Checklist For Fabrication & Installation of Tensile Fabric Shades

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

PROJECT NAME

CHECK SHEET FOR: Form No. :


Fabrication and Installation of Tensile Fabric Shades Rev. No. :
0
SUBCONTRACTOR CONTRACTOR 1 of 1
  Page :

Section of Work: CIVIL – SITE WORKS Location:


Level:
Checked by Checked by
STAGE ITEM DATE
S/C CONT. CONSULTANT
Sub-Contractor/ - Check Sub-contractor / Supplier approval.
Sup Approval
Material Approval - Check Material as per approvals for the tensile
fabric, steel components, cables and fittings.

Shop drawing - Check work as per approved shop drawing


Approval showing details of fabrication, assembly,
installation and fixing of specific items or
components are available.
Incoming material - Check seam width at overlap of fabrics to be
inspection 35mm minimum.
- All the cables to be class A

Storage and - Check the delivered material is stored under


Protection dry, shaded and well ventilated conditions to
prevent formation of wet stains.

Survey and - Check all the levels and layouts as per


Setting out approved shop drawings.
Steel erection - Check accurate bearing of steel on foundation.
- Check as per approved drawing.
- Check colour of the steel is as per the
approved colour.
- Touch up for steel paint to be done
Preparation for - Contact surfaces area free from factors
Installation of causing rips or scratching during installation of
Fabric fabric panels.
Installation of - Any wrinkles or damages in the surface
Fabric rectified.
- Fabric is cleaned and dirt and panel markings
are removed
- Check colour of Fabric as per approved & no
notable shade.
- Joints of Fabric is as per shop drawing
- Joints at Fabric is neat and same width

For S/C: Date: For CONTRACTOR QA/QC: Date For CONSULTANT REP. Date:

Name: Sign: Name: Sign Name Sign: