100% found this document useful (1 vote)
1K views25 pages

Demobilization Risk Assessment and Method Statement

Method Statement and Risk Assessment

Uploaded by

Vishu Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views25 pages

Demobilization Risk Assessment and Method Statement

Method Statement and Risk Assessment

Uploaded by

Vishu Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 25

J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

General Information

Contract Name: Michaels Pump Test Decommission Contract No:

Decommission Pump Test


Activity: Location: Site Area
Equipment including reinstatement

Initial RA / MS prepared by: Nick Hoctor Date: 06/09/18

RA / MS Reference No: 01

Review and Revision Details

RAMS shall be reviewed in operation, at least weekly and where there is a significant change to the 
activity/task (as per OSS 002) 
 
Date of last Amended Reviewed / Amended
Revision Reason for Amendment
review (Yes / No) By

A - - - First Issue

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 1 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Section 1 - Risk Assessment - Health & Safety

Fatality MEDIUM HIGH VERY HIGH VERY HIGH


SEVERITY

Reportable Injury LOW MEDIUM HIGH VERY HIGH

Lost Time Injury LOW MEDIUM MEDIUM HIGH

Minor Injury LOW LOW MEDIUM MEDIUM

Remote Possible Likely Very Likely


J N Bentley Risk Matrix
PROBABILITY

Hazard Person(s) at Risk Risk Level Control Measures Residual


Risk

‘SHOW STOPPERS’ (Initial Risk Level Very High or High)

Crane Jib/Excavator Site Team H  Trained & Competent Operators. M


clash  Lift Plan to be in place
 Planned movements.
 Directions of swing for both crane & excavator.
 All movements controlled by dedicated
Slinger/signaller(Red Helmet)

55T ALL Terrain Crane Site Team H  Plate bearing tests have been under taken at M
Stability proposed berthing area.
 Lift plan to be completed by Qualified
Appointed Person

Operation of Excavator Excavator Operator, H  Driver to be CITB approved level and have L
for lifting Site Operatives, attended JNB (or similar approved) ‘Lifting
Slinger/Signaller, with excavators course’.
Lift Supervisor,  Lift plan to be completed by Qualified
Client Personnel Appointed Person

Plant People Site team H  Follow “Working with and around plant M
segregation Clients personnel, “guidance notes
 Slinger signaller to control plant operations at
Other contractors
all times, ensuring the slinger does not entre
Zone 2 when the machine is operating and not
in a safe position (bucket down and dead man
engaged)
 Assess working area prior to entering to check
if any additional control measures are required
 Ensure walk ways and segregation fencing is
maintained at all times.
 Stop work and place the machine in a safe
position if any staff or public entre zone 1
 Ensure plant is parked in a safe flat area
overnight considering how to prevent the plant
moving / slipping when not in use.
 All operatives to approach a machine from the
operators clear line of sight.
 ‘THUMBS UP’ Procedure Followed

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 2 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Working in or adjacent Site team, public H  Adequate planning L


to Forth Estuary  Establish emergency procedures.
 Work agreed with all Statutory bodies and
Permit/Licences issued.
 Use of harness fall arrest inertia reels.
 Buoyancy aids to be worn.
 Trained experienced personnel
 Monitor weather reports
 Selection of personnel
 Tidal Data consulted with works to be
planned accordingly

Working on a slope Site Operatives H  Machines to only track up gradients that M


machine can manage
 Incline of proposed slope to be no more than
45 degrees
 Existing Access ramp to be amended prior to
use by long reach excavator/crane
 Excavators only to work in one plane unless
safe to do so. Constant monitoring to
operations.
 No go zone to be created and marked out
using pin & chain and ranging rods as dictated
by TW Design for the crane pads.

Cable Strike / Damage Site Operatives H  JNB to undertake initial site visit to ascertain M
to Existing Services whether service restrictions are visual
 JNB to obtain and review latest service
drawings and have copies available on site
 Trained and competent person to scan area
using a CALIBRATED cable avoidance tool
(CAT and Genny), prior to excavation. Copy
of calibration certificate to be available on site.
 All underground services must be spray
marked (or marker pegged) to identify the line
and location of the service
 Permit to dig system is to be implemented by
where services cross or are reasonably
anticipated within 3m of the footprint of the
excavation
 Site Supervisor to check Operatives are
suitably trained and competent for task
(SSSTS qualified to issue permits)
 Existing live services – Hand dug trial holes to
be undertaken when within the 0.5m Zone of a
known Service. Horizontal dig technique to be
utilised
 JNB to comply with HSG47 guidance relating
to underground power lines, if anticipated
 JNB to consult service providers regarding any
protection measures required to services, if
appropriate
 Excavators used to dig trial holes must be
fitted with toothless buckets
 Bucket lay down area to be signed and fenced
off
 Trial holes to be dug to determine presence of
existing field culverts / land drains / other
services, where anticipated

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 3 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

 Work area to be securely fenced off to


prevent unauthorised access
 No GPR Survey required, as considered low
risk in large open area.
 .

