Question: 1 Correct
Conduct the project kick-off meeting and inform everyone that the
project has started
Explanation
The project charter establishes a partnership between the performing and requesting
organizations. Projects are initiated by an entity external to the project such as a sponsor,
program, or project management office (PMO), or a portfolio governing body chairperson or
authorized representative. The project initiator or sponsor is responsible for approve and issue
the charter and can take the help of the prospect project manager to develop it.[PMBOK 6th
edition, Page 77 ]
Question: 2 Correct
https://www.pm-tricks.com/QuizHistory/review/6235 1/75
8/7/2019 PM-Tricks | Dashboard
Explanation
The question states that project planning is about to begin which suggests that project initiation
has been completed. The project charter is created during the Develop Project Charter process as
part of project initiation. The project team uses the project charter as a starting point for initial
project planning. The type and amount of information in the project charter varies depending on
the complexity of the project and the information known at the time of its creation. At a minimum,
the project charter should define the high-level information about the project that will be
elaborated in the various components of the project management plan.
Question: 3 Correct
https://www.pm-tricks.com/QuizHistory/review/6235 2/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Monitor and Control Project Work is the process of tracking, reviewing, and reporting overall
progress to meet the performance objectives defined in the project management plan. Of the
available choices, only comparing actual project performance against the project management
plan is performed during the Monitor and Control Project Work process. [PMBOK 6th edition, Page
107]
Question: 4 Incorrect
Explanation
The assumption log is a project document used to record all assumptions and constraints
throughout the project life cycle. The assumption log is created as an output of the Develop
Project Charter process, as such limited information is available to create this project document.
High-level strategic and operational assumptions and constraints are normally identified in the
business case before the project is initiated and will flow into the project charter. Lower-level
https://www.pm-tricks.com/QuizHistory/review/6235 3/75
8/7/2019 PM-Tricks | Dashboard
activity and task assumptions are generated throughout the project. The assumption log is used
to record all assumptions and constraints throughout the project life cycle. Therefore, of the
available options, the project business case is the best source of information to use in the
development of the assumption log. [PMBOK 6th edition, Page 77]
Question: 5 Correct
Final report
Project Charter
Explanation
The scenario suggests the project has been closed. In other words, the Close Project or Phase
process is now complete. The final report is one of the outputs from this process. The final report
includes information such as a summary level description of the project, a summary of any risks
and issues encountered and how they were addressed, a summary of how the final product,
service or result was achieved, and more. Since the vice president wants a summary overview of
project results, providing the vice president with the final report will likely meet their needs and is,
therefore, of the choices provided, the best answer to the question asked. [PMBOK 6th edition,
Page 127]
Question: 6 Correct
Expert judgment
Explanation
Organizational process assets are inputs for developing the project charter process and identify
stakeholder process . its very important question for real pmp exam .
Question: 7 Correct
Explanation
Measure project performance in order to identify and quantify any variances and perform
approved corrective actions. Preventive actions should be identified and implemented during this
process group but they will not ensure that variances won't take place throughout the project
lifecycle. Only conducting daily status meetings will not assist in monitoring and controlling the
project. Refer to PMP Exam Outline in the Monitoring and Controlling Process Group ( Task no. 1 )
https://www.pm-tricks.com/QuizHistory/review/6235 5/75
8/7/2019 PM-Tricks | Dashboard
Question: 8 Correct
Just to inform
Explanation
the kickoff meeting is conducted to communicate the start of the project, the key milestones, and
other information to inform and engage stakeholders and gain their commitment. Refer to PMP
Exam Outline in the Planning Process Group ( Task no. 12 )
Question: 9 Incorrect
https://www.pm-tricks.com/QuizHistory/review/6235 6/75
8/7/2019 PM-Tricks | Dashboard
Explanation
According to the examination content outline, following the change management plan ensures
that project goals remain aligned with business needs. Refer to PMP Exam Outline in the
Monitoring and Controlling Process Group ( Task no.2 )
Question: 10 Incorrect
Ask each one of them to explain the logic behind his opinion
Explanation
If you were to “Add the suggested scenario” (answer option a.), or “Reject adding the new
test“(answer option b.) it will be a premature decision as you didn’t discuss the reasoning behind
both opinions, and since this is the project kick-off meeting and there’s no time pressure for
resolving the conflict “Postpone the discussion for later time“ (answer option a.) seems an
appealing approach, if you were to “Ask each one of them to explain the logic behind his opinion”
” (answer option d.) it won’t be the right time for such discussion. The best course of action is to
“Postpone the discussion for a later time” (option c.).
