Design To Capacity Vip Workshop Report
Design To Capacity Vip Workshop Report
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 2 of 26
Contractor No.: N/A
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 3 of 26
Contractor No.: N/A
CONTENT
1 SUMMARY ............................................................................................................ 5
2 INTRODUCTION ................................................................................................... 6
3.3 Compositions................................................................................................................................................... 8
3.5 Turndown........................................................................................................................................................ 8
4 PRODUCT SPECIFICATIONS ............................................................................ 10
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 4 of 26
Contractor No.: N/A
6.7 Desalter.......................................................................................................................................................... 14
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 5 of 26
Contractor No.: N/A
1 SUMMARY
The Design to Capacity Value Improving Practice workshop was held on Monday 23rd June
2014. The Design to Capacity workshop is intended to identify where design margins are
required to meet project objectives and provide assurance in meeting those objectives. It is also
intended to avoid duplication of margins appearing at the design at different stages of the design
development. By explicitly identifying the required design margins, the final development
concept can be optimized.
Design margin can appear from many sources. These sources include the Basis of Design,
equipment sizing practices and industry standards. The key sources of design margin were
systematically reviewed by the workshop and the findings from the discussions are documented
in this report.
The agreed design margins need to be incorporated into the key design documents such as the
Basis of Design and the Process Design Criteria.
There are a number of areas that require further review before the design margins can be agreed:
• The acid gas treating facilities will be affected by the technology selection – the design
margins should be reviewed once the technology has been selected and a proper
assessment can be performed
• Utility systems will be reviewed once the design load cases have been defined (again,
these will be affected by the acid gas treating technology selection). These are likely to
be subject to specific review, rather than having a blanket design margin applied.
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 6 of 26
Contractor No.: N/A
2 INTRODUCTION
2.2 Methodology
The review worked through the following elements of the design in sequence to identify and
clarify the design margins that are being introduced to the project:
• Basis of Design
o Feed conditions
o Key facility parameters
• Product Specifications
• Process Design Criteria
o Design margins by equipment type
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 7 of 26
Contractor No.: N/A
• Review of design margins by system, as defined in the Block Flow Diagram (Appendix
4)
o Inlet and gathering
o Oil processing
o Produced water handling
o Gas processing
o LPG fractionation
o Acid gas treatment
o Utility systems
The presentation used for the VIP workshop is provided in Appendix 3.
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 8 of 26
Contractor No.: N/A
3 BASIS OF DESIGN
3.3 Compositions
A range of crude oil compositions have been noted over different horizons in the field.
Further clarity of expected crude oil compositions is not likely until the pilot production program
is underway.
The gas processing facilities design will be progressed based on the average gas properties
reported in the Basis of Design, adjusted for the higher GOR.
Specific analysis of variations in crude composition will be required for specific units and these
requirements are identified in Section 2.
3.4 Availability
The definition of availability was clarified in the meeting, in line with the definition in Section
3.1 above. The availability target of 0.95 requires a design margin of 5% on flowrate to account
for correction from stream day flowrates to calendar day flowrates.
3.5 Turndown
The turndown requirement of 40% was further defined in the meeting. The turndown applies to
each train of equipment – each train must be able to be turned down to 40% of its design
flowrate.
With the gas processing system, with the extra allowance of 15% for GOR uncertainty this
represents a turndown to 35% of design flowrate.
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 9 of 26
Contractor No.: N/A
The crude oil train is designed for 100% recycle and has complete turndown. Further work is
required to clarify how the 40% turndown will be achieved with the gas processing facilities.
[Action 1]
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 10 of 26
Contractor No.: N/A
4 PRODUCT SPECIFICATIONS
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 11 of 26
Contractor No.: N/A
5.4 Pumps
The pump design margins were generally accepted.
NPSH was specifically discussed. Process was instructed to advise the NPSH required, without
margin. Mechanical group will add margins to NPSH that are consistent with the type of pump
selected.