Over Head Cables Site Team H  Goal posts to be erected under GS6 M
Permit.
 Height Restriction signage to be erected.
 All machine movements to be under
slinger/signaller control.

Collapse of excavation Site Operatives H  Permit to dig system in place M


 Daily excavation checks to be carried out and
recorded
 Weekly statutory excavation checks to be
carried out and recorded on JNB Database
 No trench to be left open overnight/weekend

Falls from height Site Operatives H  Suitable edge protection to be installed around M
edge of excavation.
 Adequate access and egress to be used and
maintained into the excavation this will be by
man rider in the first instance.
 Preliminary fencing to be around excavation to
eliminate unauthorised access

GENERAL

Deliver, storage and Site team, public M  Agree delivery points and off load location L
collection of within site boundaries
equipment/materials/  Main access road to be kept clear at all times
welfare  All drivers to observe traffic warning signs on
Access Road.
 Safety rules to be on purchase orders with
specific details as incorporated in the Traffic
Management Plan
 Drivers to contact site team prior to delivery
 Provide banks-man
 Specific Lifting Plans to be in place for
unloading of Cabins with checks on hiab
tickets
 Competency checks to be carried out for all
delivery and collection vehicles
 Specific off-load and lay down areas to be
established and communicated to the
workforce.
 Morning briefings to include the day’s
deliveries and collections.
 All vehicle movements to be undertaken
under supervision of a banksman.
 In the turning area all vehicles to stop if
pedestrians are in the vicinity and not move
until they have vacated the area.

Use of plant – 25t Site team M  OSS106 – Safe Use of Plant & Equipment L

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 4 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

excavator and 55t all  Competency assessments


terrain crane  TBT 58 to be given to all non JNB and JNB
who hold Red Card
 Compliance with PUWER Regulations
 Planned routes to be used with pedestrian
segregation
 Operators to be trained and competent
 Speed limits
 Banksmen provided for reversing operations
 Stop blocks near excavations if required
 Plant security
 Golden Rules (seatbelts)
 Suitably maintained equipment
 Minimisation of tracking
 Instruction to drivers re WBV controls
 Follow Gen lift plan at all times
 Wheeled dumper to have a designated route
and exclusion zones.
 All movements of the excavator/crane to be
under constant supervision of
slinger/signaller( Red Helmet) and must only
travel over planned routes.

Mechanical failure Site operatives, Hired M  Inspection of plant carried out daily and L
drivers recorded as per JNB OSS
 Test certs for machines.
 Make site management aware of any faults.
 Items of plant with faults that affect the
operation of the machine should be shut
down and quarantined until they have been
repaired by a trained competent person

Soft / unstable ground Plant Operators, M  No plant to access to areas of soft/unstable L


ground.
Operatives
 All movements on the Tailings Storage Area to
be under supervision of slinger/signaller and
keep to designated access tracks/crane pads
 No personnel to access soft/unstable ground
until it has been made safe to do so. Access
tracks/staircase to be installed

Weather conditions with Clients personnel, M  River levels to be monitored work to be L


regards to plant and suspended where deemed unsafe to
Plant operators,
working continue operations.
Site team,  5 Day forecasts to be obtained to assist with
Other contractors forward planning and communicated in
briefing
 Wind speed to be checked

Interface with the public Site team, public M  Control plant operations L
 Impose site speed limit and erect signs
accordingly
 Barrier segregation

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 5 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

 Supervised operations
 Liaise with public ( first contact already made
– open day to be arranged as soon as
possible at site cabins)
 Warning signs to be displayed at shared
points along the Access Road

Removal of existing Site team M  Manual handling guidelines to be adhered to.- L


fencing, erecting Heras Manual handling training required. Due to size
fencing and site signage of each panel, 2 men will be used to remove
and stack existing panels and to erect
temporary Heras panels. Use wheel barrow to
reposition metal fencing, sand bags, Heras
feet (if required)
 Existing poles to pulled out using 360
excavator.
 Fencing to be delivered close to area of work
 Minimise ground damage by using plant on
dedicated route. Should damage occur to the
entrance track then it will need to be
maintained/stoned up ensuring no trip hazards
are left for the public
 Correct tools in good condition to be used for
installation operations. Existing fencing
security clamp key to be obtained and used.
 All fencing to be double clipped as per
manufacturer’s instructions
 The site may be prone to windy conditions.
Movement of fence panels must stop if wind is
strong.

