Preventive Checklist For Process Equipment
Preventive Checklist For Process Equipment
no Activity Frequency 1
1 Check the condition of take off knife , if found any damage replace the
knife Daily
2 Check the tension and joint condition oven wire band Daily
3 Check all the rollers running indication rotating propeller Daily
4 Gas leakages to be check Daily
5 Check the working of auto lubrication system Daily
6 Check the working of band tracking limit switch Daily
Operator Signature :
Operator Signature :
Operator Signature :
DISHA FOODS Pvt. Ltd
PREVENTIVE CHECK LIST
OVEN
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
MONTH:
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
MONTH:
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
DISHA FOODS Pvt. Ltd
PREVENTIVE CHECK LIST
OVEN
Frequency 1 2 3 4 5 6 7 8
1 Check the any noise in rollers gear boxs & chins and should be done Weekly
2 Check all C-fan & T-fan V-belts condition, if required replace the belt Weekly
3 Leak test to be done for gas pipe fittings near Burner Weekly
4 Burner air dampers to be clean with air Weekly
5 Tighten all nuts & bolts Weekly
6 Check all motors bearings condition & lubrication to be done Weekly
7 check the bottom roller working condition Weekly
Check the drum mounting & tightners position & lubrication to done for
bearing blocks & handle gear box
8 Weekly
16 Leak test to be done for main secondary stage gas line & PRVs Monthly
4 Check main drive tyre coupling condition & tighten all bolts Weekly
5 Tighten all base nuts & bolts Weekly
6 Check the endless motor sprockets & chain condition & apply lubrication Weekly
7 Check all rollers bearing & apply lubrication Weekly
8 Check the oil level in gear box Weekly
7 Check the oil level in main gear box & tilting gear box Monthly
8 Check the tension of main drive chain Monthly
9 Clean the stacker brush to remove any biscuit dust particles on it Monthly
10 Check gland rope packing, if required replace
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
MONTH:
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
MONTH:
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31