Question: 11 Correct
Control Procurements
Conduct Procurements
Explanation
The scenario presented describes administrative closure activities, which occur as part of the
Close Project or Phase process. While procurements are closed through the Control
Procurements process, administrative closure of procurements occurs through the Close Project
or Phase process. Activities related to the completion of the contractual agreements applicable to
the project or project phase such as: ** Confirming the formal acceptance of the seller’s work, **
Finalizing open claims, ** Updating records to reflect final results, and ** Archiving such
information for future use. [PMBOK 6th edition, Page 123]
Question: 12 Incorrect
Identify Stakeholders
https://www.pm-tricks.com/QuizHistory/review/6235 8/75
8/7/2019 PM-Tricks | Dashboard
Explanation
ِAfter approval the project management plan, the next step is Conduct kick-off meeting,
communicating the start of the project, key milestones, and other relevant information in order to
inform and engage stakeholders and gain commitment before the project execution. Refer to PMP
EXAM CONTENT OUTLINE- PLANNING PHASE - TASK NO 11 & 12
Question: 13 Correct
Explanation
The project manager does not update or modify the business documents since they are not
project documents; however, the project manager may make recommendations. so the project
manager should meet the project sponsor and inform him [PMBOK 6th edition, Page 78]
Question: 14 Incorrect
During the middle of the project, the project manager has been
exposed to an accident, and a new project manager has been
assigned. What should the new project manager do next?
Explanation
Since he is a new project manager, so the communication management plan should be updated.
Also, the resource management plan is a component of the project management plan. Option A)
incorrect because the sponsor who can update or modify the project charter according to PMBOk.
Option D) update RAM not now because we are in the middle of the project, so Everyone knows
what is the activities or work packages assigned to complete.
Question: 15 Correct
Explanation
KPI is an EEF, Then you can find it as input in developing the project charter process as EEF. it will
be part of measurable project objectives in the project charter
Question: 16 Correct
CCB, and the team members Updated the Scope and Schedule
baselines to reflect the approved changes. What should you do
next?
Explanation
After updating the impacted baselines, you should inform the stakeholders about the approved
change request. Option ( Inform the sponsor about the approved change request ) is incorrect
because the project sponsor is a part of The CCB and has information about the approved change.
Question: 17 Incorrect
Active listening
Leadership
Political awareness
Explanation
Active listening helps reduce misunderstandings and improves communication and knowledge
sharing. [PMBOK 6th edition, Page 104]
https://www.pm-tricks.com/QuizHistory/review/6235 11/75
8/7/2019 PM-Tricks | Dashboard
Question: 18 Correct
A measure that is taken to bring the future result in line with the
project plan best describes?
Corrective action
Defect repair
Preventive action
Change request
Explanation
Whenever you see "realign" or "bring back", it points to Corrective Action. When you see the word
"Keep the future results" or "ensure future results stay within baseline", or something similar, it
points to Preventive Action. Both preventive and corrective actions take care of the future results,
but preventive action is proactive, i.e. you see that a deviation may occur and you implement
preventive action to "keep" the future results within the baseline. Corrective actions, on the other
hand, are reactive - i.e. the deviation has already occurred and is above the threshold - you
implement corrective action to fix the problem and bring the results within acceptable deviation or
within the baseline.
Question: 19 Incorrect
Requirement Documentation
https://www.pm-tricks.com/QuizHistory/review/6235 12/75
8/7/2019 PM-Tricks | Dashboard
Explanation
The requirements traceability matrix is a grid that links product requirements from their origin to
the deliverables that satisfy them. The implementation of a requirements traceability matrix helps
ensure that each requirement adds business value by linking it to the business and project
objectives. It provides a means to track requirements throughout the project life cycle, helping to
ensure that requirements approved in the requirements documentation are delivered at the end of
the project. Finally, it provides a structure for managing changes to the product scope. . [PMBOK
6th edition, Page 148]
Question: 20 Correct
Final report
Explanation
The final report provides a summary of the project performance. [ PMBOK 6th edition, Page 127]
Question: 21 Correct
initiated. You want to find out the exact reasons for the
termination of the project. You also want to know which
deliverables were produced from the terminated project. Which
of the following documentation should you review to obtain
this information?
Historical Database
Explanation
Project or phase closure documents, consisting of formal documentation that indicates
completion of the project or phase and the transfer of the completed project or phase deliverables
to others, such as an operations group or to the next phase. During project closure, the project
manager reviews prior phase documentation, customer acceptance documentation from the
Validate Scope process, and the agreement (if applicable) to ensure that all project requirements
are completed prior to finalizing the closure of the project. If the project was terminated prior to
completion, the formal documentation indicates why the project was terminated and formalizes
the procedures for the transfer of the finished and unfinished deliverables of the cancelled project
to others.. [PMBOK 6th edition, Page 128]
Question: 22 Correct
https://www.pm-tricks.com/QuizHistory/review/6235 14/75
8/7/2019 PM-Tricks | Dashboard
Explanation
The next step after approved the change request by CCB is to update change log and Update the
Plans and affected baselines before implementing the approved change request.[PMBOK 6th
edition, Page115 ]
Question: 23 Incorrect
Control scope
Explanation
Approved change requests will be implemented through the Direct and Manage Project Work
process.[PMBOK 6th edition, Page120 ]
Question: 24 Correct
https://www.pm-tricks.com/QuizHistory/review/6235 15/75
8/7/2019 PM-Tricks | Dashboard
Explanation
You should discuss the impact of the change request on the project cost with the client. You
cannot process the change request unless the client agrees with its impact on any project
objective.