Flooding/ Drowning Site team M  Weather forecast to be checked daily and L


monitored.
 Tide data to be checked daily and monitored
 If the sea level rises or fast flowing then
works will be suspended and operatives
removed from work area
 Demarcated fencing/barriers to be erected.
 Ensure that no lone working is undertaken.
 Life vests to be available when working in /
close to water by trained competent
personnel
 Life buoys to be available close to working
area

‘HIGH FREQUENCY, LOW RISK’

Slips, trips & falls Site team L  Keep walk ways clear L
Clients personnel,  Work areas to be tidy
Other contractors  Dedicated Material storage area to be
accessible
 Pedestrian walkways to be installed where
possible
 Non slip boots/wellingtons as per JNB
specification

HAZARDS TO HEALTH (E.g. Noise / Vibration / Respirable Hazards / COSHH)

Work activity creating Site team, public M  Reduce noise levels as far as possible L
noise (selection of equipment, enclosure,
segregation etc)

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 6 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

 Provide adequate hearing protection


 Regular health checks (hearing)

Work activity creating Site team, public M  Eliminate the task L


vibration  Provide alternative less harmful equipment
 Job rotation
 Provide HAV Calculator
 Authority to operate plant
 Toolbox talks
 Assess surrounding land

Working in areas where Site team, public M  Provision of welfare facilities L


the risk of occupational  Induction training awareness
health  Observe good hygiene rules
diseases/infection exist  Maintenance of welfare facility
– Weils Disease  Abrasions/cuts to be covered at all times
 Tool box talks to be undertaken (Weils
Disease)
 Notices/advice to be displayed on Notice
Board

Section 2 - Risk Assessment - Environmental

Category 1 Harm MEDIUM HIGH VERY HIGH VERY HIGH


SEVERITY

Category 2 Harm LOW MEDIUM HIGH VERY HIGH

Category 3 Harm LOW MEDIUM MEDIUM HIGH

Category 4 No Harm LOW LOW MEDIUM MEDIUM

Remote Possible Likely Very Likely


J N Bentley Risk Matrix
PROBABILITY

Environmental Aspect Environmental Impact Risk level Control Measures Residual


risk

Note: list in descending order of risk level


‘SHOW STOPPERS’ (Initial Risk Level Very High or High)
Mobile plant Fuel or oil spill H  Plant to be refuelled in yard/depot where L
contaminating land or possible
entering  Plant to be on drip tray/ interceptor
watercourse/sea
 Spill kit available on site.
 Plant to be inspected for possible leaks
before use
 Fuel storage tanks to be self-bunded
Waste Site operatives H  All transfer notes to be collected and given L
to site manager
 All hazardous wasted to be separated and
placed in correct skips/bins
Evasive Species Further H  Management Plan to be implemented L
Contamination
OTHER RISKS (Initial Risk Level Medium or Low )

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 7 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

L
Wind blown waste/litter litter blowing around M  Site specific waste management plan
site developed
 Waste streaming introduced
 Enclosed/covered skips and bins provided
Damage to flora / fauna Destruction of habitat M  Care to be taken not to damage any L
existing vegetation.

Noise pollution Nuisance to  Regular noise monitoring to take place and


Operatives/ the need for silenced plant to be assessed
Neighbours. M L
 Silenced plant where possible
 Additional acoustic barriers to be installed

Section 3 - Risk Assessment - Quality

Severe MEDIUM HIGH VERY HIGH VERY HIGH


SEVERITY

Moderate LOW MEDIUM HIGH HIGH

Minor LOW LOW MEDIUM MEDIUM

Remote Possible Likely Very Likely


J N Bentley Risk Matrix
PROBABILITY

Quality Aspect Quality Impact Risk level Control Measures Residual


risk

Note: list in descending order of risk level


‘SHOW STOPPERS’ (Initial Risk Level Very High or High)
Reinstatement Breach planning H  Engineering control L
consent
OTHER RISKS (Initial Risk Level Medium or Low )
CDM Boundary fence Integrity of fence M Daily end of day inspection that all clips (doubled L
security clipped) are secured.
Erection of site notices NOT ADEQUATE M Daily end of day inspection to be carried out, L
and signs new signs to be erected, maintain existing signs

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 8 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Section 4 Vibration and Noise from Plant / Equipment / Tools


The following plant, equipment and power tools will be used during the course of this activity. Figures for noise and vibration
output are in-use figures provided by the manufacturer, supplier or hirer.