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 12 of 26
Contractor No.: N/A
5.6 Piping
The piping sizing guidelines for liquid, gas and multiphase flow were reviewed. The multiphase
line sizing should include a guide on allowable flows such as 𝜌. 𝑣 2 . [Action 6]
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 13 of 26
Contractor No.: N/A
6.3 Wellpads
Wellpads will be fitted with a combination of 6, 8 and 10 slot well manifolds. No further review
of design margins is required.
6.4 Trunklines
Trunkline sizing and configuration is subject to specific review and optimization by the FEED
design. No further review of design margins is required in this workshop.
6.5 Slugcatcher
The slugcatcher (either finger type or vessel type) will require careful review of the slug/surge
volumes. The required design margin will be reviewed and agreed after comprehensive
sensitivity analysis.
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 14 of 26
Contractor No.: N/A
A 5% availability margin and a 10% process design margin will be added to each oil treatment
trains. This gives an overall margin of 15% for the overall plant combined. Design margins are
not additive across parallel trains – 6 trains with 15% margin does not give 90% margin for the
plant.
6.7 Desalter
The desalter has a conservative design specification of the water-in-oil content of the incoming
crude oil. This will provide sufficient design margin in the design of the Desalter.
6.16 Utilities
Utilities will be like the propane refrigeration system and require review once the load cases
have been determined. In many cases these loads will be dependent on the acid gas treatment
technologies selected for the CPF.
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 16 of 26
Contractor No.: N/A
7 WORKSHOPS FINDING
The findings of the Design to Capacity Workshop have been summarized into a design margin
table that applies at the system level, see Appendix 5.
The Design to Capacity analysis worksheets are provided in Appendix 6
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 17 of 26
Contractor No.: N/A
8 ACTION PLAN
There are a number of specific actions to resolve design margins identified in the report.
The design margins need to be incorporated into the Basis of Design and the Process Design
Criteria.
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 18 of 26
Contractor No.: N/A
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
8015-0152-WP05-00-000-PC-RP-12001_00.docx
This document is property of the COMPANY and it shall not be disclosed to third parties, or reproduced, without permission of the
COMPANY.This document is tracked by ( ). When it is printed, it shall be considered as “For
information only”.The controlled copy is the version, and thus, it is the document holder’s responsibility to make sure that the latest
version is in use.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 20 of 26
Contractor No.: N/A
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
-2 ( )
VIP PROCEDURE
DESIGN TO CAPACITY
ISSUED FOR
00 17-06-2014 IFI M. Mirsaidov A. Ali R. Osorio
INFORMATION
This document is property of the COMPANY and it shall not be disclosed to third parties, or reproduced, without permission of the COMPANY.
This document is tracked by ( ). When it is printed, it shall be considered as “For information
only”.
The controlled copy is the version, and thus, it is the document holder’s responsibility to make sure that the latest version is in use.
-2 ( )
Project DEFINE Phase Design to Capacity VIP Procedure Rev.: 00 Status: IFI
COMPANY No.: 8015-0152- L-00-000-PM-PP-00004 Page: Page 2 of 9
DATE
REV STATUS UPDATE / AMENDMENT DETAILS
ISSUED
CONTENTS
1 INTRODUCTION ........................................................................................................................4
1.1 Purpose of this Document ........................................................................................................4
1.2 Abbreviations ...........................................................................................................................4
1.3 Reference Documents ..............................................................................................................4
2 DESIGN TO CAPACITY VIP .....................................................................................................5
2.1 Definition .................................................................................................................................5
2.2 Applicability and Scope ...........................................................................................................5
3 DTC VIP IMPLEMENTATION ..................................................................................................5
3.1 Workshop .................................................................................................................................5
3.2 Representation and Facilitation................................................................................................6
3.3 Methodology ............................................................................................................................6
3.4 Recording Findings and Action Plan/Tracker..........................................................................7
4 DESIGN TO CAPACITY VIP CLOSE OUT ..............................................................................7
ANNEX 1 .............................................................................................................................................8
1 INTRODUCTION
1.2 Abbreviations
BEDD Basic Engineering Design Data
BOD Basis of Design
CAPEX Capital expenditure
DTC Design to Capacity
FEED Front-end Engineering and Design
GTP Gas Treatment Plant
GTPP Gas Turbine Power Plant
HMB Heat and Material Balance
IPA Independent Project Analysis
Mid-East
PAP Project Assurance Plan
PEP Project Execution Plan
PIC Person in Charge
PFD Process Flow Diagram
UFD Utility Flow Diagram
VIP Value Improvement Practice
Worley Parsons
2.1 Definition
Design to Capacity VIP, as defined by , is a structured process that evaluates the true required
maximum capacity of each system and major piece of equipment relative to the desired overall
facility capacity.