Question: 25 Correct
Change log
RACI matrix
Issue log
Risk register
https://www.pm-tricks.com/QuizHistory/review/6235 16/75
8/7/2019 PM-Tricks | Dashboard
Explanation
In the change log, you record any change that occurs during the project, along with its impact on
any project objective [PMBOK 6th edition, Page120 ]
Question: 26 Correct
Explanation
You should first evaluate the impact of the change with the team member then inform the
customer of the impact on project constraints.
Question: 27 Incorrect
Explanation
it's a very important question for real pmp exam. the project manager should ask the CCB for
further clarifications/explanations to Ensure that changes are made in a timely manner and Ensure
changes are implemented in sequence. The CCB may also review configuration management
activities. The roles and responsibilities of these boards are clearly defined and agreed upon by
the appropriate stakeholders and are documented in the change management plan. CCB decisions
are documented and communicated to the stakeholders for information and follow-up actions.
PMBOK 121
Question: 28 Incorrect
letters of intent
Deliverables
Stakeholder register
Explanation
Agreements are used to define initial intentions for a project. Agreements may take the form of
contracts, memorandums of understanding (MOUs), service level agreements (SLA), letters of
agreement, letters of intent, verbal agreements, email, or other written agreements. Typically, a
contract is used when a project is being performed for an external customer. [PMBOK 6th edition,
Page78 ]
https://www.pm-tricks.com/QuizHistory/review/6235 18/75
8/7/2019 PM-Tricks | Dashboard
Question: 29 skipped
Explanation
Refer to PMP Exam Outline in the Closing Process Group ( Task no. 3 )
Question: 30 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 19/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Customer or sponsor approval may be required for certain change requests after CCB approval
unless they are part of the CCB. [PMBOK 6th edition, Page115 ]
Question: 31 skipped
You are the new project manager who has never managed a
project before. You have been asked to plan a new project.
Which of the following will help you to improve your chance of
choices?
Historical information.
Configuration management.
Stakeholder analysis.
Explanation
Because you have no experience, you will have to look at the experience of others. This
information is captured in the historical records from previous projects.
Question: 32 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 20/75
8/7/2019 PM-Tricks | Dashboard
Explanation
If there is a change which requires an update to the cost baseline, you will raise it, get it approved,
and then update the cost baseline. The PMBOK Guide, 6th Edition, Page: 113, 115
Question: 33 skipped
Explanation
A business case includes Cost-Benefit Analysis and organizational strategies. [PMBOK 6th
edition, Page 68,75]
Question: 34 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 21/75
8/7/2019 PM-Tricks | Dashboard
Validate scope
Close procurement
Control Quality
Explanation
In the Validate Scope process, the customer accepts the deliverables or the product. [PMBOK 6th
edition, Page166 ]
Question: 35 skipped
Business case
Brainstorming
Final report
Explanation
The approved business case is the business document most commonly used to create the project
charter. [PMBOK 6th edition, Page 77]
https://www.pm-tricks.com/QuizHistory/review/6235 22/75
8/7/2019 PM-Tricks | Dashboard
Question: 36 skipped
Make sure that the scope baseline and schedule baseline are
updated to reflect the approved change before implementing the
change.
Explanation
As the change has been approved you should always update the baseline ( in this case the scope
and schedule baseline) before implementing the change. This will ensure that you track
performance against the new scope and schedule and not the old benchmarks.
Question: 37 skipped
You are in the process of finalizing all activities for the project,
phase, or contract. Which of the following documents include
information about Objectives of Scope, Quality and Cost and
https://www.pm-tricks.com/QuizHistory/review/6235 23/75
8/7/2019 PM-Tricks | Dashboard
Final Report
Risk Register
Project Charter
Explanation
Final Report includes information about Objectives of Scope, Quality and Cost and the criteria
used to evaluate them[ PMBOK 6th edition, Page 127 ]
Question: 38 skipped
Explanation
Sponsor know that the project as behind schedule and over budget so he Knows EV report so the
next step the project manager should provide to sponsor ( work performance report ) because
WPR includes status reports and progress reports. [PMBOK 6th edition, Page 382]
https://www.pm-tricks.com/QuizHistory/review/6235 24/75
8/7/2019 PM-Tricks | Dashboard
Question: 39 skipped
Explanation
Organizational culture, and political climate is examples of (EEF). [PMBOK 6th edition, Page 78]
Question: 40 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 25/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Direct and Manage Project Work is the process of leading and performing the work defined in the
project management plan and implementing approved changes to achieve the project’s objectives.
