draft Phase 1
Baseline Schedule shall include detailed activities and Milestones for the entirety
of the Phase 1 Work and shall include a summary of the major activities, phases,
and Milestones of the Phase 2 work.
2. Design Phase:
i. For the Interim, Phase 1, and Phase 2 Baseline Schedules, the design phase
shall be a Level 5 schedule per Section 1.4.1.B.1.v (Schedule Levels) of this
Exhibit T.
ii. The schedule shall include all phase submissions according to the scope of work,
along with all applicable review times.
3. Construction Phase:
i. For the Interim Baseline Schedule, construction activities outside of Sub-Phase
1A Work shall show Level 3 activities, per Section 1.4.1.B.1.iii (Schedule Levels)
of this Exhibit T, summarizing major elements and Buildable Units.
ii. For the Interim Baseline Schedule, any construction activities following Sub-
Phase 1B NTP and/or Early Work Packages NTP shall be detailed to Level 4
activities and comply with Section 1.4.1.E (Setup and Format for Interim, Phase
1, and Phase 2 Baseline Schedules) below.
iii. For the Phase 1 Baseline Schedule, all construction activities prior to Sub-Phase
1B NTP and/or Early Work Packages NTP and where there are no Released for
Construction (RFC) plans shall be detailed to Level 4 activities and comply with
Section 1.4.1.E (Setup and Format for Interim, Phase 1, and Phase 2 Baseline
Schedules) below.
iv. For the Phase 1 Baseline Schedule, all construction activities after Early Work
Packages NTP shall be detailed to Level 5 activities and comply with Section
1.4.1.E (Setup and Format for Interim, Phase 1, and Phase 2 Baseline
Schedules) below.
v. For the Phase 2 Baseline Schedule, all construction activities where there are no
RFC plans shall be detailed to Level 4 and comply with Section 1.4.1.E (Setup
and Format for Interim, Phase 1, and Phase 2 Baseline Schedules) below.
D. Interim, Phase 1, and Phase 2 Baseline Schedule Workflow:
1. Interim Baseline:
i. The Interim Baseline Schedule shall include the design phase as indicated in
Section 1.4.1.C.2 (Design Phase).
ii. Construction Phase work shall be included as indicated in Section 1.4.1.C.3
(Construction Phase).
iii. Revisions to the Interim Baseline Schedule will not be permitted after the
Department’s acceptance that affect the activity ID’s, activity descriptions,
relationships, or durations.
iv. Following the Department’s acceptance, the Interim Baseline Schedule shall be
updated as per Section 1.5 (Monthly Progress Update Schedules) with actual
progress up to the point that the Phase 1 Baseline is accepted.
v. The activities in the Interim Baseline Schedule shall correlate directly with the
cost loaded schedule per PDBC Section 11.1.2 (Phase 1 Estimates and
Payments) and PDBC Section 11.1.3 (Compensation for the Sub-Phase 1A
Work) from which Progress Payments will be based (for Sub-Phase 1A activities
only) until the Phase 1 Baseline is accepted by the Department.
vi. Time impacts or weather impacts shall be applied to the Phase 1 Baseline
Schedule per Sections 1.6 (Buildable Unit Phase Submission Schedules) and 1.7
(Revision and Delay Schedules), once accepted, until after the Phase 2 Baseline
is accepted.
2. Phase 1 Baseline Schedule:
i. The Phase 1 Baseline Schedule shall be developed according to Sections
1.4.1.C.2 (Design Phase) and 1.4.1.C.3 (Construction Phase).
ii. The Phase 1 Baseline shall include the Interim Baseline Schedule as accepted
by the Department and shall be a continuation of the logic and plan developed in
the interim phase.
iii. Any changes made to the Interim Baseline Schedule and included in the Phase 1
Baseline Schedule will be grounds for immediate rejection.
iv. The Phase 1 Baseline Schedule shall not include any impacts or updates known
at the time of submittal. Any/all impacts are to be strictly contained within the
Interim Schedule until the Baseline Schedule is accepted by the Department in
its entirety.
v. Upon acceptance of the Phase 1 Baseline Schedule, all accepted updates
applied to the Interim Schedule shall be incorporated into the first Phase 1
Schedule Update.
vi. Upon acceptance of the Phase 1 Baseline, any/all known impacts shall be
incorporated into the schedule and the use of the Interim Schedule shall be
discontinued.
vii. The Phase 1 Baseline Schedule shall include a summary of the major activities,
phases, and Milestones of the Phase 2 Work.
viii. The activities in the Phase 1 Baseline Schedule shall correlate directly with the
cost loaded schedule per PDBC Section 11.2.4 (Estimates and Payments) from
which Progress Payments will be based (for Phase 1 Construction Work activities
only) until the Phase 2 Baseline is accepted by the Department.
ix. The activities in Phase 1 Baseline Schedule for Sub-Phase 1A and Sub-Phase
1B direct costs per PDBC Section 11.1.2 (Phase 1 Estimates and Payments),
Contractor shall provide a cash flow curve of expected progress payments over
the performance period. Plot curve using costs assigned to activities in the
Baseline Schedule. Contractor to update the curve with actuals from the
approved bi-monthly invoice payment and forecast progress payments and
submit bi-monthly to the Department per PDBC Section 11.1 (Compensation for
Phase 1 Work).
x. Contractor shall submit progress curves with the Bi-Monthly Progress update.
Show with the curves the cumulative scheduled percent complete of each phase,
time-scaled in calendar days from NTP to Contract completion. Derive schedule,
actual, and forecast progress from cash flow curve. Update progress curves with
each bi-monthly update of the current Baseline Schedule.
xi. Four Week look ahead bar chart schedule.
1. Contractor shall submit a weekly manpower/construction report and progress
schedule listing activities completed and in progress for the previous week
and the activities schedule for the succeeding two weeks that is
produced/generated from the current Baseline Schedule. The four week look
ahead bar chart schedule shall include all activities scheduled including:
activity ID, description, start and finish, total float, original duration, remaining
duration, percent complete, responsible party performing the work and
pertinent remarks as to activity status.
