Bim Execution Framework For Early Stage Estimating in PPP Projects
Bim Execution Framework For Early Stage Estimating in PPP Projects
June 2019
BIM Execution Framework
for early-stage estimating
in PPP projects
rics.org/research
BIM Execution Framework
for early-stage estimating
in PPP projects
Sadhana De Silva
Chartered Quantity Surveyor and Researcher, Australia
Dr Robert Osei-Kyei
Lecture in Project Management, Western Sydney University,
Australia
Dr Lei Zhou
Chairman, Shanghai Dragonboat Investment Management Co., Ltd,
China
Dr Xiaohua Jin
Senior Lecturer in Project Management, Western Sydney
University, Australia
Dr Nirodha Fernando
Lecturer, University of Salford, UK
Dr Solomon Babatunde
Lecturer, Obafemi Awolowo University, Nigeria
Dr Yingbin Feng
Senior Lecturer in Quantity Surveying, Western Sydney University,
Australia
Research Team:
Dr Qijuan Liu
Tianjin University of Technology, China
Mr Qian Liu
Glodon Company Limited
Mr Bingbing Zhang
Glodon Company Limited
Research Funders
RICS Research Trust, UK
Glodon Company Ltd., China
Steven Matz
Global Research Assistant
Study sponsored by : [email protected]
Fabrizio Varriale
Global Research Assistant
[email protected]
Contents
Executive summary......................................................................................................9
1.0 Introduction...................................................................................................12
2.0 Methodology..................................................................................................13
3.0 Overview of the Public Private Partnership concept............15
3.1 PPP process and models...................................................................15
3.2 Cost estimating practices in PPP....................................................17
3.2.1 Estimating for PPP projects in the UK............................................17
3.2.2 Use of estimating in PPP projects in Australia.............................18
3.2.3 Use of estimating in PPP projects in China...................................19
8.0 Conclusions....................................................................................................53
8.1 PPP projects and the state of construction industry.................53
8.2 Main research findings......................................................................53
8.3 Recommendations.............................................................................54
9.0 References.....................................................................................................55
10.0 Acknowledgements...................................................................................57
List of Figures
Figure 1 Research method.....................................................................................13
Figure 2 Phases of PPP delivery process............................................................16
Figure 3 PPP models................................................................................................17
Figure 4 Traditional vs. BIM estimating method................................................21
Figure 5 Process protocol model for BIM-enabled estimating of
capital construction cost of PPP projects.........................................34
List of Tables
Table 2.1 Expert information..................................................................................14
Table 5.1 Status of cost estimating in PPP projects (UK)................................26
Table 5.2 Status of BIM-enabled cost estimating at early stages of
PPP projects (UK)....................................................................................27
Table 5.3 Status of BIM-enabled estimating practice in PPP projects
at industry level (UK)...............................................................................27
Table 5.4 Status of cost estimating in PPP projects (Australia)....................28
Table 5.5 Status of BIM-enabled cost estimating at early stages of
PPP projects (Australia).........................................................................29
Table 5.6 Status of cost estimating in PPP projects at industry level
(Australia)..................................................................................................29
Table 5.7 Status of cost estimating in PPP projects (China)...........................30
Table 5.8 Status of BIM-enabled cost estimating at early stages of
PPP projects (China)...............................................................................31
Table 5.9 Status of cost estimating in PPP projects at industry level
(China)........................................................................................................32
Table 6.1 Definition of terms for process protocol model for
BIM-enabled estimating projects........................................................35
Table 6.2 Guidelines on using the model...............................................................37
Table 6.3 Extent of agreement results on overall satisfaction
(Expert Forum Round – 1 Outcome)....................................................38
Table 6.4 Results on extent of agreement on model update...........................39
Table 7.1 Ranking of drivers by UK PPP experts.................................................41
Table 7.2 Ranking of drivers by Australia PPP experts.....................................42
Table 7.3 Ranking of drivers by China PPP experts............................................43
Table 7.4 Ranking of drivers by all respondents
(UK, Australia and China).......................................................................44
Table 7.5 Validation results of overall top 5 rankings of drivers for
implementing BIM-enabled estimating practice in PPP.................45
Table 7.6 Ranking of barriers by UK PPP experts...............................................46
Table 7.7 Ranking of barriers by Australia PPP experts....................................47
Table 7.8 Ranking of barriers by China PPP experts..........................................48
Table 7.9 Rankings of barriers by all respondents.............................................49
Table 7.10 Validation results of overall top 5 rankings of barriers for
implementing BIM-enabled estimating practice in PPP.................50
Table 7.11 Best practices in BIM-enabled estimating for PPP
projects and their country-specific rankings....................................51
Abbreviations
AEC Architecture Engineering and Construction
AFC Anticipated Final Cost
AIQS Australian Institute of Quantity Surveyors
BEFEP BIM Execution Framework for Estimating in PPP projects
BEP BIM Execution Plan
BIM Building Information Modelling
BLT Build-Lease-Transfer
BOO Build-Own-Operate
BOOT Build-Own-Operate-Transfer
BOT Build-Operate-Transfer
BQ Bills of Quantity
BTO Build-Transfer-Operate
CECA China Engineering Cost Association
CIC Computer Integrated Construction
CPPPC Social Capital Cooperation Centre
DBFO Design Build Finance Operate
DBOM Design Build Operate Maintenance
DIT Department of Infrastructure and Transport
ECOSOC United Nations Economic and Social Council (French Abbreviation)
EOI Expression of Interest
EPC Engineering, procurement and construction
GC21 General Conditions of Contract 21
GDP Gross Domestic Product
HM Her Majesty’s
IBC Institute for BIM Canada
NATSPEC National Building Specification
NDRC National Development and Reform Commission
NRM New Rules of Management
NZIQS New Zealand Institute of Quantity Surveyors
OECD Organisation of Economic Development and Co-operation
PFI Private Finance Initiative
PPP Public Private Partnerships
PSC Public Sector Comparator
QS Quantity Surveying
RFP Request for Proposal
RICS Royal Institution of Chartered Surveyors
ROT Rehabilitate-Operate-Transfer
UK United Kingdom
VfM Value for Money
Executive summary
The use of Public Private Partnerships (PPP) as the vehicle The key advantages were efficient process of design and
to procure large-scale social and physical infrastructure estimating through reductions in time, clash detection,
projects is becoming increasingly deployed around the ease of dealing with changes and analysing their impact,
globe. This international study evaluated the use of PPP increased speed of decision-making, and visualisation,
procurement in the UK, Australia and China as three of among others.
the most mature and rapidly developing users of the PPP
The challenges were the scarcity of skilled personnel
procurement route. It focused on the ways of improving
who have knowledge and experience in using BIM
digitalisation in PPP procurement with the use of Building
and in particular for estimating, absence of a standard
Information Modelling (BIM) and its impact on early-stage
guideline for use of BIM for estimating purposes, software
estimating. This research aimed at developing an execution
integrations issues, and lack of client appetite to develop
framework for BIM-enabled early-stage estimating for PPP
BIM models (or spend for it), among others.
procured projects, learning from the situations in these three
most advanced user countries. The expectation is that such The recommendations that flow from these include: greater
a framework will also help the rapidly developing countries, levels of industry-wide training of personnel, universities and
who are increasingly reliant of PPP types of procurement. tertiary education establishments focusing on more training,
development of BIM-related estimating standards, and
The construction industry although contributing over US$10
policy level government led support (as in the case of the
trillion per annum and having 13% of global GDP is one
UK mandating level 2 BIM for public sector projects over
of the least digitalised industries (McKinsey, 2017). The
£16m). It is recommended that BIM adoption especially
past decade saw the dawn of the 4th Industrial Revolution
for estimating purposes should occur at the Project
exacerbating the need for digitalisation of the construction
Development Phase to Request for Proposal (RFP) Phase
industry, which is facing global challenges. BIM has been
where PPP consortia can implement BIM models in their
the answer of the construction industry to achieve this step
bids that would include the first generation of BIM-enabled
change although the proliferation of the FinTech sector is an
estimates for the project.
imminent addition in the decade to come. There are varying
levels of adoption of BIM in the construction industry in the This report proposes an execution framework for BIM-
three countries examined, with the UK having the lead with enabled early-stage estimating in PPP projects with three
the most mature levels of adoption and use, followed by primary components:
China and Australia.
1. Process protocol model for BIM-enabled early-stage
The research examined the practice of estimating in PPP estimating in PPP projects (Section 6.2)
projects in these three countries and concluded that there 2. Drivers and barriers for BIM-enabled early-stage
are growing similarities in the perception of advantages, estimating that should be considered (Section 7.1)
challenges and recommendations that make for the greater
adoption of BIM-enabled estimating for PPP projects. 3. Best practice guidelines for adopting BIM-enabled
early-stage estimating in PPP projects (Section 7.2)
The process protocol model (Figure 5 on page 34) is the These had cross-board acceptance from all six
main component that provides step by step guidance on international experts.
how to integrate BIM-enabled estimating at early stages
Barriers for the adoption of BIM-enabled estimating
of PPP projects. This model helps in developing a BIM
at early stages of PPP projects were defined as the
Execution Plan (BEP) for the project. Project managers,
inhibitors that discourage the use of BIM-enabled
cost managers and BIM managers involved in the project
estimating. Understanding barriers that apply to each
should use this proposed process protocol as the basis of
country is important so that adequate steps can be
a considered and systematic adoption of BIM for estimating
taken to eliminate such.
purposes. In adopting the process protocol, one should
consider the estimating practice of the country concerned. The top three barriers identified in the UK were:
For example, in the UK, the New Rules of Management Technological issues, followed by Inadequate relevant
(NRM 1) developed by the Royal Institution of Chartered knowledge and expertise in using BIM and Poor
Surveyors (RICS, 2012a & b) should be considered, while in information sharing and collaboration issues.
Australia, estimating guidelines produced by the Australian
The top three barriers in Australia were: Inadequate
Institute of Quantity Surveyors (AIQS) can be considered.
relevant knowledge and expertise at the top, followed
Similarly, in China, the China Engineering Cost Association
by Cultural resistance for using new technologies
(CECA) has detailed guidance on developing estimates
like BIM and Incompatibility between BIM data and
using its index or quota-based systems that should be
standard practices.
considered. The process protocol is designed in a generic
manner enabling easy adoption to fit individual country- The barriers identified in China were very much similar to
specific requirements. It is also accompanied by a table what was identified in the UK and Australia where the top
that defines and describes each of the terms in the protocol three were: Technological issues, at the top followed
(Table 6.1) followed by guidance notes for implementation by Inadequate relevant knowledge and expertise in
(Table 6.2). using BIM, and Implementing BIM is expensive/Cost
overrun with BIM respectively.
