Notifications - Create Notification For Maintenance Request - IW21 (

This document provides instructions for creating a notification for a maintenance request (IW21) in SAP. The instructions outline 14 steps to enter details like the notification type, description, equipment number, priority code, required end date, work center, and other fields. Once all details are entered and validated, clicking save will generate a notification reference number.

Uploaded by

skhan123456
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
379 views1 page

Notifications - Create Notification For Maintenance Request - IW21 (

This document provides instructions for creating a notification for a maintenance request (IW21) in SAP. The instructions outline 14 steps to enter details like the notification type, description, equipment number, priority code, required end date, work center, and other fields. Once all details are entered and validated, clicking save will generate a notification reference number.

Uploaded by

skhan123456
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Notifications – Create Notification for Maintenance Request IW21

Execute IW21 – Create Notification


2
1. Enter YN in the Notification Type field.
Note: We primarily use the YN notification
type for Maintenance Requests.
1
2. Click Enter

3. Notification Description – Enter a


12 description of the maintenance work being
11
requested i.e., PROBLEM or ACTION to be
taken
3 4. Equipment – Enter SAP Equipment number
0
11 5. Long Text Field – Enter additional details
for the requested maintenance
6. Person Responsible – Personnel number of
4 the employee making the request
0
7. Reported by – User id of person entering
the Notification
8. Priority Code – impact of not doing work
by Required End date
1-High – Significant un-containable SHE
5
0 threats or unrecoverable production or
service activity
2-Medium – Containable SHE threats or
recoverable production or service activity
3-Low – All other work
9. Required End – Date by which the impact
6 will be felt if work is not completed
0
10. Breakdown – If asset is not able to
7 perform its function until the repair work is
done check the Breakdown box. You will
8 be prompted to enter a Malfunction Start
Date / Time.
9 10
11. Main Work Center – Will default when you
click the Enter button in next step.
Update, only if required.
12. Click Enter to validate all details.
13. Click SAVE.

14
14. Once saved, the Notification reference
number will be shown in the bottom left
corner of the Notification window.

Page 1 of 1