Water Manager QTR Report WM
Water Manager QTR Report WM
Water Manager QTR Report WM
Introduction
Significant progress was made in the month of December to move the Jackson water system forward
towards a more stable, reliable, and safe drinking water system as highlighted in this quarterly report.
These foundational steps set the stage for rapid implementation of the projects required to stabilize the
system quickly as possible. The Christmas Water Crisis (described in detail herein) was a painful
reminder of how fragile the system remains as it will for months or even years as we work to overcome
decades of underinvestment.
It should be noted that all of this work was accomplished without any funding beyond the more than
$60,000 of my personal resources I fronted to get this process moving quickly – there was no time to
wait for the slow process of funding by the Parties. Beyond using my personal money to get things
moving, I leveraged my personal relationships to get contractors to start on my promise of future
om
payment. I am grateful to all who responded so generously to this urgent need and my pleading
requests.
.c
The following report is organized in alignment with paragraph 16 of the Order.
ya
Description of Projects and Activities la
• Initial work to create an entity to accomplish the work required under the Stipulated Order (SO)
was timely completed in December 2022.
ba
o A Mississippi corporation was created – JXN Water. All state and Federal requirements
(tax ID number) were completed.
am
o As required by the Order, the professional, operations and management (O&M), and
capital improvement accounts were created; the Parties notified of their creation; and,
nj
the information for each account was provided to the Court under seal.
• Retained legal counsel.
so
• Drafted and issued an RFP for engineering services and three national firms were selected from
the responses received
• Drafted and issued an RFP for Distribution System Valve and Hydrant Assessment and issued
notice of intent to award to Wachs Water.
• Solicited a proposal for assistance with billing and collection of past due accounts and selected
Promise Pay.
• Solicited a proposal for assistance with identification of lead service lines and selected Blue
Conduit.
• Completed Federal grant reimbursement training (6 hours).
• Attended 2 press conferences.
• Attended 3 community meetings/townhalls.
• Attended 2 City Council meetings.
• Met with Mississippi Public Service Commission.
1
• Met with City officials about personnel and equipment transition, funding transfers.
• Met with the Mississippi Community Foundation.
• Looked for new office space for the WSBA.
• Participated in multiple meetings regarding specific funding:
o American Rescue Plan Act Funds (“ARPA”) – 2 meetings, including one with Hinds
County officials
o Army Corps Of Engineers Section 219 Funds – 2 meetings
o EPA Community Grant Funds – 2 meetings
o MS State Revolving Fund – 1 meeting
o Safe Drinking Water Act Section 1442b funding – multiple meetings
• Participated in multiple interviews for local and national press.
• Led meetings with the water meter contractor.
• Met with Jacobs, a national O&M company for water systems, about setting long-term contract
in place.
om
• Hired 3 people – Chief Operating Officer, Chief Experience Officer, Drinking Water Program
Manager.
.c
• Managed the Christmas Water Crisis response and recovery as follows:
o On the evening of December 23rd and into the early morning hours of December 24th, a
ya
rapid drop in temperature (in excess of 40 degrees in 6 hours) caused a change in the
thermocline that exists in the Ross Barnett Reservoir. As temperatures dropped, the
la
density of the surface water became greater than the density of the deep water and the
ba
water turned over (the deep water rose to the surface and the surface water sank to the
deep). The water quality of the two layers of water differs in many characteristics, some
am
of which are critical to the water treatment process. Unfortunately, night operations
were unable to take the appropriate corrective action fast enough to prevent turbity to
rise in the water in the plant and had to slow production to allow the treatment process
nj
to recover. This slow down in water production created lower pressures in the system.
so
The result was a loss of nearly all water stored in the system.
ck
o During the day on December 24th, the treatment process was fully restored, but the lost
storage, combined with high demand as customers left faucets open to prevent freezing
Ja
in their homes and businesses, and the additional cold weather induced pipe breaks in
the distribution system, could not be overcome and much of the City lost water
pressure late on December 24th, with customers waking up to no water on Christmas
morning. With a significant loss of pressure in the system, a precautionary boil water
notice was issued covering the entire service area. Over the next several days, as
pressures and storage could be recovered, the precautionary notice was lifted by zip
code as many areas, especially those geographically closer to the treatment plants
which had only suffered minor pressure losses of short duration. Required bacteria
testing was performed prior to lifting the precautionary notice in any section of the
service area.
o A post event review of the causes and recovery found no single issue created the crisis,
but it was a combination of events.
