905 025 2 Anchor
905 025 2 Anchor
905 025 2 Anchor
Grouted Anchors
Content
Applications .......................................................................4
Methods .............................................................................8
Project ..............................................................................20
6 Grouted Anchors
Foundation Tie Back Bank Reinforcement
Building loads are generally applied to the construction soil In harbors and piers on waterways, a sufficient water
as compressive forces on foundations. Tension anchors depth is required to enable ships to dock. In these areas,
present an alternative for discharging tensile forces into quay and bank walls are often tied-back with single bar
the construction soil. These tensile forces are created permanent anchors. The required installation of grouted
in structures such as suspension bridges or tent-roof anchors from the water side presents a particular
constructions of buildings, e.g. the Olympic Stadium in challenge in these situations. In these cases, the anchors
Munich. If foundations are tied-back by means of grouted are often created from work pontoons.
anchors to discharge the tensile forces, the grouted
anchors become a permanent part of the structure.
Small Olympic Hall, Munich, Germany Zerben Lock, Elbe-Havel Canal, Germany
For the new Small Olympic Hall building, an excavation In parallel with the existing Zerben lock between
pit with 1,300 m² of tied-back MIP walls, 750 m² of king Magdeburg and Berlin, a new and larger lock basin was
pile walls, and 820 m² of secant pile walls were created. created, designed to accommodate the dimensions
The foundation had to be secured with 29 m long of modern European push barges. Bauer installed
permanent strand anchors as part of the roof foundations over 20,000 m² of partly tied-back sheet pile walls and
of the adjacent indoor swimming pool protruded into the 10,000 m² of excavated, reinforced diaphragm walls, as
excavation pit. During the works, impeccable permanent well as 930 uplift piles.
anchors from Bauer, dating back to 1971, were excaveted.
Grouted Anchors 7
Methods
Different methods can be used
in the manufacture of grouted
anchors, depending on the
requirement. As an option,
grouted anchors can also
be engineered as temporary
or permanent anchors and
as removable or staggered
anchors. As required, grouted
anchors can also be installed
above groundwater or against
pressing groundwater. The Bauer
grouted anchor can also be
used in all types of soil and rock.
INFO
The bearing capacity of grouted anchors is determined by the geological conditions in the area of the grout
bodies. In the case of non-cohesive soils – such as sand or gravel – primary grouting is usually sufficient.
If the grout body is located in cohesive soils, such as silt or clay, the anchor is additionally post-grouted,
which increases its load-bearing capacity by up to 30%.
10 Grouted Anchors
Embankment remediation, Vilseck, Germany
Around 42,000 m² of Mixed-in-Place ground
improvement elements were created as individual
barettes, for the remediation of a total of three
railway embankments. To monitor displacements
of the embankment, inclinometer pipes were
fitted by using an anchor drilling rig.
INFO
Grouted Anchors 11
Rotary Percussive Drilling
The rotary percussive method is a highly productive drilling additionally transported to the initial drilling location, aided
method which can be used in sand and gravel. In this case, by the water-flush. Upon reaching the final depth, and
the drill rod is locked with a drill bit at the lower end before prior to dismantling the drill rod, the drill bit is lost. The
start of drilling. The drill rod rotates and water is pumped rotary method is used for low drilling resistance and, with
through the interior of the drill rod to the drill bit, via the increasing drilling resistance, the hammer mechanism of
rotary swivel of the anchor drilling rig. At the same time, the hydraulic hammer will be switched on. Anchor drilling
the hydraulic hammer strikes the top end of the drill rod, rigs with drill rod magazines could be used for rotary
thereby supporting the action of breaking up the ground percussive drilling.
at the drill bit. The loosened soil is moved to the side and
INFO
Advantages
12 Grouted Anchors
Double-Head System
Overburden drilling with double-head system is suitable of a rotary drive, while the inner drill rod is driven in the
for all soils and rock. During the drilling process, an inner opposite direction by a hydraulic hammer. The air or
and outer drill rod with a drill bit fixed at the lower end of water flushing is done via the inner drill rod, resulting in a
each rod is screwed into the ground. For rock drillings, controlled discharge of the drill spoil in the annular space
a down-the-hole hammer is alternatively mounted to between inner and outer drill rod. The inner drill rod must
the inner drill rod. The outer drill rod is rotated by means be removed before installing the anchoring tendon.