[PMBOK 6th edition, Page 90]
Question: 41 skipped
The sponsor
The customer
Explanation
The project sponsor is the person presenting the organization's strategy ( strategic directions )
during the kick-off meeting, While the project manager presents the project implementation
strategy.
Question: 42 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 26/75
8/7/2019 PM-Tricks | Dashboard
Project Charter
Stakeholder Register
Verified deliverables
Explanation
Project Charter Key inputs in Close project or phase process because of The project charter
documents the project success criteria, the approval requirements, and who will sign off on the
project.[PMBOK 6th edition, Page 124]
Question: 43 skipped
Meet the project team members and direct them to document both
success and failures
Nothing to do
Explanation
At the end of your project, the project team should document both success and failures reasons
as lessons learned to use in future projects
Question: 44 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 27/75
8/7/2019 PM-Tricks | Dashboard
Control scope
Explanation
Change management plan, which provides the direction for managing the change control process
and documents the formal change control board (CCB). if the PM implemented the change
requests without analyzing the impact of the changes on time and cost and quality will increase
the risks in the project and lead to increased costs (cost overruns).
Question: 45 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 28/75
8/7/2019 PM-Tricks | Dashboard
Explanation
The first step after the approved Change request is Update the change log . all change requests
are recorded in the change log as a project document update. [PMBOK 6th edition, Page 120]
Question: 46 skipped
Explanation
Identify high-level risks, assumptions, and constraints based on the current environment,
organizational factors, historical data, and expert judgment, in order to propose an implementation
strategy. Refer to PMP Exam Content Outline ( Domains ) in the initiation phase. Task no 4
Question: 47 skipped
You are managing the changes made to the scope baseline. The
causes of variances and the reasoning behind the corrective
action chosen should be included in:
https://www.pm-tricks.com/QuizHistory/review/6235 29/75
8/7/2019 PM-Tricks | Dashboard
Risk Register
Explanation
The lessons learned register could be updated with techniques that are efficient and effective in
controlling scope, including causes of variances and corrective actions chosen.[PMBOK 6th
edition, Page 171]
Question: 48 skipped
Business case
Project charter.
Explanation
The business need and the cost-benefit analysis are contained in the business case to justify and
establish boundaries for the project. [PMBOK 6th edition, Page 77]
Question: 49 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 30/75
8/7/2019 PM-Tricks | Dashboard
Executing
Closing
Planning
Explanation
The project kick-off meeting is usually associated with the end of planning, so the next phase is
Executing.[PMBOK 6th edition, Page 86]
Question: 50 skipped
Do nothing
Explanation
Since the team members implemented a change request without through the CCB, as a project
manager you should send the change to CCB for approval. .
Question: 51 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 31/75
8/7/2019 PM-Tricks | Dashboard
Project WBS
Project charter
Explanation
The summary of how the project has achieved the business needs identified in the business case
is included in a project’s final report. The other choices are either project initiating or planning
documents. [PMBOK 6th edition, Page 128]
Question: 52 skipped
You are in the process of finalizing all activities for the project,
phase, or contract. The Project manager should transfer
Lessons learned and knowledge gained throughout the project
to the lessons learned repository in order to:
https://www.pm-tricks.com/QuizHistory/review/6235 32/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Lessons learned and knowledge gained throughout the project are transferred to the lessons
learned repository for use by future projects. [PMBOK 6th edition, Page 128]
Question: 53 skipped
Explanation
Because the project is external, you should follow the law, procedures, and instructions of this
country.
Question: 54 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 33/75
8/7/2019 PM-Tricks | Dashboard
Planning
Executing
Closing
Explanation
The project kick-off meeting is usually associated with the end of planning and the start of
executing. Its purpose is to communicate the objectives of the project, gain the commitment of the
team for the project, and explain the roles and responsibilities of each stakeholder.[PMBOK 6th
edition, Page 86]
Question: 55 skipped
Check with your team when to implement the request and satisfy the
request
Explanation
keyword in this question, the sponsor told the PM to listen (carefully) and (closely) to the Key SH
requests, so you should Issue a change request to CCB to added additional feature to the product.
https://www.pm-tricks.com/QuizHistory/review/6235 34/75
8/7/2019 PM-Tricks | Dashboard
Question: 56 skipped
Initiating
Planning
Executing
Explanation
Identifying stakeholders, high-level assumptions and constraints are part of developing the
project charter, which is a part of the Initiating Process Group.