3. Phase 2 Baseline Schedule:
i. The Phase 2 Baseline Schedule shall be developed according to Section
1.4.1.C.2 (Design Phase) and Section 1.4.1.C.3 (Construction Phase).
ii. The Phase 2 Baseline shall include the Phase 1 Baseline accepted by the
Department and shall be a continuation of the logic and plan developed in the
Phase 1 Baseline Schedule.
iii. Any changes made to the Phase 1 Baseline Schedule and included in the Phase
2 Baseline Schedule will be grounds for immediate rejection.
iv. The Phase 2 Baseline Schedule shall not include any impacts or updates known
at the time of submission. Any/all impacts are to be strictly contained within the
Phase 1 Schedule until the Phase 2 Baseline Schedule is accepted by the
Department.
v. Upon acceptance by the Department of the Phase 2 Baseline Schedule, all
accepted updates applied to the Phase 1 Schedule shall be incorporated into the
first Phase 2 Schedule Update.
vi. Upon acceptance by the Department of the Phase 2 Baseline Schedule, any/all
known impacts shall be incorporated into the schedule and the use of the Phase
1 Schedule shall be discontinued.
vii. The Phase 2 Baseline Schedule shall correlate directly with the cost loaded
schedule per PDBC Section 11.2.4 (Estimates and Payments) from which
Progress Payments will be based.
viii. Contractor shall provide Monthly Progress update Schedules based upon the
Phase 2 Baseline Schedule through the end of the Completion of the Contract.
ix. Four Week look ahead bar chart schedule.
1. Contractor shall submit a weekly manpower/construction report and progress
schedule listing activities completed and in progress for the previous week
and the activities schedule for the succeeding two weeks that is
produced/generated from the current Baseline Schedule. The four week look
ahead bar chart schedule shall include all activities scheduled including:
activity ID, description, start and finish, total float, original duration, remaining
duration, percent complete, responsible party performing the work and
pertinent remarks as to activity status.
E. Setup and Format for Interim, Phase 1, and Phase 2 Baseline Schedules:
1. General Requirements:
i. The Contractor shall be responsible for assuring all Work, including all Work
performed by Subcontractors, is included in the schedule.
ii. The Contractor shall be responsible for assuring that all work sequences are
logical and that the schedule indicates a coordinated plan.
iii. Show the order and interdependence of activities, with the use of appropriate
activity relationships, and the sequence for accomplishing the Work.
iv. Where Level 4 detail is required (see Section 1.4.1.B.1.iv (Schedule Levels)),
describe Buildable Units of the Project in enough detail to provide a general
overall duration and sequence of the Buildable Unit. Provide logic indicating
required interdependencies with other Buildable Units or other required work
such as, but not limited to, utility work.
v. Where Level 5 detail is required (see Section 1.3.B.1.v (Schedule Levels)), all
Level 4 elements shall be broken down into measurable activities which can be
identified and tracked by the Department.
vi. The Contractor shall provide for and coordinate independent utility work, and/or
work provided “by others” into the schedule in such a way as to minimize rework,
minimize additional protection of previously installed Work, and in an effort to
mitigate delays.
vii. The schedule shall include activities, regardless of responsibility, that directly or
indirectly relate to or have influence over planning and executing the Work in
strict accordance with the Contract Documents, and shall include all design and
preconstruction activities, procurement, Contractor’s submittals and their
forecasted approval dates.
viii. The Contractor shall be responsible for planning the design and construction of
the Project and must consider the Work to be performed, the Contract tie, the
resources available, vendors, Subcontractors, external constraints, and other
factors affecting the successful completion of the Work.
ix. The Contractor shall not be entitled to establish a Claim if the Department
disallows Contractor from finishing early.
x. The Contractor shall involve and coordinate with all Subconsultants,
Subcontractors, third parties, stakeholders, and Material suppliers in the
development and updating of schedules.
xi. Review, acceptance, or approval of schedules by Department shall not waive any
Contract requirements and shall not relieve the Contractor of any obligation or
responsibility for submitting complete and accurate information.
xii. Failure by the Contractor to include any element of Work required for
performance of the Contract shall not excuse the Contractor from completing all
Work within the Contract Completion Time.
xiii. Acceptance by the Department shall not relieve the Contractor of any of its
responsibilities for the accuracy or feasibility of the schedule.
xiv. Omissions and errors shall be corrected as described in Section 1.6 (Buildable
Unit Phase Submission Schedules) of this Exhibit T and will not entitle the
Contractor to an extension of the Contract Completion Time.
2. General Settings:
i. Calculate the Critical Path as “longest path.”
ii. The schedule may only be calculated using retained logic.
iii. Show open ends as non-critical.
iv. Total Float shall be calculated as finish Float.
v. Ignore relationships to and from other projects.
vi. Use “Duration” as the activity percent complete type.
3. Calendars:
i. All calendars shall be Project level calendars, not global or resource calendars.
ii. Calendar names should include the ODOT project number and a describing
function (i.e. YY-##### - five day w/ holidays and weather, YY-##### - seven day
cure, YY-##### - five day asphalt w/ weather).
iii. At a minimum, calendars should be established for Department reviews,
standard work week, cure/settlement periods, milestones, and any items with
temperature restrictions as per the specifications.
iv. Seasonal (winter) and environmental shutdown periods shall be shown using
non-working calendars.
v. Weather and Seasonal Conditions shall be entered into all calendars containing
physical work as non-work days per month as per Table T-1 (Weather and
Seasonal Conditions Table). Anticipated Days lost due to weather shall be
randomly distributed throughout each calendar containing physical work and
should not be tightly grouped or concentrated on particular days within each
week.
vi. All Project Milestones shall be on a seven day/week calendar with no non-work
days.
vii. All review periods for Department shall be included on a designated calendar of
five days/week and shall include typical government holidays.
viii. Anticipated weather and/or shutdown periods shall not be included for any days
past the contract completion date. In the event the contract completion date is
amended to a later date, weather days will be granted on a day for day basis
pending an Accepted Weather Delay Analysis according to Section 1.7 (Revision
and Delay Schedules).
6. Milestones:
i. Start Project: The Contractor shall include as the first Milestone in the schedule,
a Milestone named “Start Project”. The date used for this Milestone is the date
the Sub-Phase 1A NTP is issued by the Department and shall be constrained to
Start On said date.
ii. End Project Milestone: The Contractor shall include as the last activity in the
project schedule, a Milestone named “End Project”. The date used for this
milestone is considered the project completion date and shall be constrained to
Finish On or Before said date.
iii. Start Phase Milestone: The Contractor shall include as the first activity for a
project phase, an activity named "start Phase X", where "X" identifies the phase
of work.
iv. Start Buildable Unit Milestone: The Contractor shall include as the first activity
for a Buildable Unit, an activity named "start BU X", where "X" identifies the
Buildable Unit.
v. End Phase Milestone: The Contractor shall include as the last activity in a
project phase, an activity named "end Phase X" where "X" identifies the phase
of Work, and shall be tied as the predecessor to the Start of the next plan phase
Milestone.
vi. End Buildable Unit Milestone: The Contractor shall include as the last activity in
a Buildable Unit, an activity named "end BU X" where "X" identifies the
Buildable Unit.
vii. The Contractor may include additional Milestones but, as a minimum, shall
include all contractual Milestones. Milestones added by the Contractor, but that
are not contractual Milestones may be tied via activity logic to other activities but
cannot be constrained.
