Unitech Limited Vs Telangana State Industrial Infrastructure Corporation LL 2021 SC 92 389293
Unitech Limited Vs Telangana State Industrial Infrastructure Corporation LL 2021 SC 92 389293
Unitech Limited Vs Telangana State Industrial Infrastructure Corporation LL 2021 SC 92 389293
WWW.LIVELAW.IN
Reportable
Versus
With
And
With
Digitally signed by
Sanjay Kumar
Date: 2021.02.17
12:40:58 IST
Reason:
1
LL 2021 SC 92
WWW.LIVELAW.IN
JUDGMENT
Dr Dhananjaya Y Chandrachud, J
A. Background
E. Analysis
F. Summation
2
LL 2021 SC 92
WWW.LIVELAW.IN
PART A
A. Background
1 The appeals arise from a judgment dated 1 April 2019 of a Division Bench of
the High Court for the State of Telangana. Three appeals will form the subject matter
of these proceedings. The three appeals which arise have been instituted by
Ltd. (“APIIC”) invited bids to “develop, design and construct” an integrated township
project / multi services aerospace park in the area of about 350 acres of land in
pay an amount of Rs 140 crores as project land cost and Rs 5 crores towards
project development expenses. A litigation in regard to the land was pending. While
issuing a Letter of Award (“LoA”), APIIC made the allotment of the land subject to
3
LL 2021 SC 92
WWW.LIVELAW.IN
PART A
4 Pursuant to accepting the LoA on 3 December 2007, Unitech paid the first
installment of Rs 15 crores towards the purchase price of the land. This was
installments of Rs 70 crores towards the cost of land directed the Zonal Manager,
Shamshabad Zone, Hyderabad to hand over the project site to enable Unitech to
towards the purchase price of the land was paid on 11 January 2008, while the fifth
installment for another Rs 35 crores was paid on 25 January 2008. Unitech paid, in
the above manner, a total amount of Rs 165 crores: Rs 140 crores towards the cost
APIIC, Unitech and Nacre Gardens Hyderabad Limited, formerly known as (Unitech
project.
4
LL 2021 SC 92
WWW.LIVELAW.IN
PART A
commence work on the project land. On 11 May 2011, Unitech requested APIIC to
intimate, within seven days, the steps being taken to handover the land with
notice dated 29 April 2011 was further re-iterated in Unitech’s letter dated 14 May
2011 stating that APIIC would have to first establish its title to the land and to
8 On 21 May 2011, APIIC was informed that a ‘political force majeure event’
December 2011, the High Court of Andhra Pradesh in a proceeding titled as “Pratap
Karan v Govt. of Andhra Pradesh1, held that the Government of Andhra Pradesh
did not have title to the project land. Following the decision, Unitech by its
communication dated 27 March 2012 requested APIIC to clarify the position and to
jointly explore possible solutions to the title dispute over the project site.
1
Appeal Suit No. 274 of 2007 (Andhra Pradesh High Court)
5
LL 2021 SC 92
WWW.LIVELAW.IN
PART A
On 8 April 2013, Unitech again called upon APIIC to come forward to execute the
sale deed, handover the project site and ensure that the encumbrances on the
10 The State of Andhra Pradesh was re-organized into the successor States of
Andhra Pradesh and Telangana with effect from 2 June 2014 under the provisions of
addressed a letter to the newly-formed TSIIC (as successor of APIIC) seeking its
intervention in clarifying the actual status of the extent of the land awarded to them,
the cases against the erstwhile APIIC, physical handover of possession with a clear
title and compensation for loss of time and opportunity. On 2 April 2015, Unitech
sought a release of the earnest money deposit of Rs 20 crores, in light of the full
judgment of the High Court. After the decision of this Court, Unitech requested
APIIC and TSIIC, on 14 October 2015, to refund all the amounts which have been
2
(2016) 2 SCC 82
6
LL 2021 SC 92
WWW.LIVELAW.IN
PART A
received in relation to the land together with interest and damages for the loss
suffered by them, which included the cost of borrowing capital from banks, expenses
for planning and designing, opportunity costs and other costs for development.
crores towards principal and interest. This was followed by reminders on 31 May
2016 and 7 June 2016. An advocate’s notice was also issued on 13 June 2016.