According to IPA, DTC provides a method of achieving early alignment between a project’s
business, technical, and manufacturing representatives on the most appropriate level of plant
flexibility and overcapacity. This helps to save project capital by helping designers fully understand
the operability of every process step and equipment item.
The rationale behind carrying out the Design to Capacity VIP is that often systems are designed
with a degree of conservatism, or safety factor, in order to ensure that the plant will operate at its
nameplate capacity, and that probability of encountering operational problems in the future is
reduced. However, in reality too much over capacity can by itself lead to operational problems. On
the other side, if during engineering the design margin is set at very minimal level, and future
expansion is the case for that particular facility, this approach might create problems with future
debottlenecking for expansion purposes. Both of these cases are associated with operability
problems and with additional investments, which could have been avoided otherwise.
3.1 Workshop
DTC VIP will be conducted as a formal workshop and is scheduled for June 23, 2014. The
workshop will be held in FEED dedicated office of in , . Should
additional time be required, the workshop might be extended into the following day.
3.3 Methodology
Main inputs for DTC workshop are:
• PFDs • BODs
• UFDs • BEDD
• Sparing Philosophy • Process Design Criteria
• Control Philosophy
At the beginning of the DTC, workshop agenda and objectives should be clearly stated and agreed
by all participants.
DTC workshop considerations at Project, system and equipment levels should be guided by the
sequence below.
Stage 1:
1. List all significant equipment items i.e. mechanical, electrical, control system, structures
2. List all margins on product specifications
3. List feed composition to the facility
4. List potential feed composition to facility
Stage 2:
5. List design margins used or proposed, moving from Project Design Basis to final Plant /
Equipment specification
6. List design margins for each train
7. List design conditions as specified in the Project Design Basis (temperature and pressure)
8. Identify capacity commesurate with upstream and downstream processes
9. Identify capacity commesurate with other -2 facilities
Stage 3:
10. List reference design margins considered to be appropriate i.e. those as specified by
Customer Standards and / or Standard Industry practice.
11. Evaluate the effects of coincident design cases and choose appropriate load scenarios
12. Evaluate influence of operations on the design margin used (assuming deterioration of
equipment before maintenance/cleaning, particularly for heat exchangers, filters, turbines
etc.)
13. Consider risk mitigation as a result of margin vs. investment CAPEX
14. Shortlist those equipment items for which the design margins used or proposed appear to be
excessive. List action items in terms of follow up, e.g. potential re-sizing / re-costing,
updating Project design documentation, etc.
A brief outline of the DTC VIP will also be included in the VIPs Report to be issued as part of
FEED deliverables by .
ANNEX 1
Project Title:
Phase:
Date:
Venue:
Meeting Objective:
1
2
3
4
5
Desired Outcomes:
1
2
3
4
5
Project Title:
Project Title:
4. Action Plan
Design to Capacity Workshop - Action Plan
Project Title:
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 22 of 26
Contractor No.: N/A
Workshop Attendance
Attendee Company Position/Role
Gd Suryanam PMS
Akbar Ali Process
Farid Zaynullov NNP Lead Spec
Maxim Demin NNP
Hristo Georgieu BNP
Sunil Nair Lead Project Engineer
Manikandan N Process
Kumaraguru Process
Vyacheslav Petrov Engineering Systems
Manager
Karashash Salakhova Senior Oil Treat Engineer
Ruslan Lekerov Central Engineering
Philip Jones HSE Engineer
Romulo Osoris Delivery Manager
Colin Foster Engineering Manager
Maxim Margert DPD
Kallibek Jarimbetov PA
Marod Mirsaidov Project Assurance
Natalia Gorbatyuk
Tom Cuthbert WorleyParsons Project Manager
Nathan Smith WorleyParsons Process
Nagendra Singh WorleyParsons Mechanical/Lead Static
Basuden Gupta WorleyParsons Mechanical/Static &
Packages
Santosh Vaidya WorleyParsons Mechanical/Rotating
Steve Henzell WorleyParsons Facilitator
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 23 of 26
Contractor No.: N/A
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
Value Improving Practice
Design to Capacity Workshop
23 June 2014
Agenda
No Activity PIC
Greeting:
1 PMT
- Introduction
2 Project Overview, include CFQ PMT
3 OneWay moment Facilitator
Set meeting objective and expectation
4 - R&R, Facilitator
- Ground Meeting, etc.
