BRIDGE TO INDIA - India Solar Compas - July 2013
BRIDGE TO INDIA - India Solar Compas - July 2013
BRIDGE TO INDIA - India Solar Compas - July 2013
SOLAR
COMPASS
July 2013 Edition
Market Dashboard
A snapshot of the
market’s fundamentals
Latest Market Insights
An analysis of the policies,
projects, industry and finance
Key Question
Are tracking systems
viable in India?
Outlook
Projection for the
Indian solar PV market
2. Market Dashboard 02
2.1 Market Compass 02
2.2 Indian Solar Market Prices 02
2.3 Installed Capacity in India 03
3. Key Findings
4. Policies 06
4.1 National Solar Mission 06
4.2 Tamil Nadu Solar Policy 08
4.3 Andhra Pradesh Solar Policy 09
5. Projects 10
5.1 New installations (grid connected) 10
5.2 Status of on-going projects (PV) 12
5.3 Status of on-going projects (CSP) 14
6. Financing 16
7. Upstream Industry 17
9. Outlook 28
9.1 Coming quarter 28
9.2 Long-term outlook 29
10. Annexure 32
LIST OF TABLES
Table 4-1: Proposed schedule for allocations under batch one of 06
phase two of the NSM
Table 8-7: Variation of generation and EIRR with fixed tilt and 26
trackers
Table 9-1: Long term outlook of various policy based allocations 30
in India
E NA
R S
U
CE
T
MA
NT
GI
IN E R
G EM
----------------------
1
Draft policy document: Phase two of the National Solar Mission (NSM)
2
Refer to the October 2012 edition of the India Solar Compass
3
Refer to the January 2013 edition of the India Solar Compass
ANDHRA
RAJASTHAN MAHARASHTRA PRADESH
Figure 5-2: Grid connected solar projects installed in the previous quarters, that were not
covered in previous editions of the India Solar Compass
MADHYA ANDAMAN
ANDAMAN
PRADESH GUJARAT & NICOBAR
& NICOBAR
Size - 2 MW Size - 5 MW
Technology - PV Technology - PV
Off-take -APPC/Open
REC Mechanism
access + RECs Off-take - State policy Island Electrification
Developer - Deepak Spinners Developer - Avatar Solar
Technology - PV
Bearing
© BRIDGE TO INDIA, 2013
Off-take - RPSSGP
Developer - Noel Media and
Size - 1 MW
UTTAR Advertising Pvt. Ltd.
Technology - PV
PRADESH
Off-take - APPC/Open
REC Mechanism
access + RECs Size - 1 MW
Developer - Star Delta Trans- Size - 5 MW Technology - PV
formers Technology - PV Off-take - REC Mechanism
Off-take - State RPO Developer - SWELECT Energy
Developer - NTPC Systems Limited
Size - 1 MW
Technology - PV
Off-take - APPC/Open access + RECs
REC Mechanism
Developer - Vinay Corporartion
In the last quarter (April to June has come up in Andhra Pradesh. The
2013), 159 MW of solar PV capacity remaining capacity of 14 MW has been
has been added in India through added in Jharkhand through a single
just three new projects. The largest project. This project has been funded
capacity addition of 125 MW was by a central grant given to the state
achieved in Maharashtra through a specifically for this project that will
single project by Mahagenco. A 20 MW provide power to Jharkhand’s rural and
project for third-party sale of power Naxal5 -affected areas.
----------------------
5
Naxal, Naxalite and Naksalvadi are generic terms used to refer to various militant communist
groups operating in different parts of India under different organizational envelopes. They are
mostly concentrated in the eastern states of the mainland India (Chhattisgarh, Jharkhand, West
Bengal and Odisha).
experiencing excess commissioned as of 20th June 2013. All these projects are to come up
rainfall, projects that in the Bhadla solar park, Jodhpur,
In May 2013, Welspun had announced demarcated by Rajasthan Solarpark
have not begun the that it will be able to commission Development Company Limited,
construction work the entire 130 MW capacity (a 25 MW (a subsidiary of RRECL). The park
project and a 105 MW project) by
early, might struggle August 2013, which is significantly
will provide a common evacuation
infrastructure for all the projects.
to commission on time. ahead of the June 2014 deadline for
its 105 MW project. It is expected The planned time period for
that Welspun will opt for a part commissioning of these projects is 12
commissioning of its 25 MW capacity to months from the date of signing of the
avoid delays for this project. PPAs. This means that these projects
would have to achieve financial
Karnataka closure by the end of 2013 to then be
commissioned by May 2014.
Karnataka had allocated 60MW of solar
PV capacity in April 2012. The projects
were allocated to Essel Infrastructure Tamil Nadu
(10 MW), GKC Projects (10 MW), Helena In Tamil Nadu, 52 project developers
Power (10 MW), Jindal Aluminium(10 have been issued an LoI for setting up
MW),SaiSudhir Energy (10 MW), United a cumulative capacity of 690 MW under
Telecom (3 MW) and Welspun (7 MW). the state solar policy. As mentioned
Projects are to be commissioned no in the policies section, 25 developers
later than October 2013. Given that the chose to increase their allocation
deadline is right after the monsoons capacity from the earlier capacity that
and Karnataka is experiencing excess they had bid for (read the policy section
Exchange
Figure 6-1: A weakening rate
Indian-rupee
USDagainst
vs INRthe US dollar
62
60
58
Value of 1 USD in INR
56
Source: BRIDGE TO INDIA
54
© BRIDGE TO INDIA, 2013
52
50
48 INR/USD
46
44
42
40
Oct-11
Oct-12
Apr-11
Apr-12
Apr-13
Jan-11
Jan-12
Jan-13
Jul-11
Jul-12
Jul-13
Surface’s Zenith
s
Normal
Source: BRIDGE TO INDIA
© BRIDGE TO INDIA, 2013
South
----------------------
8
Azimuth is the compass direction from which sunlight is coming. At noon in northern hemisphere,
the sun is directly south and considered at azimuth angle α= 0 degree
9
The angle from ground in the vertical plane at which modules are tilted
10
Castillo JE, Russo JM, Kostuk RK, Rosenberg GA; Thermal effects of the extended holographic
regions for holographic planar concentrator. J. Photon Energy accessed
11
The Alternative Energy eMagazine
N N
E E
W N
W N W N W N
S S ss E E S E s E
----------------------
14
As per communications with SunPower India representative. BRIDGE TO INDIA has not verified the
actual plant performance data.