filed proceedings before this Court which were disposed on 1 May 20173 by granting
liberty to move the High Court under Article 226. A Writ Petition under Article 226
was instituted before the High Court for the State of Telangana4 seeking a refund of
Rs 165 crores together with interest at the SBI Prime Lending Rate (“SBI- PLR”)
from the date of payments. By a judgment and order dated 23 October 2018, a
Single Judge of the High Court allowed Unitech’s Writ Petition. The concluding
3
Writ Petition (Civil) No. 302 of 2017 (Supreme Court of India)
4
Writ Petition (Civil) No. 29722 of 2017 (Andhra Pradesh High Court)
7
LL 2021 SC 92
WWW.LIVELAW.IN
PART A
63. The respondents have not disputed either the dates of the
payments or the interest at SBI Prime Lending Rate
mentioned by the petitioners or placed any material to
contradict the same.
8
LL 2021 SC 92
WWW.LIVELAW.IN
PART A
14 A Writ Appeal was filed before the High Court by TSIIC and the State of
Telangana5. The Division Bench of the High Court upheld the order of the Single
However, the Division Bench directed a refund of the principal sum of Rs 165 crores
with interest from 14 October 2015 at the SBI-PLR, as opposed to the dates of
15 The Division Bench of the High Court has come to the conclusion that in the
exercise of the writ jurisdiction under Article 226, the Single Judge’s decision had
aligned itself with the line of precedent of this Court; justifiably entertained the writ
petition and directed a refund of the consideration. However, the order of the Single
Judge directing the payment of interest compounded inter alia at the SBI- PLR from
the dates of payment commencing from September 2007 has been modified in
terms of the direction requiring the payment of interest at the SBI- PLR from 14
5
Writ Appeal No. 1594 of 2018 (Andhra Pradesh High Court)
9
LL 2021 SC 92
WWW.LIVELAW.IN
PART A
(i) Under the LoA dated 28 November 2007, Unitech was put to notice that the
award of the contract was subject to the outcome of a litigation which was
(ii) Even the advertisement for the award of the contract indicated that it would be
subject to the outcome of a first appeal which was pending before the High
Court;
(iii) Unitech accepted the award of the contract on 3 December 2007 and made
(iv) The release of the earnest money deposit was sought on 2 April 2015 and a
refund of the entire amount paid with interest, was claimed for the first time on
14 October 2015, after the judgment of the High Court attained finality through
(v) Unitech was aware of the pending litigation and was awaiting the outcome of
the civil appeal and the tenor of the correspondence indicates that they
On the above premises, the Division Bench of the High Court took a considered
view that Unitech’s request for a refund on 14 October 2015, after the decision of
this Court confirming that the Government of Andhra Pradesh had no title to the
10
LL 2021 SC 92
WWW.LIVELAW.IN
PART B
16 Notice was issued by this Court in the Special Leave Petition filed by Unitech
on 15 April 2019.
17 On 13 February 2020, this Court recorded that a new Board of Directors had
taken charge of the business of Unitech limited. At this stage, it must be noted that
the Board of Directors of Unitech has been superseded and replaced by a Board
18 On 5 March 2020, when the proceedings came up before this Court, besides
the Special Leave Petition filed by Unitech limited and its subsidiary, the Court was
seized with two other Special Leave Petitions filed by TSIIC and the State of
Telangana, respectively. This Court noted the submissions which were urged on
behalf of TSIIC that following the re-organization of the erstwhile State of Andhra
Pradesh, a division of the assets and liabilities was required to be effected by the
2014, in the absence of which TSIIC could not alone be held liable to deposit the
entire amount as ordered to be refunded by the High Court. This Court recorded the
submission of TSIIC that it would deposit 42 per cent of the principal sum of Rs 165
commencing from 14 October 2015 must be deposited, at the rate and in the
11
LL 2021 SC 92
WWW.LIVELAW.IN
PART B
manner directed by the Single Judge of the High Court. The order of this Court
12
LL 2021 SC 92
WWW.LIVELAW.IN
PART B
the Act, TSIIC cannot be held liable for the entire amount
merely on the ground that the lands fall within the jurisdiction
of the successor State of Telangana. The submission is that
despite the objections which were raised on behalf of the
TSIIC, APIIC was not impleaded as a party to the
proceedings before the High Court.