7. Activities:
i. Level 4 Activities shall be included in sufficient detail to represent the contract
scope of work and provide for logical sequencing of major work elements of Work
packages with Buildable Units and demonstrate a logical, reasonable, workable
plan to complete the work on or before the contract completion date.
ii. Level 5 Activities shall be included in sufficient and traceable detail to indicate the
plan for constructing the major work elements within the Buildable Unit. The
activities shall comply with the scope, specifications, and any/all other contract
requirements required to construct the project.
iii. Activity Identification (ID). Assign each activity a unique identification number.
The Contractor shall propose a schedule activity ID nomenclature prior to the
completion of the CPM Baseline. The proposed activity ID nomenclature, at a
minimum, shall reflect the Location, area or segment of the project, the Buildable
Unit, the Work Element, the roadway associated with schedule activity, the
discipline performing the Work, and a unique identifier. The activity ID may
contain additional information but is not to exceed 20 characters in total length.
The activity ID should include decimal places to distinguish the differences in
Nomenclature. Once accepted, the activity ID shall be used for the duration of
the Project.
▪ Example:
• Location.Area. Buildable Unit. Work Element. Roadway. Discipline.
Unique Identifier
• K.1.MS.144.75.BR.15
o K = Kentucky
o 1 = Area 1
o MS = Main Span
o 144 = Block (Contractor Proposed Identifier)
o 75 = Interstate 75
o BR = Bridge Discipline performing the work
o 15 = Unique Identifier
iv. Location identifiers align with the progress payment for activities to roll up to the
location. The Location identify allows pay estimates to meet funding split
requirements between Ohio and Kentucky. The location identifiers are the
following:
1. O = Ohio
2. K = Kentucky
3. C = Companion Bridge
4. E = Existing Brent Spence Bridge
v. Activity Description. Each activity shall have a narrative description consisting of
a verb or work function (e.g.; form, pour, excavate) and an object (e.g.; slab,
footing, underdrain).
vi. Assign a planned duration in Working Days for each activity.
vii. Assign an appropriate project calendar to each activity in the schedule.
viii. Include activities for submittals, Working Drawings, Shop Drawing preparation,
Material procurement and fabrication, delivery of Materials, plant, and
Equipment, long lead items and other similar activities.
ix. Include review activities by the Department with a duration of not less than 10
Working Days on a calendar containing typical government holidays.
x. Do not exceed a duration of 20 Working Days for any construction activity except
as follows:
1. Level 4 activities.
2. Settlement Periods.
3. Long Lead Items.
4. Fabrication Items.
5. Shop drawing preparation.
extension of time until the Phase 1 Baseline Schedule has been “Accepted” or
“Accepted as noted” by the Department.
vii. Contractor shall provide a cost loaded Schedule in the Sub-Phase 1B Proposal.
The Schedule will be used to negotiate various components of the Contract and
will be used as a basis for developing a detailed Phase 2 Baseline Schedule
during the Sub-Phase 1B Work.
3. Phase 2 Baseline Schedule Review:
i. Provide a Phase 2 Baseline Schedule with the Phase 2 Proposal for the
Department’s review and acceptance. The Phase 2 Baseline Schedule shall
correlate directly with the cost loaded schedule from which progress payments
will be based per PDBC Section 11.2.4 (Estimates and Payments).
ii. The Department will review and respond to the Phase 2 Baseline Schedule
Submittal within twenty-one (21) Working Days (excepting holidays).
iii. The Contractor shall schedule a meeting to review the Phase 2 Baseline
Schedule Submittal no later than five Working Days after Department’s receipt of
the Phase 2 Baseline Schedule Submittal. This meeting will serve as the
Contractor’s meeting to review, explain, and discuss the Contractor’s Baseline
Schedule with the Department. The Department reserves the right to invite any
representatives deemed necessary for this meeting. Additional meetings may be
held between Department, Contractor, Contractor Scheduler, and all major
Subcontractors and Suppliers to resolve any conflicts between Contractor’s
Baseline Project Schedule and the intent of the Contract.
iv. Department will review and make comments on the Contractor’s Phase 2
Baseline Schedule. Comments made by Department on Contractor’s schedule,
during review, will not relieve the Contractor from compliance with the
requirements of the Contract Documents. To the extent that there are any
conflicts between the accepted Phase 1 Baseline Schedule and the requirements
of the Contract Documents, the Contract Documents shall govern.
v. The Contractor’s Scheduler, and all Major Subcontractors and Suppliers shall be
required to participate in all meetings necessary to reach mutual agreement and
the Department’s acceptance of the Contractor’s Phase 2 Baseline Schedule.
vi. The Department will Accept, Accept as noted, or reject in writing Contractor’s
Submittal within twenty-one (21) Working Days (excepting holidays).
vii. If the Phase 2 Baseline Schedule is “Accepted as noted”, the Contractor shall
make the necessary revisions and resubmit the revised schedule within seven
Days. Revisions to the Phase 2 Baseline Schedule beyond those requested by
the Department as a part of the “Accepted as Noted” status will be grounds for
immediate rejection.
viii. If the Phase 2 Baseline Schedule is “rejected”, the Department will indicate in
writing all portions of the schedule that are not in compliance with the contract
requirements. The Contractor and the Contractor’s Schedule Representative
shall attend a meeting with within five (5) Working Days of the Department’s
Notice. The purpose of this meeting is to resolve all issues with the baseline
schedule. At this meeting the Contractor shall provide clarification and all
requested information necessary for the Department to “Accept” the baseline
schedule.
ix. Upon the Contractor’s successful development of the Phase 2 Baseline
Schedule, the schedule will be accepted by the Department. The Department’s
acceptance is solely acknowledgement that the schedule conforms to the
requirements of this Exhibit T and other requirements of the Contract
Documents. However, acceptance by the Department does not relieve the
Contractor from subsequently correcting errors and omissions, Float
sequestering logic/duration or any other misrepresentation that may have been
included in the approved schedule.
which the schedule was submitted shall be grounds for withholding payment with
respect to Estimates.
4. Added work/activities, revisions made to logic, descriptions, calendars or any
adjustments that may manipulate the schedule calculations will result in an
immediate rejection of the schedule.
5. The Department will not process payments associated with Estimates until the
Monthly Progress Update Schedule has been received for the previous period.
6. The Level 4 information shall remain in the schedule until the Level 5 data is
“Accepted” at which time it may be dissolved from the schedule.
7. The Level 5 data shall be constructed according to the applicable requirements of
Section 1.4 (Interim, Phase 1, and Phase 2 Baseline Schedule Requirements).
D. Submission Requirements:
1. Buildable Unit Phase Submission Deadlines:
i. The Phase submission shall be submitted along with the 100% design review
plans. The 100% design review plans will not be accepted by the Department
without inclusion of the Buildable Unit Schedule submission.
ii. Submit per Section 1.6.D.2 (General Requirements).
