METHODOLOGY - Ee
METHODOLOGY - Ee
1 INTRODUCTION
This method statement is concerned with the Electrical Construction of Sierra Valley Gardens.
This document is issued may have to be revised and update upon the actual implementation for more Comprehensive technical details.
2 SCOPE OF WORKS:
Supply and Installation of Roughing-ins of Data and Telephone system, Intercom, and Public Address.
3 DRAWINGS & REFERENCE DOCUMENTS
4 WORK PREPARATION:
4.1 Site survey shall be conducted before the commencement of the said activity to identify the location of works & hazard.
4.4 Proper coordination with Owner's representatives, area supervisor and other Stakeholders prior to the start of works.
4.5 Any affected utilities should be protected or relocate to avoid possible damage during work execution (with the approval of project owner & facility).
4.6 Site Project Coordinator, Project In-Charge, Supervisor and Safety officer shall conduct daily toolbox meeting with all personnel to delegate specific
task of each worker and to download further safety instruction.
4.7 Work area must be secure, signage to restrain unauthorized person to enter particularly when works in Progress.
4.8 Housekeeping and Mobilization shall be done immediately after the activity.
5 WORK EXECUTION:
5.1 Mobilization
5.2.1 Installation of Electrical Conduit for lighting, power, TEL/DATA, Intercom, PA/BGM including hangers, supports, & accessories.
5.2.2 Installation of Wires and Cables for lighting and power on buildings including tagging & cabling works.
5.2.4 Installation of panel boards & Enclosed Circuit Breakers including all accessories.
5.2.5 Installation of Lighting Fixtures and Wiring Devices including tagging.
5.4.1 Site Clearing and demobilization of all materials, equipment & tools.
6 MITIGATING MEASURES:
6.0
1 Secure permit prior to start work execution.
6.0
2 Observe buddy system.
6.0
3 Barricade the work area to avoid by passers and inform others for the activities.
6.0
4 Proper coordination to the project owner, area owner.
6.05 Only authorized person will do the job.
6.06 Deploy enough personnel for the activity ongoing.
6.07 Avoid over stocking of materials at works area.
6.08 Provide proper access & proper coordination among each member to execute the activity safely.
6.09 Provide enough illumination during night & overtime activities.
7 PPE's REQUIRED:
A. GFCI
B. Extension chord
D. Hand-drill
E. Lightings
G. Welding Machine
H. Cutting Outfit
Submitted by: