Plumbness Check Report

This 5-page dimensional check report measures the plumbness of five recycle water tank shells at a synthetic rubber plant in Indonesia. It documents the elevations, markings, and deviations from plumbness at various points on each tank, noting whether measurements are within specified tolerances. Signatures from representatives of three companies witness and review the inspection results.

Uploaded by

Yusuf Khoir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
217 views50 pages

Plumbness Check Report

This 5-page dimensional check report measures the plumbness of five recycle water tank shells at a synthetic rubber plant in Indonesia. It documents the elevations, markings, and deviations from plumbness at various points on each tank, noting whether measurements are within specified tolerances. Signatures from representatives of three companies witness and review the inspection results.

Uploaded by

Yusuf Khoir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 50

DIMENSIONAL CHECK REPORT Page 1 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11304
Tag No. : T1375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
900 B
2700 B
1500 7.5
0
45 C
2250 C
1350 D
3150 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA

name name name


date date : date

DIMENSIONAL CHECK REPORT Page 2 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11304
Tag No. : T1375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #2 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
900 B
0
270 B
3000 15
0
45 C
2250 C
1350 D
315 0 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 3 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11304
Tag No. : T1375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #3 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
0
90 B
0
270 B
4500 22.5
450 C
2250 C
135 0 D
315 0 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 4 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11304
Tag No. : T1375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #4 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
0
90 B
2700 B
6000 30
450 C
2250 C
135 0 D
3150 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 5 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11304
Tag No. : T1375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #5 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
900 B
2700 B
7340 36.7
45 0 C
2250 C
1350 D
0
315 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date
1500
0.005
7.5

8
8
8
3000
0.005
15

8
8
8
4500
0.005
22.5

8
8
8
6000
0.005
30

8
8
8
7340
0.005
36.7

8
8
8
DIMENSIONAL CHECK REPORT Page 1 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11306
Tag No. : T2375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
900 B
2700 B
1500 7.5
0
45 C
2250 C
1350 D
3150 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA

name name name


date date : date

DIMENSIONAL CHECK REPORT Page 2 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11306
Tag No. : T2375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #2 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
900 B
0
270 B
3000 15
0
45 C
2250 C
1350 D
315 0 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 3 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11306
Tag No. : T2375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #3 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
0
90 B
0
270 B
4500 22.5
450 C
2250 C
135 0 D
315 0 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 4 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11306
Tag No. : T2375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #4 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
0
90 B
2700 B
6000 30
450 C
2250 C
135 0 D
3150 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 5 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11306
Tag No. : T2375.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #5 (Recyle Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
900 B
2700 B
7340 36.7
45 0 C
2250 C
1350 D
0
315 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date
1500
0.005
7.5

8
8
8
3000
0.005
15

8
8
8
4500
0.005
22.5

8
8
8
6000
0.005
30

8
8
8
7340
0.005
36.7

8
8
8
DIMENSIONAL CHECK REPORT Page 1 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11295
Tag No. : T6491.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
900 B
2700 B
2438 12
0
45 C
2250 C
1350 D
3150 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA

name name name


date date : date

DIMENSIONAL CHECK REPORT Page 2 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11295
Tag No. : T6491.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #2 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
900 B
0
270 B
4876 24
0
45 C
2250 C
1350 D
315 0 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 3 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11295
Tag No. : T6491.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #3 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
0
90 B
0
270 B
7314 30
450 C
2250 C
135 0 D
315 0 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 4 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11295
Tag No. : T6491.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #4 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
0
90 B
2700 B
8532 41
450 C
2250 C
135 0 D
3150 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 5 of 5

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11295
Tag No. : T6491.01 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #5 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
900 B
2700 B
10970 55
45 0 C
2250 C
1350 D
0
315 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date
2438
0.005
12.19

8
8
8
4876
0.005
24.38

8
8
8
7314
0.005
36.57

8
8
8
8276
0.005
41.38

8
8
8
9800
0.005
49

8
8
8
DIMENSIONAL CHECK REPORT Page 1 of 6

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11296
Tag No. : T6491.02 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
900 B
2700 B
1828 9
0
45 C
2250 C
1350 D
3150 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA

name name name


date date : date

DIMENSIONAL CHECK REPORT Page 2 of 6

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11296
Tag No. : T6491.02 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #2 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
900 B
0
270 B
3628 18
0
45 C
2250 C
1350 D
315 0 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 3 of 6

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11296
Tag No. : T6491.02 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #3 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
0
90 B
0
270 B
6094 30
450 C
2250 C
135 0 D
315 0 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 4 of 6

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11296
Tag No. : T6491.02 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #4 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
0
90 B
2700 B
8532 43
450 C
2250 C
135 0 D
3150 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 5 of 6

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11296
Tag No. : T6491.02 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #5 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
0
180 A
900 B
2700 B
10970 55
45 0 C
2250 C
1350 D
0
315 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date

DIMENSIONAL CHECK REPORT Page 6 of 6

Client / User : PT. IKPT / PT. Synthetics Rubber Indonesia Report No. : U3-IR-ME-P1-00….
Project : Synthetics Rubber Indonesia - U3 Project GK Job No. : 11296
Tag No. : T6491.02 Work Site : PT. Synthetics Rubber Indonesia
Item Inspection : Plumbness Date of Inspection :
Part name : Shell #1 ~ #6 (Utility Water Tank) Acceptance criteria : API 620; 2013 Edition

SKETCH

MARKING ELEVATION PLUMBNESS (mm)


RESULT
DEG. POS. (mm) A B DEV. TOL.
00 A
1800 A
900 B
270 0 B
12800 64
45 0 C
2250 C
0
135 D
0
315 D

Prepared, Witnessed / Reviewed, Witnessed / Reviewed,


PT. GRAND KARTECH PT. IKPT-TOYO GLOBAL CONSORTIUM PT. SYNTHETICS RUBBER INDONESIA
name name name
date date : date
1828
0.005
9.14

8
8
8
3656
0.005
18.28

8
8
8
6094
0.005
30.47

8
8
8
8532
0.005
42.66

8
8
8
10970
0.005
54.85

8
8
8

12800
0.005
64

8
8
8