Monitoring Report 2 Crediting Period 2 Version 1
Monitoring Report 2 Crediting Period 2 Version 1
MONITORING REPORT
The project consists of two power plants, Yanacachi Norte and Chojlla, equipped with one Francis turbine-
generator unit each, of approximately 50 MW and 39 MW of capacity, respectively. A 10 km length, 115
kV overhead transmission line transports the power output of the Project’s units to Pichu substation, the
closest National Interconnected Grid node. The said two plants were completed in the framework of an
Engineering, Procurement and Construction contract implemented from 2000 and are in operation since
June 2002, being its first Crediting Period accounted from July 1st, 2002. The second crediting period, from
July 1st, 2009 to June 30, 2016, was renewed in November 2009.
The emission of 286,329 tCO2-e to the atmosphere was avoided in the period covered by this Monitoring
Report (March 01, 2011 to June 30, 2012) in accordance to the calculations done in the framework of the
version of the baseline methodology ACM0002 approved in the CDM-PDD.
Yanacachi Norte:
8188023 N, 19634973 E
Chojlla:
8185577 N,19631439 E
UNFCCC/CCNUCC
The general arrangement of the hydropower system is shown in the next figure.
UNFCCC/CCNUCC
The hydraulic scheme of the project can be seen in the diagram below.
Ta Cacapi Intake
qu 2547 m.a.s.l.
es
iR
ive
r
Chojlla Tunel
Pero
lan L= 3800 m
iR iver
chata River
Quimsa
Chojlla Penstock
L= 1200 m.
er
lan i Riv
Kho
Chojlla Power Plant
Ta 38.4 MW
qu
es 1956 m.a.s.l.
iR
ive
r
Chojlla Intake
1969 m.a.s.l.
Pressurized Channel
Yanacachi Norte Tunnel
L = 300 m
re
L= 3800 m
iv
iR
es
Weir - Forebay
qu
Ta
er
Penstock vi Riv
Undua
UNFCCC/CCNUCC
Compared to hydropower developments based on large river impoundments, run-of-river projects have
smaller footprints and a series of environmental advantages due to their reduced areas. The footprint of the
Rio Taquesi Hydroelectric Power Project is, in addition, reduced by the use of tunnels, rather than canals,
and the extreme elevation gradient of the terrain that allows sufficient hydraulic head to be created within a
short distance. Although similar technology has been used in other generating systems in the Country, the
Project encompasses features like the use of daily instead of seasonal reservoirs on the river course, tunnels
instead of canals and oil leakage prevention systems at substations for environmental reasons, for instance.
Both power plants of the project (Chojlla and Yanacachi Norte) are completely implemented and fully
operational since the end of June 2002, when they have been successfully commissioned. The Project has
been registered as a CDM Activity with 7-year renewable crediting periods, the first of which started on
July 01, 2002 and ended on June 30, 2009. The second 7-years crediting period started on July 01, 2009
and will end on June 30, 2016.
During the reporting period, the average availability index of the plants has been 83.8%, with scheduled
unavailability summing up to 14.6% and forced unavailability to 1.6% of the total period.
No events or situations with effects on the applicability of the methodology have occurred during the
reporting period.
B.2.2. Corrections
>>
None
All data mentioned above is verified and reviewed before it is used for calculations purposes. When
needed, clarifications and additional information is required. Calculation starts only when all data has been
checked.
The next diagram shows a brief graphic description of the monitoring and CERs calculation processes.
HIDROELECTRICA
BOLIVIANA S.A.
For reference purposes, HB’s metering system is shown in the figure below.
