Free PMP Practice Exam Questions - 120 Sample Test Questions

Uploaded by

Huda AlShammari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
520 views58 pages

Free PMP Practice Exam Questions - 120 Sample Test Questions

Uploaded by

Huda AlShammari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 58

(https://www.project-management-prepcast.

com)

For your Project Management Professional (PMP)® exam using A Guide to the Project Management Body of Knowledge (PMBOK® Guide):
Time left:

Free2:23:02
PMP® Practice Exam Questions

120 Sample Test Questions


1/120 answered

1 questions marked
Based on the PMBOK® Guide Exam 6th Edition, and updated for the most current PMP
Exam!
PMP Test Questions For Practice & Preparation
The most important PMP exam prep activity is to answer as many sample questions as you possibly can. To help you, we have developed
this free preparation test. The questions come from The PM Exam Simulator (https://www.pm-exam-simulator.com/) and they are all based
on the most current PMP Examination Content Outline.

*** Updated 2020-Nov-16 - We are proud to have this up-to-date list of free questions for the latest PMP exam!

Note: The exam results created by this page are temporary. If you restart your browser, or reload, close or move away from this page in any
way, then your results will disappear.

Good luck on this sample test and your PMP Exam!

Question 1 - Qid 6113151, Risk Management, 2. Process, 11.7 Monitor Risks

The project management plan specifies that a predictive development approach has been selected to produce the project deliverables.

Where in the project life cycle will the overall project risk be the lowest?

(Please note that on the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in the
simulator, we are asking you to select the answer below.)

A
B
C
D

Hint
Marked

Question 2 - Qid 6110002, Cost Management, 3. Business Environment, 4.1 Develop Project Charter

A company is considering two projects, Alpha and Beta. Project Alpha is expected to result in a $50 million net profit, while project Beta and
is expected to net $45 million. Both projects could be very lucrative and rewarding. However, the financial controller has stated that the
company can only invest in one of these projects.

If project Alpha is selected, what will be the opportunity cost?

$95 million
$50 million
$45 million
Get the Simulator
Learn More (/orderpmpsimulator)
$5 million
Hint
Unmarked

Question 3 - Qid 6110003, Integration Management, 2. Process, 4.1 Develop Project Charter

You are managing a project to build five bridges. The project consists of five sequential phases with each phase delivering one bridge.

After theTime left:

first phase of the project is complete, which process group of the second phase should follow?

2:23:02
Initiating
Planning
1/120 answered
Executing
Closing
1 questions marked

Hint
Unmarked

Question 4 - Qid 6110005, Stakeholder Management, 2. Process, 13.1 Identify Stakeholders

The project aims to investigate the feasibility of constructing a hydroelectric dam from a technical, economic, and social point of view. The
project charter created by the project manager on behalf of the project sponsor is now approved.

Which of the following processes should be performed next?

Develop Project Management Plan


Identify Risks
Identify Stakeholders
Develop Project Charter

Hint
Unmarked

Question 5 - Qid 6110006, Stakeholder Management, 2. Process, 13.1 Identify Stakeholders

You are managing a software upgrade project for your company. Your project sponsor has a great deal of authority regarding project
decisions, but you recently discovered that he doesn't have much interest in your project. To complete the project successfully, you need
your project sponsor's continuous support.

What stakeholder management strategy should you use with your project sponsor?

Keep the sponsor satisfied


Manage the sponsor closely
Monitor the sponsor's actions
Keep the sponsor informed

Hint
Unmarked

Question 6 - Qid 6110008, Scope Management, 2. Process, 5.2 Collect Requirements

The project sponsor asks for a copy of the document that contains the description, owner, source, priority, and status of product
requirements.

Which project document is the project sponsor requesting?

The requirements management plan


The requirements traceability matrix
The scope management plan
The work breakdown structure (WBS)

Hint
Unmarked

Question 7 - Qid 6110011, Schedule Management, 2. Process, 6.2 Define Activities

You are facing problems decomposing the testing work package into the final activities required to complete the work package. Detailed
testing plans and activities cannot be determined until the system is at least 50% developed and more details become available. The
system development work package will take at least three months to complete.

What is the best way to resolve this problem?

Use product analysis techniques such as product breakdown and systems analysis to decompose the system testing work
package
Decompose the system development work package now and decompose the system testing work package later
Break down the project into multiple phases so that the system testing work package goes into the second project phase
Consult the project management plan to determine what to do in this situation
Get the Simulator
Learn More (/orderpmpsimulator)
Hint
Unmarked

Question 8 - Qid 6110014, Integration Management, 2. Process, 4.2 Develop Project Management Plan

You are about to start planning for a large and complex project. Due to the size of the project along with the regulatory and environmental
considerations, the development of a detailed project management plan will be critical.
Time left:

2:23:02
As a starting point for initial project planning, what is the first thing you should do?

Conduct a project kick-off meeting to inform and engage stakeholders and gain commitment
1/120 answered
Review the project charter to understand the high-level information about the project
Begin the process of identifying stakeholders so they can be engaged as necessary for project planning
1 questions marked
Share the project scope statement with the project team for a common understanding of project deliverables

Hint
Unmarked

Question 9 - Qid 6110020, Resource Management, 2. Process, 9.0 Project Resource Management

As you are monitoring the cost baseline for your project, you notice that project expenses are higher than expected at this point in the
project.

What is the most likely cause of the variance?

Overestimated material costs


Lack of stakeholder support
An incomplete milestone list
Excess inventory

Hint
Unmarked

Question 10 - Qid 6110029, Resource Management, 1. People, 9.4 Develop Team

Recently, you promoted your star programmer, Sam, to lead the agile development team. Sam was a fantastic software coder, and you
thought the promotion would mean that he could now share his expertise with the other development team members. However, you are
surprised to learn that the performance of Sam in his new role is not meeting your expectations.

Which empirical rule did you forget while considering the promotion of Sam?

Expectancy theory
Halo effect
Pareto concept
Murphy's law

Hint
Unmarked

Question 11 - Qid 6110032, Communications Management, 2. Process, 10.3 Monitor Communications

You have just taken over a project in execution. During your first week, you determine that the project team members spend a lot of time
responding to unexpected requests for information from different project stakeholders. Because of these interruptions, the team cannot
focus on their project activities, and as a result, the project is behind schedule.

What should you do first?

Tell the team members to stop responding to unexpected requests since it is not the responsibility of the team
Push the team to respond to all the requests faster so that they can perform their assigned project activities on time
Ask the team to forward all stakeholder inquiries to you so that the team members can focus on their assigned tasks
Review the communications management plan to understand how stakeholder requests should be handled

Hint
Unmarked

Question 12 - Qid 6110034, Scope Management, 2. Process, 5.1 Plan Scope Management

A team member submits a draft of the requirements management plan to the project manager for a review. The project manager notices
that one of the components included in the plan does not belong there.

Which of the following components did the project manager most likely notice?

A process that describes how the project requirements will be prioritized


The metrics that will be used and the rationale for using them
A process that specifies how a project scope statement will be prepared
How requirement activities will be planned, tracked, and reported
Get the Simulator
Learn More (/orderpmpsimulator)
Hint
Unmarked

Question 13 - Qid 6110038, Scope Management, 2. Process, 4.5 Monitor and Control Project Work

While reviewing your project's performance, you discover a significant variance. If the issue is not fixed before the next customer inspection,
your project might be canceled. However, after a further review conducted by the project team, you are glad to hear that bringing the
Time left:

project back on track requires only a minor correction to a configuration element.


2:23:02
What should you do first?
1/120 answered
Implement the corrective action
Submit a change request
1 questions marked
Consult the project sponsor
Delay the customer inspection

Hint
Unmarked

Question 14 - Qid 6110039, Integration Management, 2. Process, 4.5 Monitor and Control Project Work

A project manager is leading a process improvement project for a factory operation. Currently, the project manager and the team are
performing the Monitor and Control Project Work process.

Which of the following activities might be carried out during this process?

Comparing actual project performance against the project management plan


Implementing approved change requests to achieve the project's objectives
Analyzing change requests and either approving or rejecting them
Gaining formal acceptance of the deliverables by the customer or sponsor

Hint
Unmarked

Question 15 - Qid 6110040, Integration Management, 2. Process, 4.6 Perform Integrated Change Control

An organization has a policy that a change control board (CCB) must review all change requests for every project in the organization, and
that the CCB follows the recommended activities outlined in the PMBOK® Guide. Project managers and the project team do not serve as
members of the CCB.

