Project :
Client :
MECHANICAL COMPLETION FOR PUMPS
SYSTEM : DATE : ………………………………..
SUB-SYSTEM : LOCATION :
TAG NUMBER : REVISION : ………………………………..
DOCUMENT NO. : PAGE : 1
RESULT
No ITEM CHECK LIST DATE SIGNATURE REMARKS
YES NO N/A
Installed as per PID/construction drawings
1
approval
Visual Inspection for complete and correction
2
installation
3 Check initial alignment
4 Bolt Tensioning
5 Check Name plate
6 Cleanliness equipment
Pump skid and support installed base on
7
contruction drawing approval
Preservation has been done as Procedure
8
Preservation
Noted :
Received in apparent good Condition
Conforms to contract specifications
Prepared By, Checked By, Checked By, Approved By,
Client
Project :
Client :
MECHANICAL COMPLETION CERTIFICATE
SYSTEM : DATE : ………………………………..
SUB-SYSTEM : LOCATION :
TAG NUMBER : PAGE : 2
DOCUMENT NO. :
XXX herewith notify XXX & XXXX, that all sub-system/system/discipline for…....................for the…...............
have been achived Mechanical Completion and is ready for pre-commissioning activities.
This certificate confirms that the above items, as defined, have been pre-commisioning in full accordance with all applicable drawings,
specification and procedures. That all specified test have been completed to consider the system as mechanical completion
Noted :
Received in apparent good Condition
Conforms to contract specifications
Prepared By, Checked By, Checked By, Approved By,