Existing Assets Adequacy Report
Existing Assets Adequacy Report
CONTENT
1 INTRODUCTION ..................................................................................................... 5
1.1 Purpose ............................................................................................................................................................... 5
1 INTRODUCTION
( ), in partnership with the Company of , is
currently planning to develop its upstream production facilities and infrastructure to meet a target
of 1.2MMBOPD of production in the 2 oil field in Southern . The field consists
of two primary reservoirs, and , which will be developed as separate projects. It
is envisaged that the reservoir will produce up to 650MBOPD of the 1.2MMBOPD
targeted from the entire field. Presently the development is in the FEED (Define) phase
of project execution and design.
WorleyParsons has been contracted to execute the FEED phase of the Development
Project. The development includes well pads, gathering systems, water injection facilities, gas
and water treatment, a gas turbine power plant, a light oil export pipeline and tank farm
upgrades, tie-ins to the natural gas liquids and gas export systems and further expansion of
supporting facilities and infrastructure as necessary.
The Project aims to produce a comprehensive FEED Package in order to allow the progression of
the Project to the EPC (Execute) Phase.
1.1 Purpose
The purpose of this document is to determine the adequacy of the existing systems and
infrastructure at PS-1 Tank Farm for the purposes of partially utilizing them for the proposed
expansion of the Tank Farm for the Field Development Project , .
1.2 Scope
This document covers the existing PS-1 Tank Farm, approximately 90 km south of the
field, and its proposed expansion as part of the Project. The sources of information cited
in this Report include:
Minutes of Meeting between SOC and (refer Appendix 1)
and WorleyParsons Site Visit (refer 8015-0152-WP05-00-000-AL-RP-12001 Site
Visit Report – PS-1 and 2).
2 REFERENCE DOCUMENTS
8015-0152-WP05-00-000-AL-RP-12001 Site Visit Report – PS-1 and 2
CY-14-8015-0104-WP05-0057 FEED Services - PS-1 Crude Oil
Operating and Storage Temperature
8015-0152-WP05-41-411-PC-BD-08001 Basis of Design – PS-1 Tank Farm Expansion
8015-0152-WP05-41-000-EL-ES-08001 Electrical Load List (PS-1 Tank Farm)
8015-0152-WP05-41-411-HS-RP-08010 Fire Water Demand Calculation and Network
Hydraulics Report PS-1 Tank Farm Expansion
Total pressure drop from Tie-In point to Export = Suction line losses +
Pump suction flange Strainer pressure drop
= 0.34 barg.
This NPSHa of 49 meters is arrived at by considering the worst operating conditions in the
system i.e. Low-Low Liquid Level in the crude oil storage tank and crude oil pumping
temperature of 56 °C.
Thus NPSHa in the system is greater than NPSHr of the Main Export Pumps by 3 meters. Hence
the proposed crude oil booster pumps for the new tanks are adequate.
5 SAFETY EQUIPMENT
6.5 Buildings
6.5.1 Fire Fighting Depot
The existing central Fire-Fighting Depot, with capacity for four firefighting trucks is available at
PS-1 for the expansion Project. WorleyParsons understand that the existing central firefighting
depot is sufficient to cover the firefighting requirements for the tank farm expansion including
full surface tank fire and bund/dike fire, given the above existence of the systems. As such, no
8015-0152-WP05-41-411-PC-RP-08002_00 - Existing Assets Adequacy Report
Uncontrolled copy, if printed.
WORLEYPARSONS
new fire-fighting depot is required for the expansion project. This was confirmed by
/SOC via the response to Technical Query 8015-0152-WP05- L-00-CI-TQ-00023,
st
dated 21 September 2014.
7 ELECTRICAL EQUIPMENT
There are 2 x 100 % redundant incomers feeding the new proposed PS-1 switchboard, and hence
the feeders are adequate.
Notes:
1. As per Customer Supplied Data received via Transmittal No. 8015-0152- L-WP05-TE-00014.
3. The existing cable from Cubicle No. 7 of PS-1 Switchboard (existing) to 1250 kVA transformer (existing)
shall be removed. The 630 A feeder (Cubicle No. 7) will feed the PS-1 switchboard (new) in addition to the
spare feeder (Cubicle No. 22). The existing 1250 kVA transformer will be fed by outgoing transformer
feeder from PS-1 Switchboard (new).