Hand Arm Vibration (HAVS) this table should be viewed in conjunction with the “HAVS Calculator” for details of cumulative use

Where vibration exposure times are calculated these will be based on the 2.5m/s2 (100 points) exposure limit value (ELV)

Maximum
Anticipated
Source of Hand Arm Weighted Permitted
Specific Use Daily Exposure
Vibration Acceleration (m/s²) Exposure Time
Time (mins)
(mins)

Whole Body Vibration (WBV) from Mobile Plant


Plant to be Used Person Affected Control Measures
25t excavator Operator
Seat adjusted to suit the driver.
50t r crane Operator Only use well maintained haul roads
Minimise the length of time operating the machine
Spend breaks out of machine
Only use plant that is maintained in good order and
serviced regularly
Ensure tyres, where applicable, are not worn & at
the correct pressure
Comply with the JNB Working Time Policy

All plant operating on JN Bentley sites must have a manufacturer’s provided exposure limit value (ELV) =/< 1.15m/s² (see
manufacturer’s instructions / manual)
Noise: For noise levels above 85 dB(A) hearing protection MUST be worn
Plant Tool and Equipment noise also affects people working adjacent to the operator: Keep a safe distance or wear ear defenders
Hearing Protection
Noise Source Specific Use Noise Level dB(A)
(Y/N)
25 T Tonne Excavators Moving material Less than 85dba N

50T Crane Lifting Less than 85dba N

Section 5 Hazardous Substances


The following substances will be used or may be encountered during this activity. Detailed COSHH assessments are held in the
site safety file; the control measures required will be briefed to the personnel involved prior to work commencing.
Hazardous Substance COSHH Assessment Ref Precautions / Risk Controls

Gasoil 02 Gloves to be worn. See COSHH data sheet


Aggregates 48 Avoid dust were possible, Wear specific ppe
Hydraulic and engine oil 98 Avoid watercourses, Have spill kits available
Grease 193 Avoid watercourses, Have spill kits available

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 9 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Is a Methodology required? Yes No

Following the detailed assessment of Hazards, risk and control measures, is a written Methodology Y
required?

If the answer is No the severity and consequence of an injury, environmental or quality incident must be low and control
measures in the form of Site Rules, Golden Rules etc must be sufficient and adequately briefed to those involved in the task.
If a written Methodology is not required then omit Section 9 (Approach / Methodology), only.

Method Statement

Section 6 Scope of Works

This RAMS will cover the following activities:

1. Removal of Mine Pipe works & Pumps


2. Removal of Control Kiosk
3. Removal of 355mm hdpe pipe underground and reinstatement
4. Removal of Break Chamber and reinstatement
5. Removal of Legato block kentledge
6. Removal of overland 355mm hdpe pipe
7. Access Ramp Reinstatement

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 10 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Section 7 Related Documentation


This method statement is to be read in conjunction with the following documents:
Site Management Drawing
Traffic Management Plan
COSHH assessment sheets
Temporary Works Design as required
Technical Note on Slope Stability issued by MM
Lift plans for the specific plant to be available to all operatives involved in lifting and the Site Health & Safety File
Manufacturer’s instructions / hirers notes provided with plant and equipment
Personal Safety and commercial responsibilities
Manufacturers’ instructions / hirers notes
 J N Bentley OSS/Safe System of Work
 001: compliance with site and golden rules
 002: Preparation, communication and use of RA/MS
 003: Incident reporting and investigation
 004: Preparation and issue of permits to work
 101: Excavations
 102: Lifting operations using cranes and excavators
 106: Safe use of plant and equipment
 108: Safe working in confined spaces
 109: Safe use of working at height equipment
 110: Falsework and formwork
 111: Avoidance of overhead and underground services
 113: Managing and using hazardous substances
 116: Fire Safety

Section 8 Critical Pre-start Activities


Prior to work commencing on the activity, the following items must be completed:

 All Statutory Permits/Licences in place


 Welfare Facility /compound in place.
 Delivery of Plant/equipment to be used
 Disconnection of and removal of temporary generator & fuel tank
 Removal of security system

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 11 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Section 9 Approach / Methodology

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 12 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

After completion of all the above pre-start activities, work will commence following the procedure below. If at any point something
changes which requires amendments to the following procedure, work must be stopped and the risk assessment reviewed and
methodology rewritten. Under no circumstances must work be carried on outside of this procedure.

To Maximise efficiencies the sequence of works below will change depending on the Tidal Data at the time of the works
being carried out

Removal of Mine Pipe works & Pumps


 A Qualified electrician will disconnect the power/control cables from the two pumps running to the Control Kiosk.
 55T All Terrain crane will then be installed in the prescribed berthing position and rigged as per the Lift Plan
 Dismantling of the mine head pipes works will then begin.
 A combination of hand tools and the crane will be used to carry out this operation.
 Pump1 will be secured onto the crane and then the mechanical clamps will be removed.
 The pump will then be lifted out of the shaft by the crane and placed on the floor where the pump hose will then be
coiled ready for collection.
 Pump 2. will be secured onto the crane and then the mechanical clamps will be removed.
 The pump will then be lifted out of the shaft by the crane and placed on the floor where the pump hose will then be
coiled ready for collection
 On removal of the pumps the opening in the head beam will be secured by a galvanised plate which will be bolted down
to the head beam.
 The opening in the perimeter fence where the pipe went through will be secured.
 The removed pipes/valves/flow meter and the pumps will then be lifted onto a wagon by the crane for delivery to the
Frances Shaft compound.