UNFCCC/CCNUCC
SERIAL 53120604
Node of the Trunk
SIEMENS SIMEAS P Integrated Grid
TRENCH AS-145/3G
600:5 A MC8 1.5% IEC 1036
4H 3E / Y
SUBSTATION
PICHU WEST
0.2 IEC 600 44-1
BURDEN 0.02VA
ABB CPB 145
69000:120 V
SF-1
0.3 ANSI
TRPIC115
7 MVA ENDE
A381-2 A380-2 115kV/25kV
MC7
SIEMENS SIMEAS P 24.9 kV
BALLEAU
1.5% IEC 1036
24941/v3:120 V
A381 4H 3E / Y
BURDEN 0.02VA
A380 ANSI 0.3
AEC
25:5 A
MP6 MP7 AEC
100:5 A
A381-1 A380-1 ANSI 0.3
AMETEK-JEMSTAR JS09R5010-11 AMETEK-JEMSTAR JS09R5010-11
ANSI 0.3
SUBSTATION
0.2 IEC 687 0.2 IEC 687
4H 3E / Y 4H 3E / Y
BURDEN 0.5VA @ 530V BURDEN 0.5VA @ 530V
SERIAL 023201485 SERIAL 02 04 01046
PICHU EAST HB
SIEMENS SIMEAS P ABB SIEMENS SIMEAS P
69000:120 V 1.5% IEC 1036
1.5% IEC 1036 ANSI 0.3
A382-1 4H 3E / Y 4H 3E / Y
BURDEN 0.02VA A383-1 D380 R
BURDEN 0.02VA
SERIAL 012300419 SERIAL 012300420
A382 A383
MC3 MC6
S-1 25kV/400V
Líne 24,9 kV
ALSTOM MP2 MP4 ALSTOM SEYSA
400:5 A
IEC 0.2
400:5 A
IEC 0.2
1f MC09
AMETEK-JEMSTAR JS09R5010-11 AMETEK-JEMSTAR JS09R5010-11
CJL-PIC024
A382-2 0.2 IEC 687
4H 3E / Y
0.2 IEC 687
4H 3E / Y
A383-2
BURDEN 0.5VA @ 530V BURDEN 0.5VA @ 530V Local Service
SERIAL 01 23 00419 SERIAL 01 23 00420 S/E Pichu
SF-1 SF-2
YAN-PIC115
CHJ-PIC115
ITRON
SF-1 SF-2 ACE 6000 400 kVA
SERIAL 55068029 MC10 3 f 24.9kV/400V
SERIAL 2006338411
3X50:5 A
MC11
SWB-01
PT-PM-1/2/3
3X24.9kV/0.12kV
Workshop HB Enramada Mine
A384-1 A385-1
SF-1
A384 A385 D381
SIEMENS SIMEAS P SIEMENS SIMEAS P
1.5% IEC 1036 1.5% IEC 1036
4H 3E / Y 4H 3E / Y
BURDEN 0.02VA MC2 ALSTOM 1_410_648_P389A
300:5 A
BURDEN 0.02VA MC5 ALSTOM 1_410_648_P389A
300:5 A
SERIAL SA-0001A027-02 SERIAL SA-007A070-10
C400 ANSI
ABB CPB 145
C400 ANSI
ABB CPB 145
TRCJL024 SEL 734 IMCO
0.2 ANSI C 12.20
1.25 MVA
69000:120 V 69000:120 V
0.3 ANSI 0.3 ANSI
SEL 734 G2 SERIAL 2008232368
TRCHJ115 2.3 kV/24.9 kV 2.3 kV 0.2 ANSI C 12.20 1800 kVA
TRYAN115 SERIAL 2.4kV / 4.16kV
40.8 MVA 2006338410 MP11
58.7 MVA
115kV/11.5kV SEL 734 G1
3X300:5 A
115kV/11.5kV 0.2 ANSI C 12.20
MP8 MP9
SEL 734 CPH BITRONICS MTWIE1 B SIEMENS SIMEAS P SERIAL SWG-01 SWG-02
0.2 ANSI C 12.20 0.25 ANSI 460 SIEMENS SIMEAS P SEL 734 YPH BITRONICS MTWIE1 B PT-PM-1/2/3 PT-PM-1/2/3
1.5% IEC 1036 0.25 ANSI 460
1.5% IEC 1036 2006338412 3X2.4kV / 120V 3X2.4kV / 120V 2.4kV / 0.12kV
SERIAL 4H 3E / Y
BURDEN 0.02VA 4H 3E / Y
0.2 ANSI C 12.20
SERIAL 4H 3E / Y
4H 3E / Y
BURDEN 0.02VA
4.16 kV REFERENCE
BURDEN 0.02VA BURDEN 0.02VA
2008232369 SERIAL 706871
2008232367 SERIAL 706872
SERIAL SA-9807 A 70-10 SWG-01
CTM-1/2/3
SWG-02
CTM-1/2/3 115 kV
TRSACHJ TRSAYAN
E384 500kVA E385 500kVA
3X100:5 A 3X200:5 A IMCO Mine 25 kV
11.5kV/400V 11.5kV/400V
< 12 kV
MP11 MC12 ISOLET BDI 06 MC1 MP12 MC13 ISOLET BDI 06 MC4 G381 G382 < 0.6 kV
3000:5 A 4000:5 A
0.3 C 12.5 0.3 C 12.5
SCHLUMBERGER JIF-D2 SCHLUMBERGER JIF-D2
ISOLET BDE FF16 03 07 800:5 A ISOLET BDE FF16 03 07 800:5 A
MC CONTROL meter
12000:120 V C107 ANSI 12000:120 V C107 ANSI
0.6 P 75 SERIE SA-0003A007-02 0.6 P 75
TREXCCHJ
AUX. SERV.