13
LL 2021 SC 92
WWW.LIVELAW.IN
PART C
Notice has been issued in the Special Leave Petitions filed by the State of
19 The appeals arising out of the three proceedings under Article 136 of the
Constitution have been heard together since they arise out of common facts and the
same transaction.
analysis with a reference to the salient aspects of the transaction, leading to the
award of the contract and the execution of the Development Agreement between
21 On 28 November 2007, the LoA was issued by APIIC to Unitech for the
the payment of an amount of Rs 140 crores towards the value of the land, payable in
four tranches each of Rs 35 crores. Clause 3 of the LoA was in the following terms:
The Total Purchase Price for the Total Land shall be Rs.140
crores (Rupees one hundred and forty crores only). The value
of the land is fixed at Rs.40 Lakhs per acre (Rupees Forty
Lakhs per acre) and payable to APIIC as follows:
14
LL 2021 SC 92
WWW.LIVELAW.IN
PART C
i) Rs.35 Crores (Rs. Thirty Five crores only) within 7 days from
the issue of LOA to the Developer.
ii) Rs.35 Crores (Rs. thirty Five Crores only) to be paid within 30
days from the date of 1st instalment by the developer.
iii) Rs.35 Crores (Rs. thirty five Crores only) within 15 days from
the date of 2nd instalment by the developer.
iv) Rs.35 Crores to be paid within 15 days from the date of 3rd
instalment by the developer.
“(ii) Failure to pay the Total Purchase Price quoted for the
land to APIIC within the time as specified in this Letter of
Award.”
15
LL 2021 SC 92
WWW.LIVELAW.IN
PART C
Agreement dated 19 August 2008 executed between APIIC and Unitech are set out
below:
APIIC was authorized to transfer and deliver the project site admeasuring
350 acres:
(ii) APIIC covenanted to transfer and sell the land together with its rights, title
and interest free from all encumbrances by executing a sale deed in favour
of Unitech:
16
LL 2021 SC 92
WWW.LIVELAW.IN
PART C
(ii) Article 1.7 stipulates an order of priorities under which, in the event of a
conflict between the agreement and any other document, the former would
prevail:
(iii) Under Article 3.1, APIIC undertook the obligation to transfer the land to the
developer free from all encumbrances, upon the developer’s payment of the
17
LL 2021 SC 92
WWW.LIVELAW.IN
PART C
(iv) APIIC acknowledged the payment of Rs 140 crores towards the total
Article 3.2.
(v) Under Article 4.1, the developer was to have exclusive promotion and
advertising rights in respect of the project and under Article 4.2, could enjoy
immovable property.
(vi) Simultaneously with the payment of the last installment of the total purchase
(c) A declaration certifying that APIIC is the rightful owner of the land
(vii) Article 13.3 provided for the obligations of APIIC in the following terms:
18
LL 2021 SC 92
WWW.LIVELAW.IN
PART C
(viii) The consequences of default by APIIC were stipulated in Article 14.3. Thy
19
LL 2021 SC 92
WWW.LIVELAW.IN
PART C
force majeure events. Article 17.2(a) defined ‘political force majeure events’:
(xi) Article 17.6 stipulates that in the event of a political force majeure event
continuously impacting upon the project as a material adverse effect for over
20
LL 2021 SC 92
WWW.LIVELAW.IN
PART D
(i) Title was never conveyed by APIIC to Unitech In terms of the Development
Agreement;
(ii) By the judgment of this Court dated 9 October 2015, the dispute over the title
of the Government of Andhra Pradesh over the project land was conclusively
(iii) An amount of Rs 165 crores has been deposited by Unitech since September
21
LL 2021 SC 92
WWW.LIVELAW.IN
PART D
(iv) The project cannot be implemented in the absence of title to the lands in the
State Government.