Removal of Control Kiosk


 All cables/earthing rods will be removed and placed in the Control Kiosk.
 The Control Kiosk will then be lifted onto a wagon using the lifting points on the kiosk by the crane.
 The Control Kiosk will then be transported to Frances Shaft Compound.

Removal of 355mm hdpe pipe underground and reinstatement


 The line of the pipe will be marked out.
 The excavator will excavate starting at the pipe cap.
 A length of trench will then be excavated.
 A sling will be placed around the pipe and then the pipe will be pulled up onto the ground.
 The pipe will then be cut into 6m lengths and stored at a designated area ready for collection
 As the pipe is removed the area will then be backfilled and the ground profiled to tie in to the surrounding area
 This process will continue up to the break chamber.
 After the removal of the break chamber the section of pipe buried in the Access Ramp to the beach will be removed.

Removal of the Break Chamber.


 The Break chamber will be demolished by a hydraulic breaker fitted to the excavator.
 On completion the debris will be placed into skip for disposal off site at a Licenced Facility.
 The area will then be regraded using the arisings from the installation of the Chamber which are stockpiled adjacent to
the chamber

Removal of Legato block kentledge


 These works can only be carried out during the tide windows.
 A 25t excavator will access the beach by traveling down the previously installed ramp. It will be checked for any oil/fuel
leaks and the tracks will have been cleaned out prior to accessing the ramp. The excavator will be removed from the
beach at the cessation of work daily.
 The large boulders at the bottom of the ramp will be moved. These will be replaced on completion of works on the beach
to act as bank protection.
 The lifting points on the Legato blocks will be assessed. If unusable a tested eye bolt will be installed into the legato
block using a cordless drill.
 The legato blocks will then be attached to a deha/d shackle and lifted off the pipe and will then be transported to the
bottom of the ramp.
 A second 25t machine will then transport then up the bank to a designated storage area ready for collection.
 This process will be carried out for all 42 blocks that were installed.
 On completion the legato blocks will be loaded onto wagons for disposal at a Licenced Facility.

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 13 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Removal of overland 355mm hdpe pipe


 These works can only be carried out during the tide windows.
 The pipe will be will be secured to the 25t excavator at the bottom of the Access Ramp.
 The pipe will then be pulled up the beach in 10m lengths. At this point the pipe will be cut into 6m lengths.
 The second 25t excavator will then transport the pipes to a designated area ready for collection.
 This process will continue until all the pipe has been removed.
 The excavator will be removed from the beach at the cessation of work daily.
 On completion the pipes will be loaded onto wagons for disposal at a Licenced Facility

Access Ramp Removal


 On completion of the works on the beach. The large boulders will be replaced along the bottom of the ramp.
 The ramp will then be filled in using the stockpile material from the installation which is stored either side of the ramp.
 The ground will be profiled to match the adjoining areas.

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 14 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Stone Facing to Legato Block Wall


 Access to the work area will initially be the temporary staircase and walkway.
 A proprietary working platform will be installed. This will be moved and height added as required. This
platform will be removed from the river at the end of every day or if the river velocity increases.
 Masonry slots will be fixed onto the front of the legato block wall (riverside) with masonry bolts.
 Cut stone approximately 100mm thick will then be built up to a predetermined level for the day
 Materials will be lifted into position by the crane under the control of the slinger/signaller.
 Work will continue until the legato blocks have been fully covered with the stone facing blocks.
 The new blockwork wall is not to be tied into the existing wall at either end but finish flush with the
edge of the Legato blocks.

Backfilling behind the retaining wall.


 Once the block wall has been completed the wall is to be backfilled.
 The Tailings which were removed and stockpiled will be used to backfill behind the wall.
 The backfilling will carried out in accordance with the Contract Specification MMD-00-XX-DR-C-6000-
6007CONB)
 The long reach excavator will carry out this function.

Delivery of Shoring plant, walkways, legato blocks


 The crane will position itself on the crane pad specifically built for the unloading of plant/materials.
 The delivery vehicle will be marshalled into the designated delivery vehicle unload area
 The crane will then unload and place on the Tailings area at the previously designated area.
 The direction of the crane when unloading will be shown in the Lift Plan.
Excavation/Initial Reconstruction of the Downstream Area Tailings Wall
 The area to be excavated initially will be marked out by the engineer.
 This will be supervised by a banksman who will be located in a man riding basket attached to the crane
at a point where the works are visible and so that there is no clash of the crane/excavator
 THE POSITION OF THE MANRINDING BASKET AND THE SWING DIRECTION OF THE
EXCAVATOR TO BE INCLUDED IN THE LIFT PLAN. DISCUSSED AS A REMINDER IN THE
MORNING BRIEFING AND TO BE UNDER THE CONTROL OF A SIGNALLER/SLINGER FOR ALL
SIDEWAYS MOVEMENTS
 The excavation will then commence with the slope along of the edge of the whole of the excavation
being removed and stored in a temporary storage area. It may be necessary to move these arisings
using a tracked dumper.