2. General Requirements:
i. Submit all schedules within the time frames specified.
ii. Provide an electronic .xer or .xml file prepared in Primavera P6.
iii. Provide an electronic .pdf print out of the full schedule, displaying the Gantt
Chart, Activity ID, Activity Description, Original Duration, Start Date, Finish Date,
and Total Float.
3. Provide a written schedule narrative in .pdf format describing the following:
i. Current schedule interim Milestone Deadlines and Completion Deadlines.
ii. A general description of the Critical Path.
iii. Changes or shifts in the Critical Path and the reason for these changes or shifts.
iv. Overall project status (ahead, on, or behind schedule).
v. Current delays.
vi. Anticipated delays.
vi. Name the .xer or .xml file as per Table T-2 (Schedule Filename Convention).
E. Buildable Unit Phase Submission Review:
1. The Department will review the schedule within ten (10) Working Days (excepting
holidays) beginning on the first business day after the Contractor’s submission.
2. Upon “Acceptance” of the Buildable Unit Phase Submission, any all update or impact
data shall be transferred to the “Accepted” Phase Submission Schedule and
submitted to the Department within five (5) Working Days.
activities that are proposed to be added to the existing schedule. The fragnet shall
identify the predecessors to the new activities and demonstrate the impacts to
successor activities. Alternatively, the fragnet may indicate a sequence of activities
that have already happened.
3. Revision Schedule: The Work may require, the Department may request, and/or the
Contractor may make revisions to the CPM schedule in order to align the schedule to
the physical work in the field and to maintain the predictive nature of the schedule as
established in the baseline schedule. Addition of new activities or new calendars or
changes to existing activities, calendars or logic constitute a revision. The revision
shall incorporate all actualized activities up to the date of the revision. For revisions
involving extra work requested by the Department, no time extensions will be granted
unless justified in a revision schedule including said work. Any revisions which add or
remove activities from the schedule shall be tracked and be submitted with a
narrative stating the reason for the addition or deletion of activities. The Department
shall review and “approve” or “reject” the revisions. No cost may be added or
removed from the schedule, which affects the overall contract value unless
accompanied by an approved change order. If activities are added or removed from
the CPM, the Contractor may redistribute cost from like activities to account for cost
on the newly added or subtracted schedule activities.
B. Reasons for Revisions:
1. The Contractor shall revise the schedule to correct out-of-sequence logic errors that
impact the critical path.
2. A revision schedule must be compiled in order to justify any time extension related to
extra work.
3. The Contractor may elect to revise the schedule in order to reflect actual/intended
prosecution of the work or as per any part of Section 1.7.B.5.(i-v) (Reasons for
Revisions) below.
4. Department or their Representative may request a schedule revision when the
current schedule does not accurately reflect the current prosecution of the work in
order to align the schedule to actual field operations.
5. Department or their Representative may request a schedule revision when the
current schedule no longer serves as a predictive tool to plan the course of the
project due to:
i. Additional or non-performed work.
ii. Deviations from the schedule by the contractor’s operations.
iii. Progress has accelerated or decelerated.
iv. There is a general deviation in the planned activity dates as compared to
commonly held project knowledge regarding the project’s progress.
v. Accepted phasing adjustments.
C. Revision Schedule Preparation:
1. The basis of any revision or delay schedule shall be the most recently accepted
Monthly Progress Update Schedule.
2. Based on the most recently accepted Monthly Progress Update Schedule, revise the
schedule to provide a predictive tool reflecting the planned course of the project to
achieve the completion of the project by the current contract completion.
3. All revisions shall comply with applicable sections of Section 1.4 (Interim, Phase 1,
and Phase 2 Baseline Schedule Requirements).
D. Delay Schedule Preparation:
1. Determine project progress prior to circumstance(s) necessitating the time impact
analysis. The previous accepted monthly update schedule, updated to the date of the
circumstance(s) alleging to have caused delay, shall be used to display the prior
progress of the project. This schedule is referred to as the Un-impacted Schedule.
2. In a copy of the Un-impacted Schedule, prepare a new Project activity code for the
fragmentary network (fragnet).
3. Prepare a fragnet depicting the circumstance that is believed to have delayed the
project within the new activity code.
4. Insert the fragnet into the schedule logic:
i. The first activity of the fragnet shall be the successor to the last activity that was
completed prior to the alleged delay.
ii. The last activity of the fragnet shall be the predecessor to the first activity that
could not commence due to the alleged delay.
5. Run the schedule calculations and determine the finish date. This schedule is
referred to as the Impacted Schedule.
6. Compare the impacted Schedule finish date with the un-impacted Schedule finish
date in order to determine the duration of any warranted time extension.
E. Submission Requirements:
1. Revision Schedule Submission Deadlines.
i. Revision schedules shall be submitted with a Monthly Progress Update, or within
five (5) Working Days of “acceptance” of a progress update.
ii. In the event discrepancies are discovered in the Monthly Progress Update, said
discrepancies shall be resolved prior to the submission of the Revision schedule
or shall be resolved in both the Monthly Update AND the Revision if submitted
simultaneously.
iii. Revision schedules resulting from extra work believed to have an effect on the
critical path shall be submitted with the cost proposal for the extra work.
iv. Revision schedules shall be separated from Buildable Unit Phase Submissions.
v. Delay Schedule Submission Deadlines.
vi. Delay schedule submissions shall occur within five (5) Working Days of the
alleged delay event.
2. General Requirements:
i. Submit all schedules within the time frames specified.
ii. Revisions shall be based on the latest accepted Monthly Progress Update. The
Revision Schedule shall be submitted with the latest “accepted” Monthly
Progress Update in which it was based on.
iii. Provide an electronic .xer or .xml file prepared in Primavera P6 for both the
Revision schedule as well as the latest “accepted” Monthly Update Schedule.
iv. Provide an electronic .pdf print out of the full schedule, displaying the gantt chart,
activity ID, activity description, original duration, start date, finish date, and Total
Float.
v. Provide a written schedule narrative in .pdf format describing the following:
1. Current schedule interim Milestone Deadlines and Completion Deadlines.
2. A general description of the Critical Path.
3. The specific reason(s) for the revision or delay.
4. Changes or shifts in the critical path and the reason for these changes or
shifts.
5. Overall project status (ahead, on, or behind schedule).
6. Current delays.
7. Anticipated delays.
vii. Name the .xer or .xml file as per Table T-2 (Schedule Filename Convention).
F. Revision/Delay Schedule Review:
1. Department or their Representative will review the schedule within ten (10) Working
days (excepting holidays) beginning on the first business day after the contractor’s
submission.
2. If Department or their Representative does not provide written notification regarding
the disposition of the revision schedule within ten (10) Working Days, the submission
will be considered Accepted.
3. For revision schedules that are “Accepted as noted”, the Contractor shall make the
necessary revisions and resubmit the revised schedule within five (5) Working Days.
Revisions to the revision schedule beyond those requested by ODOT or their
Representative as a part of the “Accepted as Noted” status will be grounds for
immediate rejection.
4. For revision schedules that are “rejected”, ODOT or their Representative shall
indicate in writing all portions of the schedule that are not in compliance with the
contract requirements. ODOT or their Representative shall conduct a mandatory
meeting with the Contractor and the Contractor’s Schedule Representative within five
(5) Working Days of ODOT or their Representative’s written notice. The purpose of
this meeting is to resolve all issues with the revision schedule. At this meeting the
Contractor shall provide clarification and all requested information necessary for
ODOT or their Representative to “Accept” the revision schedule.
5. Acceptance of the revision schedule does not revise the Contract Documents. The
revision schedule shall be “Accepted” or “Accepted as noted” by ODOT or their
Representative prior to ODOT or their Representative evaluating any contractor
claims associated with time impacts.
6. Upon acceptance, the revision schedule shall be the basis for evaluations replacing
the original baseline logic.
1.10 Float
Use of float suppression techniques, such as; preferential sequencing (arranging critical path
through activities more susceptible to Department caused delay), lag logic restraints, zero total
or free float constraints, extending activity times, or imposing constraint dates other than as
required by the contract, shall be cause for rejection of the project schedule or its updates.
A. Definitions of Float: Total Float is the length of time along a given network path that the
actual start and finish of activity(s) can be delayed without delaying the project
completion date. Project Float is the length of time between the End Project Milestone
and the Contract Completion Deadline.
B. Ownership of Float: Float available in the schedule, at any time shall not be considered
for the exclusive use of either Department or the Contractor. During the course of
contract execution, any float generated due to the efficiencies of either party is not for
the sole use of the party generating the float; rather it is a shared commodity to be
reasonably used by either party for project issues. Efficiencies gained as a result of
favorable weather within a calendar month, where the number of days of normally
anticipated weather is less than expected, will also contribute to the Project Float. A
schedule showing work completing in less time than the contract time, and accepted by
Department, will be considered to have Project Float. No time extensions will be
granted nor delay damages paid unless a delay occurs which impacts the project's
critical path, consumes all available float and extends the work beyond the Contract
Completion Date.
C. Negative Float: Negative float will not be a basis for requesting time extensions. Any
extension of time will be addressed in accordance with the applicable sections of this
specification. Scheduled completion date(s) that extend beyond the contract (or phase)
completion date(s) may be used in computations for assessment of liquidated
damages. The use of this computation is not to be construed as an order by
Department to accelerate the project.
1.11 Progress Schedule
A. Prepare a cost loaded schedule of activities for all design and construction Work to be
done in each Phase and show status of completion per PDBC Section 11.1
(Compensation for Phase 1 Work) and Section 11.2.4 (Estimates and Payments).
B. Submit an updated progress schedule when requested by the Department. The
Department may request an updated progress schedule when progress on the Work
has fallen more than fourteen (14) calendar Days behind the latest accepted progress
schedule. Information in the updated progress schedule must include a current
percentage of completion for each cost loaded schedule activity "% Work completed"
value for each activity.
C. Contractor shall submit a cash flow curve of expected progress payments over the
performance period. Plot curve using costs assigned to activities in the Baseline
Schedule. Contractor to update the curve with actuals from the approved bi-monthly
invoice payment and forecast progress payments and submit bi-monthly to the
Department per PDBC Section 11.1 (Compensation for Phase 1 Work)
D. Contractor shall submit progress curves with the Bi-Monthly Progress update. Show
with the curves the cumulative scheduled percent complete of each phase, time-scaled
in calendar days from NTP to Contract completion. Derive schedule, actual, and
forecast progress from cash flow curve. Update progress curves with each bi-monthly
update of the current Baseline Schedule.
resource loading and final schedule report. The accompanying letter shall be signed by
an officer of the Company.
1.13 Other Schedule Submittal Requirements
A. Contractor shall coordinate schedule Submittals to avoid concurrent Submittals to
maximum extent possible. Where concurrent schedule Submittals cannot be avoided,
Contractor shall increase review time as required, to allow for Department’s review.
B. Where Submittal is concurrent with or overlaps Submittals currently being reviewed,
Contractor shall indicate priority of each outstanding submittal.
C. Following corrections resulting from Department’s Accepted as Noted to Contractors
initial Submittal, and after Department Review, Contractor shall print and electronically
distribute copies to Department, Subcontractors, and other parties required to comply
with Submittal dates indicated.
D. Contractor shall post copies in the Project meeting room at PMO and temporary field
offices.
E. When revisions are made, Contractor shall distribute to the same parties electronically
and post in same locations. Parties shall be deleted from distribution when they have
completed their assigned part of Work and are no longer involved in construction
activities.
The Contractor shall furnish products that are made in the United States according to the
applicable provisions of the Infrastructure Investment and Jobs Act, Pub. L. No. 117-58, which
includes the Build America, Buy America Act Pub. L. 117-58, §§ 70901-52.
A. Federal Requirements. All steel or iron products incorporated permanently into the
Work must be made of steel or iron produced in the United States and all subsequent
manufacturing must be performed in the United States. Manufacturing is any process that
modifies the chemical content; physical shape or size; or final finish of a product. Manufacturing
begins with the initial melting and mixing and continues through the bending and coating stages.
If a domestic product is taken out of the United States for any process, it becomes a foreign
source material.
All manufactured products used in the project are not required to be produced in the United
States.
All construction materials are manufactured in the United States—this means that all
manufacturing processes for the construction material occurred in the United States.
To provide clarity to item, product, and material manufacturers and processers, we note that
items that consist of two or more of the listed materials that have been combined together
through a manufacturing process, and items that include at least one of the listed materials
combined with a material that is not listed through a manufacturing process, should be treated
as manufactured products, rather than as construction materials. For example, a plastic framed
sliding window should be treated as a manufactured product while plate glass should be treated
as a construction material.
B. Exceptions. The Director may grant specific written permission to use foreign steel or
iron in any type of construction. The Director may grant such exceptions under the following
condition:
The cost of products to be used does not exceed 0.1 percent of the total Contract cost, or
$2,500, whichever is greater. The cost is the value of the product as delivered to the project.
The Buy America preference only applies to articles, materials, and supplies that are consumed
in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools,
equipment, and supplies, such as temporary scaffolding, brought to the construction site and
removed at or before the completion of the infrastructure project. Nor does a Buy America
preference apply to equipment and furnishings, such as movable chairs, desks, and portable
computer equipment, that are used at or within the finished infrastructure project, but are not an
integral part of the structure or permanently affixed to the infrastructure project.
C. Proof of Domestic Origin. Furnish certification to the Department showing the domestic
origin of all products covered by this section, before they are incorporated into the Work.