SELM
380:120 V TREXCYAN
AUX. SERV.
SELM
380:120 V
N/D
CJL01 G1 CJL02 G2 MP PRECISION meter
Data/Parameter EFgrid,BM,y
Unit tCO2/MWh
Description Build Margin CO2 emission factor for grid connected power generation in
year y
Source of data IPCC 2006 and CNDC’s monthly reports
Value(s) applied 0.60
Purpose of data The data are used for the calculation of baseline emissions.
Additional comment According to the Methodological Tool (version 01.1), for the second
Crediting Period, the Build Margin emission factor is calculated ex-ante,
based on the most recent information available on units already built for a
sample group m at the time of CDM-PDD submission for validation.
Data/Parameter EFCO2,i,y
Unit tCO2/BTU
Description CO2 emission factor per unit of energy of the fuel type i in year y for the
Build Margin
Source of data IPCC 2006
Value(s) applied Natural Gas: 5.72E-08 [tCO2/BTU]
Diesel Oil: 7.66E-08 [tCO2/BTU]
Purpose of data The data are used for the calculation of baseline emissions.
Additional comment The CO2 emission factor per unit of energy of the fuel type i in year y can
vary for the Operating Margin, which will be estimated ex-post, but will not
change for the Build Margin, which is to be maintained unchanged during
the Second Crediting Period
UNFCCC/CCNUCC
Data/Parameter EGPJ, h
Unit MWh
Description Electricity displaced by the Project activity in hour h of year y
Measured/Calculated Calculated
/Default
Source of data Metering system readings and logbooks.
Value(s) of monitored 452,317
parameter
UNFCCC/CCNUCC
Monitoring equipment
Type SEL-734 SEL-734 SEL-734 SEL-734
(Chojlla) (Yanacachi) (Chojlla (Chojlla
Antigua 1) Antigua 2)
Accuracy 0.2 S 0.2 S 0.2 S 0.2 S
Serial 2008232369 2008232367 2006338412 2006338410
number
Calibration 3 - 4 years 3 - 4 years 3 - 4 years 3 - 4 years
frequency
Date of last September August 27, December December
calibration 2, 2008; 2008; 18, 2006; 12, 2006;
August 31, September June 08, June 09,
2010 01, 2010 2011 2011
Validity 4 years 4 years 4 years 4 years
Type SEL-734 SEL-734
(Chojlla (Chojlla
Antigua 1) Antigua 2)
(*) (*)
Accuracy 0.2 S 0.2 S
Serial 2008232368 2006338411
number
Calibration 3 - 4 years 3 - 4 years
frequency
Date of last August 28, May 30,
calibration 2008; 2008;
April 18, August 31,
2011; 2010
Validity 4 years 4 years
Type JEMSTAR JEMSTAR JEMSTAR ITRON
(Chojlla in (Yanacachi (Chojlla (HB in
Pichu) in Pichu) Antigua Chuspipata )
1&2 in
Pichu)
Accuracy 0.2 S 0.2 S 0.2 S 0.2 S
Serial 012300419 012300420 023201485 53120604
number
Calibration 3 years 3 years 3 years 3 years
frequency
Date of last September September February April 26,
calibration 17, 2008; 17, 2008; 12, 2007; 2012
August 30, August 30, August 30,
2010 2010 2010
Validity 3 years 3 years 3 years 3 years
(*) These meters were used from March 01, 2011 to March 18, 2011.