 On completion of this the excavation will then commence at the base of the wall approximately 1.6m
towards the bank over a 8.5m width When sufficient arisings have been excavated from the front of the
excavation blinding concrete will be poured to provide a level base for the legato block installation. It
may be necessary to move these arisings using a tracked dumper.
 A two man team will then be lifted into the bottom excavation via the man riding basket, they will be
wearing harness and have a lanyard that is to be attached to the man riding basket at all times when
the man riding basket is in use. If deemed prudent due to increased flows in the river buoyancy aids are
to be worn. The man riding basket will be detached and left at the lower level.
 The man riding basket will provide access/egress for this part of the operation
 The Site Engineer will set out the front line of the Legato blocks with toe for the blinding
 Concrete blinding will be poured using the bucket of the long reach machine. This machine will be fed
concrete by the 21t excavator taking delivery at the top of the ramp and placing in a predetermined
position on the TSF.
 After the blinding concrete curing the legato blocks will be installed as per Construction Design (MMD-
00-XX-DR-C-6001-6007CONC) in this section 3 blocks high.
 The area behind the legato bloc will be excavated as per construction Drawings/sequence and concrete
poured.
 The Remainder of the installation will be as per sequence contained on Construction Drawings MMD-
00-XX-DR-C-6001-6007CONC

Installation of Temporary Access


 Once the first concrete block has been cast fully a temporary access is to be constructed.
 The area of the access will be graded by the excavator to an acceptable rake.

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 15 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

 A proprietary stair case will be installed and the bottom touching the top of the concrete block this will be
secured at the top. This will be carried out by operatives who will be wearing harness’ and attached
inertia reel fall arrest block which itself will be attached to the crane.
 Whilst still attached the operatives will walk down the stair case and secure the staircase to the concrete
block.
 After installation of the stair case a walkway with side rails will be placed on top of the concrete block
from the bottom of the stairs and secured
 Once the walkway is in place a small podium step will be placed at the end of the walkway for access to
the bottom of the work area.
 This staircase/walkway/podium step will now be the access to the bottom of the work area. With
the man rider still being available as and when required.

Stone Facing to Legato Block Wall


 Access to the work area will initially be the temporary staircase and walkway.
 Proprietary platforms will be used
 Masonry slots will be fixed onto the front of the legato block wall (riverside) with masonry bolts.
 Cut stone approximately 100mm thick will then be built up to a predetermined level for the day
 Materials will be lifted into position by the crane under the control of the slinger/signaller.
 Work will continue until the legato blocks have been fully covered with the stone facing blocks.
 The new blockwork wall is not to be tied into the existing wall at either end but finish flush with the
edge of the Legato blocks.

Backfilling behind the retaining wall.


 Once the block wall has been completed the wall is to be backfilled.
 The Tailings which were removed and stockpiled will be used to backfill behind the wall.
 The backfilling will carried out in accordance with the Contract Specification MMD-00-XX-DR-C-6000-
6007CONC)
 The long reach excavator will carry out this function.

Excavation/Initial Reconstruction of the Downstream Area Tailings Wall


 The area to be excavated initially will be marked out by the engineer.
 This will be supervised by a banksman who will be located in a man riding basket attached to the crane
at a point where the works are visible and so that there is no clash of the crane/excavator
 THE POSITION OF THE MANRINDING BASKET AND THE SWING DIRECTION OF THE
EXCAVATOR TO BE INCLUDED IN THE LIFT PLAN. DISCUSSED AS A REMINDER IN THE
MORNING BRIEFING AND TO BE UNDER THE CONTROL OF A SIGNALLER/SLINGER FOR ALL
SIDEWAYS MOVEMENTS
 The excavation will then commence with the slope along of the edge of the whole of the excavation
being removed and stored in a temporary storage area. It may be necessary to move these arisings
using a tracked dumper.