(a) The entire project was premised on the conveyance of title to the land, free
(b) A solemn representation was held out in the Development Agreement that
crores upfront;
(d) ‘Political force majeure events’ included litigation relating to the title of APIIC
force majeure event which caused a material adverse impact on the project
for over nine months, Unitech was entitled to compensatory payment from
APIIC;
(e) Upon the failure of title of the Government of Andhra Pradesh resulting from
the judgment of this Court dated 9 October 2015, the developer became
(f) The existence of an arbitration clause would not divest the High Court of its
jurisdiction under Article 226 of the Constitution to order refund with interest,
(g) The exercise of the writ jurisdiction under Article 226 in a contractual matter
is not ruled out particularly in the present case where there is absolutely no
(h) The Single Judge of the High Court had justifiably awarded interest from the
date of the first payment by Unitech in 2007. The Division Bench erred in
(i) The litigation in regard to the title of the Government of Andhra Pradesh had
nothing to do with the moneys paid by Unitech. When the moneys were paid
in 2007, the refund of the amount must date back with reference to the date of
the initial payment. Therefore, the interest must be computed from the date on
(j) When the LoA was issued on 28 November 2007, the judgment dated 23
April 2007 held the field, which was in favour of the Government of Andhra
Pradesh. Its subsequent reversal would entitle the developer to a refund with
State of Telangana and TSIIC. At the outset, he has submitted that TSIIC and the
(i) The maintainability of a writ petition under Article 226 before the High Court;
and
23
LL 2021 SC 92
WWW.LIVELAW.IN
PART D
(ii) The fact that the land comprised within the project site is not available for
Counsel have been confined are: firstly, whether interest at the SBI-PLR and the
date from which interest has been awarded by the Division Bench of the High Court
are justified; and secondly, whether the High Court was justified in imposing the
(i) The LoA dated 28 November 2017 furnished notice to Unitech of the
(ii) Unitech and its SPV were conscious of the pendency of the appeal before the
High Court arising out of the judgment dated 30 April 2007, which had ruled in
(iii) Unitech continued to pursue the project and did not claim political force
(iv) In any event, the High Court has brought about a just balancing of equities by
granting interest from the date of the decision of this Court namely 14 October
2015; and
(v) The rate of interest should be suitably scaled down from the SBI- PLR.
24
LL 2021 SC 92
WWW.LIVELAW.IN
PART D
The above submissions in regard to the payment of interest; the date from which
interest should be payable and the appropriate rate of interest, were postulated on
the liability to refund the principal amount to Unitech. As a matter of fact, it has been
expressly stated during the course of the submissions that the liability to refund is
28 The second limb of submissions is that the liability to refund the principal
amount together with interest cannot be imposed on TSIIC alone. TSIIC argues that
the liability to refund the principal sum together with interest to Unitech has to be
apportioned between TSIIC and APIIC in terms of the provisions contained in the
Andhra Pradesh Reorganization Act 2014. The submission is elaborated along the
following lines:
(i) TSIIC has deposited an amount of Rs.127.53 crores before this Court in
pursuance of the interim order dated 5 March 2020, out of which Rs.69.30
(ii) Section 68 of the Reorganization Act stipulates that the companies specified
in the IXth Schedule (including APSIIC) constituted for the erstwhile State of
sub-section(2) of Section 68, the assets, rights and liabilities of the companies
25
LL 2021 SC 92
WWW.LIVELAW.IN
PART D
(iii) Under Section 71, the Central Government is empowered to issue directions
in respect of the companies specified in the IXth Schedule inter alia for dividing
the interest and shares of the existing State of Andhra Pradesh between the
successor States;
(v) Though the Central government constituted a Committee for the distribution
of assets, it has not issued any directions, despite the committee submitting
(vi) Section 2(h) of the Re-organization Act provides for a population ratio of
approximately of 58:42, TSIIC has borne 42 per cent of the liability towards
the refund due to Unitech and the balance should be directed to be shared by
APIIC has entered appearance and filed its own counter affidavit. Mr Anuroop
Chakravarti, learned Counsel appearing on behalf of the APIIC, has opposed the
submissions urged on behalf of the State of Telangana and TSIIC that the liability to
26
LL 2021 SC 92
WWW.LIVELAW.IN
PART D
refund the principal and interest must be apportioned between TSIIC and APIIC.