2
The first was lack of additional staff to assist over the holidays. Jacobs was providing staff
augmentation through a Secondment[] Agreement but could not actually operate the plant due
to liability issues. Through the month of December, Jacob’s staff members advised JXN Water
operators (City employees under the authority and direction of the ITPM since the Effective
Date of the Stipulated Order) based on their extensive operating experience. This arrangement
had largely stabilized treatment and the plants in December up to the Christmas holidays. As all
of the Jacobs’ team was from well beyond the Jackson area, the ITPM allowed them to go home
for the holidays. As such, none were present to advise and assist during this climate- induced
water quality change.
The second factor was the lack of redundancy and flow-paced chemical controls
as well as sensors at the water intake at the reservoir. Those system weaknesses
were previously identified and are addressed in the priority project list included
om
in the Stipulated Order.
The third factor was a failure to adequately communicate to the customers, the
.c
appropriate way to allow just a trickle of water flow from faucets to prevent
ya
freezing without using too much water.
la
o The Jackson water system will remain vulnerable and at risk of similar failures for
ba
several more months as the priority projects are implemented and the full operation
and maintenance contract is put in place. This Christmas Water Crisis highlights the
am
need to execute the work as required by the Special Order as quickly as possible. The
following table lists status of the priority project list through December 31, 2022.
nj
3
SRF Omni 5.a.i Distribution System
Assessment/Modeling
1442b 5.a.ii Valve and Hydrant Issued notice of intent to award
Assessment contract
1442b 5.a.iv Distribution System
Leaks - Find and Fix
ARPA (Hinds 5.a.v Distribution System Assisted Hinds County in developing
Co) Optimization - South ARPA project with this scope of work
Jackson
SRF Omni 5.a.v Distribution System
Optimization
1442b 5.a.vii Service Line Inventory Selected Blue Conduit to do this with
JXN Water
SRF Omni 5.a.viiCorrosion Control
Renewal
om
1442b 6 System Stabilization
and Sustainability Plan
.c
1442b 7 SCADA Improvements
ARPA 8 OBC/JHF Chemical
ya
Feed Improvements
Comm Grant 9 Chlorine System
la
Replacement
ba
SRF Omni 10 Intake Structure Repair
1442b 11 Plant Treatment
Processes
am
Filters/Conventional
and Membrane
ck
• None encountered. While they cannot be quantified yet, supply chain issues continue to be a
potential delay in executing several of the projects included in the priority project list.
4
Accounting of Expenditure from, Additions to, and Remaining Balance of the ITPM Professional
Budget
• The ITPM budget will not be funded until the Quarter ending March 31, 2023. A full accounting
will be provided with that quarterly report. It should be noted that no allowance was made
during the development of the ITPM budget for needs related to the WSBA which was a last
minute add to the Stipulated Order. A request for additional funding for this purpose will be
made in the next quarter.
• Preliminary engineering will commence on several projects included on the priority project list in
the next quarter.
• The Valve and Hydrant assessment work will begin in the next quarter.
om
• The distribution system “Find and Fix” program will be well underway in the next quarter, with
as many as 50 leaks found and repaired in the next quarter.
• The Alternative Water Response Plan will be drafted but not finalized in the next quarter.
.c
• Additional staff and contractors will be added to the JXN Water team.
ya
la
ba
am
nj
so
ck
Ja