Chapter - 7 - Sedimentation

Download as pdf or txt
Download as pdf or txt
You are on page 1of 46

2/22/2013

Chapter 7
Sedimentation
Abdel Fattah Hasan, Ph.D.
Civil Engineering Department
An-Najah National University

Environmental Engineering II

for use with


Water and Wastewater Engineering
By
Mackenzie L. Davis

Lecture Outline

 Sedimentation theory
 Sedimentation practice
 Sedimentation basin design

1
2/22/2013

Introduction
 Coagulation and flocculation
to enhance the size of particles so that they
will settle in a reasonable period of time

 Softening to remove hardness by


forming an insoluble precipitate

 Particles and precipitate are usually removed


from water by gravitational settling in a
sedimentation basin, also called a clarifier or
settling tank

Sedimentation
 Water flows into the
settling basins, where
the flow is almost
devoid of turbulence.

 The water resides


here for time periods
ranging from 2 to 8
hours and flocculated
particles settle out as
sludge
The sludge is mechanically removed periodically

2
2/22/2013

Types of Sedmentation:
 Type I: discrete particle settling

 Type II: flocculant settling

 Type III: hindered settling

 Type IV: compression settling

3
2/22/2013

Type 1 Sedimentation

 Settling as discrete particles


 No flocculation during sedimentation
 Examples
 Pre-sedimentation for sand removal prior to
coagulation in surface water treatment plant
 Settling of sand particles in filter bed after
backwashing
 Settling in grit chamber (wastewater
treatment)

Discrete settling
 Assume the particles
have a density of ρs, a FB FD
spherical volume of Vp, a
mass, mp, a cross-
sectional area of Ap.
 Assume the particle
settles at a velocity of vs.
 Assume CD is the
coefficient of drag
 Assume the density of
water is ρ FG

4
2/22/2013

Newtons’ Laws of particle settling:

Drag Coefficient (CD)


 takes on different values depending on the flow
regime surrounding the particle

 The flow regime may be characterized by Reynolds


number (R)

R > 104 CD = 0.4


R < 0.5 CD = 24/R
0.5 < R < 104

5
2/22/2013

When the drag force is equal to the driving force, the particle
velocity reaches a constant value called the terminal settling
velocity (v s)

Newton Settling Velocity

6
2/22/2013

Stokes’ law
 Assume flow is laminar (R< 1)
 So, CD = 24/R
 Then terminal settling velocity:
2
g ( ρ s − ρ )d
vs =
18 µ

where µ = dynamic viscosity of water

Example 7-1

What is the settling velocity of a grit


particle with a radius of 0.10 mm
and a specific gravity of 2.65?

The water temperature is 22 oC.

7
2/22/2013

8
2/22/2013

9
2/22/2013

Ideal sedimentation basins (Type 1)

 Assumptions
 Type 1 Settling
 Four zones in the basin: inlet, outlet,
sludge, settling
 Even distribution of flow entering and
leaving the settling zone
 Uniform distribution of particles through the
depth of the inlet zone
 Particles that enter the sludge zone are
captured
 Particles that enter the outlet zone are
removed with the water.

Zones of sedimentation

10
2/22/2013

Ideal sedimentation basins (Type 1)

 Upflow clarifiers

Ideal sedimentation basins (Type 1)

 Upflow clarifiers
 Velocity of water decreases as the water
flows upward (overflow rate = vo,
hydraulic surface loading)
Q
vo =
Ac

 Velocity of the particle remains unchanged


 If vs ≥ vo, then 100% of particles remain
in tank

11
2/22/2013

Ideal sedimentation basins (Type 1)

 Rectangular basins
 Particle removal is dependent on the
overflow rate.

 In order for particle to be removed


 Settling velocity must be sufficient so that it
reaches the bottom during the time the water
resides in the tank (td).