The double-head
The d system
is suitable for all types of
ground, including rock, due
to its two independent drill
rods.
Christian Lorenz
Head of the Product
Group Anchors
Grouted Anchors 13
Auger Drilling
Auger drilling uses a hydraulically powered rotary motor to reduce wear of the auger rods. After removal of the auger
rotate the auger rod. This loosens the soil with the drill bit rod, the bore hole must be filled with mortar as quickly
and transports it to the mouth of the bore, via the auger. as possible, to prevent the bore hole from loosening or
If a hollow stem auger is used, the soil discharge can be softening. The bore hole is filled using a grouting lance.
supported by air flushing. Depending on the strength and Because the anchors are installed independently from the
abrasiveness of the ground to be drilled, different drill bits creation of the bore hole, auger drilling is a method that
are used, e.g. a 3-wing stage drill bit or a drill bit with round achieves a rapid construction progress.
shank bit function. The drill bits create a clearance to
14 Grouted Anchors
Down-the-hole Hammer Drilling
Bores in bedrock can be drilled very efficiently using energy transferred to the drill bit acts directly on the rock to
a wear-resistant and carbide-covered down-the-hole be loosened. The harder the rock, the greater the benefit of
hammer drill bit. Compressed air is directed to the down- this process. The down-the-hole hammer can be combined
the-hole hammer through the rotating drill rod. The air with various drilling systems, such as the auger or double-
serves as a driver, as well as a flushing agent to discharge head system. Alternatively, a water-driven down-the-hole
drilling debris. The down-the-hole hammer always works at hammer can be used and can offer additional benefits
the deepest point of the drilling, which means the impact under certain conditions.
INFO
Drill bits
Various drill bit designs are available to suit the characteristics of the respective rock stone – such as
strength, composition and abrasiveness. These can be combined with the down-the-hole hammer.
Grouted Anchors 15
Temporary Anchors
Temporary anchors serve to secure construction projects bore hole, using an unwinding unit. Installation of the
over a lifetime of a maximum of two years. They are anchor heads and inspection of the anchors is done by
generally constructed as stranded anchors, but can also in-company teams. Based on the installation situation, the
be installed as single bar anchors. Prestressing strands respective anchor head structure is mounted on concrete
with seven wires are employed. For quality reasons, abutments or connected to the wall as a welded structure.
these are exclusively factory-made. To protect against The load-bearing capacity of each anchor is determined
corrosion, the sections of the single strands are covered by means of a standard load test – the anchor acceptance
with PE sheaths and are factory-fitted with post-grouting test – and recorded in a log. The yellow anchor cap
pipes. The stranded anchors are supplied on rolls, stored identifies a finished anchor.
in a space-saving manner on the site and installed in the
PE anchor cap
wedge plate
basket spacer / centralizer prestressing strands sheathing
wedge
INFO
• St1570/1770, 0.6“
• St1570/1770, 0.62“
• St1660/1860 0.6“
• St1660/1860 0.62“
16 Grouted Anchors
Permanent Anchors
Permanent anchors are grouted anchors for permanent created using an adapted drilling technique. The anchor
use from two years and beyond and they become part head of the permanent anchor is also protected against
of the structure. Prestressing strands or thread rods corrosion and designed to allow re-inspection or re-
are used as base elements. Permanent anchors differ tightening of the anchor at any stage. All cavities are filled
from temporary anchors by offering additional corrosion with plastic corrosion protection compound. The anchoring
protection. For this purpose, the prestressing strands are tendon is filled with premium cement mortar inside the
greased with a plastic corrosion protection compound in corrugated tube, and the load-bearing capacity of every
the area of the free tendon lengths. The strand bundles anchor is determined by means of an anchor acceptance
are additionally protected over their entire length, with a test. Permanent anchors are also subjected to a suitability
common corrugated tube. These additional protective test. Permanent strand anchors offer the same logistical
corrosion barriers result in larger drilling diameters that are benefits as Temporary strand anchors.