Products without a traceable domestic origin will be treated as a non-domestic product.
The Department anticipates incorporating within the Phase 2 Change Order a surface
smoothness for pavements adjustment mechanism based upon ODOT’s PN 420 (01/21/2023)
and KYTC SS410
The Department anticipates incorporating within the Phase 2 Change Order a surface
smoothness for bridges and approaches adjustment mechanism based upon ODOT’s PN 555
(01/15/2021). Kentucky work starting at the northern approach of the Companion Bridge through
the southern approach span will follow ODOT’s PN 555.
The Department anticipates incorporating within the Phase 2 Change Order a fuel price
adjustment mechanism based upon ODOT’s PN 520 (07/15/2022)
The Department anticipates incorporating within the Phase 2 Change Order a steel price
adjustment mechanism based upon ODOT’s PN 525 (07/15/2022)
The Department anticipates incorporating within the Phase 2 Change Order an asphalt binder
price adjustment mechanism based upon ODOT’s PN 534 (01/21/2022)
The Department anticipates incorporating within the Phase 2 Change Order a Portland cement
price adjustment mechanism based upon ODOT’s PN 540 (10/19/2018)
This Exhibit X in no way supersedes any other commercial regulations or any other legal
requirements regulating the transportation of commercial materials. This does not preclude or
dismiss any requirement for paper tickets required by other rules and regulations.
2. Requirements
The Contractor shall send digital ticket information to the Department’s Digital Ticketing Portal
as the individual material loads are generated and shipped to the Project. The digital material
ticket (“e-Ticket”) shall contain information as required per the applicable material specification
for weight measurement and other material characteristics.
The Department will reject any load that does not have a corresponding e-Ticket unless the
cause is beyond the Contractor’s control, as determined by the Department. In such
circumstances, paper tickets may be permitted.
3. Setup, Calibration, and Data Integration
The Contractor shall cause Suppliers to cooperate with the Department and the Department’s e-
Ticketing vendor to establish digital information transfer from the Supplier’s ticketing system to
the Department’s e-Ticketing portal. No earlier than 14 Days after NTP for Construction for any
Work Package, but not later than 30 Days prior to initiating Construction Work, the Contractor
shall identify in writing the material source load read-out weighing system the Supplier utilizes.
The Contractor shall cause its Suppliers to cooperate with the Ohio Department of
Transportation’s (ODOT’s) e-Ticketing Portal vendor in the creation of an Application
Programming Interface (API) to integrate material source load read-out data with the
Department’s e-Ticketing Portal. The Department’s e-Ticketing portal vendor shall be
responsible for leading the API creation. Upon API creation, the Contractor shall utilize the API
to provide digital material source load read-out data from the material source load read-out
weighing system to the Department’s e-Ticketing Portal.
The Contractor shall conduct a test of each Supplier’s integration with the Department’s e-
Ticketing Portal prior to shipping material to the Project. Complete test at least 14 days prior to
shipping material unless otherwise approved by the Department. The test must involve at least
four test e-Tickets from each Supplier approved for used on the Project for materials to be used
on the Project. The test e-Tickets must accurately reflect the proper nomenclature and accuracy
defined; all other categories shall be marked “TEST”. After the Department confirms the test e-
Tickets have been entered into the Department’s e-Ticket Portal, void the test e-Tickets with the
reason “Setup Testing”. If any load read-out weighing system changes are intended by the
Supplier after the creation of the Supplier-specific API, coordinate with the Department to
ensure API compatibility.
The Contractor shall ensure continued internet connectivity during the API usage to maintain
connection the Department’s e-Ticketing Portal during material production and delivery to the
Project. The Contractor shall ensure delivery of e-Ticket prior to the material arriving on the
Project, but not prior to the loading of material at the source.
Upon successful testing of the data integration, physical material tickets are not required to be
submitted to the Department, but may be necessary for truck drivers per Ohio Revised Code
Section 5577.043 and Kentucky Administrative Regulations 603 KAR 5:066.
REGARDING THE
BY AND BETWEEN
AND
The project risk register is a preliminary working document. Risk assessment, risk allocation, risk acknowledgement, and potential mitigation measures will continue through project development. Potential mitigation measures listed may or may not be implemented through procurement/project
delivery/design/construction. While grouped, the project risk register is not in any order and is the opinions of the BSMT.
Risk Category
Sub-Category Title Cause ("Due to") Risk Description Effect ("Leads to") Potential Risk Mitigation Measures Risk Assignment (Department Risk, Relief/ Provisional Sum Contractor Required Department Approved
Provisional Risk, or Contractor Risk) Mitigation Efforts Effective Date of Risk
Register Event
FEMA - CLOMR / Design Builder bridge FEMA review of the Causes schedule delay and 1. Define the no-net rise and what model does
LOMR Floodplain final design impacts the effective model vs. the additional calculations to FEMA require. 1D vs. 2D model and the process
Drainage
Permit FEMA flood elevation existing model is not FEMA for permit approval. approval.
3rdP
requiring CLOMR/LOMR consistent causing 2. Define the existing and preliminary pier location
additional coordination model with FEMA prior to RFP release.
and schedule delay. 3. Develop a FEMA floodplain task force.
Unknown Soil Design-Builder changes Pre-award soil borings Design-Builder must price 1. ID areas this could occur from borings, base
Conditions near structure design / may not be in locations to the project without configuration.
Structures location significantly support updated design, adequate geotech 2. Obtain additional borings prior to design
from pre-award noise walls or other information and then must completion and prices are due. Potential RFP
Bridges
BRG
configuration structures. obtain additional borings language to request borings from ODOT/KYTC
to support design and to provide testing information to all teams.
Natural variations in 3. Review Risk geotech risk assignment language.
strata Potential site condition 4. Limit the river borings and set the navigable river
claims envelope.
Ohio River Climate Original CER - Ohio River Construction project 1. Structure the contract to allocate this risk so that
Construction
Flooding high water elevation - delays since the area flooding that exceeds a certain level will be
Flooding along the Ohio may not be available for compensable. Allows the contractors to cap their
BRG
Design Quality Quality process does Non-conforming design Difficult to rectify 1. Include robust design quality requirements,
Issues (complex not catch issue makes it to construction construction issues including Independent Quality Review for
bridge) companion bridge and Independent Quality Firm
for all design. DB team will provide independent
peer review of erection model. (2 erection models
will be developed using different software under
ODOT/KYTC contract).
2. Design risk assigned to DB through contract
Design
CN
Settlement Pile driving, sheeting, or There is a risk of Settlement could lead to 1. Tracking using monitor surveys of existing utilities.
During other construction unplanned settlement of additional cost or 2. Evaluate non-vibratory means at locations next to
Bridges
Vibratory activities cause existing mainline bridges, schedule impacts to existing sanitary sewers.
