Chapter 7 Project Implemtation
Chapter 7 Project Implemtation
MANAGEMENT/IMPLEMENTATION
▪ Project planning need is much greater for project work than for normal operations.
• Project planning provides a basis for organizing the work on the project and allocating responsibilities to individuals.
• It is a means of communication and coordination between all those involved in the project.
actions
10/29/2022 Instructor: Dr. Dagnu L. 4
7.3. Work breakdown structure (wbs)
• WBS is an important concept that the project analyst needs
to comprehend as well as use in the process of implementation
planning.
• Lists clear & unambiguous quality targets for each deliverable. Each quality target provides a set of
criteria & standards which must be achieved to meet the expectation of the customer
• Outlines a plan of activities which will assure the customer that the quality targets will be met (i.e. a
quality assurance plan )
• Identifies the techniques used to control the actual level of quality of each deliverable as it is built
(i.e. a quality control plan)
• Mitigate/reduce
• Transfer
• Accept
10/29/2022 Instructor: Dr. Dagnu L. 9
8. Develop communication plan
• The communication plan identifies the types of information to be distributed, the
distributing & responsibility of each person in the project team for distributing
• The procurement plan provides a detailed description of the products ( i.e goods
• Overview
• brief description of project
• deliverables
• milestones
• expected profitability and competitive impact
• Objectives
• detailed description of project’s deliverables
• project mission statement
• General approach
• technical and managerial approaches
• relationship to other projects
• deviations from standard practices
• Contractual aspects
• agreements with clients and third parties
• reporting requirements
• technical specifications
10/29/2022 • project review dates Instructor: Dr. Dagnu L. 13
Cont’d
• Evaluation methods
• evaluation procedures and standards
• procedures for monitoring, collecting, and storing
data on project performance
• Potential problems
✓ list of likely potential problems
planning (scheduling).
– Bar Chart
– Network Techniques
– Divides project implementation into time phased activities & shows the
duration of each activity.
– The left-hand end of the bar shows the beginning time and the right-
hand end the ending time.
3. Analyze the work content of each sub-task to determine how much time it takes to complete
individual sub-tasks.
▪ Work to be done
▪ Resources needed
▪ Results to be produced
– It is simple to understand
▪ There may be a physical limit to the size of the bar chart (this may
limit the size of the project that can be planned with this
technique).
• Activity
– Represented by an arrow
• Dummy Activity
• Critical Path
• The longest path (time); determines the project
duration
• Critical Activities
• All of the activities that make up the critical path
3
Lay Dummy
foundation
2 0 Build Finish
house work
3 1
1 2 4 3
6 1
7
Design house Order and
and obtain receive 1 1
financing materials Select Select
paint carpet
A D
1 3 4
B C
– They identify the activities that are critical to the completion of the project on
time.
Limitations
– They do not define an operational schedule that tells who does, what, and when.
2. Divisional organization
3. Matrix organization
10/29/2022 Instructor: Dr. Dagnu L. 31
a) Line and Staff Organization
• A person is appointed with the primary responsibility of coordinating the work of
• The project coordinator does not have authority and direct responsibility of line
information and seeks to promote the cause of the project by rendering advice,
He may gently coax line executives to strive for the fulfillment of project goals.
This type of organization is usually not suitable for large projects. However, it is
project manager, this division has its complement of personnel over whom
the project manager has full line authority. It implies the creation of a
separate goal oriented division of the company, with its own functional
departments.
• While the project manager still has the problem of coordinating the inputs
objectives.
a project.
– People’s problems may not be adequately solved in the short span of the project
life.
• Authority
• Orientation
• Time & cost over-runs of projects are very common in developing countries (particularly in the public sector).
What can be done to minimize time & cost overruns and improve the prospects of the successful completion of
projects?
1. Adequate formulation
3. Advance action
4. Timely availability of funds
5. Careful equipment tendering and procurement
6. Better contract management
10/29/2022 Instructor: Dr. Dagnu L. 36
7. Effective monitoring
1. Adequate Formulation
• Project formulation is often deficient because of
one or more of the following shortcomings:
– Superficial field investigation
– Hurried assessment of input requirements
• Slipshod (careless) methods used for estimating costs &benefits
– Omission of project linkages
– Flawed judgments because of lack of experience & expertise
– Undue hurry to get started
– Deliberate over-estimation of benefits and underestimation of
costs, etc
• Care must be taken to avoid these deficiencies.
– Ensure that the formulation and appraisal of the project is thorough, adequate,
and meaningful
(manpower, materials, money, etc) for each period to realize the time
plan.
III. Define properly the inter-linkages between various activities of the project.
✓ Acquisition of land
✓ Calling of tenders
– Desirable to have funds even before the final approval to initiate advance action.
Questions:
– How much should we depend on foreign suppliers?
– How much should we rely on indigenous suppliers?
• The competence & capability of all the contractors must be ensured. One weak-
link can jeopardize the timely
• Help should be extended to contractors & suppliers when they have genuine
problems.
– It should focus sharply on the critical aspects of project implementation. It must lay
more emphasis on physical milestones and not on financial targets.
• May lead to redundant paper work & diversion of resources if the system is
overcomplicated.
• Time/Cost Reports
• Variance Reports
• When
• the degree to which the project has met its goals
• the degree to which the project qualifies against a set of factors associated with success or failure
1. Project Extinction
2. Termination-By-Addition
3. Termination-By-Integration
10/29/2022
“ THE END “
Instructor: Dr. Dagnu L. 49