Ideal sedimentation basins (Type 1)

 Rectangular basins
h h hQ hQ Q Q
vs = = = = = =
to (V Q ) V l ⋅ w ⋅ h l ⋅ w As
Q
vo =
As

P= ( )100%
vs
vo

P: % of
particles
removed

12
2/22/2013

Ideal sedimentation basins (Type 1)

 A large variation in particle size will


exist in a typical suspension of
particles.
 Usually requires experimental
analysis using settling column.
 Batch settling columns
 Samples withdrawn a various times
and depths
 Solid concentrations determined
 Draw curve like that on next slide

Example (Type 1)

 A particle size distribution has been


obtained from a sieve analysis of sand
particles to be removed in a grit
chamber. For each weight fraction an
average settling velocity has been
calculated. What is the overall removal
for an overflow rate of 4000 m3/m2·day.
Settling
velocity 3.0 1.5 0.60 0.30 0.22 0.15
(m/min)
Weight fraction
remaining 0.55 0.46 0.35 0.21 0.11 0.03

13
2/22/2013

Example (Type 1)
0.6

0.5

Weight Fraction remaining

0.4

0.3

0.2

0.1

0
0 0.5 1 1.5 2 2.5 3 3.5
Settling velocity (m/min)

Example 7-2

Sleepy Hollow has an existing


horizontal-flow sedimentation tank
with an overflow rate of 17 m3/d.m 2.

What percentage removal should be


expected for each of the following
particle settling velocities in an ideal
sedimentation tank:
• 0.1 mm/s
• 0.2 mm/s
• 1 mm/s

14
2/22/2013

Type II Sedimentation
 Particles that aggregated or flocculate
during sedimentation
 Sedimentation after alum or iron
coagulation
 In wastewater during primary
sedimentation
 In settling tanks after trickling filtration
 In upper portions of secondary clarifiers
after activated sludge treatment

15
2/22/2013

Type II Sedimentation
 Causes
 Differences in settling velocities of particles
whereby faster-settling particles overtake those
that settle more slowly and coalesce with them
 Velocity gradients within liquid cause particles in
a region of higher velocity to overtake those in
adjacent stream paths moving at slower
velocities.
 Benefits
 Combination of smaller particles to make larger
particles – results in faster settling sludge
 Flocculation tends to have a sweeping effect –
faster particles tend to “sweep”

Type II Sedimentation

 No good theory
 Settling Column Model
 Want diameter sufficiently large to avoid
wall effects
 Usually 6” (~15 cm) diameter
 Height = depth of the proposed tank (or
greater)
 Sampling ports every 20 in (50 cm) or so
 % removal is plotted vs depth

16
2/22/2013

Type II Sedimentation
 Settling Column Model
 C 
% Removal = 1 - t  × 100%
 Co 

 Each intersection pt. of an isoconcentration line and the


bottom of the column defines the overflow rate, vo

H
vo =
ti

17
2/22/2013

Type II sedimentation

RTo = Ra + HH1 (Rb − Ra ) + HH2 (Rc − Rb )

The series of vo, t and R% are used to


plot 2 curves:
 R% vs t

 R% vs vo

 These can be used to size the settling


tank.
 Eckenfelder (1980) recommends that
scale-up factor:
 vo by 0.65
 t by 1.75

18
2/22/2013

19
2/22/2013

20
2/22/2013

Example (Type II Sedimentation)

The following test data were obtained


to design a settling tank. The initial
solids concentration for the test was
20.0 mg/L. Determine the detention
time and overflow rate that will yield
60% removal of suspended solids.