Understanding the drivers and barriers for BIM-enabled
estimating at early stages of PPP projects is vital for the There were six barriers identified at the top for all countries.
successful implementation of the process protocol. Drivers These were: Inadequate relevant knowledge and
are the factors that encourage and enhance the adoption of expertise in using BIM, which was clearly at the top.
BIM for early-stage estimating. Though, both second and third ranked barriers did not have
full consensus they were in overall terms: Technological
The top three drivers for the UK were: Government
issues and Low quality of BIM data. The fourth ranked
pressure towards better practices was top, followed
barrier, Incompatibility between BIM data and standard
by Easier communication and collaboration between
practices did have full consensus of all experts. Two
all stakeholders. Both Cost savings and increased
barriers were jointly ranked fifth by all experts: Cultural
efficiency in monitoring with reduction of requests
resistance for using new technologies like BIM and
for information and Greater access to information,
Liability issues including professional licensing,
enabling earlier input into feasibility, planning, design,
design liability and vulnerability to changes of BIM
costs and environmental assessment were the joint third
by unauthorised parties.
most important driver.
The third key component of the framework is the best
In Australia, the top three Drivers were: Desire for
practice guide for BIM-enabled estimating (Table 7.11) at the
innovation to remain competitive at the top spot
early stages of a PPP procured project. The guide identifies
indicating commercial pressures, followed by Accurate
seventeen aspects that BIM managers, project managers
construction sequencing and clash detection and Time
and cost managers should consider in implementing the
savings in the preparation of cost estimates respectively.
process protocol proposed. These are categorised into
The situation in China especially at the top was similar Process, Practice and Policy, covering the three main areas
to Australia with Desire for innovation to remain of concerns for implementing BIM-enabled estimating. The
competitive being considered the top driver, followed by Process category contains the measures that practitioners
Improving the capacity to provide whole life value to need to carefully consider when they are in the process
client and Facilitating increased pre-fabrication with of using the BIM for early-stage estimating. The second
information-rich BIM. It is interesting to see the emphasis category, Practice consists of practice that ensures the
China puts on prefabrication here. overall management of the use of BIM in early-stage
estimating in PPP projects. This informs practitioners of
The top four drivers for all countries were: Desire
the measures to take into consideration when drafting PPP
for innovation to remain competitive, Accurate
contracts and a BIM Execution Plan. The third category,
construction sequencing and clash detection,
Policy provides measures on how governments and
Improving the capacity to provide whole life value
external stakeholders could help to facilitate the use of BIM
to client, and Client/Competitive pressure respectively.
in early-stage estimating in PPP projects.
1.0 Introduction
Satisfying clients’ requirements has been the focal point BIM, which is the platform for an integrated project
of landmark reports since the publications of Sir Michael delivery approach, can add value to PPP projects by
Latham’s report (Latham, 1994) and Sir John Egan’s providing an established medium for collaboration and
report (Egan, 1998). For instance, over the years, the information sharing among the stakeholders (Laishram,
construction industry has been criticised for its poor 2013). McArthur and Sun (2015) affirmed that PPPs are
performance by both government and institutional now becoming an increasingly popular procurement
reports across the globe. The recent report published method and are highly challenging as they require the
by McKinsey (2017) on the global construction industry collaboration of the designers, constructors and operators
shows global construction productivity improving at the from the earliest stage of the project, with each having a
low rate of 1% compared to manufacturing at 3.6%. The particular perspective. Therefore, balancing the conflicting
situation is worse in the case of digitalisation where the needs and identifying where they align are critical steps
construction industry is lacking behind all other industries in project planning (McArthur and Sun, 2015). Hence,
except agriculture. This is corroborated by Ashworth using BIM in PPP projects can provide substantial benefits
and Perera (2015) and Elmualim and Gilder (2014) that to the project team by facilitating the information flow
fragmentation exists in the division of obligation between between stakeholders, minimising duplication of efforts
the professions, professionals and contractors. These are and allowing the team to make informed decisions to
the basis of the ill-disposed culture between contractors, optimise the project over its lifecycle.
subcontractors, suppliers and their clients. The main
Relevant previous works, especially by Laishram (2011)
goal within the construction industry is to deliver a well-
explored the hurdles in the implementation of BIM to
designed, quality product to meet clients’ requirements,
manage the construction projects procured through
on time and within budget. Be that as it may, a large
PPPs. Ganah and John (2013) examined the suitability of
proportion of construction projects fail to achieve client
BIM for enhancing value for money (VfM) in PPP projects.
satisfaction. For example, according to Egan’s report,
McArthur and Sun (2015) reviewed the best practices for
in the UK around 30% of construction projects, usually
using BIM in PPP projects among others. Despite these
buildings, fail to meet clients’ requirements in terms of
previous studies, there is a dearth of efforts at exploring the
quality (Cunningham, 2013). It is against this backdrop that
application of BIM to early-stage cost estimating for PPP
many researchers advocate Building Information Modelling
projects. Thus, research on the integration of BIM into early-
(BIM) as the panacea and a genuinely necessary change
stage cost estimating for PPP projects is a timely need. It
in the construction industry. BIM has certainly created a
is on this premise that this research becomes imperative
clamour in the construction industry to shift the way that
with a view to developing the best practice framework for
design and construction documents are produced and
BIM-enabled early stage cost estimating for PPP projects in
communicated. In joining developed countries like the US
order to enhance value for money in PPP projects.
and those in Scandinavia where high-level adoption of BIM
is found, the UK government mandated the use of BIM This research aims to achieve the following:
by September 2016, for all those involved in larger-scale
• Review methods of estimating practised in early-stage
public sector projects.
estimating for PPP projects
BIM has received much attention in the management • Explore application of BIM to early-stage estimating
of infrastructure projects delivery with the possibility
to change the traditional construction practices. For • Analyse best practice in estimating and use of BIM
instance, a number of earlier researchers have alluded to for estimating
the benefits of BIM, such as reduction in design errors, • Evaluate drivers and barriers for BIM-enabled
reduction in project time and cost, better production early-stage estimating in PPP projects
quality, lifecycle data management, and an integrated
• Develop an execution framework for BIM-enabled
project delivery approach that encourages collaboration
early-stage estimating
among different stakeholders to the project over its
lifecycle (Ashworth and Perera, 2018). Public Private The next section identifies the approach used to achieve
Partnerships (PPPs) are exceptionally complex contractual these aims.
arrangements evolved to manage different risks
associated with projects by assigning the responsibilities
to various project stakeholders. Increasingly, governments
around the world consider PPP as an option of choice
for large-scale physical and social infrastructure projects.
2.0 Methodology
The research methodology consists of a literature review, The case studies phase of the research involved primary
organisational case studies and Delphi-based expert data gathering through case study interviews identifying
forum. These qualitative methods enable the research organisational practice of early-stage estimating and the
to capture the state of BIM-enabled estimating in PPP level of use of BIM. It enabled the research to identify
projects at an in-depth and comprehensive level enabling best practice, as well as identify weaknesses that
a holistic view. The overview of the research method is require improvement leading to drivers and barriers.
provided in Figure 1. The conceptual process model established was further
developed and reviewed in this phase.
The research data was gathered from three partner
countries: UK, Australia, and China. Each country was The final phase of the research involved the formation of
represented by a project team that investigated the an Expert Forum consisting of six international experts
use of PPP, the early-stage estimating processes and in PPP and estimating. The forum included two experts
the level of use of BIM in PPP projects for the three from each country as indicated in Table 2.1. It enabled the
countries. Information gathered was collated and analysed research to capture the knowledge and experience of the
subsequently to develop the framework. experts in PPP and BIM. The expert forum was conducted
in two stages where drivers and barriers for adoption
The literature review was initially used to conceptualise
of BIM for estimating in PPP projects were reviewed
the state of early-stage estimating in PPP projects and the
and refined. It further enabled the research to refine
use of BIM in general. The first stage of the review was
and validate the process model developed at the case
to develop a greater understanding of the PPP process
studies phase and to finalise the framework. The final BIM
and stages involved and the role of estimators at different
Execution Framework consists of drivers and barriers for
stages. This was followed by a review of BIM and the level
BIM adoption in early-stage estimating in PPP projects, a
of use in general. Subsequently, drivers and barriers for
detailed model for executing BIM-enabled estimating and
the adoption of BIM were investigated. This stage helped
a set of best practice guidelines.
in conceptualising a process model for BIM-enabled
estimating in PPP projects. The next section of the report examines the estimating
process in PPP projects and the issues related to use
of BIM.
• Final framework
Expert
– Model
forum
– Drivers & barriers
– Best practice
Years of
Country Designation Qualifications experience
UK Expert 1 Associate Professor in BIM & Digital Technologies, MSc in Information 15 years in academia,
Research Fellow Technology in Property construction industry
and Construction research and advisory
PhD (Computer-Aided-
Learning in Building
Pathology)
Expert 2 Construction Manager /Group CEO International, PGCert APL, FCIOB, 42 years in construction
The Chairperson of a professional institution FCMI, FIoD, FHEA, EURBE industry
Australia Expert 1 Senior Cost Planner of a leading international B App Science in 32 years in
property and infrastructure company involved in Building, OAM, FAIB construction industry,
PPP procurement and academia
China Expert 1 Vice General Manager of an engineering company, PhD, MSc (Mgmt), BEng 12 years in construction
General Secretary of a municipal association, industry specialising
Deputy Dean, (PPP research Centre) of a university in PPP
Expert 2 Consultant to the World Bank OECD and the B.Eng., M.Eng., M.Fin. 20 years in construction
ECOSOC of the United Nations; and PhD industry, research and
Advisor to the Ministry of Finance of China, the academia
State Development and Reform Commission and
many local governments in China on PPP
Approval of project
investment and
procurement
Key steps:
• Assemble resources
Project • Develop a project plan
Development
Phase • Develop a probity plan
• Commence key works streams
• Private sector interface
Key steps:
• Develop invitation for EOI
Approval to Expressions
invite expressions • Obtain approval to release
of Interest
the EOI
of interest Phase
• Release invitation for EOI
• Evaluate EOI responses
• Shortlist bidders
Key steps:
Approval to issue Request for • RFP development phase
an RFP to shortlisted Proposal – Develop RFP documentation
Phase
bidders – Seek approval to release
• RFP bid phase
• RFP evaluation phase
• Selection of preferred bidder
Approval
of preferred
bidder Key steps:
• Establish then negotiating team
• Set the negotiation framework
• Report to government
• Contract close/execution
Negotiation • Financial close
and Completion
Phase
Key steps:
• Formalise management
responsibilities
• Monitor project delivery
• Manage variations
Approval • Monitor the service outputs
to execute Contract • Maintain the integrity of
Management the contract
a contract
Source: Commonwealth of Australia (2016) National Public Private Partnership Guidelines – Vol. 2: Practitioners Guide, 2015, Department of Infrastructure
and Regional Development, Canberra, Australia
Divestiture
Build – Transfer
specifications, preliminary cost plan and estimates that are territories Commonwealth of Australia, 2016, Volume 6. In
lacking a rational basis may prove disastrous for project this context, the Australian PPP market is widely accepted
stakeholders (Li, Shen, and Love, 2005). Furthermore, to be among the most sophisticated and mature PPP
it is well documented that the early-stage preliminary markets in the world.