wedge plate
cement mortar post-grouting pipe
basket spacer / centralizer tubular sleeve sheathing with anchor head seal
corrosion protective compound
wedge
bearing plate
with pipe socket
INFO
Installation
Plastic corrosion protection compound “Nontribos MP2” is pumped in below the wedge plate. Above the
wedge plate and under the anchor cap, “Denso-Jet mixture” is filled. A special tool, such as a pipe cutter, a
pump for the corrosion protection compound or a Denso boiler is required for installing the anchor head.
Grouted Anchors 17
Removable Anchors
In some instances it may not be possible to have anchors is dismantled, and fully removable anchors, where
prestressing strands remaining in the neighboring the whole steel tendon is dismantled. With removable
construction soil. In these cases, grouted anchors can be anchors, it is important to design the heights of the
constructed as removable anchors, which can be removed anchors’ initial drilling positions in the retaining structure,
at the end of their lifetime. Installation and dismantling of to match the heights of the building within the excavation
these anchors is, however, associated with increased time pit. Ideally, the anchors’ initial drilling positions are located
and expenditure. Two different construction options are above the ceiling of the building and can then be removed
available, depending on the requirement: partly removable from this level.
anchors, where only the free anchor length of the ground
PE anchor cap
wedge plate
basket spacer / centralizer prestressing strands sheathing
wedge
Depen
Depending on the client’s requirements, partly removable and fully
removable anchors are available. These can be removed depending on
the planned lifetime.
Moritz Hahn
Project Manager
18 Grouted Anchors
Staggered Anchors
In the case of bond type grouted anchors, an increase in in accordance with DIN standards, with both part anchors
the grout body length to more than 7 m, will only result being tested at the same time, but independent of one
in a slight increase of the anchor forces. With the Bauer another by means of two independently controllable
staggered anchor, the anchor capacity can be significantly hydraulic cylinders. Additionally, the displacements of the
increased by installing two optimized part anchors in a two part anchors are determined using two independent
bore. Dividing the anchor force over two grout bodies precision dial gauges. Staggered anchors can be used
results in a very efficient power transmission of the anchor effectively in soils with a low load-bearing capacity.
load into the ground. Bauer staggered anchors are tested
PE anchor cap
wedge plate
prestressing strands sheathing
post-grouting pipe
centralizer bearing plate
wedge
INFO
Sequence
In the acceptance test, the shorter part anchor of the staggered anchor is always loaded up first to the test
load. The longer part anchor is tested thereafter.
Grouted Anchors 19
Project
A wealth of experience and
qualified employees form the
basis of our extensive range of
construction services. We offer
tailor-made solutions for every
project and each individual
challenge.
A special
spe feature of the
construction site was its
narrowness in parts. More-
over, the anchor works
were carried
out below
groundwa-
ter level.
Christian Lorenz
Head of the Product Group p
Anchors
ors
22 Grouted Anchors
Once the anchor drilling
rig was set up at the start
position, the actual drilling
could begin.
The inner drill rod was removed from the bore hole
with an excavator and placed in the drill rod box.
INFO
Grouted Anchors 23
BAUER Spezialtiefbau GmbH
BAUER - Strasse 1
86529 Schrobenhausen, Germany
Tel.: + 49 8252 97- 0
[email protected]
www.bauer.de
05/2020
905.025.2