Measuring/Reading/ Measured continuously, recording hourly, aggregated monthly
Recording frequency
UNFCCC/CCNUCC
Calculation method HB’s injections at node of the Trunk Integrated Grid for HB, where its
(if applicable) billing is referred to, are measured through the Commercial Recording
System. The injections of HB’s non-Project’s sources is calculated
following the procedure described below:
1. Gross production measured at each generator terminals through HB’s
metering systems is used, including the Chojlla Antigua (HB’s non-
Project power source).
2. Project’s gross production is divided by the total gross production to
get the proportion of Project’s generation of the total injections.
3. The above proportion is applied to the node (of the Trunk Integrated
Grid) records from monthly SMEC for getting the Project’s injection at
that node.
QA/QC procedures Double check by audit of sales receipt. Sales are calculated by the CNDC
and reported in the Monthly Economic Transactions Report (DTE by its
acronym in Spanish). The Project’s metering system complies with
technical specifications and CNDC standards. Registered information is
compared to the information on the DTE. To prevent the use of energy
from Chojlla Antigua for the emission reduction calculations, Project
injections should be lower than those resulting from the energy balance
done with monthly SMEC’s data to calculate HB’s chargeable energy (for
the periods in which Chojlla Antigua effectively injects power to the grid).
Purpose of data Data is used for the calculation of baseline emission.
Additional comment The ITRON meter (HB in Chuspipata) was operating since May 01, 2012.
UNFCCC/CCNUCC
Data/Parameter EGm/n/y
Unit MWh
Description Net electricity generated and delivered to the grid by power plant/unit m or
n in year y or hour h
Measured/Calculated Calculated
/Default
Source of data Metering system readings
Value(s) of monitored Due to space restrictions, please refer to Table E.1
parameter
Monitoring equipment Due to space restrictions, please refer to Table 1, Annex 1.
Measuring/Reading/ Measured continuously, recording hourly, aggregated monthly
Recording frequency
Calculation method Measurement of energy injected by sets of units in a given plant is done
(if applicable) through the Commercial Recording System (SMEC), a meters’ system
remotely accessed from the CNDC premises.
Energy injections per generating unit are available at CNDC’s DTrs.
The DTr provides the individual estimated energy of each thermal power
source and is used to determine the generation delivered to the grid by each
thermal source according the CNDC’s monthly SMEC registries.
For OM, the data is monthly measured y and yearly recorded.
For BM, in the second crediting period, only once, ex-ante at the start of the
second crediting period.
QA/QC procedures Commercial metering and recordings of generation is used. The QA/QC
procedures consist of verifying whether the data is used by the CNDC for
transactional purposes related to the electricity market.
Purpose of data The data are used for the calculation of baseline emissions
Additional comment
UNFCCC/CCNUCC
Data/Parameter NCVi
Unit Natural Gas: BTU/ft3
Diesel oil: BTU/l
Description Net calorific value (energy content) of fossil type i in year y
Measured/Calculated Measured
/Default
Source of data Monthly information reported in the CNDC’s web page.
Value(s) of monitored Natural gas:
parameter PLANT NCV
Guaracachi 926 BTU/ft3
Karachipampa 973 BTU/ft3
Aranjuez 973 BTU/ft3
V. Hermoso 916 BTU/ft3
Carrasco 915 BTU/ft3
Kenko 946 BTU/ ft3
Bulo Bulo 921.2 BTU/ ft3
Entre Rios 923.6 BTU/ ft3
Diesel oil:
PLANT NCV
Aranjuez 33,710 BTU/l
Data above is given only as an example for March, 2011. NCV can vary
depending on the quality and properties of the fuel.
Monitoring equipment Not available
Measuring/Reading/ For OM, the data is monthly monitored and yearly recorded.