cost estimate will change around 20% with the final cost
The PSC is developed to test whether PPPs provide
(Ashworth and Perera, 2015, 2018).
better VfM over traditional procurement options and to
Generally, the success of a project largely depends on the act as a benchmark against which bids are compared
accuracy of the early estimate of the project’s Anticipated (Commonwealth of Australia, 2016). Since the PSC is a
Final Cost (AFC) (HM Treasury and Infrastructure UK (2013)). valuable tool for government in determining VfM, it is vital
Furthermore, early cost estimates are vulnerable to that the PSC is prepared carefully and comprehensively.
influencing behaviours when allied to the desires of key The guideline publication Commonwealth of Australia
stakeholders to ensure a proposal secures funding and 2016, National Public Private Partnership Guidelines
meets (sometimes conflicting) objectives. According to – Volume 4: Public Sector Comparator Guidance –
HM Treasury and Infrastructure UK (2013), AFC for any 2008, provides directions on the development and
project or programme consists of two components (1) use of the PSC. The Australian government and all the
a Base Cost (which is the value the estimators believe states and territory governments require application of
represents the most likely expenditure required to deliver PSC to ensure VfM and high levels of integrity in PPP
the requirement) and (2) a Risk Allowance. Furthermore, procurements. This is evident according to publication
risk allowance is accounted for the course of action over Commonwealth of Australia 2016, National Public
the project’s life such as the development of the design, Private Partnership Guidelines – Volume 6: Jurisdictional
the greater understanding of the solution’s interfaces with Requirements – 2014, which contains state and territory
its physical environment, scope changes and specific risks governments’ specific PPP guidelines namely, New
(HM Treasury and Infrastructure UK, 2013). Two steps are South Wales Requirements (2012), Partnerships Victoria
involved when developing the AFC. (1) Generating the initial Requirements (2013), Queensland Requirements (2011),
estimate and (2) Testing the initial estimate against the Western Australian Requirements (2010), South Australian
appropriate project out-turn reference data. The initial cost Requirements (2009), Tasmanian Requirements (2009),
estimate can be created at the inception stage from the Northern Territory Requirements (2009), and Australian
Green Book Supplement. This estimate is usually created Capital Territory Requirements (2009).
from the initial risk estimates and the reference class
It is important that estimated net capital costs should
forecasting (Infrastructure Risk Group, 2013). Importantly,
reflect the best available information and prevailing best
to cross check any early estimate, the out-turn data for
practice, as incorrect estimates may lead to cost overruns
comparable projects should be used (HM Treasury and
and may adversely impact on the interests of project
Infrastructure UK, 2013).
stakeholders. In the case of PPP projects, end users (or
the public sector) generally bear the consequence of
3.2.2 Use of estimating in PPP projects cost overruns by way of paying extra margins on services
in Australia delivered. This is particularly evident in the operation of
In Australia, the growing importance attached to PPP social and economic infrastructure projects procured
procurement at national and state level has led to through PPPs across many countries including UK and
formulating policy and guidelines and establishing separate Australia (Doloi, 2011).
groups and units to assist various government agencies in In Australia, based on data from 56 projects and a survey
undertaking PPPs (Siddiquee, 2011). Australia’s National of 102 quantity surveying firms, Ajibade and Pasco (2008)
PPP Working Group was established in 2004 with revealed that the accuracy of pre-tender building cost
jurisdictional representation of the Australian government estimates has not improved over time and the majority
and all the states and territory governments to lead of the respondents were dissatisfied to a certain degree
PPP policy development and process improvement regarding the accuracy of estimates in the industry.
(Infrastructure Australia, 2018). Subsequently, Australia Notwithstanding, the findings of research conducted in
developed a National PPP Policy Framework and National Australia by Doloi (2011) clearly highlighted the requirement
PPP Guidelines to provide a consistent framework for a radical shift in cost estimation of complex projects
that enables public and private sector collaboration to rather than relying on traditional cost estimation principles,
enhance public service delivery through private sector which remain inadequate in addressing demand for cost
participation in provision of infrastructure and related management in modern complex projects. Thus, BIM
services. According to the Commonwealth of Australia being not new to Australia and having an abundance of
(2016), National Public PPP Guidelines – Overview (2008), advantages may help in enhancing the accuracy of early-
PPP guideline publications comprise volumes (1 – 6) of stage cost estimates, avoiding unfavourable procurement
National PPP Detailed Guidance Material. Deviations from decisions especially in case of PPPs that have direct
the national guidelines are allowed as per the individual impact on public interests.
Jurisdictional Requirements Documents of states and
3.2.3 Use of estimating in PPP projects Investment estimates are of paramount importance as
in China a basis for VfM evaluation and measurement of financial
expenditures. The vast majority of PPP projects in China
In China, the project investment estimate is based on are started once the feasibility study is completed. That
the project design or feasibility study documents at the is, the VfM Evaluation Report, the Financial Capability
decision-making stage that define the composition of Demonstration Report and the PPP Implementation
the proposed project in accordance with the prescribed Plan are all based on the Feasibility Study Report and
procedures, programmes and bases. It is one of the the investment estimates, measurement basis, project
important factors in project investment decision-making output, and operation and maintenance costs, economic
(Yan Ling and Yin Yilin, 2017). evaluation parameters (Gong and Wei, 2016). Moreover,
The Construction Project Cost Advisory Code (GB / T the pre-investment estimate, project output and operation
51095-2015) provides that the estimated investment can and maintenance costs of PPP projects are the core
be divided into construction project investment estimates, basis for calculating government subsidies and feasible
single project investment estimates, and unit project gap subsidies or adjusting users’ payment quotas. If the
investment estimates. The investment estimate in the estimation is not accurate, the data on project output and
project proposal stage can be compiled using the index operation and maintenance costs will have a direct impact
of production capacity, coefficient estimation, proportion on the expenditures of the financial departments and will
estimation, index (quota) estimation or the hybrid method. affect the experience of infrastructure users. Therefore,
The investment estimation in the feasibility study stage the investment estimation benchmark is the basis for the
adopts the quota-based estimating method. These quotas VfM to evaluate and measure the financial expenditure.
are investment indicators or benchmarks that estimates Relevant industrial authorities are required to provide
can be evaluated against. more accurate investment estimation benchmarks, project
output, and operation and maintenance costs benchmarks
In the traditional investment management model, the to enable the implementation of PPP projects.
investment decision-making (feasibility) stage usually
constrains the investment estimation. However, because Inaccurate investment estimates will aggravate the Two
the project conditions are far from being certain at this Standard and One Standard investment in PPP projects
stage, the project construction plan is not yet specific and lead to the project investment being out of control.
enough, and the proposed projects are generally not Both the Ministry of Finance and the NDRC have indicated
yet formed, it is very difficult to estimate investment in the relevant documents that Two Standards and One
and the error can be substantial. More often, in order to Standard in the practice of the PPP project is legal (that
launch the project, investment is underestimated, and is, the social capital with corresponding capacity can
profits are overestimated, while the rigor of investment build itself without further bidding by the contractor at
estimates is ignored. the construction stage). However, Two Standards and
One Standard also has its drawbacks. When selecting
Due to the inaccurate, sometimes missing, preliminary social capital, the basis for project investment and annual
estimates of PPP projects in China, a series of problems government operation subsidy (if any) during the project
have arisen. A corresponding benchmark (index) system operation period comes from the feasibility study report
is missing for the preliminary estimation of PPP projects. and the project investment estimate General Index (Zhang,
According to the information released by the Ministry of 2016). If the estimation of investment is still determined
Finance, the Social Capital Cooperation Centre (CPPPC) using the traditional pricing method (e.g., expanding the
and the National Development and Reform Commission index method or quotas) and the accurate bidding price
(NDRC), such a benchmark system is very important for and pricing system cannot be set up, there is no effective
the development of the more advanced municipal PPP government investment review of the whole process of
projects (such as rail transit, landscape greening, water cost supervision, resulting in the one-time gaming gambler
supply, drainage, heating, hospitals, education, affordable mentality that exacerbates the social capital side to grab
housing PPP projects). Although China has national excess construction profits (Yu, 2012). At the same time,
benchmarks for PPP projects such as rail transit, water PPP projects in this context are similar to those projects of
supply, drainage, heating and underground integrated a general contracting arrangement – both winning bidders
pipe corridors, the benchmark (index) system is not (social capitalists or general contractors) are identified at
perfect enough to guide local practices. Furthermore, the pre-project stage (conceptual or preliminary design
such a system has not been established for landscaping stage) to sign the total contract. It is similar to the method of
PPP projects. Although a clear estimation benchmark cost management and investment control of engineering,
system has not been established for the PPP projects procurement and construction (EPC) projects. Relevant
of hospitals, education and affordable housing projects, industry authorities should formulate more accurate
there are professional reference books (but their accuracy investment estimation indices applicable to various types
is unknown). In summary, it is imperative to establish a of PPP projects in order to curb the risk caused by the
reasonable and sound estimation benchmark (index) Two Standard and One Standard. The earlier stage of the
system to guide the implementation of PPP projects. contracting phase of the project is estimated to be distorted
and the project investment is out of control.