(i) Before the appointed date of 2 June 2014, determined under the Re-
organization Act, a final audit was completed on 1 June 2014 and a joint
(ii) The certificate issued on behalf of TSIIC and APIIC by its Managing Directors
records that all the assets and liabilities having a bearing in the balance sheet
as on 1 June 2014 have been audited and included in the demerger scheme
and that all assets and liabilities were duly apportioned between Andhra
from the terms and conditions which have been spelt out in Part II of the third
Schedule. The Schedule elucidates that the project site which forms the
subject matter of the Development Agreement was a part of the area which
falls within the jurisdiction of TSIIC. The liability by the terms of the demerger
30 The Special Leave Petition6 which was filed before this Court by TSIIC raised
several objections to the correctness of the order passed by the High Court. Among
the grounds which were urged in support of the Special Leave Petition were the
following:
6
SLP (C) No. 10135 of 2019
27
LL 2021 SC 92
WWW.LIVELAW.IN
PART D
(i) The High Court ought not to have entertained a writ petition under Article 226
23.1;
(iii) TSIIC can provide the land to Unitech and hence a direction for refund with
(iv) There was a violation by Unitech of the terms of the bid document and the
LoA and the Development Agreement deviated from the bid and the LoA;
(v) Unitech bid for the project and accepted the LoA with full knowledge of the
pending litigation over title to the land forming a part of the agreement, and
(vi) APIIC entered into the agreement with Unitech and ought to share the
31 The State of Telangana, in its submissions before this Court in the Special
Leave Petition had similarly assailed the judgment of the High Court on several
which is invalid;
28
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
(ii) The land which is comprised in the project site can be made available for the
project as the land owners have agreed to transfer the land to the
Government of Telangana;
(iii) The terms and conditions of the LoA were not complied with by Unitech;
(iv) In view of the arbitration agreement, a writ petition under Article 226 could not
be maintained; and
(v) The liability, if any, has to be shared between the successor states of Andhra
E. Analysis
32 Much of the ground which was sought to be canvassed in the course of the
pleadings is now subsumed in the submissions which have been urged before this
Court on behalf of the State of Telangana and TSIIC. As we have noted earlier,
during the course of the hearing, learned Senior Counsel appearing on behalf of the
State of Telangana and TSIIC informed the Court that the entitlement of Unitech to
seek a refund is not questioned nor is the availability of the land for carrying out the
project being placed in issue. Learned Senior Counsel also did not agitate the
ground that a remedy for the recovery of moneys arising out a contractual matter
cannot be availed of under Article 226 of the Constitution. However, to clear the
ground, it is necessary to postulate that recourse to the jurisdiction under Article 226
29
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
33 A two judge Bench of this Court in ABL International Ltd. v. Export Credit
precedent of this Court8 to conclude that writs under Article 226 are maintainable for
This exposition has been followed by this Court, and has been adopted by three-
judge Bench decisions of this Court in State of UP v. Sudhir Kumar9 and Popatrao
cautions that the plenary power under Article 226 must be used with circumspection
when other remedies have been provided by the contract. But as a statement of
principle, the jurisdiction under Article 226 is not excluded in contractual matters.
7
(2004) 3 SCC 553
8
K.N. Guruswamy v. State of Mysore, AIR 1954 SC 592; Gujarat State Financial Corporation. v. Lotus Hotels
(P) Ltd, (1983) 3 SCC 379; Gunwant Kaur v. Municipal Committee, Bhatinda, (1969) 3 SCC 769
9
2020 Scconline SC 847
10
Civil Appeal 1600 of 2000 (Supreme Court of India)
30
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
Article 23.1 of the Development Agreement in the present case mandates the
party has not acted as an absolute bar to availing remedies under Article 226.11 If
the state instrumentality violates its constitutional mandate under Article 14 to act
fairly and reasonably, relief under the plenary powers of the Article 226 of the
Therefore, while exercising its jurisdiction under Article 226, the Court is entitled to
enquire into whether the action of the State or its instrumentalities is arbitrary or
unfair and in consequence, in violation of Article 14. The jurisdiction under Article
11
Harbanslal Sahnia v. Indian Oil Corporation Ltd., (2003) 2 SCC 107; Ram Barai Singh & Co. v. State of Bihar
& Ors., (2015) 13 SCC 592
31
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
trial. But equally, it is well-settled that the jurisdiction under Article 226 cannot be
ousted only on the basis that the dispute pertains to the contractual arena. This is for
