How To Change 2G To Master and 3G To Slave
How To Change 2G To Master and 3G To Slave
• Some times RBS Batteries not charging when 3G is Master so we change 2G to Master
Batteries start charging
• Before you start to take action check Battery voltage
• After you make 2G master all external Node ,External alarm ,RU position should be
define
• Check RBS Batteries voltage should be about (54-55)VDC
• Make sure if you have 2 FAN group should be standard and if 4 FAN group it should be
extended
• Follow slides one by one till the end
Change Master and Slave in DUW
In this Example we want to make DUG Master therefore we have to start with Element Manager
3
1
2
4
Change Master and Slave
In this Example we want to make DUG Master therefore we have to start with Element Manager
3
1
2
Change Master and Slave in
Baseband
Form your Browser write ( https://169.254.2.2 ) Select EMGUI
Login Method Choose Username ( User name :rbs & Password :rbs )
rbs rbs
Change Master and Slave ( If BB Is Master)
From Equipment Technology then Select this link
Change Master and Slave ( If BB Is Master)
Go Equipment Support Function then Click Edit Attributes
Change Master and Slave ( If BB Is Master)
If Support System Control is ON means BaseBand is Master , if Off means it’s Slave
Change Master and Slave 2G –OMT
then Open OMT
Go Configuration then Define then Node Parameters in support System Control ( if its true means DUG
is Master and if it’s False means Slave )
In this Example already False We Have to Change it to True
Change Master and Slave
then Open OMT
3
Change Master and Slave
then Open OMT
BEFORE AFTER
2
Define RU Position
Configuration then Define then RU Position
Define RU Position
Select Device We have two section shelf and Slot
Define RU Position
Shelf , Slot Distribution
Define RU Position
Adding External Node
In order to adding External Node you have to make your Node Master then add Existence node that
you have to know its EC Port
Adding External Node
Then add External Node , in this example our External Node connected A6
Adding External Node
Then add External Node , in this example our External Node connected A5
Adding External Node
Then add External Node , in this example our External Node connected A5
Adding External Node
Now is added
Thanks