Detailed Cost
Estimate
4.3.1 Issues in the UK et al. (2015) studied the contractual and legal concerns
associated with BIM implementation by looking critically
A BIM Execution Plan (BEP) should be collaboratively
at the GC21 2nd edition, an Australian standardised
developed at the early design stage (Wu and Issa, 2014), to
construction contract. The authors proposed several
identify key project tasks, outputs and model configuration.
changes to the GC21 to suit the implementation of BIM
The Computer Integrated Construction (CIC) Research
in Australia. Some of the proposed changes include: the
Program (2011) described a BEP as a tool to provide a
need to adopt a collaborative contract structure with
standardised workflow and general guidance for strategic
equitable risk and reward mechanisms, recognition of
BIM implementation in a holistic approach for a project or
the model as a contract document and the need for
a group of projects. It is evident that early development
standardisation of communication/information exchange.
and effective use of a BEP has a strong influence on
the success of a project BIM. Against this backdrop Currently, there is no published standard construction
several BEP templates are developed. For instance, in form that specifically stipulates BIM provisions, and this
Australia, NATSPEC (National Building Specification) (2012) is certainly a major setback to BIM adoption for PPP
developed the National BIM Guide, which aims to establish projects in Australia (Kuiper and Holzer, 2013), (DIT,
a set of considerations when using BIM in an Australian- 2012). Notwithstanding, most BIM projects in Australia
based project. The National BIM Guide aims to assist adopt requirements and standards from other countries
clients, consultants and stakeholders to clarify their BIM with similar construction practices, including the UK
requirements in a nationally consistent manner. Furthermore, other projects with BIM adoption, consider
BIM as part of the design documentation (Kuiper and
In the UK, the AEC (UK) (2012) BIM Protocol builds on the
Holzer, 2013), (DIT, 2012). These notwithstanding, there
guidelines and frameworks defined by the UK standards
have been attempts by industry stakeholders to develop
documents including the Construction Project Information
guidelines for the implementation of BIM in the Australian
Committee (2013), and other BEP templates to include
construction industry. For example, NATSPEC (the
the Hong Kong Institute of Building Information Modelling
National Building Specification) has developed the National
(2011), Institute for BIM in Canada (IBC) (2013) and Indiana
BIM Guide, which aims to establish a set of considerations
University Architect’s Office (2015). These are reviewed
when using BIM in an Australian-based project (NATSPEC,
within the context of this research.
2011). The National BIM Guide is currently being used
A review of the BEP templates revealed a strong internal by clients, consultants and other project stakeholders
consistency among the templates. The consistency who are interested in adopting BIM in their projects.
across templates included the need to: set project goals, Moreover, the guide informs project stakeholders of the
define organisational roles, agree on model structure and BIM requirements for specific construction contracts
BIM information exchanges, document technological in Australia (NATSPEC, 2011). Other efforts by industry
infrastructure needs, document and schedule project stakeholders on BIM implementation in Australia includes
deliverables, and identify specific use cases required to the release of the Building and Construction Procurement
achieve these goals. Other requirements include: design Guide: Project Team Integration and Building Information
reviews, programming, maintenance scheduling, facility Modelling at the Australian Construction Industry Forum.
energy analysis, cost estimation, site analysis, 3D design Essentially, this guide provides helpful guidance on BIM
coordination, space management, 4D (phase) planning, issues. Also, the Australia and New Zealand BIM Best
design authoring, building system analysis, code validation, Practice Guidelines published by the Australian Institute
and sustainability evaluation among others. of Quantity Surveyors (AIQS) and New Zealand Institute
of Quantity Surveyors, (NZIQS) (2018), highlight key
4.3.2 Issues in Australia knowledge areas and specifics about BIM, what to expect
in a BIM project, quality assurance, legal issues to be
One of the most reported obstacles to the successful
aware of whilst working on BIM projects and information
adoption of BIM is the perceived legal risks associated
on what quantity surveyors need to know about BIM
with its integration and the need for implementation in
and a timeline of a quantity surveyor’s role in the BIM
a collaborative environment. Undoubtedly, many of the
Execution Plan. This document intends to provide a guide
existing standardised construction contracts used in
for quantity surveyors, cost managers or cost estimators
Australia were drafted before the emergence of BIM.
looking to be involved with a project utilising BIM.
Therefore, many of these contracts do not have BIM
Inevitably, these guidelines may complement the outcome
provisions, particularly on the need for a collaborative
of this research in proposing BIM-enabled cost estimating
environment in contract administration. This has therefore
framework for PPP projects.
been a major cause of delay in the successful adoption
of BIM in the Australian construction industry. Manderson
5.0 Organisational
practice case studies
This section is focused on the findings of face-to-face
interviews conducted in relation to cost estimating
practice in PPP projects in different countries comprising
the UK, Australia and China. Two organisations with
involvement or experience in PPP projects were identified
in the UK and Australia and three in China. A series
of interviews with two key professionals per company
involved in estimating were carried out. The results are
analysed in the following key headings:
1. Cost estimating process used at PPP phases
2. Dealing with differences between cost estimates
prepared at PPP phases and negotiations
3. Extent of computer usage in the estimating process
4. BIM application in estimating for PPP projects (project
level/enterprise level)
5. BIM-enabled estimating practice in PPP projects
(industry level)
The following sections of this chapter present the findings
from the interviews conducted on a country basis. In
presenting the results PPP projects were divided in to two
stages as follows:
• Stage A: Approval of project investment and
procurement selection [initial Public Sector Comparator
(PSC) Development]
• Stage B: Project Development Phase to Request for
Proposal (RFP) Phase (during which the upgraded
project estimate is prepared to compare bids)
UK
Criteria Status
Project team members involved • Project manager, project architect, client, commercial lead, project estimator, project design
in the cost estimating process team, site manager, and construction team members.
Information received to prepare • Mainly conceptual and schematic drawings at the early stage of the project and later on
the project cost estimate specifications.
Tools and techniques for • Use of norms from local authorities, benchmark the contractor’s data against historical data or
cost estimating internal data and further benchmark against the contractor’s pricing strategies, obtain specific
cost from nominated suppliers, cost data from similar PPP project schemes, price books, past
project cost data adjusting the time and location as well.
Level of detail of project • Nominal bills, subcontractor’s quotes, cost analysis, schedules of quantities
cost estimate and early elemental cost estimate.
5.1.2 Dealing with differences between 5.1.3 Extent of computer usage in the
cost estimates prepared at PPP phases estimating process
and negotiations Computers are utilised to a large extent at both stages
It is clear that the public authority responsible for the PPP of cost estimate preparation. Microsoft Excel and CostX
has a primary responsibility to keep the project and the are the most common software used for cost estimating
budget within scope. Therefore, they would go through and report generation. At Stage A, CostX and Excel are
details of relevant work and benchmarks, and afterwards used extensively. At Stage B, Revit and Vico Office cost
compile a summary of differences to reconcile. software are used as BIM-enabled estimating tools. Other
Contractors would generally realise that they must work software used in the preparation of cost estimate includes
within the envelope, for the scheme to go ahead. The Navisworks, Vector5 and AutoCAD (some of which are
contractors (PPP consortia) would always be aware of the used for measuring volumes of road and area etc).
budgetary limits of the project and they usually attempt to
be within these limits. They know that they must reconcile 5.1.4 BIM application in estimating for PPP
the cost plan back to the previous estimate that was projects (project level/enterprise level)
based on the design phase development.
The following table summarises the BIM Application in
estimating for PPP projects in the UK.
Table 5.2 Status of BIM-enabled cost estimating at early stages of PPP projects (UK)
UK
Criteria Status
BIM use • Endeavour to use BIM on infrastructure project delivery especially for road and ports related projects.
Advantages • Time (reduction), clash detection, production of base data, ease of effecting changes in design or
amendment to quantities and rates.
• Design changes or amendments to quantities and rates are very easy to deal with if BIM is used.
• Cost or carbon implications can be generated from federated models.
• BIM-enabled cost estimating tools would be quite quick and can have significant benefit at Stage B,
thereby reducing the taking off time.
• BIM model can be used as a basis of designing other similar projects in future if required.
Challenges • Lack of availability of qualified personnel with relevant BIM and estimating knowledge.
• Quantity surveying (QS) firms working with BIM need to be aware of the limitations of various BIM software
from experience.
• It is difficult and expensive to enforce adopting of standards and maintaining those, as a large number of
designs come through in the form of sketches, which are not properly managed to expected level.
Table 5.3 Status of BIM-enabled estimating practice in PPP Projects at industry level (UK)
UK
Criteria Status
Incompatibilities between BIM-enabled estimating • Not many incompatibilities exist between BIM-enabled estimating output
output and the prevailing estimating practice and the prevailing estimating practice requirements.
requirements/standards in the local construction • Some issues of incompatibility of Bills of Quantity (BQ) items and how BIM
provide quantities.
• Mainly it is associated with the level of training, adopting and adapting,
culture, government requirements and inconsistency. .
Recommendations for enhancing BIM-enabled cost • Better training and better understanding of what is in the market, cultural
estimating in local construction industry change, prompt adoption of BIM while challenging the barriers, federated
model (the model that combines all dimensions of BIM), teaching and
giving experience on BIM-enabled cost estimating software during
the undergraduate or post graduate programmes and increasing BIM
awareness within organisations .
Australia
Criteria Status
Project team members involved • Estimating manager, bid manager, project manager, design manager, design team, cost
in the cost estimating process planners and estimators, subcontractors and supply chain participants, specialist consultants
and estimators and financing institution and facilities manager.
• Majority stay throughout the process to offer cost information and to help with cost estimates
towards achieving the best output.
Information received to prepare • Mainly conceptual and schematic drawings, specification, design brief, schedule of areas and
the project cost estimate client’s preference scheme.
Tools and techniques for cost • Start with looking at the design, cost implication, programme implications related to every
estimating aspect of the building.
• High-level cost planning by means of costing ideas and options while providing feedback to the
design team so that the most optimised solution is achieved at the start.
• Benchmarking in terms of application of cost/m²
• Rates based on other similar projects to form a view on an appropriate value for a project to guide
the consultant’s design to be in-line with the client’s’ expectations.
• In the end, elemental bills with the ability to be coded on trade basis, so that market cost
information is obtained easily on each trade.
Level of detail of project cost • A very high-level cost plan at the start and then progressed to more detailed bill of quantities.
estimate • Final estimate is more detailed than cost/m² of functional area. Elemental bill of quantities with
the ability to change from elemental to trades.
5.2.2 Dealing with differences between 5.2.4 BIM application in estimating for PPP
cost estimates prepared at PPP phases projects (project level/enterprise level)
and negotiations The following table summarises the BIM application in
There is limited room for negotiations between the estimating for PPP projects in Australia.
client and the PPP consortia. Benchmark process and
consultant evaluations are used to ensure prices are cut
down to the minimum possible.
Table 5.5 Status of BIM-enabled cost estimating at early stages of PPP projects (Australia)
Australia
Criteria Status
BIM use • BIM for estimating in PPP is in its infancy and not widely used in PPP bid preparation.
• BIM is mainly used for design purpose and visualisation of some selective PPP projects.
• BIM is used for various estimating purposes of other projects.
Advantages • BIM enables electronic documentation, 3D visualisation, ability to easily detect change, manipulation of
data, good decision-making and speed.
• Quantities can directly be extracted from the model.
• Fully updated model (including what is in that building) is handed over at the end of the project to the
facilities manager/operating authority, making operation of the facility easier.
• 3D BIM makes it possible to visualise, walk through and spin around the modelled designs making clients
impressed with BIM (clients can look at it, feel it and see what is happening).