Based on this scenario, which of the following activities might be performed by members of the CCB?

Submitting a change request


Implementing approved change requests
Initiating and closing a project
Monitoring implementation of approved changes

Hint
Unmarked

Question 16 - Qid 6110041, Integration Management, 2. Process, 4.6 Perform Integrated Change Control

A company has authorized a dedicated change control board (CCB) to review and evaluate all change requests that are submitted for any
project.

If the project sponsor is a member of the CCB, which of the following best describes an individual or group that can request a change on a
project?

Project manager
Project sponsor
Project team
Any stakeholder

Hint
Unmarked

Question 17 - Qid 6110055, Procurement Management, 2. Process, 12.3 Control Procurements

One of your contractors is not performing to the agreed-upon standards. You want to terminate the contract and engage another contractor
for the same job. You need to determine the specific legal procedure for the early termination of the contract.

What should you do?

Check the procurement management plan


Look at the scope statement
Review the risk register
Consult the contract Get the Simulator
Learn More (/orderpmpsimulator)
Hint
Unmarked

Question 18 - Qid 6110058, Stakeholder Management, 2. Process, 13.1 Identify Stakeholders

A project is divided into four sequential phases. The second phase of the project has just been completed, and the third phase is about to
begin.
Time left:

2:23:02
What should the project manager do first?

Begin the process of directing and managing the project work


1/120 answered
Perform the process of identifying the project stakeholders
Start the process of monitoring and controlling the project work
1 questions marked
Begin the process of developing the project management plan

Hint
Unmarked

Question 19 - Qid 6110061, Stakeholder Management, 2. Process, 13.1 Identify Stakeholders

An organization has a project management office (PMO) that ensures all relevant project documents are created, and all project
management processes are followed according to established best practices.

What should the project manager review first to identify stakeholders for a newly started project?

The business documents as a source of information about the project's stakeholders


The communications management plan to learn about the project's stakeholders
The stakeholder engagement plan to identify the management strategies and actions required to engage stakeholders
effectively
The requirements documentation for information on potential stakeholders

Hint
Unmarked

Question 20 - Qid 6112348, Schedule Management, 2. Process, 6.5 Develop Schedule

The following table is an activity list that includes the duration and predecessor for a series of project activities.

What is the duration of the critical path?

11
14
9
13

Hint
Unmarked

Question 21 - Qid 6110065, Stakeholder Management, 2. Process, 13.1 Identify Stakeholders

A project manager is in the process of developing the stakeholder register. As the first step in this process, she needs to create a list of
potential stakeholders and decides to use a data gathering technique called brain writing. 

What is the first thing to do when usingGet


thatthe Simulator

technique? Learn More (/orderpmpsimulator)


Convene a data gathering meeting with the participants
Develop your own template for a stakeholder register
Send a list of questions to participants before the creativity session
Consult the stakeholder engagement plan to understand how the stakeholders are to be identified

Hint
Unmarked
Time left:

2:23:02
Question 22 - Qid 6110066, Communications Management, 2. Process, 10.0 Project Communications Management

A project 1/120
manager does most of her communicating with team members, internal project stakeholders, and external project stakeholders
answered
via email. The project manager incorporates specific techniques when composing her emails to reduce any misunderstandings.
1 questions marked
Which of the following is not considered one of these techniques?

Concise expression
Clear purpose directed to the needs of the reader
Controlled flow of words and ideas
Communications register

Hint
Unmarked

Question 23 - Qid 6110070, Risk Management, 2. Process, 11.3 Perform Qualitative Risk Analysis

As the project manager, you are leading a brainstorming session with key stakeholders to identify project risks. Once the project risks are
determined, you immediately proceed to nominate different team members as risk owners and assign them the task of developing
individual risk response plans.

Have you properly conducted risk management planning?

No, you should be the one developing the risk response plans as you are ultimately responsible for the outcomes of the
project.
Yes, the risk response plans are an output of the Identify Risks process and should be developed right after the risks have
been identified.
No, before assigning risk responsibility to team members, you need to assess each risk's probability of occurrence and its
impact.
Yes, the team members should be assigned responsibility for a risk as soon as possible and tasked with creating a risk
response plan.

Hint
Unmarked

Question 24 - Qid 6110072, Scope Management, 2. Process, 5.2 Collect Requirements

You are managing a project to build a database and need to acquire information from the stakeholders of the project. The team is using
brainstorming, focus groups, interviews, questionnaires, and benchmarking to understand and document the stakeholders' needs.

The methods the team is using are representative of which tool and technique?

Data gathering
Data analysis
Decision making
Data representation

Hint
Unmarked

Question 25 - Qid 6110074, Scope Management, 2. Process, 5.4 Create WBS

The project is in execution, but your project team is unable to stop arguing about the project milestones and the specific risks associated
with them. This on-going conflict puts the project at risk of running behind schedule.

What would likely have helped avoid this conflict had it been properly created first?

A project charter
Physical resource assignments
Quality metrics
A work breakdown structure

Hint
Unmarked

Question 26 - Qid 6110075, Scope Management, 2. Process, 4.5 Monitor and Control Project Work

During project execution, the team discovers that some of the buttons on the remote control developed by the project for a new product do
Get the Simulator
Learn More (/orderpmpsimulator)
not work according to the specifications. A change request is submitted and approved to replace the buttons.
Which of the following best describes this change request?

Corrective action
Preventive action
Defect repair
Gold plating
Time left:

Hint
Unmarked
2:23:02
Question1/120
27 - Qid 6110076, Schedule Management, 2. Process, 6.4 Estimate Activity Durations
answered

A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks
1 questions marked
the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager
provides an estimate of 8-10 months.

What estimation technique does the project manager use?

Expert judgment
Three-point estimating
Analogous estimating
Bottom-up estimating

Hint
Unmarked

Question 28 - Qid 6110079, Quality Management, 2. Process, 8.2 Manage Quality

A project manager is performing quality assurance for a project whose quality standards are very stringent. In order to meet and exceed the
quality requirements, the project manager uses a set of technical guidelines, which were applied during the design phase of the project to
optimize quality.

What tool or technique is the project manager using in this scenario?

Design for X (DfX) where the X in DfX represents the quality aspect of the product
Design of experiments (DOE) as a quality improvement methodology
The Manage Quality process to ensure compliance with project quality requirements
Process analysis to identify opportunities for process improvements

Hint
Unmarked

Question 29 - Qid 6110081, Stakeholder Management, 2. Process, 13.1 Identify Stakeholders

You have compiled a list of potential stakeholders for your project, and now you are classifying the stakeholders with regard to the direction
of their influence. As you work through your way down the list of stakeholders, you have come to the project sponsor.

How should this stakeholder be classified?

Downward
Sideward
Outward
Upward

Hint
Unmarked

Question 30 - Qid 6110083, Scope Management, 2. Process, 4.5 Monitor and Control Project Work

During project planning, the project team rigorously defined the project scope. During project execution, a senior engineer calls the project
manager and suggests a simpler and more efficient design which could benefit the project.

What should the project manager do next?

Nothing, no changes are needed since the project scope was rigorously defined
Discuss the change with the project sponsor
Evaluate the impact of the proposed change on the project constraints
Ask that the engineer submit a change request

Hint
Unmarked

Question 31 - Qid 6110087, Schedule Management, 2. Process, 6.4 Estimate Activity Durations

You are working with a team to estimate how much time is required for each activity. You are using a document that contains information
on the categories of labor, material, and equipment required to complete the project. You are also interested in the skill levels, required
certifications, and the grade levels for Get the Simulator

supplies. Learn More (/orderpmpsimulator)


Which of the following documents would you primarily refer to for this purpose?

Resource breakdown structure


Organizational breakdown structure
Work breakdown structure
Risk breakdown structure
Time left:

Hint
Unmarked
2:23:02
Question1/120
32 - Qid 6110090, Risk Management, 2. Process, 11.2 Identify Risks
answered

While performing project work, a team member notices that there is a potential new risk, which could impact the project's critical path.
1 questions marked
What should the team member do immediately?

