Appendix To Tender
Appendix To Tender
Location
Appendix to Tender
Clause, Sub-Clause references and terminology according to FIDIC ‘Conditions of Contract for Plant
and Design-Build for Electrical and Mechanical Plant, and for Building and Engineering Works
Designed by the Contractor, First Edition 1999, Errata Reprint’.
Sub-
Item Clause Entry
Definition of Sections:
Description Value: %* of Time for Completion Delay Damages
(Sub-Clause 1.1.5.6) Accepted Contract (Sub-Clause 1.1.3.3) (Sub-Clause 8.7)
Amount days QAR per day
(i) School and To be determined 770 days 75,000
Associated from BoQ
Works Taking
Over
* These percentages shall also be applied to each half of the Retention Money under Sub-Clause 14.9
Sub-
Item Clause Entry
Definition of Milestones:
Description Time for Completion Penalties
(Sub-Clause 8.6) (Sub-Clause 8.6) (Sub-Clause 8.6)
i) School Works ready for 707 days QAR 25,000
AV & ICT works (active
components) to
commence by other
contractor
Delay Damages for the Works 8.7 & QR 450,000 per day
14.15(b)
Maximum Amount of Delay Damages 8.7 10% of the final Contract Price Total
Advance Payment 14.2 10% of Accepted Contract Amount
Number and timing of instalments 14.2 Instalments: one
Timing: per Sub-Clause 14.2 and on
Engineer’s consent to Contractor’s
programme
Start repayment of advance payment 14.2(a) When the total of all certified interim
payments (excluding the advance payment
and before deductions and repayment of
retention) exceeds the amount of advance
payment paid
Repayment amortization of advance 14.2(b) At 10% of the total of all certified
payment interim payments (excluding the advance
payment and before deductions and
repayment of retention) or at such a rate
that the total advance payment amount is
fully repaid by the Contractor when the
Works are taken-over
Percentage of retention 14.3 10%
Limit of Retention Money 14.3 No limit
Plant and Materials shipped 14.5 (b)(i) Not applicable
Plant and Materials delivered to Site 14.5 (c)(i) List of Plant and Materials:
All Plant and Materials
Currency/currencies of payment 14.15 Qatari Riyals
Sub-
Item Clause Entry