0% found this document useful (0 votes)
72 views1 page

Cim Cat

The document contains questions for a CIM (Computer Integrated Manufacturing) systems exam to be submitted on Monday 21st. Question One asks to explain four basic CIM system components, outline two CAM application categories and discuss five examples of each, and discuss the advantages of FMS. Question Two asks to draw a process flow of a generative CAPP system modular structure and outline its seven parts. Question Three asks to discuss shop floor data collection to monitor job progress as part of CIM and outline classifications of shop floor data collection systems.

Uploaded by

George Opar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views1 page

Cim Cat

The document contains questions for a CIM (Computer Integrated Manufacturing) systems exam to be submitted on Monday 21st. Question One asks to explain four basic CIM system components, outline two CAM application categories and discuss five examples of each, and discuss the advantages of FMS. Question Two asks to draw a process flow of a generative CAPP system modular structure and outline its seven parts. Question Three asks to discuss shop floor data collection to monitor job progress as part of CIM and outline classifications of shop floor data collection systems.

Uploaded by

George Opar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CIM CAT to Submit by Monday 21st

QUESTION ONE

a) Explain four basic components of a CIM System

b) Outline two application categories of CAM and Discuss any five under each category

c) Discuss The advantages of FMS

Question Two.

a) Draw a process flow of the modular structure of a generative CAPP system

b) Outline all the seven generative part.

Question Three.

a) Discuss the data collect from the shop floor that help monitoring the progress of the
jobs as an integrated part of CIM
b) Outline and discuss the shop floor data collection systems classifications.