the simple reason that the State and its instrumentalities are not exempt from the
duty to act fairly merely because in their business dealings they have entered into
the realm of contract. Similarly, the presence of an arbitration clause does oust the
jurisdiction under Article 226 in all cases though, it still needs to be decided from
invoked. The jurisdiction under Article 226 was rightly invoked by the Single Judge
and the Division Bench of the Andhra Pradesh in this case, when the foundational
representation of the contract has failed. TSIIC, a state instrumentality, has not just
reneged on its contractual obligation, but hoarded the refund of the principal and
interest on the consideration that was paid by Unitech over a decade ago. It does
34 In the present case, the basic postulate underlying the contract between the
parties was the availability of the land which comprised the project site. The LoA
dated 28 November 2007, stated that the allotment of land was subject to the
outcome of the pending appeal before the High Court of Andhra Pradesh. The
dispute over the title of the Government of Andhra Pradesh was the subject of the
32
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
pending litigation. At the same time, the LoA mandated that Unitech must pay the
amount stipulated - including the purchase price of Rs.145 crores for the land as
Acting on the LoA, Unitech did in fact comply with its obligation to pay, having paid a
total amount of Rs.165 crores towards the purchase price, besides the earnest
which was executed between APIIC and Unitech contains specific representations to
the effect that APIIC was authorized to transfer and deliver the project site
Agreement, APIIC was to sell and transfer the land absolutely together with its right,
title and interest, free from all encumbrances by executing a sale agreement. The
terms of the agreement were to prevail in the event of any conflict with any other
document which formed a part of the bidding process. The terms of the agreement
were placed on the pedestal of the highest priority for interpretation, as compared to
other documents, including the LoA. Under the terms of the Development
Agreement, APIIC was obligated to sell and transfer the land together with its right,
title and interest free from all encumbrances “forthwith upon payment of the last
installment of the total purchase price by the developer”. That Unitech paid the total
possession together with title upon the payment of the last installment of the
purchase price unequivocally emerges from Article 3.1 and Article 4.1 of the
postulated on the availability of the land. Apart from the terms of the agreement
which have already been emphasized, representations in regard to the title to the
reads as follows:
34
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
Article 17 stipulates force majeure events. Article 17.2 provides for political force
majeure events comprising inter alia “direct litigation related to APIIC’s/GoAP’s title
36 Article 14.3.4 expressly stipulates that the developer shall not be liable for the
failure to meet any of its obligations under the agreement, in the event, that it could
encumbrances or title issues on any portion of the land which may have a material
were unable to execute the sale deed in favour of the developer in respect of the
land within the time specified, APIIC shall, if so required for the developer, make
majeure event, Unitech was, in terms of Article 17.6, solely entitled to issue a notice
more than nine months. In that event, APIIC was obligated to make the
terms of the agreement is expressly defined, including for the purposes of Article
14.3.1, to mean an amount which is the aggregate of (i) the total purchase price; and
(ii) interest calculated at the SBI-PLR on the total purchase price “from the date on
paid”. The applicable rate was also defined12 to mean the Prime Lending Rate of the
37 The failure of title in the erstwhile APIIC and the Government of Andhra
Pradesh attained finality upon the decision of this Court in State of Andhra
which the entire contract was founded stood nullified as a consequence of the failure
12
“Article 1(h)- ‘Applicable Rate’ means the prime lending rate of the State Bank of India, compounded-
annually.”
13
(2016) 2 SCC 82
36
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
of title. The agreement clearly provides that the ability of the Government of Andhra
Pradesh/TSIIC to convey full title to the developer forms the basis of the
contract. The failure of title entitles Unitech to claim a full refund together with
Single Judge and the Division Bench of the High Court have elaborately considered
the precedents of this Court and correctly concluded that Unitech is entitled to a
unexceptionable and has correctly not been called into question at the stage of the
hearing, despite the grounds which were raised in the pleadings in the proceedings
initiated under Article 136 of the Constitution by TSIIC and the State of Telangana.