Challenges • As the design consultants and the estimators have different thoughts on what should be included
on the model, a lot of modification to the model is still required so that it can be utilised to extract
cost information.
• Having the model in a way that information could be extracted easily.
• Lack of appetite for implementing preliminary concept designs into models by designers at the start of
the project.
Table 5.6 Status of cost estimating in PPP projects at industry level (Australia)
Australia
Criteria Status
Existing incompatibilities between • Mismatch in data formats between different software.
BIM-enabled estimating output and
the prevailing estimating practice
requirements/standards in the
local construction
China
Criteria Status
Project team • Initial team includes professionals of various disciplines, technical personnel in engineering technology,
members involved engineering economy, cost and finance, implementation agencies, government-funded representatives,
in the cost feasibility study units, consulting agencies and industry authorities.
estimating process • The bidding team includes professionals from operation department, marketing department, legal
department, commerce department, finance department, investment department and other departments
related to the project.
Information • Initially, relevant policy documents of the PPP project and project operating costs, feasibility study report
received to prepare provided by the implementing agency and relevant industry specifications and standards.
the project cost • The consulting organisation collects the relevant policy documents of the PPP project, the relevant industry
estimate specifications, standards and project operating costs. Basic project operation information obtained through due
diligence conducted by consulting organisation.
• Usually, no drawings but simple sketches along with any relevant information, properties of the building including
the structure, use, several floors above ground, several floors underground, decoration standards, etc.
• At the bidding stage, additional information on project payment mechanism, price adjustment mechanism,
project contract price determination method and adjustment method (if any), engineering quantity list (if any),
distribution of rights and obligations and bidding indicator setting, etc.
• Design drawings for some projects, for which the government completes preliminary works of the project prior to
contract award.
Tools and • Initial project cost estimate using feasibility study and unit costs (cost/m²) based on relevant standards,
techniques for historical cost indicators of similar projects, government-issued quota and current market prices.
cost estimating • The cost estimate at bidding stage compliant with government-issued quota and equivalent to investment
estimate prepared at feasibility study phase.
Level of detail • Initial estimate including benchmark prices based on quantity determined by the feasibility study report and unit
of project cost costs (cost/m²).
estimate • At the bidding stage, the cost estimate including financial data such as financing, loans, and interest % and cost
indicators with reference to unilateral cost of similar projects.
5.3.2 Dealing with differences between project is completed, it will be settled with the construction
cost estimates prepared at PPP phases and party according to the actual situation. The preliminary
estimate is only a reference.
negotiations
Where there is a difference between the project costs
At Stage A, the project cost estimate is usually based
estimate prepared at Stage B and the selected bidder’s
on the initial feasibility study. At Stage B, if the design
project cost included in the Bid Proposal, the purchaser
documents are obtained, the quotation is generally
shall determine the social capital selected, the difference
based on the design budget. Where there is a difference,
between the social capital bid quotation and the purchase
the design estimates supersede and if the feasibility
control price. This is only from the client’s side. The bid
study of Stage A is based on the quotation, the stage
price shall prevail, and the operating cost shall be adjusted
will be consistent. After the drawings are published, the
according to the price adjustment mechanism stipulated in
construction and installation project fees will be re-
the PPP project contract.
determined, and the contract will be signed. After the
Table 5.8 Status of BIM-enabled cost estimating at early stages of PPP projects (China)
China
Criteria Status
BIM use • BIM is not used currently for estimating purposes.
• Guanglianda estimating software is used to calculate the amount.
• Even if some design adopts BIM, the information volume of the model is unable to meet the application of
various stages such as cost and construction management.
Advantages • Enterprises do not perceive many advantages of using BIM-enabled estimating when compared to the
traditional use of Guanglianda software.
• Future versions of BIM-enabled estimating will enable modelling costs from inception to final bid model.
• There are many benefits during detailed design development and later operation and maintenance phases.
Recommended • At Stage A, BIM cannot be effectively be used unless it is for a very similar building or structure for which a
best practices BIM model exists.
• At Stage B, BIM models can be developed to support bids. However, the PPP practice in China does not allow
for such level of detail at present. Therefore, to adopt BIM-enabled estimating, PPP practice needs to be
changed through policy drivers.
Table 5.9 Status of cost estimating in PPP projects at industry level (China)
China
Criteria Status
Existing incompatibilities between • Difficulty in using BIM to complete the investment estimating before determining the
BIM-enabled estimating output and investment intention because of its holistic nature. Though it is used at some stage which
the prevailing estimating practice is problematic.
requirements/standards in the • BIM model standards completed by different design institutes are different, thus, unable
to unify the index conditions (cost benchmarks and quota) associated with the cost library
local construction
and the model.
Recommendations for enhancing • Requirement to improve the BIM technology itself and integration with other software.
BIM-enabled cost estimating in
local construction industry
5.4 Comparative analysis of The UK showed the comparatively highest level of usage
followed by China and Australia. Although, general usage
estimating practice in PPP of BIM is much higher in all countries, use of 5D BIM was
projects in the UK, Australia limited and use in PPP projects even scarcer.
Designs at very early stages lack the detail that is required
and China for a BIM model, making its usage at early stages
This section compares and contrasts the PPP project limited. This is universal and common to all countries.
estimating practices between the three countries the UK, The main challenges come from lack of knowledge in
Australia and China. the construction industry on the use of BIM and the
poor level of skills. Education was identified as one of
The project team members involved in bid preparation the primary requirements. Policy and legislative support
stages are similar in all three countries. The notable for BIM implementation was evident in the UK but such
difference here is that in China there were more agencies positive approaches were less prevalent in China and even
involved in these processes. Data provided at bid stages non-existent in Australia. In China, it was clear that the
were much similar in the UK and Australia whereas in absence of a unified standard was a main challenge even
China drawings were usually not provided at this stage. if the designer decides to adopt BIM. In Australia, it was
The findings on the extent of computer usage in the seen that a BIM-enabled cost management best practice
estimating process indicated that there is widespread guide has just been introduced.
computer usage at both stages (i.e. stages A and B) of Policy frameworks and government pressure were seen
cost estimate preparation. In the UK and Australia, Excel as important recommendations for Australia and China.
and CostX were commonly used at Stage A, while Revit All countries would expect greater level of contractual
and Vico Office were used as BIM estimating tools at Stage support for implementation of BIM in projects and in
B in the UK. Microsoft Excel was commonly used at Stage particular PPP projects.
A in China, whereas Guanglida engineering cost software
was used at Stage B. BIM usage in PPP projects was found to be moderate in
the UK. In Australia, there was moderate levels of usage
At Stage A, use of BIM for estimating purposes is not (especially for large-scale projects) for construction
very practical due to the fact that single rate estimating projects in general, but the extent of BIM usage was for
techniques such as cost per m2 is primarily used. However, PPP projects was very low. In China, the extent of BIM
there is a much more positive prognosis for the use of BIM- usage was high generally for construction projects but not
enabled estimating during the Stage B of PPP projects. significant for PPP projects.
Decision
Missing data
Data
Review of PPP documents
Process
Function
Database
Yes Check for contradicting/ Function with
Clarify contradictions
& revise missing information manual input
No
Cost/m2 rate of
functional areas
Check for agreement No Agree on aligning
on aligning model objects with model objects with
cost data formats cost data formats
Prepare preliminary
cost plans Yes
Cost model/Estimate
Update Cost model/Estimate
No
Check for
compliance with price No
guidelines/Quotas
Yes
Table 6.1 Definition of terms for process protocol model for BIM-enabled estimating projects
Review PPP bidding PPP bidding documents are reviewed and checked by all partners of the PPP sponsor consortium
documents including financier, construction contractor and facilities management contractor to determine
if there is missing information that would be vital for bidding. Construction contractors may have
2 their own teams including design, cost and management sub-consultants and various specialised
subcontractors. PPP sponsor consortium liaise with authorised private consultants (PPP
advisory) and public sector authority regarding clarifications on missing information.
Check for contradicting/ Similar checking process as described in above 2 is carried out for contradicting information
3 missing information as well.
Clarify contradictions PPP sponsor consortium liaise with authorised private consultants (PPP advisory) and public
sector authority regarding clarification on contradicting information. After clarifications are
4 and revise
made, relevant documents are revised as applicable. This process is continued until no further
contradiction is found.
Missing data Missing data is obtained from respective sources of information and issued to PPP sponsor
5 consortium by authorised private consultants (PPP advisory) or public sector authority once
clarifications are made.
Develop schedule of The initial schedule of functional areas of the proposed project is developed based on drawings,
specifications, applicable industry standards and norms. As for example, in cases of a school
6 functional areas
project, schedule of areas of classrooms, libraries, staff facilities, sports facilities etc., are
developed based on prevailing industry standards and norms.
Industry standards, There are various prevailing standards and norms applicable to project types, specific
7 norms etc. functions, geographical locations etc. that are utilised in deriving schedule of functional
areas of PPP projects.
Cost/m2 rate of Cost/m2 rates of functional areas are obtained from historical database information, price books,
8 functional area subcontractor quotations etc.
Prepare preliminary This is a very high-level cost plan/estimate, which is prepared to establish the framework cost
9 cost plan for the proposed PPP project. This preliminary cost plan also provides a guideline for cost control
during design development.
Check for agreement on It is important to ensure whether the design team (including BIM manager) and cost planning
team are in agreement on aligning model objects with cost data formats to have compatibility
10 aligning model objects
between BIM model objects and cost data formats.
with cost data formats
Agree on aligning model Agreement between design team (including BIM manager) and cost planning team is expected in
aligning model objects with cost data formats. This would save the time in estimating and helps to
11 objects with cost data
enhance the efficiency of the process.
formats
Design model in a BIM 3D-type BIM is created using information from PPP bidding documents in BIM authoring software.
At this stage, due consideration is given to factors such as construction approach, resource
12 authoring software
planning, complexities of design components, clash detection, programme etc., that would have
direct impacts on project cost.
Translated BIM into Once the translation is done, the model is analysed and reviewed for completeness. 3D
a chosen 5D cost visualisation and virtual reality walk-throughs of the BIM can be used to keep the project team and
client informed of the construction scenario, design, activities etc. Simulated BIM helps to control
modelling software
13 design and value engineering facilitating project costs to be within the framework cost.
BIM data can automatically be exported into bills of quantities templates of computer aided
estimating software. 5D cost model is derived by attaching time scale (to become 4D) and overlay
of costs (to become 5D) to a 3D model.
continued
continued
15 Cost model/Estimate Cost model/estimate is derived applying unit rates to quantities on desirable templates.
Unit cost database Unit rates of bills of quantity items are obtained from various cost databases, price books, etc.