 On completion of this the excavation will then commence at the base of the wall approximately 1.6m
towards the bank over a 8.5m width When sufficient arisings have been excavated from the front of the
excavation blinding concrete will be poured to provide a level base for the legato block installation. It
may be necessary to move these arisings using a tracked dumper.
 A two man team will then be lifted into the bottom excavation via the man riding basket, they will be
wearing harness and have a lanyard that is to be attached to the man riding basket at all times when
the man riding basket is in use. If deemed prudent due to increased flows in the river buoyancy aids are
to be worn. The man riding basket will be detached and left at the lower level.
 The man riding basket will provide access/egress for this part of the operation
 The Site Engineer will set out the front line of the Legato blocks with toe for the blinding
 Concrete will be unloaded by the 21t excavator and placed in the tracked dumper body.
 The tracked dumper will then travel to the long reach machine.
 Concrete blinding will be installed using the bucket of the long reach machine which will collect the
concrete from the body of the tracked dumper.
 After the blinding concrete curing the legato blocks will be installed as per Construction Design (MMD-
00-XX-DR-C-6008-60011CONC) in this section 3 blocks high.

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 16 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

 The area behind the legato bloc will be excavated as per construction Drawings/sequence and concrete
poured.
 The Remainder of the installation will be as per sequence contained on Construction Drawings MMD-
00-XX-DR-C-6008-60011CONC

Installation of Temporary Access


 Once the first concrete block has been cast fully a temporary access is to be constructed.
 The area of the access will be graded by the excavator to an acceptable rake.
 A proprietary stair case will be installed and the bottom touching the top of the concrete block this will be
secured at the top. This will be carried out by operatives who will be wearing harness’ and attached
inertia reel fall arrest block which itself will be attached to the crane.
 Whilst still attached the operatives will walk down the stair case and secure the staircase to the concrete
block.
 After installation of the stair case a walkway with side rails will be placed on top of the concrete block
from the bottom of the stairs and secured
 Once the walkway is in place a small podium step will be placed at the end of the walkway for access to
the bottom of the work area.
 This staircase/walkway/podium step will now be the access to the bottom of the work area. With
the man rider still being available as and when required.

Stone Facing to Legato Block Wall


 Access to the work area will initially be the temporary staircase and walkway.
 Proprietary platforms will be used
 Masonry slots will be fixed onto the front of the legato block wall (riverside) with masonry bolts.
 Cut stone approximately 100mm thick will then be built up to a predetermined level for the day
 Materials will be lifted into position by the crane under the control of the slinger/signaller.
 Work will continue until the legato blocks have been fully covered with the stone facing blocks.
 The new blockwork wall is not to be tied into the existing wall at either end but finish flush with the
edge of the Legato blocks.

Backfilling behind the retaining wall.


 Once the block wall has been completed the wall is to be backfilled.
 The Tailings which were removed and stockpiled will be used to backfill behind the wall.
 The backfilling will carried out in accordance with the Contract Specification MMD-00-XX-DR-C-6008-
60011CONC)
 The long reach excavator will carry out this function.

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 17 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 18 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Section 10 Emergency procedures


Certain activities will require the development of specific emergency procedures. Examples include confined space entry, working
from MEWP/MCWP, roof work, working in proximity to overhead power cables, working in areas that are hazardous to health e.g.
presence of substances/chemicals whether they are present as part of Client operations or as part of our activities. This section
shall be completed in these events and shall contain details of the procedure to be followed, the names of responsible persons,
their roles and contact numbers/details
Procedure in response to a Safety Incident

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 19 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

In the event of a General Emergency / Injury:


 Inform site management (Nick Hoctor 07580851559) in the first instance. First aider to administer first aid if
minor injury. If more serious call emergency services 999 (112 mobile) or arrange for Injured Person to be taken
to A&E (hospital route in site QES pack.)

Hospital Route below: Cumberland Infirmary, Newtown Road, Carlisle, CA2 7HY

In the event of injured persons need recovering from to ground level.


 Inform site management (Nick Hoctor 07580851559) in the first instance
 First Aider to Assess safe access/egress a stretcher is to be lowered into the bottom of the works by either crane
or taken down access staircase First aider to administer first aid if minor injury. If more serious call emergency
services 999 (112 mobile) or arrange for Injured Person to be taken to A&E (hospital route in site QES pack.)

In the event of personnel falling into a watercourse:


 Only trained personnel on site to carry out the following:

1. 1 person to take charge of the situation from the embankment (Organise/supervise) - Call emergency services
999 (112 from mobile) (Hazardous Area Response Team (HART)) after calling the emergency services he / she
is to delegate the following:

- 1 person to carry out casualty care (calm / reassure) & immediate rescue (self, rope or pole rescue only (if
available))
- 1 person downstream to carry out rope or pole rescue only (Shout & throw only), if available
- 1 person upstream to debris spot & prevent boats entering that may cause more danger, if applicable.

2. Remaining people on site are to assist in keeping crowd back to prevent people entering dangerous waters,
guide emergency services, assist person carrying out casualty care, assist person attempting to carry out
downstream rescue.