bids for a public project. Having invited private entrepreneurs to submit bids on
stipulated terms and conditions, it must be held down to make good its
representations. The State and its instrumentalities are duty bound to act fairly under
Article 14 of the Constitution. They cannot, even in the domain of contract, claim an
exemption from the public law duty to act fairly.14 The State and its instrumentalities
do not shed either their character or their obligation to act fairly in their dealings with
private parties in the realm of contract. Investors who respond to the representations
held out by the State while investing in public projects are legitimately entitled to
14
Indsil Hydropower v. State of Kerala, Civil Appeal Nos. 5943-5945 of 2019 (Supreme Court of India), para
33; ABL International Ltd. v. Export Credit Guarantee Corporation of India, (2004) 3 SCC 553, para 23; Central
Bank of India v. Devi Ispat Ltd., (2010) 11 SCC 186, para 28
37
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
assert that the representations must be fulfilled and to enforce compliance with
38 The Single Judge of the Andhra Pradesh High Court, in the course of the
of Rs.660.55 crores as due and payable. Interest on the basis of the SBI-PLR was
The Single Judge noted that the respondents to the writ proceedings had not
disputed (i) the dates of payment or (ii) interest at the rate of the SBI-PLR and no
material to contradict the computation was submitted. In appeal, the Division Bench
however directed that the claim for interest should be computed from 14 October
2015. This was the date on which Unitech addressed a communication seeking a
October 2015 on the absence of title to the land in the Government of Andhra
(i) Unitech was placed on notice that the award of the contract was subject to the
(ii) Unitech was aware of the outcome of the first appeal yet, as a developer, it
of moneys from the date of initial payment. The entitlement of Unitech to a refund of
the amounts paid is embodied in the terms of the contract which envisage that a
38
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
default on the part of APIIC in conveying the land or the existence of political force
payment”. Moreover, the date from which compensatory payment has to be made is
specifically provided : the Development Agreement provides that it will be "from the
date on which the first payment of project price" is made. The Division Bench was in
error in curtailing the right of Unitech to claim a refund with effect from the dates on
which the respective payments were made. Obviously, Unitech had entered into the
project since it wished to pursue it. Unitech cannot be penalized for wanting to
continue with the agreement, as APIIC navigated disputes over its claim to the land.
While Unitech was put to notice of the existence of a litigation, the Development
covenants would supersede all other understandings and that its terms would rank
as the first, in order of interpretive priority. The judgment of the Division Bench
suffers from a clear and patent error in restricting the liability of paying interest with
effect from 14 October 2015. The liability must date back, in terms of the
Development Agreement, from the date on which the respective payments were
made by Unitech. Interest at the contractual SBI-PLR rate has to be paid to Unitech.
However, considering the facts and circumstances of this case, the conscionability
of Article 14.3.1 read with Article 1(h) of the Development Agreement stipulating
Clause 17 of the LoA expressly mentioned that the title of the land is lis pendens
and subject to the outcome of the proceedings pending before the Andhra Pradesh
High Court. Unitech considered this circumstance and consciously entered into the
39
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
judgement of the Andhra Pradesh High Court and did not issue a termination notice,
until the title was conclusively denied by a judgement of this Court. A Constitution
Bench of this Court, in the case of Central Bank of India v. Ravindra15, when
In a similar vein, in interpreting Section 74 of the Indian Contract Act, 1872, this
upholding the reasoning of the Kerala High Court in full, a two judge Bench of this
15
(2002) 1 SCC 367
16
Oriental Kuries Ltd. v. Lissa, (2019) 19 SCC 732; Bhubaneshwar Development Authority v. Susanta Kumar
Mishra, (2009) 4 SCC 684
17
(1987) 2 SCC 424
40
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
Development Agreement with full knowledge of the pending litigation and with an
intention to continue with the project after a delay of over seven years, up until a
decision by this Court, we find that the interest rate is payable to Unitech, without
compounding.
39 This leaves the court with the last facet which pertains to the dispute inter se
between TSIIC and APIIC. The Single Judge has imposed the liability to refund on
TSIIC clarifying however, that it is "entitled to recover it from the State of Andhra
Pradesh and the APIIC, if under law they are entitled to do so”. The Division Bench
41
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
provides as follows:
The corporations which are listed out in the IXth Schedule include APIIC which
appears at Serial No.17. Section 68(2) states that the assets, rights and liabilities of
apportioned between the successor states in the manner provided in Section 53.
42
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
41 Section 6518 allows for the successor states of Telangana and Andhra
Pradesh to agree on the manner in which the benefit or burden of any particular
Government on a reference made, within three years from the appointed date, by
following terms:
18
“65. Where the successor States of Andhra Pradesh and Telangana agree that the benefit or burden of any
particular asset or liability should be apportioned between them in a manner other than that provided for in the
foregoing provisions of this Part, notwithstanding anything contained therein, the benefit or burden of that asset
or liability shall be apportioned in the manner agreed upon.”