16 These rates are verified through various industry price information sources and subcontractor
quotations.
Subcontractor cost Cost information on specialised trades/elements is obtained through quotations or price lists
17 information from nominated subcontractors/subcontractors.
Cost checks and This involves cost checks and negotiations within members of the PPP sponsor consortia towards
seeking agreement on cost reductions. These cost reductions could be achieved by means of
18 negotiations within PPP
changes to designs, specifications, programmes, rates, overheads and profits etc.
sponsor consortium
Check for agreement on This is seeking the agreement on cost reductions subsequent to the process carried out in
19 cost reductions 18 above.
Check for compliance Prior to finalisation of the estimate, which represents the capital construction cost segment
of the collective bid proposal, further checks are made to see whether the final estimate is in
20 with Price guidelines/
conformity with Price guidelines/Quotas issued by PPP clients.
Quotas
Update Cost Model/ Cost Model/Estimate is updated based on negotiated cost reductions within PPP sponsor
21 Estimate consortium and/or if the Cost model/Estimate does not comply with Price guidelines/Quotas.
22 Update BIM BIM model is updated, if the cost reductions result in design changes.
Detailed cost estimate This is the estimate of the capital construction cost, which is included in the bidding price (among
23 other price components) of the PPP sponsor consortium
6.2.1 The usage of the process protocol Thus, the following guidelines (Table 6.2) offer useful
model for BIM-enabled estimating insights for practitioners on how to use the model in
their respective PPP project environments. The guideline
The process model is intended to be used for BIM- begins with hiring a BIM Manager by a member of the PPP
enabled estimating practice in UK, Australia and China Consortia who is responsible for design, construction,
for PPP projects. However, with each country having its cost management and project management. Their role is
own policies, practices and procedures for PPP project to guide the estimating process utilising the BIM-enabled
execution, caution should be taken to adapt it suitably. estimating process protocol developed.
Evaluate model steps against PPP project practices, policies BIM Manager, Project Manager, Design Manager and Cost Manager
and requirements
Identify practices, policies and requirements, those that deviate BIM Manager, Project Manager, Design Manager and Cost Manager
from the model and decide on how to deal with differences
Prepare coordinated BIM execution plan in line with model BIM Manager, Project Manager, Design Manager and Cost Manager
steps (as applicable) for designing and estimating processes
Inform each project participant of the model process and their BIM Manager, Project Manager, Design Manager and Cost Manager
role and responsibilities
At the end:
Identify deviated practices from the model process and offer BIM Manager, Project Manager, Design Manager and Cost Manager
recommendations for future practitioners on:
• measures to be followed to comply with the modelled
process without deviations
• possible minor amendments to the modelled process,
where compliance is challenging
6.2.2 Validation of model Overall outcome of the Expert Forum Round -2 (Table 6.4)
justifies model satisfaction (first column) validation results
In order to validate the model (from Expert Forum Round
obtained from Expert Forum Round -1, those range
-1), experts from all three countries were invited to rank their
from 3 (Good/Satisfactory) to 4 (Very Good), indicating
extent of agreement with the model. Table 6.3 shows the
their acceptance of the model for its intended practice
overall results for their agreement with the model validation
in PPP projects.
outcome. As shown in the table, the extent of agreement
(second column) mean scores obtained for the overall top In addition, respondents strongly agree on the initial
five rankings range from 4 (Agree) to 5 (strongly agree). validation outcome which is “Very Good” regarding overall
Specifically, respondents strongly agree on the initial satisfaction/benefits which could be achieved in using
validation outcome which is “Very Good” with regard to BIM-enabled estimating over traditional estimating practice
flowing aspects of the model: in PPP projects. This outcome justifies furthermore, the
high anticipation and optimism of the industry experts
a. Comprehensiveness and adequacy of the model
regarding BIM-enabled estimating in PPP projects.
in representing every step of the BIM-enabled
estimating process
b. Ease of understanding the model for use in guiding the
process of cost estimating
Table 6.3 Extent of agreement results on overall satisfaction (Expert Forum Round - 1 Outcome)
Good/
China 3
Satisfactory
4 Agree
Experts’ responses as indicated in Table 6.3 reveal that Overall results on model validation and model updates
they agree on the model update, which is intended to indicate that experts from the UK, Australia, and China
be an improvement in terms of comprehensiveness, agree that the model would provide a beneficial outcome
representation, efficiency and ease of understanding of to their respective countries in influencing efficient
the BIM-enabled estimating process adopted by PPP and effective cost estimating practice through BIM-
sponsor consortia in estimating the Capital Construction enabled cost estimating in PPP projects. This reveals
Cost of PPP projects. There were no further comments on high anticipation and optimism of the industry experts
further improvements on the model. Thus, the model as regarding BIM-enabled cost estimating in PPP projects,
indicated in Figure 5 (page 34) represents the final model which would inevitably become a driver for enhancing
for BIM-enabled Estimating Process for Estimating Capital BIM-enabled cost estimating in PPP projects.
Construction Cost of PPP projects.
7.1.1.4 Overall ranking and comparison ‘Desire for innovation to remain competitive’ is ranked
of drivers for implementing BIM-enabled first with a mean value of 3.92. It is also ranked first by
the Australian and Chinese respondents, whereas the
estimating practice in PPP among the three UK respondents ranked it fifth. This outcome shows that
countries the Australian and Chinese experts considered this driver
Table 7.4 presents the overall rankings of the drivers for more important than their UK counterparts. This outcome
implementing BIM-enabled estimating practice in PPP by is not very surprising because the UK PPP market is not
all respondents. Included in the table are the rankings for as competitive as the Australian and Chinese markets.
each country for the purpose of comparison. This could be as a result of the well matured and
developed UK PPP market compared to the other two
The top three rankings in order are ‘Desire for innovation countries. In Australia and China, local investors face
to remain competitive’, ‘Accurate construction sequencing fierce internal rivalry. In this regard, there is an urgency
and clash detection’ and ‘Government pressure towards for local investors and PPP consortia to be innovative to
better practices’. remain competitive.
Table 7.4 Ranking of drivers by all respondents (UK, Australia and China)
Drivers for implementing BIM-enabled estimating practice in PPP in the UK Australia China Overall
local construction Industry Average Average Average Average Rank
Accurate construction sequencing and clash detection 3.50 3.50 3.75 3.58 2
Time savings in the preparation of cost estimates 3.50 3.00 3.25 3.25 4
Easier communication and collaboration between all stakeholders 4.25 1.75 3.63 3.21 5
Improving the capacity to provide whole life value to client 3.50 1.50 4.50 3.17 6
Designing health and safety into the construction process 2.25 2.00 3.00 2.42 14
It allows precise future prediction of the construction costs 3.00 0.75 2.25 2.00 18
UK Australia China
Rank Overall Ranking for UK/Australia/China Average Average Average Overall Average
5
1 Desire for innovation to remain competitive 4.00 5.00 4.33
(Strongly agree)
4
2 Accurate construction sequencing and clash detection 4.00 3.50 4.33
(Agree)
3
3 Automation of schedule/register generation 4.00 2.50 3.67
(Undecided)
4
4 Improving the capacity to provide whole life value to client 5.00 3.00 4.33
(Agree)
5
5 Client/Competitive pressure 4.00 5.00 4.67
(Strongly agree)
Table 7.6 shows the results on the ranking of barriers by Poor information sharing and
3.50 2
collaboration issues
the UK experts. Four barriers emerged as the top three.
Two of these barriers are ranked second. The barriers Low quality of BIM data 3.00 3
include: ‘Technological issues’, ‘Inadequate relevant Cultural resistance for using new
knowledge and expertise in using BIM’, ‘Poor information 2.50 4
technologies like BIM
sharing and collaboration issues’ and ‘Low quality of BIM
data’. The first ranked barrier is ‘Technological issues’ BIM data ownership issues including
2.50 4
data security
with a mean value of 4.00. Technological issues refer to
the lack of BIM protocols such as client-specific protocols Implementing BIM is expensive/
2.50 4
for estimating the cost of PPP projects. The absence Cost overrun with BIM
of detailed BIM protocol for PPP estimating hinders the Lack of a check mechanism
2.00 5
urgency to adopt BIM for PPP estimating. Although there for designs
could be some BIM protocols in existence, these are not
Liability issues including professional
specifically designed for PPP projects. The technological licensing, design liability and
interface among programs also contributes to the 2.00 5
vulnerability to changes of BIM by
technological challenges in the use of BIM for PPP cost unauthorised parties
estimating. BIM requires many interrelated and cross-
Incompatibility between BIM data
referenced information and interfaces, and these pose a 2.00 5
and standard practices
lot of technological challenges. Estimating PPP project
costs requires a lot of information and it is often difficult Culture of adoption 1.00 6
to acquire the information needed to input into the BIM-
enabled estimating application.
Barriers for implementing BIM-enabled estimating practice in PPP in the UK Australia China Overall
local construction Industry Average Average Average Average Rank
Inadequate relevant knowledge and expertise in using BIM 3.50 5.00 3.83 4.11 1
Incompatibility between BIM data and standard practices 2.00 4.00 3.50 3.17 4
Cultural resistance for using new technologies like BIM 2.50 4.00 2.50 3.00 5
Implementing BIM is expensive/Cost overrun with BIM 2.50 1.50 3.83 2.61 8
BIM data ownership issues including data security 2.50 2.00 3.17 2.56 9
7.1.2.5 Overall ranking and comparison five rankings of barriers for implementing BIM-enabled
of barriers for implementing BIM-enabled estimating practice. ‘Inadequate relevant knowledge and
expertise in using BIM’ and ‘Cultural resistance for using
estimating practice in PPP among the new technologies like BIM’ obtained a score of 5 which
three countries signifies that the experts strongly agree on their positions.
The overall rankings of barriers for implementing BIM- Similarly, ‘Incompatibility between BIM data and standard
enabled estimating in PPP were sent to experts for practices’ obtained a score of 4, which implies the experts
validation. Specifically, experts from the UK, Australia, agree on its position and inclusion in the top five rankings.
and China were invited to rate their level of agreement For two barriers, namely, ‘Technological issues’ and ‘Low
on the top five overall rankings of barriers. As shown quality of BIM data’, their scores are 3.0, which means that
in Table 7.10, the experts generally agree on the top the experts were undecided concerning their positions.
