Quotation AC MR Hamad
Quotation AC MR Hamad
Scope of work
Supply and installation of indoor and outdoor units
Supply and installation of PI ducting
Supply and installation of drain pipe to the nearest drain point
Supply and installation of mechanical ventilations
Pressure testing and commissioning of all the machines
Air conditioning distribution map
Serial Place Type of unit Quality Size
Ground floor
1 Family Sitting + Hall + Pantry Ducted Split 2 5+5
2 Guest Bedroom Ducted Split 1 3
3 Maid Room Split Unit 1 1.5
4 Kitchen Split Unit 1 3
5 Maid Room Split Unit 1 1.5
1st floor
6 Main Bedroom Ducted Split 2 3+3
7 1st bedroom Ducted Split 1 3
nd
8 2 bedroom Ducted Split 1 3
9 3rd bedroom Ducted Split 1 3
10 Stair & Hall Ducted Split 1 4.5
Total 12 38.5 Tons
Serial Material Description Make
1 Indoor units - Ducted Split THAILAND
2 Outdoor Units - Ducted Split THAILAND
3 Decorative Splits THAILAND
4 Pre Insulated Sheet PAL
5 Acoustic lining (initial 3.0 meters of ducting ½’ thk *32 kg/m3 KIMKO
6 Copper Pipes & Fittings MAKSAL –South Africa
7 Coating / Adhesive Sealant THERMOSEAL -UAE
8 Elastomeric rubber insulation closed cell GULF “O” FLEX
9 2.5mm 4 Core Wire Control DUCAB
10 Thermostat Wire 1 MM 1 Core O.GENERAL
11 ISOLATER WIRE 6 MM 1 CORE DUCAB
12 Canvas Cloth For Ducting INDIAN
13 Grilles & Diffusers ( All Are Powder Coated ) Long Linear Grills AIRTECHNICS
14 Mechanical Ventilation ( S& P /VENT ) EUROPE
15 Vibration isolator - WEICCO
Exclusion
Any subject which is not quoted
Any civil works and carpentry works
Any electrical works and plumbing works
Temporary power supply
Any platform or outdoor Brackets
Any BMS or home automation work
Guarantee Clause:
One Year Service after installation free of charge
Five Years Warranty for the air conditioners
One Year Warranty for the installation
Quotation Price:
One hundred and five thousand Dirhams Only AED 105,000
Payment
1st payment: 60 % advance payment upon sign the contract.
2nd payment: 15 % when finish the installing the air conditioner
units.
3rd payment: 15 % when finish the installation duct.
4th payment: 10% after testing & commissioning of units.