CN
Construction significant ground walls, noise walls, utilities analyze and resolve any
Activities vibrations due to soil collapse or structural damage
settlement
The project risk register is a preliminary working document. Risk assessment, risk allocation, risk acknowledgement, and potential mitigation measures will continue through project development. Potential mitigation measures listed may or may not be implemented through procurement/project
delivery/design/construction. While grouped, the project risk register is not in any order and is the opinions of the BSMT.
Risk Category
Sub-Category Title Cause ("Due to") Risk Description Effect ("Leads to") Potential Risk Mitigation Measures Risk Assignment (Department Risk, Relief/ Provisional Sum Contractor Required Department Approved
Provisional Risk, or Contractor Risk) Mitigation Efforts Effective Date of Risk
Register Event
Unknown/ Presence of unknown Utilities may be in conflict Unanticipated utility Complete utility investigation and conflict
Utilities
Undisclosed or undisclosed with planned work but not conflicts must be identification in pre-award phase. Use RFP to
CN
Utilities underground utilities identified on the plans resolved during allocate and properly share risk with contractor.
construction adding both
cost and time
Differing Site Certain latent There is a risk that Depending on where 1. Complete and review borings
Geotechnical
Conditions- conditions, either restrictive conditions are they are encountered 2. Add appropriate mitigation for Contractor
Geotechnical natural or man-made, discovered during could lead to increased performance and provide relief, if appropriate.
CN
Restricted Wall Construction limits are Wall construction has Project cost and schedule Define tight locations, and inform the DBT.
Construction Limits very close to existing potential of damage to increase due to required
Walls
CN
Operational Operations such as pile Damage to or failure of Construction schedule 1. Contractor required to monitor utilities.
Utilities
Impacts to Utilities driving and compaction utilities due to vibration delay and cost impacts 2. Basement videotaping required before construction
CN
Buy America Compliance with Buy Contractor does not Construction acceptance Include Buy America requirements in the RFP.
America requirements provide Buy America not granted until Clearly communicate these requirements during
is not achieved during certifications or does not documentation is meetings with industry.
Requirements
Railroad Railroad review and Certain work may occur in Contractor is required to 1. Evaluate concept I-W railroad parcel locations for
Coordination and approval process for the RR ROW. Minimum price the project without piers to be included in the railroad agreement.
Railroad
Agreements work inside of RR ROW coordination will include knowing what the RR will 2. Early coordination with railroads to better define
DES
is lengthy and aerial easements. approve or how long it expectations to prepare the RFP.
unpredictable will take to obtain 3. Railroad right of entry will be on the DBT.
approval
Approvals / Permits
United States Undefined Coast Guard Neither BSMT nor the Contractor is delayed with 1. Coordinate CG requirements and include them in
Coast Guard requirements bidders are clear on what beginning work in this the RFP to the extent possible.
ENV
Section 9 the CG will require area or is unable to permit 2. Develop a Task Force Team to coordinate with the
the approach that was Coast Guard and determine risk profile.
included in the proposal.
The project risk register is a preliminary working document. Risk assessment, risk allocation, risk acknowledgement, and potential mitigation measures will continue through project development. Potential mitigation measures listed may or may not be implemented through procurement/project
delivery/design/construction. While grouped, the project risk register is not in any order and is the opinions of the BSMT.
Risk Category
Sub-Category Title Cause ("Due to") Risk Description Effect ("Leads to") Potential Risk Mitigation Measures Risk Assignment (Department Risk, Relief/ Provisional Sum Contractor Required Department Approved
Provisional Risk, or Contractor Risk) Mitigation Efforts Effective Date of Risk
Register Event
United States Undefined USACOE Permit process cannot Contractor is delayed with 1. Coordinate in advance with executives and high-
Approvals / Permits
Army Corps of requirements begin until design and beginning work in this level staff at USACE.
Engineers 408 means and methods are area or is unable to permit
ENV
Differing Site Urban area has been Contaminated materials Contamination must be Determine appropriate entity to complete
Conditions- previously used. are discovered during remediated adding cost environmental report. Assess risk after
Haz Mat
concerns, e.g.,
contaminated soils,
LUST, within project
limits are not known.
Delayed Utility Utility relocations must Utilities (or tenants) do Contractor is delayed and 1. Improve utility coordination / quality / accuracy by
Relocations be completed prior to not complete relocations must implement reviewing existing "Conflict Matrix" with latest
commencing in time workarounds requiring design and getting new information from utilities.
construction remobilizations / 2. Evaluate / establish relocation timelines based on
Utilities
EXT
Decision-Making Critical Program There is a risk that Delays, rework increase 1. Develop Project Management Plan to define roles
Process decisions must be made proactive decisions are project cost and schedule, and responsibilities and define
MANAGEMENT
promptly. A structured not made, and the proper affecting design and/or approvals/coordination requirements. The agreed
Management
and effectively structure is not in place to construction milestones upon review / approval durations will be placed the
Program
Too restrictive Too restrictive criteria Right balance between Less innovation leads to 1. Consider opening typical requirements when
Procurement
project scope prohibit innovation project scope and higher bids. developing the RFP.
minimum criteria in order 2. Consider soliciting feedback to Scope prior to
to allow innovation from advertisement.
DBT. 3. Actively engage the ATC process allowing alternative
approaches.
The project risk register is a preliminary working document. Risk assessment, risk allocation, risk acknowledgement, and potential mitigation measures will continue through project development. Potential mitigation measures listed may or may not be implemented through procurement/project
delivery/design/construction. While grouped, the project risk register is not in any order and is the opinions of the BSMT.
Risk Category
Sub-Category Title Cause ("Due to") Risk Description Effect ("Leads to") Potential Risk Mitigation Measures Risk Assignment (Department Risk, Relief/ Provisional Sum Contractor Required Department Approved
Provisional Risk, or Contractor Risk) Mitigation Efforts Effective Date of Risk
Register Event
Failure To Letting contractor slide Not using DBEs and Federal action, loss to 1. Outreach events.
MANAGEMENT
Management
Attain DBE because they "tried" to instead using "good faith construction community 2. DBE utilization as part of proposal.
Program
Goal/Lack get DBEs to bid and/or effort" to develop and use talent, 3. DBE specific consultant.
of DBE contractor didn't use community loses jobs 4. DBE reciprocity between Ohio and Kentucky.
availability DBE due to cost. 5. Consider DBE coordinator as key person on DBT.
MARKET
Market Conditions Saturated construction Necessary labor for the Contractor labor costs 1. Allow flexibility on interim milestones.
Other
- Labor market or rising project is not available at increase 2. Allow flexibility to work during traditional
inflation typical costs seasonal/weather shutdown.
3. Collaborate on a Workforce development plan.
Market Conditions Materials supply chain Necessary materials for Material cost or 1. Provide flexibility on interim milestones.