Recording frequency For BM, in the second crediting period, only once ex-ante at the start of the
second crediting period and yearly recorded.
Calculation method Not available
(if applicable)
QA/QC procedures Only official information made available by the CNDC is used.
Purpose of data The data are used for the calculation of baseline emissions.
Additional comment
UNFCCC/CCNUCC
Data/Parameter m,y
Unit Not available
Description Average net energy conversion efficiency of power unit m in year y
Measured/Calculated Not applicable
/Default
Source of data Use either:
Document manufacturer’s specifications (if the efficiency of the plant
is not significantly increased through retrofits or rehabilitations); or
Data from the utility, the dispatch center or official records if it can be
deemed reliable: or
The default values provided in the table in Annex 1: Default efficiency
factors for power plants of Methodological tool (version 01) “Tool to
calculate the emission factor for an electricity system”
Value(s) of monitored Not applicable
parameter
Monitoring equipment Not applicable
Measuring/Reading/ Recording and monitoring is made only once for the crediting period.
Recording frequency
Calculation method
(if applicable)
QA/QC procedures If the data used is significantly lower than the default value of the
applicable technology, project proponents should assess the reliability of
the values, and provide appropriate justification if deemed reliable.
Otherwise, the default values above shall be used.
Not applicable for the Project.
Purpose of data The data are used for the calculation of baseline emissions.
Additional comment
1. Calculation of the Emission Factor Operating Margin (EFgrid, OM, y) is done using the Dispatch Data
Analysis, based on data on fuel consumption and net electricity generation of each power plant/
unit (Option C of the Tool to calculate the emission factor for an electricity system. Version 01,
Annex 12 of EB 35 report). The main source of information is the Load Dispatch National
Committee (CNDC by its short form in Spanish) whose objective is to manage the Wholesale
Electrical Market in the Interconnected Grid to assure reliability, security and minimum cost. The
Dispatch Data OM emission factor is the weighted average emission rate of the generating units at
the top of the merit order that produce ten percent of total system generation, varying at each hour,
accumulated for each hour and averaged over the hours of the year during which the Project
operates. To determine this, it is to be obtained: i) the grid system dispatch order of operation
(merit order) for all power plants; ii) the energy (MWh) dispatched from each plant during each
hour that the Project activity is operating, and (iii) data necessary to calculate the emission factor
for each unit in the system, mainly:
The calculation requires hourly data for those hours when the Project produces electricity. The mean
Operating Margin Emission Factor for the monitoring period is 0.73 tCO2/MWh.
EG PJ , h EFEL , DD , h
EFgrid ,OM DD , y h
(1)
EGPJ , y
Where: EFgrid, OM-DD, y is the dispatch data analysis operating margin CO2 emission factor in year y
(tCO2/MWh),
EGPJ, h is the electricity dispatched by the project activity in hour h of year y (MWh),
EFEL, DD, h is the CO2 emission factor for the power units in the top of the dispatch order in
hour h in year y (tCO2/MWh),
EGPJ, y is the total electricity displaced by the project activity in year y (MWh),
h, refers to the hours in year y in which the project activity is displacing grid electricity
y, year in which the project activity is displacing grid electricity.
According to the methodology used, if hourly fuel consumption data is not available, then the
hourly emissions factor is calculated based on the energy efficiency of the power unit and the type
of fuel used, as follows:
EG EF n,h EL , n , y
EFEL , DD, h n
(2)
EG n,h
n
Where: EFEL, DD, h is the CO2 emission factor for power units in the top of the dispatch order in
hour h in year y (tCO2/MWh),
EGn, h is the net energy generated and delivered to the grid by power unit n in hour h
(MWh),
EFEL, n, y is the CO2 emission factor of power unit (n) in year y (tCO2/MWh),
n, power units in the top of the dispatch,
h, hours in year y in which the project activity is displacing grid electricity.
The CO2 emission factor of the power units (n) should be determined as per the guidance for the
simple OM method, using the options B1, B2 or B3. According to the data and parameters
available in the Bolivian power system, option B1 is used to calculate the CO2 emission factor
(EFEL, n, y).