15
SunCarrier Omega presentation
16
The figure is based on the claims of SunCarrier representatives and the actual plant data has not
been verified by BRIDGE TO INDIA
17
DEGERenergie brochure accessed here; Mecasolar, accessed here.
100
0
6 7 8 9 10 11 12 13 14 15 16 17
Time of Day (Hours)
Table 8-2: Gain in yield for various axis tracking technologies for
a system size of 1 MW
An effective way to
determine if tracking
is for a typical summer day. The graph
helps us understand the comparative
8.6 FACTORS
systems make generation between various INFLUENCING
financial sense is to
technologies on a given day. The actual AN INVESTMENT
compare Return of a
generation from a similar 1 MW plant
would vary according to the location, DECISION INTO
PV installation with
irradiation data, weather conditions, TRACKING
a tracking system to
modules used, inverters used, etc.
MECHANISMS
At noon, when the sunlight is A developer‘s decision to opt for
without a tracking perpendicular to the ground, all tracking systems in any project
system. systems generate equally. Tracking depends on its financial viability.
systems generate more electricity than An effective way to determine if
fixed tilt systems in the early hours tracking system makes financial
of the morning as well as in the late sense is to evaluate the change in
afternoon. This excess generation on Equity Internal Rate of Return (EIRR)
a daily basis results in higher annual of a PV installation with tracking
generation and an increased CUF of systems as compared to without a
the plant using such trackers. tracking system. If the EIRR increases
appreciably then the additional
investment (CAPEX and OPEX) can
be justified. In the case that the
EIRR change is negligible (<1%) or
----------------------
18
Values from PVSyst report
lifetime of the project. structures used in the project (refer to Performance data of projects with
the financial analysis section below to tracking systems in various projects
understand the CAPEX variation). in India has been collected from
tracking system suppliers and the
Tracking systems incur an additional
performance data available from
O&M cost. Each tracker design
government sources. As there is
is unique leading to different
very little data available for dual axis
maintenance costs. For instance:
tracking systems, the values used in
SunPower’s T0 trackers use one motor
the analysis for dual axis trackers are
to drive up to 400 kW of modules
an approximation based on information
whereas Raytracker believes in a more
provided by experts in the solar
distributed actuation21 using several
industry.
----------------------
19
The drive mechanism could be electrical, mechanical or hydraulic
20
Ideematec GmbH
21
The drive mechanism of the tracker could be actuated electrically, mechanically or hydraulically.
22
Solar Pro, “PV Trackers, Smith; Stephen”, July 2011
23
MNRE,“Net exported power-summary”, Oct 2012-April 2013
24
Average CUF of a solar PV power plant in India using 14%efficiency C-Si modules
CUF (%) 19 22 23 25
Land Area35 (acres )36 4.5 37 5.0 6.0 7.0
CAPEX (` millions)
38
70 77 82 90
Annual O&M (` millions) 0.8 1.2 1.4 1.6
Source: BRIDGE TO INDIA
----------------------
25
Central Electricity Regulatory Commission (CERC), ”Petition No. 242/SM/2012”, October 2012
26
CERC, “Petition No. 243/SM/2012”, October 2012
27
An approximation based on Tamil Nadu’s workable tariff of ` 6.48 @5% escalation and Andhra
Pradesh’s lowest bid of ` 6.58.
28
Based on prices in solar PV industry in India in May 2013
29
IFC, “Utility Scale Solar Power Plants”, February 2012
30
CERC, “Petition No. 243/SM/2012”, October 2012
31
BRIDGE TO INDIA analysis
32
As per the data obtained from industry sources.
33
Average increase in CAPEX calculated from data obtained from industry sources in June 2013
34
Based on the % increase in CAPEX
35
Approximate land area for a 1 MW solar PV power plant using C-Si modules.
36
1 acre = 4,046 m2
36
CERC, ”Petition No. 242/SM/2012”, October 2012
38
Evaluated from assumptions in Table 5.1 and 5.3
15
Case 2: If the cost of
14.8 horizontal single axis
14.6 tracking is 7.5% of the
CAPEX
14.4
14.2 Case 3: If the cost of
horizontal single axis
14 tracking is 6% of the
13.8 CAPEX
Different equity IRRs for different cases
© BRIDGE TO INDIA, 2013
Source: BRIDGE TO INDIA
----------------------
39
BRIDGE TO INDIA financial model
500
A capacity of 1.7 GW
has already been 400
CE – Chief Engineer
FiT – Feed-in-Tariff
PV – Photovoltaic
OUR PROPOSITION
OUR MODEL
CONTACT US
Akhilesh Magal
akhilesh.magal@bridgetoindia.
com
Contact
[email protected]
www.bridgetoindia.com
Follow us on facebook.com/
bridgetoindia
www.bridgetoindia.com/blog