Construction
- Materials or rising inflation the project are not procurement time 2. Provide flexibility in materials where possible.
MARKET
available at typical costs or increase 3. Review potential material indexes. Consider using
prices fuel and asphalt, cement, fuel, steel, and
asphalt/binder. Review potential additional project
specific indexes.
Market Capacity Industry of regional There is a risk that this Schedule delay, high 1. Closely monitor other major ODOT / KYTC programs
Exceeded contractors indicates potential capacity pricing, or potentially to watch market trends.
Construction
MARKET
Market Conditions Saturated construction Number of contractors Higher prices and limited 1. Early outreach and press releases.
- Contractor market or other project capable of delivering large competition 2. Balancing contractor input and accommodation on
Procurement
Interest competition projects is limited. Project risk profile with BSMT needs.
MARKET
may not attract adequate 3. Allow follow up one on one meetings with
competition interested offerors prior to RFQ release to
address their risk concerns and provide a status
update. Also through website notices / updates.
4. Deliver on the procurement schedule dates.
Delayed Steel Schedule includes Structural steel fabrication Delay completion of 1. Consider potential structural steel design hold
point release criteria to allow more fabrication
Procurement
The project risk register is a preliminary working document. Risk assessment, risk allocation, risk acknowledgement, and potential mitigation measures will continue through project development. Potential mitigation measures listed may or may not be implemented through procurement/project
delivery/design/construction. While grouped, the project risk register is not in any order and is the opinions of the BSMT.
Risk Category
Sub-Category Title Cause ("Due to") Risk Description Effect ("Leads to") Potential Risk Mitigation Measures Risk Assignment (Department Risk, Relief/ Provisional Sum Contractor Required Department Approved
Provisional Risk, or Contractor Risk) Mitigation Efforts Effective Date of Risk
Register Event
Maintenance of High traffic volume and Ingress/egress into the Safety and travel delay 1. As part of the TMP include the requirements
traffic tight urban setting construction area for the traveling public to be pulled into the maintenance of traffic
plans.
Traffic / Mobility
Kentucky ROW Concept required ROW New ROW must be ROW acquisition cost and 1. BSMT will develop a right of way clearance schedule
takes in Kentucky acquired schedule increase to be included in the RFP.
2. Consider having Design Builder place the parcel
Schedule
Longworth Hall Building owner delay. Longworth Hall demolition Construction project 1. Include schedule delay relief to the Design Build team
Delay and area made available delays since the area may within the RFP.
Construction
The name of the prequalified WTS and related 24-hour contact information shall be provided to
the Department. If the designated WTS will not be available full time (24/7), the Contractor may
designate an alternate (secondary) WTS to be available when the primary is off duty; however
the primary WTS shall remain the point of contact at all times. Any alternate (secondary) WTS is
subject to the same training, prequalification and other requirements outlined within this plan note.
At all times the Department, or Department’s representatives, must be informed of who the
primary WTS (and secondary WTS, if applicable) is at the current time.
The WTS position has the primary responsibility of implementing the Traffic Management Plan
(TMP), monitoring the safety and mobility of the entire work zone, and correcting Temporary
Traffic Control (TTC) deficiencies for the entire work zone. The WTS, and alternate WTS when
on duty, shall have sufficient authority to effectively carry out the identified WTS responsibilities
and duties. The duties of the WTS are as follows:
1. Be available on a 24-hour per day basis.
2. Be on site for all emergency TTC needs within one hour of notification by police or project
staff, and effect corrective measures immediately on existing work zone TTC devices.
3. Attend preconstruction meeting and all project meetings where TTC management is
discussed.
4. Be available on site for other meetings or discussions with the Department upon request.
5. Be aware of all existing and proposed TTC operations of the contractor, subcontractors
and suppliers, and ensure coordination occurs between them to eliminate conflicting
temporary and/or permanent traffic control.
6. Coordinate project activities with all Law Enforcement Officers (LEOs). The WTS shall
also be the main contact person with the LEOs while LEOs are on the project.
7. Coordinate and facilitate meetings with ODOT personnel, LEOs and other applicable
entities before each plan phase switch to discuss the work zone TTC for implementing the
phase switch. Submit a written detail of MOT operations and schedule of events to
implement the switch between phase plans to the Department 5 calendar days prior to this
meeting.
8. Be present, on site for, and involved with, each TTC set up/take down and each phase
change in accordance with CMS 614.03.
9. On a continual basis ensure that the TTC zone and all related devices are installed,
maintained, and removed in compliance with the contract documents.
10. On a continual basis facilitate corrective action(s) necessary to bring deficient TTC zones
and all related devices into compliance with contract documents in the timeframe
determined by the Department.
11. Inspect, evaluate, propose necessary modifications to, and document the effectiveness
of, the TTC devices and traffic operations on a DAILY BASIS (7 days a week). In addition,
perform one weekly night inspection of the work zone setup for daytime work operations;
and one daytime inspection per week for nighttime projects. This shall include (but not be
limited to) documentation on the following project events:
a. Initial TTC setup (day and night review).
b. Daily TTC setup and removal.
c. When construction staging causes a change in the TTC setup.
d. Crash occurrences within the construction area and within the influence area(s)
approaching the work zone.
e. Removal of TTC devices at the end of a phase or project.
f. All other emergency TTC needs.
12. Complete the Department approved (CA-D-8) within GoFormz after each inspection as
required in # 11 and submit it to the Department by the end of the workday in which the
inspection occurred. The CA-D-8 includes a checklist of all TTC maintenance items to be
reviewed. Contact [email protected] to obtain a user account. Any
deficiencies observed shall be noted on the CA-D-8, along with recommended or
completed corrective actions and the dates by which such corrections were, or will be,
completed. A copy of the current CA-D-8 document can be found on the Office of
Construction Administration’s Inspection Forms website.
13. Have copies of the ODOT Temporary Traffic Control Manual and contract documents
available at all times on the project.
A. The amount of ($1,000) for any day in which the WTS fails to perform the duties set forth
above.
B. The amount of ($1,000) for any day that a TTC issue is identified in the field and is not
corrected in the given timeframe per the Department. Deduction B shall not apply to
situations covered by Deduction C.
C. The amount of ($5,000) for any day that a lane or ramp is blocked (fully or partially) without
TTC, as determined by the Department. This deduction shall be in addition to any other
disincentives established for unauthorized lane use.
For days in which more than one deduction listed above occur, the highest deduction amount will
apply.
If three or more total days result in TTC issues described in Deduction B or C above, the
primary WTS shall be immediately removed from the work in accordance with C&MS 108.05.
Upon removal the Department shall notify ODOT Central Office
([email protected]) to register a removal against the statewide prequalification
for the primary WTS. Three removals shall cause statewide disqualification for any previously
prequalified WTS.