Correction Rules For Tender Errors
Correction Rules For Tender Errors
20 September 2002
Scope
This Circular promulgates the new rules for correcting errors that may be
found in tenders for works contracts. For the purpose of this Circular, “error” here
means arithmetical error or any form of deviation from a conforming tender including
without limitation omission to provide the required information pursuant to a condition
of tender.
Effective Date
3. The correction rules appended to WBTC No. 24/98 are not applicable to
tenders issued on or after 1.10.2002.
Implementation
4. The correction rules appended to this Circular shall apply to all works
tenders for which the first notice of tender invitation is issued on or after 1.10.2002.
Departments should draw tenderers’ attention to its use in the first 6 months, i.e., tender
invitations made between 1.10.02 and 31.3.03.
( W S Chan )
Deputy Secretary for the Environment,
Transport and Works (Transport and Works) W2
Section 1 - General
1.1 For errors which have been specifically addressed in the general or special
conditions of tender, the errors shall be dealt with strictly in accordance with the relevant
conditions of tender. The following rules shall only apply where the errors have not
been specifically addressed in the conditions of tender.
2 If the following error(s) in the pricing document are found after the
opening of tenders, correction shall be made as follows, depending on the type of
contract being tendered: *It is not subject to re-measurement.
(前期數量出錯可補回)
(a) The tender sum stated on the Form of Tender shall remain
unchanged irrespective of any corrections made hereinafter. If
there is a discrepancy between the amount in “words” and in
(b) If there are errors in the Bills of Quantities, they shall be corrected
(i)如果發現缺少《⼯程量清 as follows:
單》的⼀⾴或多⾴,則在以下
第(ii)款的規限下,缺失⾴中所
(i) if one or more pages of the Bills of Quantities are found
有項⽬的費率應標記為零,並且
應將其視為費⽤已被允許在《⼯程 missing, subject to sub-paragraph (ii) below, the rates for all
量清單》其他地⽅輸⼊的費率,以 items in the missing page(s) shall be marked as zero and the
及
costs shall be deemed to have been allowed for in rates
entered elsewhere in the Bills of Quantities, and
(ii)如果⼯程量清單中包含臨時
⾦額,應急費⽤,主要成本總 (ii) where the Bills of Quantities contain a Provisional Sum, a
額,任何其他預定價項⽬或它們 Contingency Sum, a Prime Cost Sum, any other pre-priced
的任意組合,並且投標⼈沒有在
其⼯程量清單中正確包含任何或
item or any combination of them and the tenderer fails to
所有這些項⽬,則應在⼯程量清 include any or all of them correctly in his Bills of Quantities,
單中正確恢復這些⾦額。和 then such sum (or sums) shall be correctly reinstated in the *** (1g)
Bills of Quantities; and
Optional item, Pc rate, Pc qty- (item1 i)不計?
(iii)結算Sub-total sum?
(iii) errors in the casting of cash columns shall be corrected; and *** (1g)
(iv)Amount/ agree with the (iv) the extension may be amended to agree with the quantity and
quantity = Revised rate ;
可以修改延伸利率與數量和費率 rate or (dependent on the judgement of the tender examiner)
相⼀致,或者(取決於招標審查 the rate may be amended to agree with the quantity and the *** (1g)
員的判斷)可以修改費率以與現
⾦欄中的數量和延期相符,但在
extension in the cash column but in no case will the alteration
任何情況下都不會更改允許利率 of both rate and cash extension be permitted; and
和現⾦延期;和
(v) indistinct rates shall be clarified to agree with the quantity
(v)Rate x qty = Amount
and the extension in the cash column.
(c) Where no extension amount and no rate has been made against any
item or quantity in the Bills of Quantities it shall be deemed that the
(c) 如果未對⼯程量清單中的任何
項⽬填寫⾦額和費率,則應視為
cost of the item or quantity has been allowed for in rates entered
已在⼯程量清單中其他位置輸⼊ elsewhere in the Bills of Quantities and the rate shall therefore be
的費率中已計⼊該項⽬或數量的 marked as zero.
成本,因此該費率應標記為零。
新item沒加; marked 0 Where new item is introduced Rate for the new item shall be
marked as zero
(f) After correcting all the errors in accordance with (1)(b), (c), (d) and
(e), the difference between:
在按照(1)(b), (c), (d)和(e)糾正所有錯誤之後,兩者之間的差異為:
投標總價減去所有臨時總和,應急總
(i) the tender sum minus the total of all Provisional Sums, the
和,主要成本總和(但不包括利潤和 Contingency Sum, Prime Cost Sums (but not profit and
出勤率),任何其他預定價項⽬和調 attendance on them), any other pre-priced items and the
整項
Adjustment Item, and Optional item, Pc rate, Pc qty- (item1
i)不計?
(ii) the corrected total of the Bills of Quantities minus the total of
校正後的⼯程量清單的總和減去所有
臨時總和,應急總和,主要成本總
all Provisional Sums, the Contingency Sum, Prime Cost
和(但不包括利潤和出勤率),任何 Sums (but not profit and attendance on them), any other
其他預定價項⽬和調整項⽬的總和 pre-priced items and the Adjustment Item
(g) Subject to (1)(h), the plus or minus percentage will be applied to the
tendered rates including those corrected under (1)(b)(iii) and (iv) *** (1g)
除(1)(h)另有規定外,加減百分⽐將
適⽤於招標價格,包括根據 (1)(b)(iii) and including Preliminaries/Preambles but excluding all pre-priced
& (iv) 進⾏更正的價格,包括初步/序
⾔,但不包括所有預定價項⽬
items and the Adjustment Item.
除可以根據需要調整投標⼈ The same principle and relevant procedures as in (1) shall apply except
提交的價⽬表和近似數量以 that the Schedule of Rates and approximate quantities submitted by the
反映要進⾏的近似⼯作量以
tenderer may be adjusted as necessary to reflect the approximate
使計算出的總價值外,應採
⽤與(1)相同的原則和相關 quantities of work to be carried out so that the total value so calculated is
程序。 等於投標⾦額,⽬的 equal to the tender sum, with the intent that resultant rates may be used for
是根據合同條款使⽤合計匯
valuing variations in accordance with the terms of the Contract.
率來評估變化。 僅在發⽣算
術錯誤或數量嚴重錯誤時才 Adjustment of quantities and rates should only be necessary in the event
需要調整數量和費率。 of arithmetical errors or when the quantities are grossly in error.
擴展⾴和總數的錯誤應予以糾
(i) Errors in extensions and casting of page totals shall be
正,並在總帳中列明已更正的⾦ corrected and the rectified amounts carried to the
*** (3b-vii)
額。 General/Grand Summary.
如果發現缺少《⼯程量清單》的⼀⾴ (iv) If one or more pages of the Bills of Quantities are found
或多⾴,則在以下第(vi)款的規定 missing, subject to sub-paragraph (vi) below, the rates for all
下,缺失⾴中所有項⽬的費率應標
記為零,且費⽤應視為已經 允許在
items in the missing page(s) shall be marked as zero and the *** (3b-vii)
數量清單中其他位置輸⼊的匯率
determined as follows:
*Same as lump sum with bills of quantities
新item沒加; marked 0 Where new item is Rate for the new item shall be
introduced marked as zero
(c) After correcting all the errors in the manner abovementioned, the
tender sum shall be corrected to the corrected grand total of the Bills
在以上述⽅式糾正所有錯誤之 of Quantities.
後,應將投標⾦額更正為已更正的
⼯程量清單總額。
END