Recommend the project be placed on hold for a day to avoid the risk
Document the risk in the risk register
Draft an emergency fallback plan since the critical path is in jeopardy
Generate a risk report using quantitative and quantitative analysis of the identified risk to alert the team of the schedule
impacts

Hint
Unmarked

Question 33 - Qid 6112005, Procurement Management, 2. Process, 12.3 Control Procurements

You are managing a project that is nearing its end and planning to settle all pending claims with the vendors. In one case, you are not
satisfied with the delivery of their final product. All conversations with the vendor have ended in an impasse.

What should you do in this situation?

Pay the vendor as some products were delivered


Take the vendor to court
Discontinue further meetings with the vendor and hold back payment
Identify some form of alternative dispute resolution

Hint
Unmarked

Question 34 - Qid 6112009, Risk Management, 2. Process, 11.0 Project Risk Management

Your company was awarded a contract that includes a 10% bonus payment if the project is completed two months early. You consider
several options to exploit this opportunity.

What is the best course of action for you to increase the chances of receiving the bonus?

Reduce project scope


Level resources
Crash the schedule
Purchase insurance

Hint
Unmarked

Question 35 - Qid 6112010, Quality Management, 2. Process, 8.2 Manage Quality

The quality management plan specifies the use of a data representation technique to show the strength of relationships between four
factors.

Which of the following tools or techniques should be used to comply with the plan?

Affinity diagram
Matrix diagram
Scatter diagram
Quality diagram

Hint
Unmarked

Question 36 - Qid 6112012, Stakeholder Management, 2. Process, 13.1 Identify Stakeholders

You have just taken over a project in which some of the deliverables will be produced by external vendors. You want to familiarize yourself
with those who are involved in the project from the sellers' side.

Where would you look to obtain this information?


Get the Simulator
Learn More (/orderpmpsimulator)
Bid documents
Stakeholder register
Seller proposals
Stakeholder engagement plan

Hint
Unmarked

Time left:

Question 37 - Qid 6112018, Stakeholder Management, 2. Process, 13.0 Project Stakeholder Management
2:23:02
Your project has been plagued with numerous change requests.
1/120 answered
What is the most likely reason?
1Incomplete
questions stakeholder
marked register
Lack of a detailed procedure to close the project
Failure to implement risk responses
Change management plan did not authorize a change control board

Hint
Unmarked

Question 38 - Qid 6112019, Quality Management, 2. Process, 8.3 Control Quality

In the design phase, external experts verified that the team's blueprints for a new crane complied with requirements. During the build
phase, the customer performed a walkthrough and found that some welding joints on the crane were defective. The crane needs to be
reworked to ensure it can be operated safely.

How could this situation have been avoided?

Outsourcing the welding to an external vendor


Testing the welding before the customer walkthrough
Using the requirements traceability matrix
Defects are part of any project and cannot be avoided.

Hint
Unmarked

Question 39 - Qid 6112028, Integration Management, 3. Business Environment, 1.2 Foundational Elements

For an upcoming project, a needs assessment and business case have been completed, and the project management office (PMO) is
reviewing a draft of the benefits management plan. The PMO highlights an element of the benefits management plan and requests that the
element be removed before the document is finalized.

Which of the following was most likely the element the PMO requested to remove?

Expected tangible and intangible value to be gained by the implementation of the project
A set of options to be considered for addressing the business opportunity
A timeframe for realizing the benefits of the project
Measures to be used to show benefits realized

Hint
Unmarked

Question 40 - Qid 6113170, Resource Management, 1. People, 9.4 Develop Team

You have been requested to fill in for a project manager who has called in sick midway into project execution. As you get yourself familiar
with the project team, you are impressed to see how well the team members collaborate and work through issues smoothly and effectively.

Based on your observations, where is the team on the Tuckman ladder?

(Please note that on the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in the
simulator, we are asking you to select the answer below.)

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

A
B
C
D

Hint
Unmarked

Question 41 - Qid 6112039, Scope Management, 2. Process, 5.3 Define Scope

To define the product that will be produced by the project, the project team is using a product analysis technique that helps with breaking
down the high-level requirements into the level of detail needed to design the product.

Which of the following is the product analysis technique used by the team?

Work breakdown structure


Product planning
Progressive elaboration
Product breakdown

Hint
Unmarked

Question 42 - Qid 6112054, Integration Management, 3. Business Environment, 4.7 Close Project or Phase

A three-phase project to build a prototype is underway. The first phase entails design. In the second phase, the manufacturing team would
produce the parts from the design specifications. In the third phase, the production team would assemble the parts to construct the
prototype. The project is now at the end of the first phase.

What should be done with the phase's deliverables?

Verified by the testing team for quality compliance


Transferred to the production team
Transitioned to the project management office (PMO)
Handed over to the manufacturing team

Hint
Unmarked

Question 43 - Qid 6112056, Integration Management, 2. Process, 4.3 Direct and Manage Project Work

A project is nearing its end when the project manager receives an approved change request to replace a defective unit.

What should the project manager do next?

Capture the problem in the issue log


Meet with the change control board
Have the defective unit repaired
Have the defective unit replaced

Hint
Unmarked

Question 44 - Qid 6112060, Integration Management, 2. Process, 4.6 Perform Integrated Change Control

A technician has just tested a piece of equipment and found a defect. The technician has informed the project manager and submitted a
change request to repair the defect, indicating that the repair will require significant rework.

Get the Simulator

What should the project manager do first? Learn More (/orderpmpsimulator)


Approve the change request
Consult the change management plan
Instruct the team to repair the defect
Reject the change request due to significant rework

Hint
Unmarked
Time left:

2:23:02
Question 45 - Qid 6112061, Integration Management, 2. Process, 4.0 Project Integration Management

At the end1/120
of aanswered
design project, a competitor has gained market share with a new technology that has rendered the project?s deliverable
obsolete. The project sponsor is pleased with the work of the project team who finished within budget and on time but thinks that the
project1 should have
questions been terminated much sooner.
marked

What might have the manager of the project done differently in this situation?

Used phases and phase gates


Established a change control board (CCB) to review and render decisions for all submitted change requests
Terminated the project when the new technology was introduced
Scheduled more frequent lessons learned meetings with the project team

Hint
Unmarked

Question 46 - Qid 6112064, Schedule Management, 2. Process, 6.0 Project Schedule Management

A project is underway to construct a wind farm in an area with no communication infrastructure. The plan is to monitor progress and
coordinate the scheduling of the project activities using project management software and provide daily status updates to the project
sponsor at the home office. Two project teams will work and reside onsite in rotating seven-day tours.

Which of the following is the most likely challenge the teams will face while controlling the schedule?

Stability of requirements
Technology support
Human resource availability
Project importance

Hint
Unmarked

Question 47 - Qid 6112068, Resource Management, 1. People, 9.5 Manage Team

A project is behind schedule because department managers reassigned project team members to work on other assignments. After
negotiations with the managers, you agreed to a temporary solution where a core group of project resources is dedicated to performing the
project work until more resources are approved.

What conflict resolution technique did you most likely employ in this situation?

Compromise or reconcile
Force or direct
Collaborate or problem solve
Smooth or accommodate

Hint
Unmarked

Question 48 - Qid 6112072, Scope Management, 2. Process, 5.6 Control Scope

During a daily stand-up meeting, one of the programmers mentions that she had some extra time and added functionality, which was not
included in the original design. She believes the customer will appreciate the added functionality.

What is your best course of action?

Remove the added functionality and ensure that the project team builds the software as designed going forward
Thank the programmer for the extra effort and notify the customer of the new functionality that has been added
Update the cost baseline since the project will run over budget due to the cost of adding new functionality
Accept the added functionality, but ask the programmer to build only what has been designed going forward

Hint
Unmarked

Question 49 - Qid 6112082, Quality Management, 2. Process, 8.2 Manage Quality

The project manager is managing the research and development of a new cancer screening test. The project manager would like to
determine whether the processes currently in use in the project are effective in meeting the quality requirements specified by the customer.

