Cold Start Up Check List
Cold Start Up Check List
Project:
8 x 135 MW
LIGNITE BASED THERMAL POWER PLANT, BHADRESH
Doc. Title:
Doc No:
RWPL/OPR/CL_001
Issue Date: No of Sheets:
21/02/2014
(including cover sheet)
6
Revision Record:
Sr. Verification /
Activity Check
No Remarks
1 Ensure all PTW returned, man, material & temporary structure removed from area.
2 HT/LT side on 6.6 KV/415 V supply charged, DC voltage, UPS, Battery chargers are
healthy & in service.
3 Ensure all monitoring & testing instrument are put in service & are normal
4 Ensure there is not restriction for boiler expansion.
5 Ensure all air nozzles of bed cleaned.
6 Ensure all man holes of furnace, APH, U Seal planem & ESP are closed.
7 Ensure all coal feeders outlet gate is closed.
8 Ensure bed material in furnace is filled up to 700 mm height & there is no clinker &
oversize material in furnace bed.
9 Ensure boiler vents are open including drum & start up.
10 Ensure SH & RH drains are open.
11 Ensure CW System is started (refer doc. no. RWPL/OPR/SOP_007) & maintain CW
header pressure 0.20Mpa to 0.23Mpa.
12 Ensure ACW System is started (refer doc. no. RWPL/OPR/SOP_005) & maintain CW
header pressure > 0.40Mpa.
13 Ensure CCCW System is started (refer doc no. RWPL/OPR/SOP_006) & maintain
CCCW header pressure > 0.30Mpa.
14 Ensure PAC/IAC with dryer is started (refer doc no. RWPL/OPR/SOP_002) & header
pressure > 0.65Mpa.
15 Ensure all PTW related to Boiler should be closed.
16 Ensure all boiler vents are open
17 Ensure that down comer, water wall & economizer drain are closed.
18 Ensure local drum gauge glass & hydra step in service.
19 Ensure boiler fill pump is lined up & started (refer doc. No. RWPL/OPR/SOP_022) to fill
drum up -100mm to - 150mm level (also start Hydrazine dozing by consulting to
Chemist).
20 Ensure oil gun cleaning is done & atomization test completed.
21 Ensure LDO line flushing up to oil gun completed & oil strainer cleaned.
22 Ensure LDO pump is lined up & started (refer doc. no. RWPL/OPR/SOP_004) & put in
long recirculation with discharge pressure 2.5Mpa.
23 After drum filling, start dearetor filling (by using Boiler fill pump/condensate make up
pump).
24 Ensure U valve blower, ID fan, SA fan, PA fan lined up and air path through.
Sr. Verification /
Activity Check
No Remarks
25 Ensure two U valve blower are started (refer doc. No. RWPL/OPR/SOP_043) & ensure
proper air flow to both U seal. Put third one on link mode (CV of U seal header to PA
header should be closed & in AUTO mode). Maintain discharge pressure 47KPa
26 Ensure both ID fans are started (refer doc. No. RWPL/OPR/SOP_010) & furnace draft is
between – 50 Pa to + 50 Pa.
27 Ensure both SA fans are started (refer doc. No. RWPL/OPR/SOP_011).
28 Ensure both PA fans are started (refer doc. No. RWPL/OPR/SOP_009).
Ensure loading of PA fan is increased (upto 90,000 Nm³/hr) for proper fluidization of bed
29
material & check for fluidization through view glass.
30 Ensure loading of SA fan is increased (upto 60,000 Nm³/hr).
Ensure RH side gas damper is closed & maintain 30% to 40% of rated air flow (Air flow
31
should be > 138,000 Nm³/hr).
32 Ensure economizer recirculation valve is open.
Ensure other pair of ignition duct oil gun are in service to increase the average bed
45
temperature upto 400˚C. Ignition duct outlet temperature should be less than 800˚C.
At 0.2 Mpa drum pressure, close drum & SH vents. Also close SH drain (except high
46
temp SH & platen SH outlet header drain).
Ensure DM transfer pumps are running & hot well level is normal, then start CEP
47
(refer doc.no. RWPL/OPR/SOP_008).
48 Ensure BFP is started (refer doc.no. RWPL/OPR/SOP_012).
Ensure phosphate dozing is started with consultation of DM plant
49
(refer doc.no RWPL/OPR/SOP_037)
50 Ensure at 0.3Mpa drum pressure high temperature SH outlet header drains are closed .
63 Ensure HP/LP bypass oil pump lined up & started (refer doc.no. RWPL/OPR/SOP_034).
Ensure that the opening of HP/LP bypass is increased to achieve the MS temperature
67
280˚C at 1.0Mpa pressure & RH steam temperature 220˚C at 0.2Mpa pressure
68 Ensure all RH drains are closed.
69 Check that EH oil pump is lined up & then start it (refer doc.no. RWPL/OPR/SOP_035).
After synchronization, ensure that load is raised to 10MW (@1MW/min) & warm up for 60
90
minutes.
91 Ensure economizer valve is closed at 10MW load.
Ensure that ESP is ready for charging & charge ESP when all oil gun is removed & ESP
92
inlet flue gas temperature Is greater than 110˚C.
After that ensure that load is raised to 40MW (@1MW/min) & warm up for 60 minutes (all
93
MAL drains should be closed at 30MW load).
94 Ensure that UAT is taken in service at 18MW load.
96 Ensure that turbine casing drains & MS line drains closed at 34MW load.
98 Ensure that LP drip pump is started to regulate the excess air < 7%.
Ensure MS temperature & pressure is increased as per cold start up curve & increase
99
loading of ID/SA/PA fan as per requirement.
Ensure with continuously rising temperature & pressure, load is added to rated load
100
(135 MW) @ 1MW/min.
101 Ensure that the HP heaters are charged at 50MW load.