Doc. No.

BK91-1331-BSC-870-MEF-DAS-0001
DATA SHEET FOR DIESEL TANK
(BSC-830-V-01/02/03) Revision A

Date of Issue
13/01/2023
-

Page 1 of 6

EPCC for B9 Camp Electrical System Upgrade

DATA SHEET
FOR
DIESEL TANK(BSC-830-V-01/02/03)

Document No: BK91-1331-BSC-870-MEF-DAS-0001

A ISSUED FOR APPROVAL 13/01/2023 DV. VKNA. A. Rajan. Egor Sirotsin

REV. DESCRIPTION DATE PREP'D CHK'D REV'D APP'D


Doc. No. BK91-1331-BSC-870-MEF-DAS-0001
DATA SHEET FOR DIESEL TANK
(BSC-830-V-01/02/03) Revision A

Date of
13/01/2023
Issue -

Page 2 of 6

REVISION DESCRIPTION SHEET

Rev. Page Date Reason for Revision

A 6 13/01/2023 Issued for Approval

NO. Page Para. Modifications


Doc. No. BK91-1331-BSC-870-MEF-DAS-0001

DATA SHEET FOR DIESEL TANK Revision A

(BSC-830-V-01/02/03)
Date of
13/01/2023
Issue -

Page 3 of 6

1 Equipment Name: Diesel Tank


2 Tag Number: BSC-830-V-01/02/03 PO Number:
3 Quantity: 3 Manufacturer:
4 Operating and Design Conditions
5 Design Code: ASME Sec. VIII Div. 1 Design Life: Years 25
o
6 Service: Diesel Ambient Temperature: C Min.-5 Max.55
o o
7 Operating Temperature: C 15~50 Min. Design Metal Temperature: C -5
8 Operating Pressure: kPag ATM Medium: Sweet Sour Lethal Wet H2S
o
9 Design Temperature: C 200 Location: Indoor Outdoor Underground
10 Design Pressure: kPag ATM Under Shed: Yes No
3
11 Density: kg/m 836 Vessel Type: Horizontal Vertical
12 Inside Diameter: mm 2800 Head Type: 2:1 Semi-Ellipse Other Type
13 Shell Length Tan to Tan (m) mm 10500 Thickness (Shell/Head): mm By Vendor
3
14 Capacity: m 70 Insulation Thickness: mm N/A
15 Corrosion Allowance: mm Shell: 2, Head: 2, Nozzles: 2 Net Weight: kg By Vendor
16 Max. Design Wind Speed: m/s 45 Full of Water Weight: kg By Vendor
17 IBC Site Class D, Operating Weight: kg By Vendor
Seismic Design: --
18 SS=0.3g, S1=0.1g Joint Efficiency (Shell/Head): -- 0.85/0.85
19 Importance Factor: -- I=1.25 Support -- Saddle
20 Max. Allowable Working Pressure: MPag By Vendor
21 Materials
22 Code: ASME Sec. II Jacket Shell: N/A
23 Shell: SA 516 Gr.70 Jacket Head: N/A
24 Head: SA 516 Gr.70 Shell Body Flange: N/A
25 Nozzle (Pipe): SA 106 Gr.B Shell Body Flange Gasket: N/A
26 Nozzle (Plate) / RF Pad: SA 516 Gr.70 Insulation : N/A
27 Nozzle (Forged): SA-105 Insulation Supports/Clips: N/A
28 Flange: SA-105 Saddle: SA-36 / SA 516 Gr.70
29 Backing Plate Welded to Shell: SA 516 Gr.70 Internals: SA-36
As per
30 Bolts: BK91-1101-GEN-999-MEC-SPC-0002
Earthing Boss: SS 304

As per
31 Nuts: BK91-1101-GEN-999-MEC-SPC-0002
Name Plate: SS 304

32 Sacrificial Anodes: N/A Separation Packings: N/A


Nonmetallic Flat Gaskets, Non-
33 Gasket: Stairs, Handrails Platform SA 36 Galvanized
asbestos
34 Internal and External Attachments
35 Type of Support: Saddle Skirt Leg Mist Eliminator Yes No

36 Manway with Davit/Hinge: Yes No Separation Packings: Yes No

37 Vortex Breaker: Yes No Skid Mounted: Yes No

38 Insulation Supports/Clips: Yes No Ladder,Hand Railing& Platform: Yes No

39 Desanding device: Yes No Inner Ladder: Yes No

40 Lifting Lugs: Yes No Sacrificial Anodes: Yes No


41 Earthing Lug ( 2 Nos. ) YES Inlet Pipe / Dip pipe YES
42 Name Plate YES Platform support clip YES
Doc. No. BK91-1331-BSC-870-MEF-DAS-0001
DATA SHEET FOR DIESEL TANK
Revision A
(BSC-830-V-01/02/03)
Date of
13/01/2023
Issue -