Get
What does the project manager need to the first
obtain to make
this determination?
Simulator Learn More (/orderpmpsimulator)
Quality control measurements
Resource breakdown structure
Requirements traceability matrix
Acceptance of deliverables from the customer

Hint
Unmarked
Time left:

2:23:02
Question 50 - Qid 6112095, Quality Management, 2. Process, 8.3 Control Quality

During an1/120
inspection
answeredof a project deliverable, the team detects the same defect in the deliverable that has already been identified during a
previous inspection. The project manager is confused about how this could have happened since a change request was approved to repair
the defect. After discussing
1 questions marked the issue with the team, the project manager learns that the team never implemented the approved change
request.

What could have helped prevent this situation?

Holding an approved change requests review


Conducting a retrospective meeting
Performing a root cause analysis
Creating a quality report

Hint
Unmarked

Question 51 - Qid 6112200, Quality Management, 2. Process, 8.1 Plan Quality Management

The team has just reported to you that they have completed the Plan Quality Management process. You review their work and see that they
have produced the quality management plan, and made the necessary updates to the project management plan and project documents.

What did they forget?

Determine quality metrics


Define quality roles and responsibilities
Revise the lessons learned register
Update the requirements traceability matrix

Hint
Unmarked

Question 52 - Qid 6112235, Integration Management, 2. Process, 4.6 Perform Integrated Change Control

You are managing a project to build a house for a private client. A few weeks before the project's planned completion date, the client calls
and asks to add an outdoor sauna to the property. You analyze the project schedule and determine that this change would be fairly easy to
implement without having an impact on the completion date.

What should you do first?

Begin construction since the project completion date is not violated


Review the requested change against all project constraints
Have the sponsor verify if the change violates construction regulations
Consult with the change control board on how to handle the change

Hint
Unmarked

Question 53 - Qid 6112294, Integration Management, 2. Process, 4.1 Develop Project Charter

You have been asked to lead a product development project which will use an agile framework. Currently, you are in the process of drafting
the project charter, and you want to bring together stakeholders and subject matter experts to discuss perceived project risk, success
criteria, and other topics.

What is the best way for you to accomplish this objective?

Facilitate an iteration retrospective


Invite the relevant participants to the daily scrum meetings
Conduct interviews with the identified individuals
Schedule a focus group

Hint
Unmarked

Question 54 - Qid 6112434, Procurement Management, 2. Process, 4.7 Close Project or Phase

A multi-phase project has reached a phase gate. The key project stakeholders want to determine if the phase has met its success criteria
and if the project should proceed to the next phase.
Get the Simulator
Learn More (/orderpmpsimulator)
In addition to the project management plan, which documents will be required?

Risk register and risk report


Lessons learned register and lessons learned repository
Business documents and project charter
Agreements including procurement contracts
Time left:

Hint
Unmarked
2:23:02
Question1/120
55 - Qid 6112456, Integration Management, 2. Process, 4.4 Manage Project Knowledge
answered

You are1 in the process


questions of establishing a knowledge management system for your project.
marked
Which of the following actions will be the least beneficial in this process?

Reviewing the lesson learned register


Monitoring stakeholder engagement
Examining the resource breakdown structure
Studying the project team assignments

Hint
Unmarked

Question 56 - Qid 6112463, Stakeholder Management, 2. Process, 13.3 Manage Stakeholder Engagement

You are leading a large project that involves many stakeholders. You want to get two new team members up to speed with the overall
dynamics of the project and engage effectively with the project stakeholders.

What should you do?

Ask the team members to record any issues they encounter into the issue log
Review the stakeholder register with the new team members
Schedule a meeting with the new team members and all project stakeholders
Submit a change request to update the stakeholder engagement plan

Hint
Unmarked

Question 57 - Qid 6112493, Resource Management, 1. People, 9.1 Plan Resource Management

You are facilitating a meeting with your project team to develop the team charter. At the start of the meeting, a team member states, "I
don't understand the importance of this meeting. We are all professionals, and this isn't our first project working together. Wouldn't our
time be better spent getting an early start on project execution?" The body language of the other team members suggests that they agree
with the comments.

How should you respond to the team member?

As long as everyone is in agreement, then let's skip the team charter and get ahead of schedule
Let's use the team charter from our last project as a starting point and then update it as necessary
The team charter is required by the project management office (PMO) for all projects
The team charter will eliminate any potential conflicts which will improve our productivity

Hint
Unmarked

Question 58 - Qid 6112596, Procurement Management, 2. Process, 12.1 Plan Procurement Management

You are leading a project to build an oil pipeline in a foreign country. You want to outsource some of the construction work to local
contractors and are in the process of preparing the bid package for prospective sellers.

Which of the following documents would you leave out of the package?

Request for proposal


Statement of work
Independent cost estimates
Bid documents

Hint
Unmarked

Question 59 - Qid 6112605, Communications Management, 2. Process, 10.1 Plan Communications Management

You are developing the communications management plan for a construction project. You want to determine the information needs of the
project stakeholders, specifically focusing on the type and the format of information that will be required to communicate with the
stakeholders.
Get the Simulator
Learn More (/orderpmpsimulator)
What is your best course of action?
Develop the stakeholder register
Review the requirements documentation
Conduct a communication requirements analysis
Consult the stakeholder engagement plan

Hint
Unmarked
Time left:

2:23:02
Question 60 - Qid 6125134, Cost Management, 2. Process, 7.4 Control Costs

The following
1/120 Gantt chart displays the schedule for a software upgrade project. The system analysis was completed on August 12th, but the
answered
system design and development activities are still in process as of October 3rd. Once the product is developed, the project team will need to
1 questions
test and which must be completed by October 17th. The method used to determine the earned value is based on percent
deploy it, marked
complete.

What is the cost variance as of October 3rd?

-$650
$3,750
$650
$3,100

Hint
Unmarked

Question 61 - Qid 6112614, Resource Management, 1. People, 9.0 Project Resource Management

A servant leader has just been assigned to an upcoming product development project and believes that the project is well-suited to
Kanban. However, the development team is unfamiliar with this approach.

What is the servant leader's best course of action?

Discuss Kanban during a daily standup meeting


Review Kanban at the iteration retrospective
Let the team members learn Kanban on their own
Have the team attend a workshop on Kanban

Hint
Unmarked

Question 62 - Qid 6112667, Scope Management, 2. Process, 5.3 Define Scope

You are developing the project scope statement. You have specified the deliverables for the project, included the requirements under which
the deliverables will be accepted, and explicitly stated what is out of project scope.

What else should you include in the project scope statement?

Project exclusions
Acceptance criteria
Project approval requirements
Product scope description

Hint
Unmarked

Question 63 - Qid 6112676, Resource Management, 2. Process, 9.3 Acquire Resources

A project manager is in the process of obtaining team members. She wants to understand the availability of the team members required to
complete project work.

What should the project manager do to find this information?

Look at the resource calendars


Contact the project management office
Review the resource requirements
Examine the resource breakdown structure

Get the Simulator


Learn More (/orderpmpsimulator)
Hint
Unmarked
Question 64 - Qid 6112685, Quality Management, 2. Process, 8.2 Manage Quality

A project to reduce the defect rate of the manufacturing process is underway. To analyze and improve the process, the project team is now
carrying out the quality assurance activities.

Which of the following would be the most beneficial for this project?
Time left:

2:23:02
Introducing the use of a kanban board into the manufacturing process
Consulting with a certified Six Sigma Black Belt expert
Utilizing rolling wave planning for the project
1/120 answered
Adopting a just-in-time (JIT) manufacturing process
1 questions marked
Hint
Unmarked

Question 65 - Qid 6112687, Risk Management, 2. Process, 11.6 Implement Risk Responses

During project planning of a large, complex project, project management best practices were rigorously and thoroughly followed. During
project execution, the project experienced several critical risks, which were foreseen and previously identified. Despite the meticulous
planning, the project failed to achieve the established objectives due to these realized risks.

What may have gone wrong in this scenario?

The realized risks had not been identified earlier in the project
The risk responses were poorly devised
The qualitative risk analysis was inadequate
There was little or no action taken to manage the known risks

Hint
Unmarked

Question 66 - Qid 6112688, Communications Management, 1. People, 10.2 Manage Communications

A team member volunteered to provide the project status update in a weekly presentation to the key stakeholders. After the first meeting
has taken place, feedback from the stakeholders suggests that the presentation was not very engaging.