Question: 57 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 35/75
8/7/2019 PM-Tricks | Dashboard
Change the WBS, project schedule, and project plan to reflect the
new requirement
Explanation
it's a very important question, you should know that any regulatory requirement you must follow
and issue a change request
Question: 58 skipped
Explanation
its tricky question, Customer or sponsor approval may be required for certain change requests
after CCB approval unless they are part of the CCB. [PMBOK 6th edition, Page 115]
Question: 59 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 36/75
8/7/2019 PM-Tricks | Dashboard
In the final stage of the project, the sponsor rejected the final
product where he said it didn't meet the project goals. Which
document you will review to convince him:
Project charter
Stakeholder Register
Agreement
Explanation
keyword ( Project Goals ). The project goals are a component of the project charter. [PMBOK 6th
edition, Page 81]
Question: 60 skipped
Project charter
Change Log
Stakeholder register
Explanation
At a high level, the project charter ensures a common understanding by the stakeholders of the
key deliverables, milestones, and the roles and responsibilities of everyone involved in the
project. [PMBOK 6th edition, Page 81]
https://www.pm-tricks.com/QuizHistory/review/6235 37/75
8/7/2019 PM-Tricks | Dashboard
Question: 61 skipped
You and your team are currently developing the project charter
and are looking for valuable inputs you can use to complete it.
All of the following are inputs in the Develop Project Charter
process except?
Business case
Agreements
Explanation
Business case, Agreements, and Enterprise environmental factors are inputs of developing the
project charter process [PMBOK 6th edition, Page75 ]
Question: 62 skipped
Use a single prime contractor and have this contractor award any
subcontracts
Explanation
in multi-phase projects, the best practice Periodically reviews the business case to check you will
continue in the project or cancel the project. Although the business documents are developed
prior to the project, they are reviewed periodically. [PMBOK 6th edition, Page 77]
Question: 63 skipped
Explanation
When closing the project, the project manager reviews the project management plan to ensure
that all project work is completed and that the project has met its objectives. [PMBOK 6th edition,
Page 123]
Question: 64 skipped
Validate Scope
Control quality
Explanation
Final acceptance on the deliverables as a part of the close project or phase.Formal acceptance a
result of validate scope process.
Question: 65 skipped
During the Kick- off meeting, the stakeholders did not accept a
project management plan. What should you refer to persuade
the stakeholders?
Project charter
Explanation
Project charter includes High-level requirements, Project purpose, High-level project description
and boundaries, High-level risks, Summary budget, Key Stakeholder list, and the project charter is
the key input in develop project management plan process. so you refer to charter to persuade the
stakeholders.[PMBOK 6th edition, Page 81]
Question: 66 skipped
Explanation
The project kick-off meeting is usually associated with the end of planning and the start of
executing. Its purpose is to communicate the objectives of the project, gain the commitment of the
team for the project, and explain the roles and responsibilities of each stakeholder.[PMBOK 6th
edition, Page 86]
Question: 67 skipped
Communicate ground rules and ensure they are followed in all the
meetings
https://www.pm-tricks.com/QuizHistory/review/6235 41/75
8/7/2019 PM-Tricks | Dashboard
Set objectives of the kick off meeting clearly, so that all the attendees
are aware of the meeting agenda
Explanation
( Communicate ground rules and ensure they are followed in all the meetings ) Ground rules are a
set of rules governing how the team interact, make decisions, and handle issues that must be
resolved. This would also help resolve conflicts inevitable in any project. Ground rules should be
established at the very start of the project, preferably at the kick-off meeting.. so communicate
ground rules is best as it helps the project manager prevent future conflicts without any harmful
emotion to the team.
Question: 68 skipped
Explanation
Although the change in the product will increase the profitability as well as reduce the
manufacturing time, you must Discuss the impacts with your team first.