5 DTC Process Overview Facilitator
6 Review updated PFDs PMT
7 DTC - Equipment of System 1 All
8 DTC - Equipment of System 2 All
9 DTC - Equipment of System 3 All
10 DTC - Equipment of System 4 All
11 DTC - Equipment of System 5 All
Wrap-Up:
- Review outstanding issues
12 - Assign task Facilitator
- Next steps
- Plus/Delta
13 Adjourn Facilitator
Integrity Management Framework
Elements
3
Amine Stripper Reboilers
AX903 Bundle Replacement
Replacement Bundle
u Basis of Design
u Basic Engineering Design Data
u Process Design Criteria
§ Corporate design guides
§ Industry standards
u Sparing Philosophy/Availability
u Control Philosophy
u Equipment specifications
u Contracting basis
Methodology
Stage 1:
u List all margins on product specifications
u List feed composition to the facility
u List potential feed composition to facility
u List all significant equipment items i.e. mechanical, electrical,
control system, structures
Stage 2:
u List design margins used or proposed, moving from Project
Design Basis to final Plant / Equipment specification
u List design margins for each train
u List design conditions as specified in the Project Design Basis
(temperature and pressure)
u Identify capacity commensurate with upstream and
downstream processes
u Identify capacity commensurate with other -2
facilities
Methodology
Stage 3:
u List reference design margins considered to be
appropriate i.e. those as specified by Customer
Standards and / or Standard Industry practice.
u Evaluate the effects of coincident design cases and
choose appropriate load scenarios
u Evaluate influence of operations on the design margin
used (assuming deterioration of equipment before
maintenance/cleaning, particularly for heat exchangers,
filters, turbines etc.)
u Consider risk mitigation as a result of margin vs.
investment CAPEX
u Shortlist those equipment items for which the design
margins used or proposed appear to be excessive.
u List action items in terms of follow up, e.g. potential re-
sizing / re-costing, updating Project design
documentation, etc
Basis of Design
BoD Sources of Design Margin
u Feed streams
§ Flowrates of primary and associated streams
§ Composition
§ Impurities
§ Physical properties
u Product streams
§ Product qualities (RVP, dew points, etc)
§ Physical properties
u Facility performance
§ Availability
u Future provisions (if any)
Performance Requirements
- -
13,14 23,148 203 0,178 Average
S.No Component (low H2S) (High H2S) Mole %
Mole % Mole %
psia 116
Reid Vapor Pressure [RVP] - Summer
(kPa abs.) (800)
psia 145
Reid Vapor Pressure [RVP] – Winter
(kPa abs) (1000)
Condenser & Reboiler 20% on margin (including flow, area, duty, and in addition
to fouling factors)
Service m2 °C / kW Service m2 °C / kW
Raw Gas 0.20 Hot Crude Oil 0.70
Sales Gas 0.15 Desalted Oil 0.53
Fuel Gas 0.20 Stabilized Oil 0.53
LPG 0.20 Chilled Water 0.17
Propane 0.15 Potable Water 0.17
Lean / Rich Amine 0.40 Boiler Feed 0.17
Glycol 0.35 Superheated Steam 0.09
Process Water 0.35 Formation Water 0.53
Stripped Water 0.35 Cooling Water 0.35
General Recommendation
<3.5 0.01-0.03
3.5-10 0.04-0.07
10-40 0.07-0.11
40-150 0.11-0.27
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
FORMATION DEVELOPMENT FEED
WORLEYPARSONS
2 PROJECT,
Doc. title DESIGN TO CAPACITY VIP WORKSHOP REPORT Rev.: 00 Status: AFU
COMPANY No.: 8015-0152-WP05-00-000-PC-RP-12001
Page: 25 of 26
Contractor No.: N/A
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
Margin
System Downtime Process GOR Flow Distribution Other Specification Comment
Allowance Margin Uncertainty Allowance Allowance Allowance
Inlet Manifold & Slug Catcher 5% 10% 0% 0% 0% Specific review of surge volume allowance required
Produced Water Handling 5% 10% 0% 0% 0% Water handling capacity will be installed in stages as demand increases -
design margin approach not strictly appropriate
8015-0152-WP05-00-000-PC-RP-12001_00.docx
Uncontrolled copy, if printed.