What is the best way for the project manager to address this situation with the team member?

Discuss the issue with the team member


Prepare a formal written document
Utilize formal verbal communication
Send an email to the team member

Hint
Unmarked

Question 67 - Qid 6112694, Stakeholder Management, 2. Process, 13.3 Manage Stakeholder Engagement

A corporate restructuring project is in execution. The job responsibilities of many key stakeholders are being disrupted, which has caused
challenges in keeping the stakeholders engaged in a positive manner.

Which of the following actions is the project manager least likely to perform in this situation?

Manage stakeholder expectations through negotiation and communication


Develop approaches to involve stakeholders based on their needs, expectations, interests, and potential impact on the
project
Address any risks or potential concerns related to stakeholder management and anticipate future issues that may be
raised by stakeholders
Engage stakeholders at appropriate project stages to obtain, confirm, or maintain their continued commitment to the
success of the project

Hint
Unmarked

Question 68 - Qid 6112702, Resource Management, 2. Process, 9.6 Control Resources

You are leading a software development project where the developers are colocated within rented office space. Writing the code is taking
longer than anticipated, and you have contacted the landlord requesting to rent the office for another week. Unfortunately, the landlord
tells you that the office is already booked. You capture the problem in the project documents.

What should you do next?

Record the issue in the issue log


Revise the resource management plan
Update the risk register
Get the Simulator
Learn More (/orderpmpsimulator)
Request additional funds
Hint
Unmarked

Question 69 - Qid 6112760, Procurement Management, 2. Process, 12.2 Conduct Procurements

During a bidder conference, a supplier asks why a section is missing from the request for quotation (RFQ). Upon realizing that the section is
indeed missing, the project manager becomes flustered and stumbles through a brief reply. When the seller responses were received, all but
Time left:

three prospective suppliers fail to address the missing section.


2:23:02
What is the best course of action?
1/120 answered
Hold the bidder conference again, and explain the importance of the point that was initially missed
Select from the three vendors that submitted complete proposals
1 questions marked
Send a revised RFQ to all prospective suppliers and allow them the opportunity to resubmit their proposals
Extend the deadline and allow all of the vendors to resubmit their proposals

Hint
Unmarked

Question 70 - Qid 6112783, Schedule Management, 2. Process, 6.6 Control Schedule

You are leading a project to develop a new web application. Together with your project team you reprioritize the product backlog,
determine velocity for the past iterations, and adapt your work plans accordingly. Additionally, you facilitate retrospectives every two
weeks.

Which of the following processes describes the work you are performing?

Monitor Risks
Manage Quality
Control Schedule
Develop Schedule

Hint
Unmarked

Question 71 - Qid 6112785, Schedule Management, 2. Process, 6.1 Plan Schedule Management

You are part of a cross-functional development team piloting an adaptive approach to project management in an organization that has
traditionally used a predictive approach. You realize that you have to tailor the template of the schedule management plan.

Which of the following components of the template are you likely to tailor the most?

The rules of performance measurement, the summary milestones, and the key deliverables
The organizational procedures links, the units of measure, and the project organization charts
The schedule model development, the release and iteration length, and the reporting formats
The project schedule model maintenance, the level of accuracy, and the level of precision

Hint
Unmarked

Question 72 - Qid 6112817, Risk Management, 2. Process, 11.7 Monitor Risks

A project team performs monthly risk audits for a project, where a large number of identified risks have been realized. So far, the risk
responses have been appropriate, and the reserves sufficient. An executive for the requesting organization criticizes the project manager
improper risk audits, stating that only independent, external resources should perform risk audits.

How should the project manager respond?

Explain that risk audits can be performed either internally or externally as long as they follow the project management
plan
Agree with the executive and submit a change request to update the project management plan to have the audits
conducted externally
Follow the guidance provided by the executive and hire a team of external auditors to conduct the risk audits going
forward
Explain that if the current risk audits are not sufficient, then a comprehensive project audit should be carried out

Hint
Unmarked

Question 73 - Qid 6112819, Risk Management, 2. Process, 11.1 Plan Risk Management

You are developing the risk management plan for your project. In support of this process, you need to determine the acceptable level of
overall project risk exposure.

What should you do first?

Getproject
Determine the risk appetites of key the Simulator

stakeholders Learn More (/orderpmpsimulator)


Consult the risk exposure register within the organizational process assets
Facilitate a brainstorming meeting to develop a comprehensive list of project risks
Develop a set of responses to individual project risks to mitigate overall project risk

Hint
Unmarked

Time left:

Question 74 - Qid 6112895, Integration Management, 2. Process, 4.3 Direct and Manage Project Work
2:23:02
You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements,
develop deliverables,
1/120 answeredhandle changes, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle.

With the project life cycle selected, how will the product be delivered?
1 questions marked
As subsets of the overall product
As a single final product at the end of the project
As work packages of the WBS
As product increments based on customer's value

Hint
Unmarked

Question 75 - Qid 6112983, Resource Management, 1. People, 9.2 Estimate Activity Resources

As a project manager, you are in the process of estimating the team resources that will be required for your project. The challenge you are
having is that, due to the nature of the project and the selected development approach, only a few of the top levels of the WBS have been
identified with the remainder to be progressively elaborated throughout the project.

What is the best approach to determine the team resource requirements for the project?

Check the organizational process assets for similar projects and use analogous estimating
Apply bottom-up estimating using the work breakdown structure (WBS) as a guide
Utilize parametric estimating for the individual work packages within the existing WBS
Decompose the WBS down to the work package level during initial project planning

Hint
Unmarked

Question 76 - Qid 6112986, Scope Management, 2. Process, 5.4 Create WBS

You are part of a project team designing a new type of a vehicle. You are about to begin work on a work package for the braking system of
the vehicle and want to review the acceptance criteria before starting the work.

Where can you find this information?

Project management plan


Activity attributes
Requirements documentation
The WBS dictionary

Hint
Unmarked

Question 77 - Qid 6112994, Integration Management, 2. Process, 4.7 Close Project or Phase

A project to construct an assembly line is nearly complete. The project manager closes procurements, shares the final project report,
updates the lessons learned repository, and obtains feedback from the relevant stakeholders.

What should the project manager do next?

Provide final payment to the suppliers


Send a summary of how the final product achieved the business needs
Transfer the completed assembly line to operations
Send formal written notice to the vendors that the contracts have been completed

Hint
Unmarked

Question 78 - Qid 6113034, Risk Management, 2. Process, 11.5 Plan Risk Responses

A project team is mulling over two risk responses for inclusion in the risk register. The first risk response has two criteria that must be met
and costs $5,000. The second risk response has four criteria that must be met, but only costs $2,000.

What action is the project team least likely to take in selecting the best risk response?

Running a Monte Carlo simulation


Get the Simulator

Performing an alternatives analysis Learn More (/orderpmpsimulator)


Conducting a cost-benefit analysis
Using multicriteria decision analysis

Hint
Unmarked

Question 79 - Qid 6113042, Resource Management, 2. Process, 9.3 Acquire Resources


Time
To acquire left:

resources for the project, the project manager consults the resource management plan. The plan calls for the scrum master to be

2:23:02
assigned to the team. However, the only individual in the company qualified to serve as a scrum master has already started working on
another project, and her functional manager does not cooperate on a potential resolution.
1/120 answered
How could this situation have been prevented?
1The
questions
project marked
manager should have checked the project's resource calendars for the availability of the scrum master.
The project sponsor should have directed the project manager to serve as both the project manager and the scrum
master.
The scrum master should have refused to work on the other project knowing that she is the only qualified resource in the
company.
The availability of the scrum master should have been negotiated between the functional manager and the project
manager during project initiation.

Hint
Unmarked

Question 80 - Qid 6113179, Integration Management, 2. Process, 1.2 Foundational Elements

A project team is using the Stacey Complexity Model to map the degree of uncertainty in the project and select the appropriate project life
cycle. As the meeting progresses, it becomes evident that while the requirements are well-known, the team is unfamiliar with the
technology required to implement them. As a result, the team selects an adaptive project life cycle.

Where on the Stacey Complexity Model did the team most likely map the project?

(Please note that on the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in the
simulator, we are asking you to select the answer below.)