https://www.pm-tricks.com/QuizHistory/review/6235 42/75
8/7/2019 PM-Tricks | Dashboard
Question: 69 skipped
Explanation
Continuous monitoring gives the project management team insight into the health of the project
and identifies any areas that may require special attention.[PMBOK 6th edition, Page 105]
Question: 70 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 43/75
8/7/2019 PM-Tricks | Dashboard
Explanation
EEF key inputs in Develop Project Charter. Anything issued from the government you MUST
consider it. Option ( Meeting with Stakeholders and evaluate the impact ) not correct because
While creating the Project charter there is no plans or baseline to evaluate the impact. Very
important question for the real exam.[PMBOK 6th edition, Page 78]
Question: 71 skipped
Tacit knowledge
Explicit knowledge
Embedded knowledge
Experience knowledge
Explanation
Knowledge is commonly split into “explicit” (knowledge that can be readily codified using words,
pictures, and numbers) and “tacit” (knowledge that is personal and difficult to express, such as
beliefs, insights, experience, and “know-how”).. [PMBOK 6th edition, Page 100]
Question: 72 skipped
Explanation
Conduct benefit analysis with relevant stakeholders to validate project alignment with
organizational strategy and expected business value. EXAM CONTENT OUTLINE in ( initiating )
task no 7
Question: 73 skipped
Explanation
Capture, analyze, and manage lessons learned, using lessons learned management techniques in
order to enable continuous improvement. Exam Content Outline in ( Monitoring and Controlling)
task no.6
Question: 74 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 45/75
8/7/2019 PM-Tricks | Dashboard
Conduct procurement
Explanation
( Agreement ) is input in Develop project charter Process. Agreements are used to define initial
intentions for a project. Agreements may take the form of contracts, memorandums of
understanding (MOUs), service level agreements (SLA), letters of agreement, letters of intent,
verbal agreements, email, or other written agreements. Typically, a contract is used when a project
is being performed for an external customer. [PMBOK 6th edition, Page 78]
Question: 75 skipped
Explanation
Only this option will address the issue ( Negotiate with the sponsor about this issue )
Question: 76 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 46/75
8/7/2019 PM-Tricks | Dashboard
Business Case
Issue log
Business need
Explanation
Projects are initiated to realize business opportunities that are aligned with an organization’s
strategic goals. Prior to initiating a project, a business case is often developed to outline the
project objectives, the required investment, and financial and qualitative criteria for project
success. The business case provides the basis to measure success and progress throughout the
project life cycle by comparing the results with the objectives and the identified success criteria.
[PMBOK 6th edition, Page 546]
Question: 77 skipped
Analyze the impact of the change with the team on other project
constraints
A workaround
https://www.pm-tricks.com/QuizHistory/review/6235 47/75
8/7/2019 PM-Tricks | Dashboard
Explanation
First, you should analyze the impact with the team members on all project constraints ( Cost,
Time, Quality, resources,...)
Question: 78 skipped
Identify Stakeholders
Explanation
The stakeholder register is developed during the Identify Stakeholders process. [PMBOK 6th
edition, Page 507]
Question: 79 skipped
Explanation
First, you must evaluate the impact on all the project constraints before issue change request
such as ( Time & scope & quality & Risk,....) . in the scenario project manager evaluated the impact
only on cost.
Question: 80 skipped
Project manager
Project Sponsor
PMO directive
Explanation
For the real exam, you should know that the project manager presents the implementation
strategy of the project and the sponsor present the organization strategy.
Question: 81 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 49/75
8/7/2019 PM-Tricks | Dashboard
Explanation
keyword ( significant requirement ) so as a project manager, you should Issue a change request
for revising requirement documentation
Question: 82 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 50/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Project approval requirements must be documented early in the project during the initiation
phase. These requirements show the requisites for project success, the names of persons signing
off on the project and deliverable requirements. Since the project charter is created in the initiation
phase of the project, the project manager must include these requirements in the charter. [PMBOK
6th edition, Page 81]
Question: 83 skipped
You are the project manager of the GHY Software Project for
your company. You’ve recently completed the project and need
to distribute the project closure report. Who should get a copy
of the project closure report?
Project sponsor
All stakeholders
Explanation
The Communications management plan include Person or groups who will receive the
information, including information about their needs, requirements, and expectations. [PMBOK 6th
edition, Page 377]
Question: 84 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 51/75
8/7/2019 PM-Tricks | Dashboard
Change log
Issue log
Risk report
Stakeholder register
Explanation
The change log is used to communicate changes and approved, deferred, and rejected change
requests to the impacted stakeholders. [PMBOK 6th edition, Page 382]
Question: 85 skipped
You are in the process of finalizing all activities for the project,
phase, or contract. Which of the Following Key inputs for this
Process?
https://www.pm-tricks.com/QuizHistory/review/6235 52/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Project Management Plan, OPA are key inputs for Close Project or phase [PMBOK 6th edition,
Page 71 ]
Question: 86 skipped
Before initiating any such project, the value of the project to the
organization must be determined. Which of the following is the
most critical factor to be considered in such a scenario?
Investment requirement
Explanation
All projects must be Alignment with the strategic goals to the organization.
Question: 87 skipped
Explanation
After approved change request the first step is to update change log, but it's not an option in this
question so you should select Update the scope and schedule baselines to reflect the approved
change. Before solving the change request questions, you should understand and memorize the
following steps: 1- Meeting with stakeholder to understand the reason / What he needs to change.
2- Analyze the impact of the change with the project team on Project Constraints ( Scope - Cost –
Schedule – Quality – Risk – etc….) 3- Inform stakeholder about the impact of such change. 4-
Send change request to the CCB. 5- Send a request to the sponsor ( if the sponsor is not part of
the CCB). 6- After approval by CCB/ Sponsor record the change in the change log. 7- Update
project management plan, Baselines, and documents. 8- Communicate / inform the key
stakeholder. 9- Implement the Approved change Request by the Project team in Direct and
manage project work process.