Option B1. If for a power unit m data on fuel consumption and electricity generation is available,
the emission factor (EFEL, m, y) should be determined as follows:
FC i , m, y NCVi , y EFCO 2, i , y
EFEL , m , y i
(3)
EGm , y
UNFCCC/CCNUCC
Where: EFEL, m, y is the CO2 emission factor for power unit m in year y (tCO2/MWh),
FCi, m, y is the amount of fossil fuel type i consumed by power unit m in year y (Mass or
volume unit),
NCVi, y is the net calorific value (energy content) of fossil fuel type i in year y (GJ/mass or
volume unit),
EFCO2, I, y is the CO2 emission factor of fossil fuel type i in year y (tCO2/GJ),
EGm, y is the net quantity of electricity generated and delivered to the grid by power unit m
in year y (MWh),
m, all power units serving the grid in year y except low-cost / must-run power units
i, all fossil fuel types combusted in power unit m in year y,
y, either the three most recent years for which data is available at the time of submission of
the CDM-PDD to the DOE for validation (ex ante option) or the applicable year during
monitoring (ex post option), following the guidance on data vintage in step 2 of the
baseline methodology procedure.
In this case “m” is replaced by “n”, in order to apply it in the dispatch data analysis OM method.
To determine the set of plants (n), the CNDC provides: a) the grid system dispatch order of
operation for each power plant of the system; and b) the energy (MWh) dispatched from all plants
in the system during every hour that the Project is operating (EGh). Every hour h, each plant’s
generation (EGh) is stacked using merit order. The set of plants (n) consists of those plants at the
top of the stack (i.e., having the least merit), whose combined generation (ΣEGh) comprises 10% of
the total generation from all plants during that hour.
2. Calculation of the Build Margin Emission Factor (EFgrid, BM, y). In the second crediting period, the
ex-ante approach is used for calculating the Build Margin emission factor based on the most recent
information available on plants already built. The group used consists of those power plants whose
capacity additions represent the 20% of the total system generation (in MWh). In the case of the
Bolivian power system, the generation of the five power plants that have been built most recently is
lower than the injections of those capacity additions in the electricity system that comprise 20% of
the system’s annual energy. The resulting EFgrid, BM, y, is 0.60 tCO2/MWh.
The build margin emission factor is the generation-weighted emission factor (tCO2/MWh) of all
power units m during the most recent year y for which power generation data is available,
calculated as follows:
EG EF
m, y EL , m , y
EFgrid , BM , y m
(4)
EG
m
m, y
Where: EFgrid, BM, y is the build margin CO2 emission factor in year y (tCO2/MWh),
EGm, y is the net quantity of electricity generated and delivered to the grid by power unit in
year y (MWh),
EFEL, m, y is the CO2 emission factor of power unit m in year y (tCO2/MWh),
m, refers to the power units included in the build margin,
y, most recent historical year for which power generation data is available
The CO2 emission factor of each power unit m (EFEL, m, y) should be determined as per the guidance
for the simple OM method of operating margin emission factor, with options B1, B2 and B3, using
for y the most recent historical year for which power generation data is available, using for m the
power units included in the build margin.