21
2/22/2013

Example (Type II Sedimentation

Suspended Solids Concentrations (mg/L)

Depth Time (min)


(m) 10 20 35 50 70 85
0.5 14.0 10.0 7.0 6.2 5.0 4.0
1.0 15.0 13.0 10.6 8.2 7.0 6.0
1.5 15.4 14.2 12.0 10.0 7.8 7.0
2.0 16.0 14.6 12.6 11.0 9.0 8.0
2.5 17.0 15.0 13.0 11.4 10.0 8.8

Example (Type II Sedimentation

Percent removals

Depth Time (min)


(m) 10 20 35 50 70 85
0.5 30 50 65 69 75 80
1.0 25 35 47 59 65 70
1.5 23 29 40 50 61 65
2.0 20 27 37 45 55 60
2.5 15 25 35 43 50 56

22
2/22/2013

Example (Type II Sedimentation)


20% 30% 40% 50% 60% 65% 70%
Time [min] Depth [m] Depth [m] Depth [m] Depth [m] Depth [m] Depth [m] Depth [m]
0 0 0 0 0 0 0 0
10 2 0.5 0.35 0.23 0.18 0.12 0.05
20 1.4 0.75 0.5 0.35 0.25 0.15
30 1.22 0.75 0.55 0.42 0.23
40 1.8 1.1 0.75 0.57 0.34
50 1.5 1 0.72 0.46
60 1.95 1.25 0.85 0.6
70 2.5 1.55 1.03 0.75
80 1.85 1.33 0.9

Example (Type II Sedimentation)

23
2/22/2013

Example (Type II Sedimentation)


Detention Time

69
67
65
% Removal

63
61
59
57
55
40 45 50 55 60 65 70 75
Detention time [min]

Overflow Rate

69
67
65
% Removal

63
61
59
57
55
40 45 50 55 60 65 70 75 80 85
Overflow rate [m/d]

Type III Sedimentation

 Hindered or zone
 Example: settling in lime soda ash
sedimentation, activated sludge
sedimentation, sludge thickeners
 Particles settle as a zone or blanket
 Usually have a clear interface between
the settling sludge and the clarified
effluent
 Rate of settling = f(concentration of
solids and their characteristics)

24
2/22/2013

Type IV (Compression Settling)


Settling tests are required
Rate of consolidation in region is ∝ to difference
in depth at time t and depth to which sludge
will settle after long time (24 hrs)

Models:
http://www.wastewaterhandbook.com/webpg/
th_settling_60intro.htm

25
2/22/2013

SEDIMENTATION PRACTICE

Circular sedimentation Basin

26
2/22/2013

Flocculator-clarifier provides mixing,


flocculation, & sedimentation in a
compartmented concentric circular tank

Flocculator-clarifier, plan view

27
2/22/2013

Horizontal (rectangular)
sedimentation basin

28
2/22/2013

Ballasted sedimentation

High Rate Sedimentation – Lamella Clarifier

29
2/22/2013

High-Rate Settling
Clarification process can be accelerated by:
 Increasing the particle density

 Reducing the distance a particle must fall prior to


removal

To reduce the distance the particle must fall:


 A series of inclined plates or tubes are placed in a
rectangular horizontal flow settling basin.
 The plates or tubes are inclined to a degree that
allows the collected solids to slide down the surface
to the sludge zone.
 Typically the tube is a square, about 5 cm on each
side, and the angle is about 60o

Inclined
Plates
Settler

Inclined
Tubes
Settler

30
2/22/2013

High-Rate Settling:
 Three typical configurations are named to reflect
the direction of flow of water with respect to the
direction that the particles will leave the plates or
tubes:
Countercurrent Countercurrent
Cocurrent
Crosscurrent

Cocurrent
Crosscu-
rrent

Countercurrent high rate settling:

settling time t for a particle


to move between parallel plates

31
2/22/2013

Countercurrent high rate settling:


If the trajectory of a particle that is shown
in Countercurrent settling is considered:
 All particles with a settling velocity vs will
be removed
 particles with a larger settling velocity are
also removed;

Cocurrent high rate settling:

 All particles with a settling velocity vs will be removed


 particles with a larger settling velocity are also
removed;

32
2/22/2013

Crosscurrent high rate settling:

 All particles with a settling velocity vs will be removed


 particles with a larger settling velocity are also
removed;

Non-Ideal Behavior of Settling Tanks

Numerous factors affect settling tank


performance, such as:

 Turbulence
 Inlet energy dissipation
 Density currents
 Wind effects
 Outlet currents
 Sludge equipment movement

33
2/22/2013

High rate sedimentation

SEDIMENTATION BASIN DESIGN


 Primary focus of this chapter are:
 Design of rectangular tanks
 Design of high-rate settlers

 No. of Tanks:
 Usually, 2 tanks placed together in parallel with
a common wall.
 In general, 4 tanks are preferred for maximum
flexibility in operation over a wide range of flow
rates with allowance for one unit being out of
service at the maximum flow rate, however
may result in an unacceptable capital cost.

 ST design include: inlet, settling, outlet and


sludge zones.

34
2/22/2013

Inlet Zone Design


 Preferred arrangement:
 direct connection between the flocculation basin and
the settling tank through a diffuser wall. Designed
using the same procedure that was used for baffle
walls in flocculation tanks

 Diffuser wall design criteria:


 Location: 2 m downstream of the inlet pipe.
 Headloss: 4 to 5 times the velocity head of the
approaching flow.
 Port velocities typically must be about 0.20 to 0.30
m/s for sufficient headloss.
 Holes (diffusers): 0.10 to 0.20 m in diameter
spaced about 0.25 to 0.60 m apart and evenly
distributed on the wall. The lowest port should be
about 0.6 m above the basin floor

Settling Zone Design


 Overflow rate (vo)is the primary design
parameter for sizing the sedimentation basin

35
2/22/2013

Settling Zone Design


 SWD: 3-5 m; practical minimum depth required for
sludge removal equipment, and controlling
parameter to limit scour of particles from the sludge
blanket

 L/W: min of 4:1; to provide plug flow and minimize


short circuiting

 L/D: min of 15:1

 L > 30m of open tanks is affected by wind, so:


- Wind breakers placed every 30 m
- Free board of 0.6 m is used to act as wind
barrier

Settling Zone Design


 Horizontal flow velocities (=Q/Av): 0.005-0.018 m/s.
Must be controlled to avoid:
 Turbulence (R < 20,000)
 Backmixing (Fr > 10-5)
 scour of particles from
the sludge

36
2/22/2013

Large R indicates a high degree of turbulence

low Fr indicates that water flow is not dominated


by horizontal flow, and backmixing may occur

R may be reduced and Fr increased by the


placement of baffles parallel to the direction of flow.
Baffles must be placed above the sludge collection
equipment and should be about 3 m apart

Detention time (t)

 GLUMRB (2003) recommends:


- min t of 4 h of detention time
- or an overflow rate (vo) <= 1.2 m/h

 Modern designs use t of 1.5 to 2.0 h

37
2/22/2013

Outlet Zone Design


 The outlet zone is composed of launders running
parallel to the length of the tank.
 The weirs should cover at least 1/3, and preferably
up to 1/2, the basin length
 The water level in the tank is controlled by the
end wall or overflow weirs.
 V-notch weirs are attached to the launders and
broad-crested weirs are attached to the end
wall
 Orifices may

be used on
the launders

38
2/22/2013

(Q>40,000 m3 /d)

(Q<40,000 m3 /d)

39
2/22/2013

t of Tube
settlers: 3.5-5
min.

t in parallel
plate modules:
5-20 min

40
2/22/2013

41
2/22/2013

42
2/22/2013

43
2/22/2013

44
2/22/2013

45
2/22/2013

Example (Sedimentation Design)

Two sedimentation tanks operate in


parallel in a plant used for color removal
with alum coagulation. The combined flow
to the two tanks is 0.30 m3/s. The depth
of the tank is 2.0 m and each tank has a
detention time of 1.5 hr:
 What is the surface area of each tank?
 What is the overflow rate?
 What is the weir length required?

Outcomes

Based on this lecture and Chapter 7, you


should be able to
 Describe the physical phenomena that
underlie the design and operation of
sedimentation tanks
 Design a sedimentation tank

46

You might also like