********** UNDER NO CIRCUMSTANCES SHALL ANYONE ENTER THE WATER TO ATTEMPT RESCUE ***********

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 20 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Procedure in response to an Environmental Incident

If a fuel spillage or hydraulic hose burst occurs:


 The spillage should be contained to the immediate area by the use of soils and the Spill kits should be deployed
to absorb the spillage where possible. The Site Agent (Nick Hoctor 07580851559) or Supervisor should be
summoned to advise of the appropriate course of action to clear the spillage and arrange for the contaminated
materials to be correctly disposed of. The EA hotline will be contacted on 0800 807060 to report any spillage or
incident

 Silt netting to be installed prior to the installation. Adequate additional silt netting to be available to deploy
downstream of the works in an emergency
In the event of a major environmental incident, Operations Manager, Contracts Manager or Lead QES
Advisor ONLY are to contact Specialist Environment Clean up Sub-Contractor Alder & Allan (available 24/7
365 days a year) (0800 592827)

Procedure in response to a Fire

In the event of a Fire:


All Site Personnel will evacuate to the Assembly Point till Emergency Services arrive. The Fire Marshall (Nick
Hoctor 07580851559) will then undertake a “role call”. If the Fire is able to be put out by site fire extinguishers or
soils to snuff out without placing Operatives or Plant in jeopardy, this may be actioned. The Site Manager (Nick
Hoctor 07580851559) / Supervisor should be summoned immediately in the event it can’t be controlled.

Procedure in response to other Activity Specific incidents

Section 6d –Uncontrolled Land slip during Construction Activities


 Batters/slopes to be visually checked everyday before loading crane pad.
 Watching brief of the Batters to be constant whilst construction activities are ongoing.
 Crane/excavator to be positioned as far back as possible on the Crane pad
 Any movement/cracking of batters witnessed Alarm Call to be given.
 If deemed safe All plant to be removed as far back as practically possible otherwise all plant
operators are to egress their machines immediately and move to the Access Ramp
 All operatives in the excavation shall retreat upstream of the works to the far bank.
 All operatives on the top of the TSF to retreat to the Access Ramp.
 No plant/operatives are to return to the areas until given the All Clear by the Site Management (This
after consultation with Specialist Advice)
 In the event that there is a significant collapse which has infiltrated the River Allen Operations
Manager, Contracts Manager or Lead QES Advisor ONLY are to contact Specialist Environment Clean
up Sub-Contractor Alder & Allan (available 24/7 365 days a year) (0800 592827)

Section 11 Personal Protective Equipment


In accordance with Company site rules, personnel must wear hard hats, safety boots and high visibility jackets / vests and
gloves at all times in work areas. On some of our Frameworks; light eye protection is also mandatory. In addition to mandatory
PPE; the work covered by this method statement also requires:

Light eye protection Y Face fitted RPE Waterproofs


Medium impact goggles Safety wellingtons Life Jacket / Preserver Y

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 21 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Hi-viz jacket / vest (yellow) Harness Y Gauntlets


Ear plugs Restraint Lanyard Cut resistant gloves
Ear muffs Fall Arrest inertia block Y Other (describe)
Other (describe) Other (describe) Other (describe)

Section 12 Permits to Work


The following Permits to Work will be required for this activity (refer to OSS 004);
Permit to Dig
Permit To Load( Crane Pad)

Section 13 Labour

The following labour resources are expected to be utilised during the course of this activity.

Job Title / Designation Number Specific Training / Competence Required


General Foreman 1 SMTS First Aid
Lead Hand 1 CSCS
Machine OP 1 CSCP
Operative 2 CSCS, Slinger/Signaller
Crane op 1 CSCP

Section 14 Management and Supervision


Implementation of the approach / methodology and various risk control measures identified in this risk assessment and method
statement will be monitored by the Site Supervisor with the assistance (where applicable) of the Site Engineer / Works Manager
/ Foreman / Lead Hands. Details as below:

Site Supervisor Name: Nick Hoctor Role Site Agent

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 22 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Section 15. Briefing


Before any work commences, the Site Supervisor will ensure that a briefing is provided for all personnel involved in carrying out
this work activity.

The work activity briefing is intended to be a two-way process and all operatives are expected to challenge the proposed
approach, particularly if they feel that a safer and more practical work method can be adopted.

All personnel will sign below to confirm that they understand the content of this risk assessment and method statement.

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 23 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Name (Print) Name (signature) Company Date

Section 16 Management of Change Record

Additional Hazards and


Control Measures Changed
Date Details of change to methodology / environment documented in RA Approved by
(Sections 1 / 2 / 3) (sign)
(Y / N)

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 24 of 25
J N Bentley Management Systems

BIMS 02-04.3 Risk Assessment / Method Statement

Control measures
31/05/1
Change of methodology due to ground conditions encountered added in Emergency
8
Response Section

Form No. BIMS 02-


© J N Bentley 2017 04.3
Revision: K Date: 28/06/2017 Page 25 of 25

You might also like