DAILY DIARY
East side available from stage-3 traffic diversion done on 06.11.2022, trial trench work started on
08.11.2022 but work is slow due to lack of manpower.
East side D-wall scope length – 352.494m, work front available – 50.761m length. Due to trial
trench utility & diversion identification work delay in d-wall.
SI. No. SOR Issued? Description of SOR NCR Issued? Description of NCR
1 No
-
No -
Quality Issues
Reinforcement should be rested on wooden logs instead of placing on ground & need to cover.
SI. No. SOR Issued? Description of SOR NCR Issued? Description of NCR
- -
1 No No
2 Backhoe loader – 2 No
12 Chipper – 1 No
Manpower Report
1 L&T Staffs 08
3 Unskilled Workers 17
4 Sub-contractor 00
D-wall PB1-5, Trench excavation work Guide wall grid 15, Base PCC work.
Muck disposal