Daily Diary - 947 RPT - 12-12-2022 - NS

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

General Consultants

For Chennai Metro Rail Project,


Phase - II

CHENNAI METRO RAIL LIMITED

DAILY DIARY

Contractor: L&T Construction Limited Day: Monday

Reported By: Santhosh Shift: Night

Report No: 947 Rainfall: No

STATION: Royapettah Metro Station

Night Shift Work Progress

1. D-wall PB1-5(P): Bite-1 Trench excavation in progress. Current depth = 22.35m/26.67m.


2. Guide wall grid-15: base PCC work.
3. 10 Trip de-sander muck disposed.
4. De-watering Pumping Arrangement:
10HP pump – 1 no (Near store sump).
2HP pump – 1no (Near Site entrance).
5HP Pump - 1no (Near hospital entrance).
2HP pump – 1no (Near North shaft).
2HP pump – 1no (Near store).
2HP pump – 1no (Near Labor Rest area).

Slow/ Nil Progress

 East side available from stage-3 traffic diversion done on 06.11.2022, trial trench work started on
08.11.2022 but work is slow due to lack of manpower.
 East side D-wall scope length – 352.494m, work front available – 50.761m length. Due to trial
trench utility & diversion identification work delay in d-wall.

Safety & Environment Issues


General Consultants
For Chennai Metro Rail Project,
Phase - II

 Improper Material stacking & revised site utilization plan to be submitted.


 Wheel wash bay and boot wash to be provided.
 Trial trench area proper hard barricading with sign board to be displayed.

Safety & Environment Related Observations & Non-Conformances

SI. No. SOR Issued? Description of SOR NCR Issued? Description of NCR

1 No
-
No -

Quality Issues

 Reinforcement should be rested on wooden logs instead of placing on ground & need to cover.

Quality Related Observations & Non-Conformances

SI. No. SOR Issued? Description of SOR NCR Issued? Description of NCR

- -
1 No No

Plant & Equipment Details

SI. No. Description

1 Bauer Trench Cutter – 1 No


(10.02.2022 assembling work started and TPI completed on 21.02.2022)

2 Backhoe loader – 2 No

3 80T Crawler Crane – 1 No

4 100T Crawler Crane – 1 No


(Mobilized to site on 19.02.2022 and TPI completed on 21.02.2022)

5 DG (500 KV A – Desander & Site Supply) – 1 No


(19.02.2022 Mobilized and 26.02.2022 Charged)

6 DG 250 KV A – Office & Site Supply) – 1 No


(27.05.2022 Mobilized and 30.05.2022 Charged)

7 Light Mast (7.5 KV A) – 1 No


General Consultants
For Chennai Metro Rail Project,
Phase - II

8 Bar Bending Machine (7.5 HP) – 2 Nos


(16.03.2022 Mobilized and 1nos - 16.04.2022 Charged, 1nos – 17.05.2022 charged)

9 Bar Cutting Machine (7.5 HP) – 1 Nos


(16.03.2022 Mobilized and 1nos – 16.04.2022 Charged)

10 Step down Transformer (800 KV A) – 1 No


(Mobilized on 27.04.2022, Not Charged)

11 Diesel Air Compressor – 1 No (Mobilized on 11.03.2022)

12 Chipper – 1 No

Plant & Equipment Breakdown/Idle Status

SI. No. Description

1 100T Crawler crane – 01 No Idle (09:00 PM to 06:00 AM)

2 80T Crawler crane- 01 No Idle (09:00 PM to 06:00 AM)

4 Bar Bending & Cutting Machine – 01 No Idle (09:00 PM to 06:00 AM)

5 Chipper- 01 No idle (09:00 PM to 06:00 AM)

Manpower Report

SI. No. Descriptions No. of Persons

1 L&T Staffs 08

2 Supervisors/ Skilled Workers 13

3 Unskilled Workers 17

4 Sub-contractor 00

Total Manpower at Site 38


General Consultants
For Chennai Metro Rail Project,
Phase - II

Site Progress & Shortcomings Photographs with Description

D-wall PB1-5, Trench excavation work Guide wall grid 15, Base PCC work.

Muck disposal

Subramanian Ramaiah Sanjeev Kumar Mandal

Resident Engineer Chief Resident Engineer