WMS of Plasterboard Ceiling Installation 1
WMS of Plasterboard Ceiling Installation 1
WMS of Plasterboard Ceiling Installation 1
Ceiling Installation
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 1 of 11
Reviewed by Approved by
Project
Submitted by Manager
Contractor Project Engineer Construction
QA/QC EHS
Manager
Signature
:
Name:
Date:
Time:
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 2 of 11
Table of Content
Section Description
1.0 Introduction
2.0 Resources
2.1 Material
2.2 Machinery & Equipment
2.3 Manpower Involved/Plan
2.4 Contractor Involved
3.0 Primary Requirement
3.1 Coordination Requirement
3.2 Others Operation Requirement
3.3 Receiving
3.4 Handling
3.5 Storage
4.0 Work Activity Methodology/ Arrangement
4.1 Site Preparation
4.2 Mobilization & Installation
5.0 Inspection, Testing, and Commissioning Proposal
6.0 List of Attachment / Appendices / References / Drawing
7.0 Hirarc Assessment
1.0 Introduction
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 3 of 11
This document shall address the typical work for plasterboard ceiling installation work at KM5 May21 new
building.
IMCS Specification: -
2.0 Resources
2.1 Materials
All materials used on site must be approved type and they are as follows: -
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 4 of 11
3.2.2 Location for storage and the type of material to store must be approved by
Kinetics.
3.3 Receiving
3.3.1 Once material received on site, prepare to unload and arrange inspection with
Kinetics QAQC for approval before delivery to site for installation work.
3.3.3 Upon arrival of the material, the consignment shall be verified by the supervisor to
match the packing list and inspected by Kinetics QAQC & Client.
3.3.4 All material received at site shall be visually inspected for any damages.
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 5 of 11
3.4 Handling
3.4.1 By manual handling, safety concern and safe equipment operating techniques.
Workers to avoid overloading the transporting equipment while moving materials.
Controlled by Site Supervisor.
3.4.2 Supervisor shall monitor the work and ensure the work is complied with all safety
requirements.
3.5 Storage
3.5.1 Proper barricade & barrier ownership tagging to be used for materials storage.
3.5.3 Keep storage areas free from accumulated material that cause tripping, fire, or
explosions, or that may contribute to the harboring of rats and other pest.
3.5.4 Daily housekeeping shall be carried out to ensure the cleanness of the area.
4.1.2 Investigate & coordinate of existing buildings, structure, M&E which may affected
the progress of the works.
4.1.3 Identify the storage location for materials, tool and equipment.
4.1.4 The working areas must be barricade using barricade cone and safety tape to
avoid people to enter the working area.
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 6 of 11
No Activity Sequence
1 a) To inform related Project Manager, System Owner and KINETICS EHS
management before start work for the day.
b) To obtain the entire relevant valid EHS document, SIPP and PTP before start
work.
c) To assign all the workers, staff to attend safety induction before start work.
d) Get the valid permit for the workers and machinery to enter the site.
c) Precautions must be taken before and during activity in accordance with DOSH
standard and Intel Safety standard.
d) During the progress of activity, the work shall be under the continuous
supervision of a supervisor.
3 Covid-19 Prevention
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 7 of 11
i) If found abnormal of body temperature, kindly report it out to Kinetics EHS and
Intel EHS. Required to go to Kulim Hi-Tech government hospital for further
checkup.
j) All other standard Covid-19 safety measures and procedures by Intel and
Kinetics to apply and follow strictly throughout the entire progress.
a) To inform related Project Manager, System Owner and EHS Management before
start work for the day.
b) Obtained the entire relevant valid EHS document before start work.
d) Shall be use manpower to mobilize the materials into the work location and
storage area with proper signage and barrier ownership.
e) Get advice from KINETICS project management team for the location for material
storage.
f) Shall be used forklift or pallet jack to mobilize the materials into the work area if
necessary.
5 To brief the workers on the job sequence and streamline their job for hazard
avoidance prior work starts.
6 a) To prepare the power supply to the working area by using extension wire for
temporary lighting at night.
Method statement
7 Preparation of work
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 8 of 11
Site activity will not commence until confirmation that all the planning and
safety checks are completed.
Supervisor shall be familiar with the shop drawing and method of statement.
To inform and obtain prior approval from Kinetics EHS, Project Coordinator
before start work.
To use mobile scaffold or ladder for work at height.
Setting-out
The ceiling installation location to be marked out for reference to follow.
Introduction
This Method Statement describes a proper work procedure shall be carried
out during the Gypsum Plasterboard Concealed Ceiling Installation works
stage as per stated in shop drawings.
Control Measures
To build live mock-up section for QAQC (QAM) inspection and buy off before
proceeding with installation work.
Line walk with relevant parties.
Arrange a meeting before start the job with together with Kinetics and Intel.
Make sure supervisor monitor closely the job.
To comply with proper PPE such as safety helmet, face shield, face mask,
safety boots, hand glove, safety vest and ear plug.
Workers must wear safety harness and hooked at solid structure.
Scaffold erected by qualified personnel and supervised by scaffold supervisor.
Weekly inspection by scaffold supervisor.
Guard rail, mid rail and toe board should be erected at scaffold platform.
Spotter must be full time below the working area.
To ensure that ladder being used inspected, tagged and safe to use.
Buddy system while using ladder.
Three-point contact at ladder.
Spotter must be full time below the working area.
Barricade the work area with relevant warning and safety signage.
Secure tools, materials and equipment in proper method when working. Use
strap or buckets.
Ensure all power tools were inspected and tagged before operating it.
Use the right tool for the job.
Operate tools according to the manufacturers' instructions.
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 9 of 11
To check live system if already works are completed entire at above ceiling
level.
To use mobile scaffold or ladder to work at height.
To ensure the level set by the main contractor at the respective floors as
follows: Setting point to the areas are set to the required ceiling level.
To ensure mark the ceiling level for the ceiling channel are on the side of the
wall.
To fix the plaster ceiling in accordance to the method of installation.
To Inspect metal stud and track are properly assembled and set before the
plaster ceiling is to be ready for installation.
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 10 of 11
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name: Date: 11/06/2022
Contact no.:
Company:
Page 11 of 11
ITP shall also address the “Hold Point”, where approval on the work activity is required.
Refer to Attachment 1: Inspection and Test Plan
ITP Reference Number :