UK Australia China
Rank Overall Ranking for UK/Australia/China Average Average Average Overall Average
2 Technological issues 4 2 5
3
(Undecided)
7.2 Best practices in BIM-enabled the key factors estimators should consider in developing
and designing estimating practices for BIM-enabled
estimating for PPP projects estimating in PPP projects. As presented in Table 7.11,
the best practices are divided into three major categories,
The BIM Execution Framework for estimating in PPP namely: Process, Practice and Policy.
projects comprises a component that highlights best
practices in BIM-enabled estimating. This section presents
UK Australia China
Rank Best Practice Average Average Average Overall Average
Process
1 Prepare a list of bidding documents 4.00 5.00 3.50 4 (Agree)
3 Clarify contradictions and revise documents accordingly 4.50 5.00 4.00 5 (Strongly Agree)
Practice
Make BIM-enabled cost management (including early stage
1 3.00 3.00 5.00 4 (Agree)
estimating) a client requirement
Particular conditions include references to National level BIM
2 guidelines, execution plans, etc as compulsory practices and 4.00 5.00 4.50 5 (Strongly Agree)
procedures to be adhered to
Amend standard forms of contracts to facilitate BIM practices
3 in construction contracts and BIM to be regarded as a 3.00 5.00 4.00 4 (Agree)
contract document
Policy
Government/Public Authorities to prepare BIM guidelines for
1 4.00 4.50 5.00 5 (Strongly Agree)
various practices like estimating
Professional Institutions to support BIM implementation in
2 5.00 5.00 4.50 5 (Strongly Agree)
construction practices and provide training
8.0 Conclusions
8.1 PPP projects and the state of All countries had similar perceived benefits of BIM-enabled
early-stage estimating with increased accuracy of estimates,
construction industry better predictability and cost management, clash detection,
among others. The main concerns revolved around the
Governments worldwide are faced with satisfying increased mismatch of estimator requirements to BIM data outputs,
demand for social and physical infrastructure, exacerbated lack of skills, knowledge and capability to use BIM effectively
by population growth and urbanisation. But they face in estimating and legal issues related to BIM adoption
the dichotomy of balancing tax revenue with public and use among others. There was greater expectation for
spending and consequently seeking alternative sources of governments to intervene and promote BIM adoption, as is
funding. Using private capital for development of large- the case of UK.
scale infrastructure projects is an age-old concept but
received a new lease of life with the large-scale adoption The research proposed a BIM Execution Framework for
by the UK in the early 1990s, resulting in the advent of the Estimating in PPP projects (BEFEP) comprising three
Private Finance Initiative. The common term use for using components:
private capital for public sector projects is Public Private • A process protocol model for BIM-enabled estimating
Partnership (PPP).
• Drivers and barriers for implementing BIM-based
The onslaught of the 4th Industrial Revolution in the past estimating in PPP projects
decade saw the increased need for digitalisation in the
• Best practice guidelines for BIM-enabled estimating.
construction industry. The need is aggravated by the
construction industry being notoriously slow in digitalisation The aim of the model is to develop a process protocol for
(second last among all sectors). The past decade saw the BIM-enabled cost estimating specifically targeted at PPP
introduction of BIM as a primary way to achieve a stepwise projects. The model was developed in three stages of
change in the digitalisation of the construction industry. consultation with the industry experts and finally validated
However, the level of adoption of BIM is not universal and through the expert forum. The model will be a useful
significantly varies between subsectors of construction document to analyse estimating requirements in developing
and countries. With this backdrop this research aimed at an overall BIM Execution Plan for a PPP project.
investigating the use of BIM in early-stage estimating for
Drives and barriers for BIM-enabled early-stage estimating
PPP projects.
were evaluated for all three countries separately. The overall
ranking of drivers and barriers vary slightly in importance
8.2 Main research findings between the three countries. The top five validated drivers
in rank order are: Desire for innovation to remain
This research investigated the practice of early-stage competitive, Accurate construction sequencing and
estimating in PPP projects in the UK, Australia and China. clash detection, Automation of schedule/register
These three countries are seen as countries that have a generation, Improving the capacity to provide whole-life
fairly advanced and mature PPP practice. The primary value to client, and Client/competitive pressure.
methodology employed in this research was to conduct
organisational practice case studies corroborated through a In a similar way the top six barriers in rank order are:
Delphi-based international expert forum of PPP estimators. Inadequate relevant knowledge and expertise in
using BIM, Technological issues, Low quality of
The research revealed there are different levels of BIM BIM data, Incompatibility between BIM data and
usage in the three countries, with the UK having the standard practices, Cultural resistance for using
highest and most advanced level of usage followed by new technologies like BIM, Liability issues including
China and Australia. However, the problems faced in BIM professional licensing, design liability and Vulnerability
adoption were very similar in all countries. The UK and to changes of BIM by unauthorised parties.
Australia have very similar estimating practices (commonly
identified through the British Commonwealth practice of The research also identified seventeen best practice
quantity surveying). China has not yet fully transited to guidelines that were put into three categories as
market-oriented commercial management practices and Process, Practice and Policy. These are measures that
thus the legacy of quota-based estimating systems seems project managers, cost managers and BIM managers
prominent (see Perera et. al 2015 for more details of cost should consider in developing BIM Execution Plans for
management in China). estimating costs in PPP projects.
8.3 Recommendations The research found that BIM is not very practical at the
very early stage due to lack of adequate design detail.
This study provided a comprehensive review of early- But it can be used at consortia bid proposal stage
stage estimating in PPP projects and the use of BIM in onwards. However, a separate class of visual modelling
enhancing the estimating process. The review covered and cost estimating software is currently emerging (for
three of the most advanced users of PPP as a procurement example dRofus™ and DESTINI Profiler™). Although
approach for large-scale public sector social and physical these software do not generate a COBie (Construction-
infrastructure projects. Using the findings of this research Operations Building Information Exchange) or IFS
the following key recommendations are made. (Industry Foundation Classes) compliant BIM as such,
they are useful in understanding the concept of design
1. Adopt the BIM Execution Framework proposed in and cost implications from an early stage itself. The
this report and integrate it with the cost management interviewees for case studies indicated their use as well.
processes of each country. It is therefore recommended that further research should
2. Start implementing the use of BIM during the Project be carried out in evaluating the potential use of such
Development Phase to Request For Proposals Phase software for early-stage cost planning in large-scale
of PPP projects. projects including PPP projects.
3. Encourage or mandate the use of BIM and BIM- Greater levels of digitalisation are imminent in the progress
enabled estimates for consortia bids in PPP projects. of the construction industry, and PPP projects have a
4. Develop country-specific standards for BIM-enabled greater role in implementing digitalisation and promoting
estimating based on the process protocol proposed. such. Adoption of BIM provides a significant opportunity
to achieve greater digitalisation. The construction
5. Use the guidelines provided through drivers and industries of the UK, Australia and China are moving
barriers for BIM-enabled estimating in developing BIM towards greater levels of BIM adoption and 5D BIM, where
Execution Plans for projects. BIM provides an interface for estimating is already a reality.
6. Use the Best Practice Guide as a document providing This research puts forward a framework that enables
guidance and a checklist in writing BIM execution development of BIM execution plans for PPP projects to
plans for PPP projects. ensure efficient and effective BIM-enabled estimating at
7. Take steps in educating the workforce on BIM- early stages of PPP Projects.
enabled estimating with necessary training and
academic programmes.
8. Encourage public authorities and construction clients
to mandate BIM for projects considering the long-term
benefits that it generates for PPP projects.
9. Governments should take action to mandate
use of BIM in PPP type of public sector projects
considering the successes of the lead taken by the
UK government in this respect.
10. Explore the impact and possibilities of complementary
digitalisation technologies such as blockchains,
Internet of Things and big data analytics in achieving
greater levels of digitalisation in estimating and overall
construction procurement.
9.0 References
Abanda, F.H., Kamsu-Foguem B. and Tah J.H.M, (2017). BIM – New rules Computer Integrated Construction (CIC) Research Program (2011). BIM
of measurement ontology for construction cost estimation, Engineering project execution planning guide – version 2.1, Pennsylvania State
Science and Technology, an International Journal, (In press). University, University Park, PA, USA.
Abdel Aziz, A. M. (2007). Successful delivery of public-private Construction Project Information Committee (2013). Post contract-award
partnerships for infrastructure development. Journal of construction building information modelling (BIM) Execution Plan (BEP), available at:
engineering and management, 133(12), pp.918-931. http://www.cpic.org.uk/cpix/ (Accessed 20 August 2018).
AEC (UK) (2012). AEC (UK) BIM protocol: implementing UK BIM standards Cunningham, T. (2013). Factors Affecting The Cost of Building Work –
for the architectural, engineering and construction industry, available at: An Overview. Dublin Institute of Technology, U.K.
https://aecuk.workpress.com/documents (Accessed 20 August 2018).
Department of Finance, (2017). Procurement Issues including
Ajibade, A. A., and Pasco, T. (2008). The accuracy of pre- tender building Conventional and PFI/PPP Procurement. Retrieved from https://www.
cost estimates in Australia, Construction Management and Economics, finance-ni.gov.uk/articles/public-private-partnerships-ppp-projects-and-
26(12), pp.1257-1269 procurement-issues
Ashworth, A. and Perera, S. (2015). Cost Studies of Buildings [6th edition]. Department of Infrastructure and Transport, (2012), Traditional
Taylor and Francis, Routledge, London. Contracting Reform Developing a National Approach: Traditional
contracting of infrastructure projects (Report, Department of
Ashworth, A. and Perera, S. (2018). Contractual Procedures in the Infrastructure and Transport, 2012)
Construction Industry [7th edition]. Taylor and Francis, Routledge, London.
Doloi, H.K. (2011). Understanding stakeholders’ perspective of cost
Australian Institute of Quantity Surveyors Ltd and New Zealand Institute estimation in project management, International Journal of Project
of Quantity Surveyors, Inc (2018). Australia and New Zealand BIM Best Management, 29, pp.622–636.
Practice Guidelines. Australia, New Zealand.
Eastman, C., P. Teicholz, R. Sacks and K. Liston. (2011). BIM handbook –
Babatunde, S. O., Perera, S., and Adeniyi, O. (2019). Identification of critical a guide to building information modeling for owners, managers, designers,
risk factors in public-private partnership project phases in developing engineers, and contractors. 2nd ed. Hoboken, NJ: John Wiley & Sons.
countries: A case of Nigeria, Benchmarking: An International Journal,
26(2), pp.334-355, https://doi.org/10.1108/BIJ-01-2017-0008 Efficiency and Reform Group (2011). Government construction strategy,
Cabinet Office, London, UK.
Boussabaine, A. (2007). Cost Planning of PFI and PPP Building Projects.
Oxon: Taylor and Francis. Egan, J. (1998). Rethinking construction. Department of Environment,
Transport and the Region.
Cheung, E., Chan, A. P., Lam, P. T., Chan, D. W., and Ke, Y. (2012).