UNFCCC/CCNUCC
3. Calculation of the Combined Margin Emission Factor (EFgrid, CM, y). The Combination Margin
Emission Factor (or the Baseline Emission Factor as indicated in the older Version 06) is
calculated as follows:
During the current second crediting period, the next weights are used:
wOM = 25% and wBM = 75% (i.e., wOM = 0.25 and wBM =0.75)
Total 8,702.60 1,002.84 452.317 65,771.07 14,930.10 699,262.95 42,072.58 1,467.81 329,943.23 0.73
TABLE A3. Build Margin, Second Crediting Period "ex ante". Additions represents 20% of the system generation
N O P Q R S T U V
Starting Year Type Generation Fuel Consumption Net Cal Value Conver Factor Fuel Consumption Carbon Content Emissions BM Emission Factor
GWh MMFt3 BTU/Ft3 TJ/BTU TJ tC/TJ tCO2/tC tCO2/TJ tCO2/MWh
( ∑ EG m,y · EF EL,m,y ) / ∑ EG m,y
=(O*P*Q*1000000) IPCC, 2006 =(S*T) =(R*U/N)/1000
ARJ13 Aug/2008 Nat Gas 2.01 22.35 977.87 1.0548E-09 23.05 14.80 3.67 54.27 0.62
ARJ14 Aug/2008 Nat Gas 2.56 27.66 977.87 1.0548E-09 28.53 14.80 3.67 54.27 0.61
ARJ15 Aug/2008 Nat Gas 1.75 18.37 977.87 1.0548E-09 18.95 14.80 3.67 54.27 0.59
ANG3 Aug/2008 Hydro 1.83
GBE1 Oct/2007 Biomas 39.40
QHE2 Oct/2007 Hydro 1.64
QHE1 Oct/2007 Hydro 1.64
GCH11 Apr/2007 Nat Gas 370.41 4,315.42 960.99 1.0548E-09 4,374.34 14.80 3.67 54.27 0.64
ARJ9 Aug/2006 Nat Gas 10.30 113.71 977.87 1.0548E-09 117.29 14.80 3.67 54.27 0.62
ARJ10 Aug/2006 Nat Gas 10.40 115.19 977.87 1.0548E-09 118.81 14.80 3.67 54.27 0.62
ARJ11 Aug/2006 Nat Gas 10.28 113.93 977.87 1.0548E-09 117.52 14.80 3.67 54.27 0.62
ARJ12 Aug/2006 Nat Gas 7.67 85.76 977.87 1.0548E-09 88.46 14.80 3.67 54.27 0.63
SRO2 Jul/2006 Hydro 30.78
SRO1 Jul/2006 Hydro 34.69
SIS5 May/2004 Hydro 116.62
CHJ3 Jun/2002 Hydro
YAN1 Jun/2002 Hydro
LAN3 Mar/2001 Hydro 10.18
KIL3 Mar/2001 Hydro 18.00
BUL1 Jun/2000 Nat Gas 312.34 3,021.09 926.20 1.0548E-09 2,951.48 14.80 3.67 54.27 0.51
BUL2 Jun/2000 Nat Gas 300.75 2,909.38 926.20 1.0548E-09 2,842.35 14.80 3.67 54.27 0.51
Average 0.63 .
TOTAL Mar 01, 2011 - Jun 30, 2012 88.40 452.317 67.6% 0.63 286,329
UNFCCC/CCNUCC
E.4. Summary of calculation of emission reductions or net anthropogenic GHG removals by sinks
Baseline Emission
Project emissions
emissions or reductions or net
or actual net
Time Period baseline net Leakage anthropogenic
GHG removals
GHG removals (tCO2e) GHG removals
by sinks
by sinks by sinks
(tCO2e)
(tCO2e) (tCO2e)
Total 286,329 0 0 286,329
E.5. Comparison of actual emission reductions or net anthropogenic GHG removals by sinks with
estimates in registered PDD
Values estimated in ex-ante Actual values achieved during
Item
calculation of registered PDD this monitoring period
Emission reductions or GHG March 2011-June 2011: 60,801 March 2011-June 2011: 74,650
removals by sinks (tCO2e) July 2011-June 2012: 189,001 July 2011-June 2012: 211,679
Total: 249,802 Total: 286,329
The larger energy produced is due to the better water availability. For projection purposes, in the PDD a
figure of 409.51 GWh was used as a forecast for the electricity injections to the grid. The current
monitoring period reveals that Project’s injections to the grid sum up to around 450 GWh.
TABLE E.6.1: RIO TAQUESI HYDROELECTRIC POWER PROJECT: Summary of energy injected to
the grid [GWh]
The fact that the emission factor for the operating margin was different from that projected in the PDD is
also important while explaining the differences between the PDD expected and the actual calculated
emission reductions. The said emission factor was affected by the addition and operation of thermoelectric
units. These were more predominant in the daily dispatch for the current monitoring period than that
expected while producing the PDD, with the consequent variation of the operating margin and also the
combined emission factor.
UNFCCC/CCNUCC
TABLE E.6.2: RIO TAQUESI HYDROELECTRIC POWER PROJECT: Summary of mean Emission
Factor values [tCO2-e].
-----