19
“66. Where, by virtue of any of the provisions of this Part, either of the successor States of Andhra Pradesh
and Telangana becomes entitled to any property or obtains any benefits or becomes subject to any liability, and
the Central Government is of opinion, on a reference made within a period of three years from the appointed
day by either of the States, that it is just and equitable that such property or those benefits should be
transferred to, or shared with, the other successor State, or that a contribution towards that liability should be
made by the other successor State, the said property or benefits shall be allocated in such manner between the
two States, or the other State shall make to the State subject to the liability such contribution in respect thereof,
as the Central Government may, after consultation with the two State Governments, by order, determine.”
43
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
Section 71(a) speaks of the interests and shares of the existing State of Andhra
Pradesh in the companies specified in the IXth Schedule between the successor
States. APIIC has brought on record the certificate issued by the Managing Directors
of TSIIC and APIIC recording the auditing of assets and liabilities as on 1 June
“CERTIFICATE
44
LL 2021 SC 92
WWW.LIVELAW.IN
PART E
in the course of the pleadings. Para 1 of Section 1 Part II of the Scheme is in the
following terms:
“1. Upon the coming into effect of the Scheme and with effect
from the Appointed Date and subject to this Scheme, all the
operational Units of the Demerged Undertaking (including all
the estate, assets, rights, title, interest and authorities
including accretions and appurtenances of the Demerged
Undertaking namely Cyberabad Zone, Jeedimetla Zone,
Karimnagar Zone, Patancheru Zone, Shamshabad and Moula
Ali Zone, Warangal Zone vest with the Transferee Company
and shall, subject to the provisions of the scheme in relation
to the mode of vesting and pursuant to Section 53 of the Act
and without any further act or deed, or be deemed to have
been apportioned and transferred to and vested in the
Transferee Company as a going concern so as to become as
and from the Appointed Date, the estate, assets, rights, title,
interest and authorities of the Transferee Company as
detailed in the Schedule-I”
Schedule I provides for the Zonal offices pertaining to Telangana region. Serial no.3
refers to the Shamshabad and Mauli Ali region which includes the area covered by
the project site. The land which is comprised in the project site falls exclusively
43 We clarify that following the course of action which has been adopted by the
learned Single Judge, we are not adjudicating finally upon the rights inter se
between TSIIC and APIIC. TSIIC shall refund the amounts due and payable to
Unitech in terms of the present judgment. TSIIC would be at liberty to pursue its
rights and remedies in accordance with law over its claim for apportionment on
46
LL 2021 SC 92
WWW.LIVELAW.IN
PART F
F. Summation
44 TSIIC and the State of Telangana have brought to our notice that the
Development Agreement, on the basis of which Unitech has sought to avail its
contractual remedy has not been registered or assessed to stamp duty. Under
Article 3.1 of the Development Agreement, the obligation of paying registration fees
and stamp duty is on Unitech. It is well-settled law that the Stamp Act is a fiscal
measure enacted to secure the revenue for the State, and not to arm the opponent
defeated on the sole ground of the payment of stamp duty. The Development
Revenue Authority in the State of Telangana for assessment of stamp duty and to
the competent authority for registration. The assessment shall be completed within
thirty days. The appropriate stamp duty and registration charges liable to be paid in
terms of the determination shall be paid by TSIIC and be deducted from the refund
45 For the above reasons, the appeals shall stand disposed of in the following
terms:
TSIIC within two weeks to the competent authority for registration and for
assessment of stamp duty. The assessment to stamp duty and formalities for
47
LL 2021 SC 92
WWW.LIVELAW.IN
PART F
towards stamp duty, penalty (if any) and registration charges shall be paid
initially by TSIIC into the account of the competent authority within two weeks
TSIIC to Unitech;
(ii) The appeal filed by Unitech, arising out of SLP(C) No 9019 of 2019 is
allowed in part by setting aside the direction of the Division Bench of the High
Court which confined the liability to pay interest only with effect from 14
October 2015;
(iv) The amount which has been deposited in the Registry of this Court in
accrued interest. The balance due and payable under the terms of this
judgment shall be refunded by TSIIC to Unitech within two months from the
(v) In terms of the directions of the Single Judge of the High Court, TSIIC will be
48
LL 2021 SC 92
WWW.LIVELAW.IN
PART F
46 The appeals arising out of the Special Leave Petitions filed by the State of
Telangana and TSIIC shall also stand disposed of in terms of the present judgment.
…….………….…………………...........................J.
[Dr Dhananjaya Y Chandrachud]
…….…………………………...............................J.
[MR Shah]
New Delhi;
February 17, 2021.
49