A
B
C
D

Hint
Unmarked

Question 81 - Qid 6113060, Quality Management, 2. Process, 8.3 Control Quality

Your project team members are writing software code together as a pair and reviewing each other's work to determine if the code conforms
to the requirements documentation.

Which of the following will be a result of these reviews?

Accepted deliverable
Acceptance criteria Get the Simulator
Learn More (/orderpmpsimulator)
Work performance data
Verified deliverable

Hint
Unmarked

Question 82 - Qid 6113063, Resource Management, 1. People, 9.5 Manage Team

As part ofTime left:

the Direct and Manage Project Work process, the project manager conducts an iteration planning meeting. The meeting is

2:23:02
dominated by the most senior developer who frequently and sharply interrupts the other team members. The project manager wants to
ensure that during the next iteration planning meeting all voices are heard.
1/120 answered
What is the project manager's best course of action?
1Discuss
questions marked
the issue with the senior developer, and for the next meeting allocate equal amounts of time for each team
member to speak
Inform the senior developer's functional manager about this unacceptable behavior and request that the manager take
disciplinary action
Post a copy of the team's social contract in the meeting room and review the contents at the start of the next iteration
planning meeting
Invite the sponsor to the next iteration planning meeting to have the senior developer be more thoughtful in the presence
of the sponsor

Hint
Unmarked

Question 83 - Qid 6113070, Scope Management, 1. People, 5.0 Project Scope Management

The scrum master, business analyst, programmers, and testers have been assigned to a product development project. The performing
organization is well-versed with the traditional waterfall framework but will incorporate scrum for the software development phase of the
project.

What is the best strategy to ensure that all of the scrum roles and responsibilities are served in the project?

Remove the business analyst from the software development phase since that role is only associated with waterfall
project management
Mentor the business analyst to serve in the role of the product owner during the software development phase since those
roles are closely aligned
Request that one of the programmers serve as the voice-of-the-customer for the purposes of prioritizing the items in the
product backlog
Ask the most experienced tester to approve or reject the deliverables during the sprint review as testers are typically most
familiar with the product

Hint
Unmarked

Question 84 - Qid 6113086, Communications Management, 2. Process, 10.2 Manage Communications

The construction project has many people and specialized teams at the worksite every day. Frequent communication between the team
leads is critical for safety and efficiency.

Which agile ceremony can this project incorporate to increase timely cross-functional communication?

Iteration reviews
Risk-based spikes
Retrospectives
Daily standups

Hint
Unmarked

Question 85 - Qid 6113087, Communications Management, 2. Process, 10.3 Monitor Communications

At times over a project life cycle, the team must adopt a few agile ceremonies. The aim is to communicate quicker in times of tight
deadlines. Unfortunately, team members are not getting the information needed during the ceremonies.

What is the best option to confirm that the information is received and understood?

Validate with the team that the information was captured and facilitate feedback discussions
Spread out the ceremonies over months between each event to ensure comprehension
Mandate that all project team members update the information radiators after each ceremony
Reduce the number of project team members that attend the ceremonies

Hint
Unmarked

Question 86 - Qid 6113096, IntegrationGet the Simulator


Management,
4.0Learn
1. People, Project Integration
More Management
(/orderpmpsimulator)
A project manager is wrapping up the hardware development phase of a product development project. The project will now transition to
the software development phase.

How might the project manager's role change with respect to integration management?

Act as a servant leader by determining the relative size of the story points of the items in the product backlog
Delegate the control of the detailed project work planning and product delivery to the project team members
Time
Ensure thatleft:

the project team members each have specific tasks assigned to them and recorded in a Gantt chart

2:23:02
Strengthen the change management controls to ensure that scoop creep is minimized or entirely eliminated


answered
Hint1/120 Unmarked

1 questions marked
Question 87 - Qid 6113118, Resource Management, 1. People, 9.4 Develop Team

You are conducting a sprint retrospective in accordance with the communications management plan. The development team members
want to try pair programming as they believe it will improve productivity by reducing rework. Even though you are very skeptical, you agree
to implement the practice as you want to empower the team to be a self-managing unit.

What should you do next?

During the upcoming sprint, measure velocity and, if it decreases, discontinue pair programming and reprimand the team
members
Invite the project sponsor and other key stakeholders to demonstrate the increased collaboration between the project
team members
Submit a change request to update the communications management plan with the new agile practice of pair
programming
At the end of the upcoming sprint, revise the burndown chart, evaluate the productivity, and update the lessons learned
register

Hint
Unmarked

Question 88 - Qid 6113123, Integration Management, 1. People, 4.3 Direct and Manage Project Work

A project manager is leading a daily standup meeting with a scrum team as part of the Direct and Manage Project Work process. A developer
raises an impediment stating that he is struggling with the software code necessary to authenticate users on the sign-in page. The
developer indicates that the impediment could result in a schedule delay to the current sprint.

What is the project manager's best course of action?

Write the software code for the developer since it is the project manager's responsibility to remove impediments
Submit a change request to update the schedule baseline to reflect the delay caused by the impediment
Move the user authentication feature back into the project backlog and ask the product owner to reprioritize it
Recommend that the scrum team members use swarming as a technique to clear the impediment

Hint
Unmarked

Question 89 - Qid 6113125, Scope Management, 1. People, 5.2 Collect Requirements

Collecting requirements for the project and creating the WBS has been a daunting task because stakeholders' needs are vague and are only
expressed in the most general terms due to the nature of the project. As a result of this uncertainty, the project manager is concerned about
excessive changes, wasted work, and rework anticipated during project execution.

What is the project manager's best course of action?

Develop a project scope statement and decompose it down to the work package level as part of initial project planning
Request that the project team use an iterative and incremental approach to product development with short feedback
loops
Implement a robust change control system to only allow for the most important changes to be incorporated into the
product
Generate an activity list from what is currently known and use the Kanban board to break the activities down to their tasks

Hint
Unmarked

Question 90 - Qid 6113126, Scope Management, 1. People, 5.2 Collect Requirements

A project manager is implementing the requirements management plan for a software upgrade project that will incorporate some agile
elements. The project manager needs to quickly define cross-functional requirements and reconcile stakeholder differences to build a
consensus among the relevant stakeholders.

What is the project manager's best course of action?

Create a questionnaire and send it out to all of the stakeholders to determine the project requirements
Get the Simulator
Learn More (/orderpmpsimulator)
Conduct an in-person interview with each of the relevant stakeholders to determine their needs
Facilitate a requirements workshop with all of the relevant stakeholders to develop user stories
Perform a job shadowing exercise with the intended end-users of the existing software

Hint
Unmarked

Question 91 - Qid 6113130, Integration Management, 3. Business Environment, 2.4 Organizational Systems
Time left:

2:23:02
The organization?s leadership wants projects to include more agile methodologies.

Before mandating any agile methods to be used in a project, what should be done first?
1/120 answered
Pause current projects to align them to the new agile cadence
1Ask
questions marked
employees to vote on who wants to take part in agile projects
Assess organizational culture and readiness for the transformation
Provide agile training to those who will be part of the pilot project team

Hint
Unmarked

Question 92 - Qid 6113133, Risk Management, 2. Process, 11.3 Perform Qualitative Risk Analysis

You are establishing the relative priorities of individual risks identified in the project.

Which of the following tasks is the least likely to impact this prioritization?

Reviewing the assumption log


Examining the risk register
Researching the stakeholder register
Creating the risk report

Hint
Unmarked

Question 93 - Qid 6113135, Integration Management, 3. Business Environment, 1.2 Foundational Elements

Team members are frequently changing during the long timeline of a multi-phase project. The project manager is questioning whether to
include agile practices to accommodate the changes.

What should the project manager do prior to moving to a hybrid approach?

Ensure project finances are secured for the next project phase
Reduce the team size to nine people, plus or minus two
Target a smaller project as a proof of concept to test the feasibility
Evaluate the benefits of incorporating agile practices

Hint
Unmarked

Question 94 - Qid 6113136, Schedule Management, 3. Business Environment, 6.1 Plan Schedule Management

Midway into project execution, new cybersecurity laws take an immediate effect and require audits of the system. The project has a well
thought out project management plan. The audits may come at any time throughout the system?s development.

What is the best way for the project manager and team to address the risk of audits disrupting the project plans?