Design to Capacity Workshop
Project Title: -2 ( )
Phase: Project Define Phase
Date: 23-Jun-14
Venue: Project Meeting Room
Meeting Objective:
1 Ensure that design margins are aligned with Project Drivers and facility development plans.
Achieve early alignment between the project’s business, technical, and manufacturing representatives
2 on the most appropriate level of plant flexibility and overcapacity
Save project capital by helping designers fully understand the operability of every process step and
3 equipment item.
4
5
Desired Outcomes:
3
4
5
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа, возможно, неактуальна. Последняя версия размещена на портале ИСУП.
© 2014. . All rights reserved.
Design to Capacity Workshop - List of Participants
Project Title: -2 ( )
Phase: Project Define Phase
No Name Role
1 Gd Suryanam PMS
2 Akbar Ali Process
3 Farid Zaynullov NNP Lead Spec
4 Maxim Demin NNP
5 Hristo Georgieu BNP
6 Sunil Nair Lead Project Engineer
7 Manikandan N Process
8 Kumaraguru Process
9 Vyacheslav Petrov Engineering Systems Manager
10 Karashash Salakhova Senior Oil Treat Engineer
13 Romulo Osoris Delivery Manager
14 Colin Foster Engineering Manager
15 Maxim Margert DPD
16 Kallibek Jarimbetov PA
17 Marod Mirsaidov Project Assurance
18 Natalia Gorbatyuk
19 Tom Cuthbert WorleyParsons Project Manager
20 Nathan Smith WorleyParsons Process
21 Nagendra Singh WorleyParsons Mechanical/Lead Static
22 Basuden Gupta WorleyParsons Mechanical/Static & Packages
23 Santosh Vaidya WorleyParsons Mechanical/Rotating
24 Steve Henzell WorleyParsons Facilitator
25
26
27
28
29
30
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа возможно неактуальна Последняя версия размещена на портале ИСУП
Design to Capacity Workshop
Project Title: -2 ( )
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа возможно неактуальна Последняя версия размещена на портале ИСУП
Design to Capacity Workshop
Project Title: -2 ( )
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа возможно неактуальна Последняя версия размещена на портале ИСУП
Design to Capacity Workshop
Project Title: -2 ( )
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Design to Capacity Workshop
Project Title: -2 ( )
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа возможно неактуальна Последняя версия размещена на портале ИСУП
Design to Capacity Workshop
Project Title: -2 ( )
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа возможно неактуальна Последняя версия размещена на портале ИСУП
Design to Capacity Workshop
Project Title: -2 ( )
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа возможно неактуальна Последняя версия размещена на портале ИСУП
Design to Capacity Workshop
Project Title: -2 ( )
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа возможно неактуальна Последняя версия размещена на портале ИСУП
Design to Capacity Workshop - Action Plan
Project Title: -2 ( )
Uncontrolled when printed or saved. Please refer to Portal for the latest version.
Распечатанная или сохраненная версия документа, возможно, неактуальна. Последняя версия размещена на портале ИСУП.
© 2014. . All rights reserved.