A comparative study of critical success factors for public private Elmualim, A., and Gilder, J. (2014). BIM: innovation in design management,
partnerships (PPP) between Mainland China and the Hong Kong influence and challenges of implementation. Architectural Engineering and
Special Administrative Region. Facilities, 30(13/14), pp.647-666. design management, 10(3-4), pp.183-199.
Commonwealth of Australia (2016). National Public Private Partnership Exactal (2017)., CostX® | Exactal CostX: CostX: Construction Estimating
Guidelines – Vol. 2: Practitioners Guide, 2015, Department of Software | On-screen Takeoff Software, available at: http://www.exactal.
Infrastructure and Regional Development, Canberra, Australia. co.uk/products/costX (accessed 4 August 2017).
Commonwealth of Australia (2016). National Public Private Partnership Ganah, A., and John, G. A. (2013). Suitability of BIM for enhancing value
Guidelines – Overview 2008, Department of Infrastructure and Regional on PPP projects for the benefit of the public sector.
Development, Canberra, Australia.
Haque, M. E. and Mishra, R. (2007). 5D virtual constructions:
Commonwealth of Australia (2016). National Public Private Partnership – Designer/constructor’s perspective. In: 10th international conference
Policy Framework. Version 2, 2015, Department of Infrastructure and on Computer and information technology, 27-29 Dec. 2007, 2007
Regional Development, Canberra, Australia. Dhaka, Bangladesh. pp.1-4.
Commonwealth of Australia (2016). National Public Private Partnership HM Government, (2013). Industrial Strategy: government and industry
Guidelines – Volume 4: Public Sector Comparator Guidance, 2008, in partnership, construction 2025
Department of Infrastructure and Regional Development, Canberra,
Australia HM Treasury and Infrastructure UK. (2013). Green Book supplementary
guidance: valuing infrastructure spend. London: HM Treasury and
Commonwealth of Australia (2016). National Public Private Partnership Infrastructure UK.
Guidelines – Volume 6: Jurisdictional Requirements, Version 8, 2014,
Department of Infrastructure and Regional Development, Canberra, HM Treasury. (2014). Private Finance Initiative Projects: 2014 Summary
Australia Data. London: HM Treasury
Holzer, D. (2015). The BIM Manager’s Handbook, Part 3: Focus on Pang Jiali, and ZHU Hai-bo (2016). A Brief Talk on Barriers and
Technology. John Wiley & Sons. Countermeasures of BIM Technology in Engineering Contract
Management. Value Engineering, 35(32), pp.79-80.
Indiana University Architect’s Office (2015). BIM guidelines and standards
for architects, engineers, and contractors, available at: http://www. Petru, A. (2014). Funding the future: innovative ways cities are paying for
indiana.edu/~uao/docs/standards/IU%20BIM%20Guidelines%20and%20 infrastructure, available at: http://www.triplepundit.com/2014/06/
Standards.pdf (Accessed 15 June 2017). funding-future-innovative-ways-cities-paying-infrastructure-projects/
(Accessed 10 June 2017).
Infrastructure Australia (2018)., ‘National PPP Working Group’ ,
Infrastructure Australia, viewed 26th February 2018, http:// RICS (2012 a) RICS New rules of measurements, volume 1 – order of cost
infrastructureaustralia.gov.au/policy-publications/public-private- estimating and elemental cost planning. 1st edn. UK: RICS.
partnerships/national-ppp-working-group.aspx
RICS (2012 b) RICS New rules of measurements, volume 2 – detailed
Infrastructure Risk Group. (2013). Managing Cost Risk & Uncertainty in measurement for building works.
Infrastructure Projects. London: Infrastructure Risk Group and Institute of
Risk Management. Ruikar, K., Anumba, C. J., and Carrillo, P. M. (2005). End-user perspectives
on use of project extranets in construction organisations. Engineering,
Institute for BIM in Canada (IBC) (2013). BIM PxP toolkit package, available Construction and Architectural Management, 12(3), pp.222-235.
at: https://www.ibc-bim.ca/documents (Accessed 15 June 2017).
Seul-Ki, L., Kim, K.-R., and Yu, J.-H. (2014). BIM and ontology-based
Kuiper, I., and Holzer, D. (2013). Rethinking the contractual context for approach for building cost estimation. Automation in Construction, pp.96-105.
Building Information Modelling (BIM) in the Australian built environment
industry. Construction Economics and Building, 13(4), pp.1-17. Shuli, Z. (2016). Application of BIM technology in project life cycle cost
management (Doctoral dissertation, Changchun Institute of Technology).
Laishram, B. (2013). Building Information Modelling in public private
partnership projects–perspectives and hurdles. ICSECM 2011, Kandy Siddiquee, N. A. (2011). Rhetoric and Reality of Public–Private Partnerships:
– Sri Lanka – 15th to 17th December 2011. https://protect-eu.mimecast. Learning Points from the Australian Experience, Asian Journal of Political
com/s/hM0sC1w6Af6zRVVtLciHy?domain=civil.mrt.ac.lk? http://dl.lib. Science, 19(2), pp.129-148, DOI: 10.1080/02185377.2011.600163
mrt.ac.lk/bitstream/handle/123/9507/SEC-11-105.pdf?sequence=1&is Siemiatycki, M. (2012). The theory and practice of infrastructure public-
Allowed=y private partnerships revisited: the case of the transportation sector.
Latham, M. (1994). Constructing the team: final report of the government/ Pobrano z: http://www.Ub.Edu/Graap/Final%20Papers%20PDF/
industry review of procurement and contractual arrangements in the UK Siemiatycki%20Matti.Pdf [dostep: 22.12. 2016].
construction industry. Smith, P. (2014). BIM and the 5D project manager, Procedia – Social and
Li, H., Shen, Q. and Love, P. (2005). ‘Cost modelling of office buildings in Behavioural Sciences, 119, pp.475-484.
Hong Kong: an exploratory study’, Facilities, 23(9/10), pp.438-452. Strategic Forum for the Australasian Building and Construction Industry
Ling, Y. and Yilin, Y. (2017). Project Costs. Ed.3 Machinery Industry Press (2015), Building and Construction Procurement Guide: Project Team
Integration and Building Information Modelling, Australian Construction
Love, P.E.D., Junxiao, L., Matthews, J., Chun-Pong, S., and Smith S. Industry Forum and Australasian Procurement and Construction Council,
(2015). Future proofing PPPs: Life-cycle performance measurement and ACT, Australia.
Building Information Modelling, Automation in Construction, 56, pp.26-35.
Sylvester, K. E. and Dietrich, C. (2010). Evaluation of Building Information
Manderson, A., Jefferies, M., and Brewer, G. (2015). Building information Modelling (BIM) Estimating Methods in Construction Education. In 46th
modelling and standardised construction contracts: a content analysis of ASC Annual International Conference Proceedings Associated Schools
the GC21 contract. Construction Economics and Building, 15(3), pp.72-84. of Construction Boston, MA.
McArthur, J. J., and Sun, X. (2015). Building Information Modelling in The City UK (2014). Financial market series: infrastructure-trends, demands
Canadian Public-Private-Partnership Projects, available at: https://www. and challenges, available from: http://www.thecityuk.com/research/
researchgate.net/profile/Jenn_Mcarthur/publication/316361758_Building_ our-work/reports-list/infrastructure-2014/ (Accessed 20 August 2018).
Information_Modeling_in_Canadian_Public-Private-Partnership_Projects/
links/58fb8059a6fdccde9894cb61/Building-Information-Modeling-in- Wu, W. and Issa, R. R. (2014). BIM execution planning in green building
Canadian-Public-Private-Partnership-Projects.pdf projects: LEED as a use case. Journal of Management in Engineering,
31(1), A4014007.
McKinsey Global Institute (2017). Reinventing Construction: A Route To
Higher Productivity, McKinsey Global Institute Publication Xiaoxia, G. and Wei, L.S. (2016). Analysis of PPP project issues. Private
Science and Technology 12, pp.155-155.
Mingyu, Z. (2016). Research on Legal Issues in PPP Financing Project
between Government and Society (Doctoral dissertation, Dongbei Xiaoyang, Y. (2012). Study on PPP Cooperation Strategy of Large-Scale
University of Finance and Economics) Project Based on Game Theory. (Doctoral dissertation, Nanjing University).
NATSPEC (2012). NATSPEC BIM management plan template (v1.0), Zou, Y., Kiviniemi, A., and Jones, S. W. (2016). Developing a tailored RBS
available at: http://www.bim.natspec.org/images/NATSPEC_Documents/ linking to BIM for risk management of bridge projects. Engineering,
BIM_Management_Plan_Template_v1.0.pdf (Accessed 10 July 2017). Construction and Architectural Management, 23(6), pp.727-750.
10.0 Acknowledgements
RICS Research Trust awarded the research grant for the project
to Professor Srinath Perera (Director, Centre for Smart Modern
Construction) with further sponsorship from Glodon Company Ltd.,
in China.
Professor Yilin Yin (Tianjin University of Technology, China), Dr Lei
Zhou (Chairman, Shanghai Dragonboat Investment Management
Co., Ltd, China), Dr Nirodha Fernando (University of Salford) and
Dr Solomon Babatunde (Obafemi Awolowo University, Nigeria) were
the co-investigators of this international study.
Professor Perera led the research team comprising the co-
investigators and Project Researcher Ms Sadhana De Silva
(Chartered Quantity Surveyor), Dr Xiaohua Jin, Dr Robert Osei Kyei,
Dr Yingbin Feng from Western Sydney University, Dr Qijuan Liu from
Tianjin University of Technology, China.
Mr Qian Liu of Glodon Company Ltd and Mr Bingbing Zhang also
assisted in data collection for the project.
The Principle Investigator Professor Perera and the team take this
opportunity to thank many construction organisations from the
UK, Australia and China who provided data for the project. Further
special appreciation goes to the international team of experts who
provided invaluable service and time for the project. The research
team also wish to thank the RICS Research Trust and Gloden
Company Ltd for the project grant and sponsorship. The team
also acknowledge the resource and facilities provided by the four
universities (Western Sydney University, University of Salford,
Tianjin University of Technology and Obafemi Awolowo University).
The research findings were presented at the final research
dissemination workshop conducted as Western Sydney University
on 16 November 2018 where over 80 international delegates from
many countries attended.
Americas
Latin America North America
[email protected] [email protected]
Asia Pacific
Australasia Greater China (Hong Kong)
[email protected] [email protected]
Greater China (Shanghai) Japan
[email protected] [email protected]
South Asia Southeast Asia
[email protected] [email protected]
EMEA
Africa Europe
[email protected] [email protected]
Ireland Middle East
[email protected] [email protected]
rics.org
JUN2019/DML/23549/GLOBAL