Handle the audits as an unplanned spike


Reschedule the audits to the end of the project
Request that the sponsor removes the audits
Inform stakeholders that the project will miss its objectives

Hint
Unmarked

Question 95 - Qid 6113138, Integration Management, 2. Process, 4.7 Close Project or Phase

A plan-driven project has many deliverables planned to be released at the end of the phase. The project manager wants to ensure that the
deliverables are completed as expected.

Which agile practices can the project manager recommend to the team to make certain that the deliverables are completed and delivered
as expected?

Definition of ready and iteration reviews


User stories and confidence votes
Definition of done and demonstrations
Backlog refinement and retrospectives
Get the Simulator
Learn More (/orderpmpsimulator)
Hint
Unmarked

Question 96 - Qid 6113139, Resource Management, 2. Process, 9.5 Manage Team

A project manager facilitates a discussion with the team about experimenting with some agile practices in their plan-driven project. A
suggestion of incorporating daily standups is on the table. The team members, however, are unsure of what is expected of them.
Time left:

2:23:02
What can the project manager suggest the project team members do prior to the daily standup?

Make sure their work progress is reflected in the burndown chart


1/120 answered
Submit the necessary progress reports to the product owner
Estimate work items that will be developed after the daily standup
1 questions marked
Resolve any defects that have been found in the previous day

Hint
Unmarked

Question 97 - Qid 6113142, Risk Management, 2. Process, 11.6 Implement Risk Responses

The project team is undergoing an agile transformation. This requires the team members to maintain their original project plans in the
current management tool, but also enter performance data in the new tool built around agile practices. The team identifies that the
information in the two tools is out of sync. This risk has been identified earlier in project planning.

What is the best course of action for the project manager?

Accept the risk since agile values individuals and interactions over processes and tools
Recognize that the risk has now become an issue and implement the planned response
Conduct a probability and impact assessment to determine a risk score
Communicate to the project sponsor that work may be delayed due to clerical errors

Hint
Unmarked

Question 98 - Qid 6113143, Integration Management, 2. Process, 2.4 Organizational Systems

Projects in a program are using various project management approaches, such as plan-driven, agile, hybrid. The project teams are
complaining that because of that, the team members must enter the same work, hours, risks, and other data in multiple tools. The
redundant work is impeding on their productivity time.

What is the best course of action for the program manager?

Direct the teams to continue entering the data in the various systems
Determine what tools and data provide the appropriate oversight
Switch all projects in the program to the agile project management approach
Pause all data entry until a valuable solution can be determined

Hint
Unmarked

Question 99 - Qid 6113144, Integration Management, 2. Process, 1.2 Foundational Elements

An organization is to undertake a multi-phased project. The sponsor wants to pursue the project objectives as they have been planned but
also wants to accommodate and adjust to new information and changes in the environment as the project progresses.

Which project management approach should the project manager select for this project?

Waterfall
Agile
Hybrid
Phased

Hint
Unmarked

Question 100 - Qid 6150814, Risk Management, 3. Business Environment, 11.4 Perform Quantitative Risk Analysis

Your sponsor has committed to building a high-speed rail from one major inland city, Azules, to the coast. You have two possible routes,
either Brazos or Corazon.

Given the costs, odds, and rewards of high demand and low demand of each route in this decision tree, what is the expected monetary
value of the route to Brazos?

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

1.6 billion
-2 billion
0.8 billion
10.8 billion

Hint
Unmarked

Question 101 - Qid 6113147, Integration Management, 2. Process, 4.4 Manage Project Knowledge

Senior leadership has returned from a conference where they have learned about the agile practice of retrospectives. Even though the
organization does not manage any projects in an agile manner, they mandate that from now on this ceremony is included in all projects.

How should the outputs from the retrospectives be stored and managed?

Senior leadership determines the location of the outputs and who may access the contents
The project team stores the outputs in a location that the project manager can control and limit changes
The project team determines a location that is accessible for relevant stakeholders to view and track
The project manager establishes the location and allows the customer to view and make recommendations

Hint
Unmarked

Question 102 - Qid 6113155, Resource Management, 1. People, 9.0 Project Resource Management

The resource management plan for an international project calls for a scrum team to be colocated during the regular workweek. However,
after five sprints were completed, the project manager got a change request approved to cut costs by transitioning the team to a virtual
environment working remotely from their homes with the start of the sixth sprint.

After the team begins working remotely, what will be the best method to understand the impact of the change on the team's productivity?

Check the product burndown chart to look for any changes to the trendline
Calculate the CPI at the end of each sprint to determine the change in the team's productivity
Review the product burnup chart to compare velocity before and after the change
Update the project schedule network diagram to reflect the changes in the team's environment

Hint
Unmarked

Question 103 - Qid 6113157, Resource Management, 1. People, 9.1 Plan Resource Management

As part of the Plan Resource Management process, project team members hold a brainstorming session to charter working agreements. The
team identifies 37 agreements that include communication guidelines, decision-making and conflict resolution processes, core hours, a
definition of a story point, how and when user stories will move through the Kanban board, etc.

What should the project manager do next?

Submit a change request to revise the resource management plan to incorporate the team's working agreements
Verify that all of the project team members support the working agreements and document the agreements in the project
charter
Review the team's working agreements at the start of every daily standup and during the sprint review meetings
Ask the project team members for their top five to ten agreements and document the information in the team charter

Hint
Unmarked

Question 104 - Qid 6113159, Resource Management, 1. People, 9.5 Manage Team

A project manager implements the project management plan meticulously but is struggling with leading the project team effectively. There
is a great deal of unhealthy tension between the project team members as well as with the project manager. The project manager has had
several outbursts during sprint retrospectives,
Get thewhich
Simulator
theLearn
has caused meeting
Moreto be abruptly adjourned.
(/orderpmpsimulator)
What should the project manager do first?

Submit a change request to revise the project management plan to eliminate the requirement for retrospectives
Take a proactive step in improving his own emotional intelligence (EI) to become a more effective leader
Reduce the story size by splitting user stories and use relative estimation with the entire team to estimate
Lead a training session with the project team members to help them become emotionally competent
Time left:

Hint
Unmarked
2:23:02
Question1/120
105 -answered
Qid 6113216, Stakeholder Management, 2. Process, 13.2 Plan Stakeholder Engagement

A project is six months into its nine-month projected duration. The project manager reports that the project is at least three months behind
1 questions marked
schedule because certain key stakeholders were resistant to consequential changes due to the project.

What might have been done differently during project planning to avoid this situation?

Better execution of the Manage Stakeholder Engagement process


Development of a stakeholder engagement assessment matrix
Creation of a comprehensive stakeholder register
Establishment of a more robust communications management plan

Hint
Unmarked

Question 106 - Qid 6113623, Schedule Management, 2. Process, 6.3 Sequence Activities

Two team members are arguing over how to organize the work packages in the work breakdown structure (WBS). One says the work
packages should be arranged in the order the work is planned to be carried out, while the other insists the order of the work packages in the
WBS does not matter. The two ask the project manager for advice.

What is the project manager's best response?

Work is decomposed and sequenced in the Define Activities process.


Any approach is good as long as the team members avoid the conflict.
The chronological order of tasks is defined in the Sequence Activities process.
The approach should be defined by the project management office (PMO).

Hint
Unmarked

Question 107 - Qid 6113718, Resource Management, 2. Process, 9.3 Acquire Resources

You are leading a project to design a high-efficiency solar cell. The project needs copper, silver, and silicon among other materials. You have
ordered custom-built manufacturing equipment, secured permission to install a solar array on the roof for testing, and reserved a
conference room for daily stand-up meetings.

What is the result of your efforts?

Resource histogram
Resource management plan
Resource assignment matrix
Physical resource assignments

Hint
Unmarked

Question 108 - Qid 6113733, Cost Management, 2. Process, 7.3 Determine Budget

During project execution, several unexpected issues have developed and are now threatening the project schedule and budget.

What is the best course of action for the project manager to address the issues?

Use contingency reserves


Review project funding requirements
Use management reserves
Review organizational process assets

Hint
Unmarked

Question 109 - Qid 6113755, Risk Management, 2. Process, 11.2 Identify Risks

To produce the deliverables, the project will procure goods and services from outside the organization. The project manager has instructed
the team to develop a comprehensive list of individual project risks related to those procurements.

