INSTALLATION OF COLD AND HOT WATER PIPING SYSTEM AND Ref. No:
ACCESSORIES Above Ground
Rev. No: 0
SUBCONTRACTOR X CONTRACTOR Page : 1 of 1
SECTION OF WORK: Water supply LOCATION:
LEVEL: WIR No.:
STAGE ITEM Checked by Checked by Date

S/C CONT CONS.


SETTING OUT Check Layout

MEP/CIVIL Check Level.


Chipping in the wall.

INSTALLATION Check for Services Clearances, and the same approved


by consultant site team (civil)
1. Check materials are as per approved material
submittal.
2. Check that size of pipe is as per approved
drawing.
3. Check that all pipes passing inside the wall
installed as per approved shop drawings.
4. Check the installed isolation valves are as per
location shown in approved shop drawing
5. Check that expansion / contraction joints are
provided as per approved shop drawings.
6. Check that Air vents installed as per approved
shop drawings. (With Isolation valve).
7. Check that water hammer arrestor is installed
as per approved shop drawings. (With Isolation
valve).
8. Check PRV’s are installed as per approved
shop drawings.
9. Ensure that the Backflow preventers installed
as power approved shop drawings.
10. Check that pipes have been tested for leaks.
(1.5 working pressure – 24 hours)
11. Check that network is cleaned by Chlorine as
per method statement point 7.9.
12. Check that samples (from network/ and tank)
are sent to ITL test (third party) to check water
quality.
13. Check that service identification labels are
provided on exposed pipes and in access
doors.
14. Check that annular spaces between pipes and
sleeves have been sealed with approved
material.