Question: 88 skipped
Figure out the impact on the scope of the work, cost and other
project constraints before you write up the change request
Make the change. It’s going to save time and nobody will want the
project to take longer than it should.
Tell the team member that you’ve already communicated the deadline
for the project, so you can’t make any changes now
https://www.pm-tricks.com/QuizHistory/review/6235 54/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Although the change will cut the schedule down by a month, you must first Figure out the impact
on the scope of the work, cost and other project constraints before you write up the change
request.
Question: 89 skipped
Explanation
Archive project documents and materials using generally accepted practices in order to comply
with statutory requirements, for potential use in future projects, and audits. PMP Exam Content
Outline in ( Closing ) task no. 6
Question: 90 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 55/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Keyword ( informal conversations ) Networking, including informal social interaction and online
social networking. Online forums where people can ask open questions (“What does anyone know
about…?”) are useful for starting knowledge-sharing conversations with specialists. [PMBOK 6th
edition, Page 103]
Question: 91 skipped
Information Management
Focus groups
Benchmarking
Explanation
Information management tools and techniques are used to create and connect people to
information. They are effective for sharing simple, unambiguous, codified explicit knowledge.
[PMBOK 6th edition, Page 103]
https://www.pm-tricks.com/QuizHistory/review/6235 56/75
8/7/2019 PM-Tricks | Dashboard
Question: 92 skipped
Explanation
The project is no longer valid, you and your teams need to follow the proper closing procedures
which involve documenting the lessons learned and update the OPA
Question: 93 skipped
Validate Scope
Explanation
Conduct benefit analysis with stakeholders to validate project alignment with organizational
strategy and expected business value.
Question: 94 skipped
Project Charter
Business case
Explanation
The Project Charter formally authorizes the project and provides the Project Manager with the
authority to apply resources to project activities. Although the project sponsor may create the
project charter, it is recommended that the Project Manager participates in the development of the
project charter. Please refer to sPMBOK® Guide - Sixth Edition: Project Integration Management
page 75.
Question: 95 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 58/75
8/7/2019 PM-Tricks | Dashboard
Positive risks
Budget estimates
Risk analysis
Explanation
According to PMBOK® Guide - Sixth Edition, Sec 4.1.3.1 Page 81, the project description and
Project purpose or justification must be included in the project charter.
Question: 96 skipped
Call for a project kick-off meeting and politely inform everyone that
the project has started and request their cooperation
Explanation
Explanation: The sponsor or initiator of the project is responsible to establish (approve and issue)
the charter, and can take the help of the prospect project manager to develop it.
Question: 97 skipped
https://www.pm-tricks.com/QuizHistory/review/6235 59/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Explanation: It is important to capture all the project lessons in a lessons learned repository at the
end of the project. Releasing of resources to be done eventually after all closure work is
completed. The baseline cannot be updated with actuals. Operations have already provided their
acceptance as mentioned in the question.
Question: 98 skipped
The agreement
Explanation
Explanation: The contract must be referred for the closure requirements and responsibilities apart
from what is documented in the project management plan. The procurement SOW does not
describe this procedure and there is no document called the project closure plan. The
requirements documentation is about the project requirements which will be scoped.
Question: 99 skipped
Close the project even if customer could not make it to the meeting
Reschedule the meeting to 2 days from now and tell the customer to
attend without fail.
Explanation
Explanation: The sponsor should be consulted for major decisions if need be. The sponsor may
take part in the closure discussions apart from the project manager. In internal projects. The
customer and sponsor can be the same.
Explanation
Explanation: Lessons learned documents are prepared all through the project and finalized during
the Close project process and is not included as a part of the Final Project Report.[PMBOK 6th
edition, Page 127]
Explanation
Explanation: Ensure all project closure procedures are followed and lessons learned are updated.
No one will be interested in work performance reports though a status of deliverables will be
https://www.pm-tricks.com/QuizHistory/review/6235 62/75
8/7/2019 PM-Tricks | Dashboard
recorded. No point in completing the work since funds are not available. Resources can released
only after project closure activities are completed.
Explanation
Explanation: Accepted deliverables were output from Validate Scope, after ensuring that the
deliverables fully satisfied all requirements.
https://www.pm-tricks.com/QuizHistory/review/6235 63/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Explanation: As the change is already approved, and it is clear that the relevant baseline has been
updated, it can be now implemented, but after informing the concerned stakeholders about it first.
These are created while developing the project charter and managing
project knowledge respectively
Both are created when executing the work, that is in the Direct and
Manage Work process
Explanation
Explanation: The assumptions log is created at the time of project charter creation, and the
lessons learned register when managing project knowledge.
https://www.pm-tricks.com/QuizHistory/review/6235 64/75
8/7/2019 PM-Tricks | Dashboard
Perform a trend analysis of the actual values for the last week and
this week
Explanation
Explanation: Variance analysis compares planned and actual measures. As a project manager, you
are responsible to check whether there is any variance between planned and actual measures for
the project progress. Trend analysis is not required as per the question. Root cause analysis and
alternatives analysis will have to be done later. Refer PMBOK Guide 4.5.2.2 Data Analysis
(Variance analysis, page 111).
https://www.pm-tricks.com/QuizHistory/review/6235 65/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Explanation: Any impacted baselines should be updated before the change is implemented. The
implementation plan is already done and it has already been assessed that the scope baseline will
be impacted.
Project Schedule
Business Case
Explanation
Explanation: Answer = A. Project management plan. It describes how the project will be executed,
monitored and controlled and closed.[PMBOK 6th edition, Page 86]
https://www.pm-tricks.com/QuizHistory/review/6235 66/75
8/7/2019 PM-Tricks | Dashboard
Project Charter
Business Case
Explanation
Explanation: Answer =. Enterprise Environmental Factors, as this includes cultures and global,
regional or local trends, practices and habits.
The WBS
https://www.pm-tricks.com/QuizHistory/review/6235 67/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Explanation: Answer = The project charter. "The project charter provides the project manager with
the authority to plan, execute, and control the project". (PMBOK Guide pg77).
Manage communications
Explanation
Explanation: Answer =. The issue log is first created in the Direct and Manage Project Work
process. It may be updated in other processes.
https://www.pm-tricks.com/QuizHistory/review/6235 68/75
8/7/2019 PM-Tricks | Dashboard
The human mind can retain only 7 pieces of tacit knowledge, but up
to 700 pieces of explicit knowledge.
Explanation
Explanation: Answer = A. Explicit knowledge is shared by codifying, recording and circulating, but
tacit knowledge is shared by human interaction. B and C are incorrect statements. In option D, the
various PMI Practice Standards are also explicit knowledge.
Project charter
Explanation
The project manager is participating in the development of project charter using the statement of
work to understand the product requirements and descriptions. The output of this process is a
https://www.pm-tricks.com/QuizHistory/review/6235 69/75
8/7/2019 PM-Tricks | Dashboard
project charter. Once approved, it formally initiates the project. A project charter documents the
high-level project description and business needs of the project, along with the current
understanding of the customer's needs, risks, and the name of the sponsor
Explanation
The kick-off meeting is done in the beginning of the project and then again before starting each
new project phase. It has four main objectives: a) Publicly state the beginning of the project; b)
Outline the project goals, as well as the individual roles and responsibilities of team members; c)
Clarify the expectations of all parties; and (d) Get a commitment from all those who influence the
project's outcome.
take?
Discuss with the senior manager the reason for abrupt project
termination
Explanation
Conduct Scope Verification. In the event of project termination, the project manager should do
scope verification to determine the extent of completion of the project. In this case, scope
verification is measured against the deliverables to the point of the project cancellation. Options
Release the team members AND Document the lessons learned can be done later.
https://www.pm-tricks.com/QuizHistory/review/6235 71/75
8/7/2019 PM-Tricks | Dashboard
Explanation
As a part of the project closure activity, a project manager should first review all prior information
from the previous phase, closure, to ensure all work is completed and the project has met its
objectives. Since project scope is measured against the project management plan, the project
manager will review the document to ensure completion before considering the project closed.
Plan Communications
Explanation
Although Jerry is developing the team, the Develop Project Team process cannot be chosen as the
correct answer as he is doing multiple activities. All of these activities are performed in the Direct
and Manage Project Work process.
Explanation
Project approval requirements are listed in the Project Charter. Therefore, your team leader should
refer Project Charter to learn about those requirements.
Validate Scope
Control Scope
Explanation
During the Monitor and Control Project Work process, all project work is monitored and controlled,
including approved changes and defect repairs.[PMBOK 6th edition, Page 107]
https://www.pm-tricks.com/QuizHistory/review/6235 73/75
8/7/2019 PM-Tricks | Dashboard
Explanation
Project closure procedures must be followed. They must be followed irrespective of whether the
project was successfully completed or if it was terminated. We always follow closure procedures.
https://www.pm-tricks.com/QuizHistory/review/6235 74/75
8/7/2019 PM-Tricks | Dashboard
Review the issue log in order to minimize the impact on the project .
Explanation
Very important question for PMP Real exam. Based on the above options, the First step to do in
project closure is archive project information and documents for future use by the organization.
The Last step to do in project closure is: Obtain feedback from relevant stakeholders in order to
evaluate their satisfaction.