What is the best course of action for the project


Get team?
the Simulator
Learn More (/orderpmpsimulator)
Consult the project charter
Review procurement documentation
Develop a procurement register
Check the probability and impact matrix

Hint
Unmarked
Time left:

2:23:02
Question 110 - Qid 6113796, Cost Management, 2. Process, 7.4 Control Costs

You are managing a renovation project of a house which is to be completed at a budget of $100,000. Earned value analysis shows that so far
1/120 answered
you have completed 40% of the work and spent $60,000.
1 questions marked
How much more will it cost to complete the project if the cost performance remains unchanged?

$160,000
$149,254
$120,000
$89,254

Hint
Unmarked

Question 111 - Qid 6125212, Procurement Management, 2. Process, 12.3 Control Procurements

A major dispute arises with a vendor on a project. The project manager claims that the vendor has failed to perform its contractual
obligations, while the vendor complains that the project is behind on payments.

What is the best course of action for the project manager in this situation?

Refer this issue to a third party for mediation or arbitration


File a contract claim and then work directly with the vendor to resolve the issue
Terminate the contract, document lessons learned, and find another vendor
Conduct a procurement audit

Hint
Unmarked

Question 112 - Qid 6125216, Resource Management, 1. People, 9.5 Manage Team

You want to recognize the contributions of some of the high-performing team members so far in the project.

Which of the following do you need to guide you through this process?

Organizational process assets


Stakeholder register
Project team assignments
Quality metrics

Hint
Unmarked

Question 113 - Qid 6150715, Schedule Management, 2. Process, 6.2 Define Activities

You are managing a project to construct a bridge at a location that is highly regulated by multiple levels of government. You are in the
process of developing a plan that will establish the criteria and the activities for developing, monitoring, and controlling the schedule.

Which of the following should you gather to complete this process?

The charter, project management plan, estimation databases, and PMO templates
Government standards, the assumption log, schedule management plan, and milestone list
The resource breakdown structure, lessons learned register, and scheduling methodology
The project scope statement, risk register, and project team assignments

Hint
Unmarked

Question 114 - Qid 6151376, Resource Management, 2. Process, 9.2 Estimate Activity Resources

One of the project activities requires that a search of a large area is conducted to find debris from an explosion of a failed prototype. The
project is now in planning, and there is a debate among the team members on the type and quantity of resources needed to complete this
activity.

What should the project manager do first?

Select any resource and quantity to complete the task by the due date
Request the team to vote and make
Get athe
decision
majority
based on
Simulator Learn More (/orderpmpsimulator)
Research various levels of resource capability and skills, types, and sizes
Utilize a PMIS to manage resource pools and allocate resources

Hint
Unmarked

Question 115 - Qid 6151382, Cost Management, 2. Process, 7.1 Plan Cost Management

A projectTime
managerleft:

is developing a cost management plan and needs to determine the best source of funding for a project that is dictated by

2:23:02
a legal requirement. The cost of capital is estimated at 9.7% for non-dividend paying equity, 6.7% for debt, and 5.1% for self-funding. The
NPV of the project is $500,000, and the opportunity cost is $750,000.
1/120 answered
What is the project manager's best course of action?
1Fund
questions marked
the project with equity since there are no dividend obligations
Select the self-funding option since it provides the lowest cost of capital
Perform an alternatives analysis since there are multiple factors to consider
Recommend the termination of the project since another project has a higher NPV

Hint
Unmarked

Question 116 - Qid 6151383, Cost Management, 3. Business Environment, 7.2 Estimate Costs

You are in the process of developing an approximation of the monetary resources needed to complete project work for a large-scale
multinational project which will take at least seven years to complete. Your previous projects have all been domestic with short timeframes.

As part of the process you are currently performing, what might you need to do differently compared with your past projects?

Create a stakeholder engagement assessment matrix


Develop a more robust risk management plan
Consider additional enterprise environmental factors
Include additional organizational process assets

Hint
Unmarked

Question 117 - Qid 6151389, Scope Management, 2. Process, 5.5 Validate Scope

You are assigned to a software development project, and you are conducting a product review with an important client. Although the
deliverables were previously verified, the client detects a defect and rejects one of the deliverables.

What should you do?

Submit a change request to fix the deliverable


Refund the customer for the value of the deliverable
Ask the project team to repair the defect
Begin the claims administration process

Hint
Unmarked

Question 118 - Qid 6151393, Integration Management, 1. People, 4.3 Direct and Manage Project Work

Not all team members are properly checking out resources used in the project.

What is the best option for the project manager?

Wait until there is a need or the team is impacted


Escalate the issue to the functional managers
Discuss the checkout rationale with the team
Remove the process of checking out resources

Hint
Unmarked

Question 119 - Qid 6151395, Scope Management, 2. Process, 5.6 Control Scope

In a pharmaceutical project, human trials have been started. The CEO is thrilled about the success of the trials up to this point. She
announces that the size of the patient pool for the trials should double from the one originally planned and results tracked in the new
system launching this week.

What should the project manager do first?

Ramp up production to match the demand of the CEO


Consider what might be included in a change request
Adjust the scope baseline to reflect the increased trial size
Communicate the change in theGet scope to Simulator
the

the project stakeholders


Learn More (/orderpmpsimulator)
Hint
Unmarked

Question 120 - Qid 6114007, Schedule Management, 2. Process, 6.5 Develop Schedule

Following is an illustration of a project network activity node that includes some information about activity D.

Given theTime left:


provided, what is the total float of activity D?
information

2:23:02
1/120 answered

1 questions marked

2
14
16
18

Hint
Unmarked

End Exam and Show Results

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

 Instructions
Test your exam-readiness with these 120 free PMP questions:

You have 1.2 mins per question


Select the best answer per question
Mark questions for review
Use "hint" if you are stuck
Unanswered questions count as incorrect
Perfect for PMP Practice Exam (https://www.pm-exam-simulator.com) preparation

Click the red button at the bottom of the page to end the exam and see your results.

 Restart the Exam

Clear All & Restart Exam! (https://www.project-management-prepcast.com/pmp-practice-exam-questions-sample-test/)

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

Get the Simulator


Learn More (/orderpmpsimulator)
Time left:

2:23:02
1/120 answered

1 questions marked

OSP INTERNATIONAL LLC


Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

 (http://twitter.com/pmexamtips)  (https://www.facebook.com/PrepCast)
 (http://www.pinterest.com/pmexamtips/)
 (https://www.youtube.com/user/CorneliusFichtner)

Company Info Customer Service


About Us (/about-us) Contact Us (/contact)

Our Team (/team) Help (https://pmhelpdesk.zendesk.com/hc/en-us)

Our Mission (/our-mission) Search (/search)

Terms & Conditions (http://www.osp-international.com/tc) Sitemap (/sitemap)

Privacy Notice (http://www.osp-international.com/privacynotice) Corporate Project Management Training (/project-management-corporate-


training)

Group Discounts (/group-discounts)

PM PrepCast Discount Coupon (/discount-coupon)

Scholarships (/scholarships)

Resources Exam Prep Training


Free PMP® Newsletter (/free/pmp-exam-newsletter) PMP® Exam Simulator (http://www.pm-exam-simulator.com)

Free PMP® Questions (/free/pmp-exam/free-pmp-exam-questions) PMP® Formulas (http://www.pmformulas.com/)

Free PMI-ACP® Questions (/free/pmi-acp-exam/free-questions) PMI-ACP® Exam Training (http://www.agileprepcast.com/)

Free CAPM® Simulator (/capm)


Get the Simulator
Learn More (/orderpmpsimulator)
CAPM® Exam Training (http://www.pm-prepcast.com/capm)
PMP® Exam Prep (https://www.project-management-prepcast.com/)

PrepCast PMP® Practice Exam (https://www.pm-exam-simulator.com)

Time left:

2:23:02
Copyright © 2008 - 2022 OSP International
1/120 answered LLC.

PMI, the PMI Authorized Training Partner logo, PMBOK, PMP, PgMP, PfMP, CAPM, PMI-SP, PMI-RMP, PMI-ACP, and PMI-PBA are registered marks of the Project Management Institute, Inc.