ITP For Access Control SystemTesting and Commissioning

This inspection and test plan outlines the testing and commissioning process for an access control system project. It lists two key activities: documentation verification and system testing. Documentation will be reviewed for pre-qualification, shop drawings, and material approvals. Testing will include pre-commissioning checks of the installed system and final testing of cables to ensure compliance with project specifications. The contractor and consultant must approve the plan and sign off upon completion of work.

Uploaded by

Tamer Eid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
442 views

ITP For Access Control SystemTesting and Commissioning

This inspection and test plan outlines the testing and commissioning process for an access control system project. It lists two key activities: documentation verification and system testing. Documentation will be reviewed for pre-qualification, shop drawings, and material approvals. Testing will include pre-commissioning checks of the installed system and final testing of cables to ensure compliance with project specifications. The contractor and consultant must approve the plan and sign off upon completion of work.

Uploaded by

Tamer Eid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION & TEST PLAN

REF. NO.
MOCK-UP ZONE PROJECT & GUARD BOOTH) REV. NO.
DATE :
PAGE : 1 OF 1

ACTIVITY: Access control system Testing and Commissioning

AREA/LOCATION:

ITP approved by CONTRACTOR's QA/QC: ITP approved by Consultant:


Signature: Signature:
Date: Date:
INSPECTION LEVEL
SERIAL NO. DESCRIPTION FREQUENCY SPECIFICATION / CRITERIA VERIFICATION RECORD
ITL CONTRACTOR Consultant

1 DOCUMENTATION
Once (Approval prior to
1.1 Pre-Qualification subcontractor Project specifications and drawings. -- R R
submit the submittal)

1.2 Shop Drawing Approval Each Shop Drawing Project specifications and drawings. -- H R

Each submittal ( prior to


1.3 Material Approval Project specifications and drawings. -- H R
order the material).

Once (Approval prior to


1.4 Method Statement Approval Project specifications and drawings. -- H H
start of activity)

2 Testing and Commissioning

Each Area where applicable


2.1 Pre-commissioning of the system (As per Consultant Project specifications and drawings. -- W W
requirements)

Each Area where applicable


Final Testing and Commissioning:
2.2 (As per Consultant Project specifications and drawings. -- W H
Fluke Test for the cables.
requirements)

LEGEND: H: HOLD W: WITNESS S: SURVEILLANCE R: REVIEW


ITP Sign-Off post completion of Works
CONTRACTOR APPROVAL Consultant APPROVAL

NAME : NAME :

SIGN : SIGN :
DATE: DATE:

PAGE 1 of 1