Page 4 of 6

1 Fabrication and Testing Requirements


2 Fabrication Code: ASME Sec.VIII Div.1, 2013 EditionImpact Test: As per Code

3 NDE Code: ASME SEC. V 2013, Edition Hydraulic Test Pressure: As per ASME Sec Ⅷ Div Ⅰ UG99(b)

4 Welding Code: ASME SEC. IX, 2013 Edition Stress Relief (PWHT): Not required
5 Non-destructive Testing Hardness Test: As per Code
As per BK91-1101-GEN-999-
6 Ultrasonic As per code Internal Coating: CPT-SPC-0001
As per BK91-1101-GEN-999-
7 Magnetic particle inspection (MPI) As per code External Painting & Coatings: CPT-SPC-0002
8 Dye penetrate inspection (DPI) As per code Code Stamp Required: Yes No
9 Radiography Spot Third Party Inspection: Yes No
10
11 Nozzle Schedule
12 Flange
Nozzle Mark Qty. Size Service
13 Rating Type Face
14 N1 1 4" 150# WN RF Inlet
15 N2 1 6" 150# WN RF Gauge Hatch
16 N3 1 2" 150# WN RF Vent
17 N4 1 2" 150# WN RF Outlet
18 N5 1 2" 150# WN RF Drain
19 N6a/b 2 2" 150# WN RF LG
20 N7 1 2" 150# WN RF TG
21 N8 1 2" 150# WN RF Level Switch
22 MW1/2 2 24" 150# WN RF Manway with With blind flange and davit assembly.
23 The nozzle flange code is ASME B16.5.
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
Doc. No. BK91-1331-BSC-870-MEF-DAS-0001
DATA SHEET FOR DIESEL TANK
Revision A
(BSC-830-V-01/02/03)
Date of
13/01/2023
Issue -

Page 5 of 6

1 Notes
2 1 Vendor to complete this data sheet and shall confirm the materials listed above.
3 2 Reference P&ID: BK91-1101-BSC-830-PRO-UID-0001.
4 3 Applicable Specifications:
5 BK91-1101-GEN-999-MEC-SPC-0002 Specification for Welded Pressure Vessels,
6 BK91-1101-GEN-999-MEC-SPC-0003 Specification for Equipment Welding,
7 BK91-1101-GEN-999-MEC-SPC-0004 Specification for Stairs, Handrail, Platform etc.
8 4 All dimensions are in mm.
9 5 Lifting Lug impact design factor shall be 2.0.
10 6 Shell stiffeners shall be continuous welded on both sides. No stitch weld.
11 7 All "Hold" marks shall be provided in next stage.
12 8 Nozzle location, projection and orientation shall be provided in next stage.
13 9 Dimension 100 at N4 above bottom is considered to collect clean diesel in tank, because a small quantity of particles
14 and water may be separated and deposited at the bottom during storage.
15 10 All Dimensions are in mm unless otherwise specified.
16 11 Bolt holes in flanges shall straddle main center line of vessel.
17 12 Vendor shall provide lifting trunnion / Lifting Lug.
18 13 All carbon steel plates shall be fully killed.
19 14 All flanges shall be as per ASME B16.5. Flange gasket face shall have 125 to 250 AARH finish.
20 15 All vessel external surface shall be painted as per Project Painting Specifications.
21 All platform gratings ladder, handrail, structural bolts shall be hot dip galvanized.
20 16 Vendor shall provide bolts and gaskets for all man way and nozzle with blind flange.
21 17 Equipment shall be cleaned and dried after hydro-test
22 18 Venting requirement shall cater for maximum nitrogen inflow rate while line purging
23 19 Grade of Stainless steel used shall be 316L
24 20 All attachments on the Shell|Head shall be same as that of the Shell/Head material
25 21 Washers shall be provided under all nuts and bolt heads
26 22 Potable Water shall be used for Hydro test.
27 23 Any tank nozzle not connected to the piping system or appurtenance shall be closed with blind flange.
28 24 Gaskets used for Hydro test shall be same as service gaskets.
29 However Service gaskets shall not be used for Hydro test.
30 25 Nozzle <= 2” shall be stiffened with 40 wide x 6 thk plates at 90 degrees apart.
31 26 All materials used for pressure components shall be normalized
32 27 Pressure bearing components and load bearing members with thickness’ <50mm
33 shall be certificated in accordance with EN 10204 3.1
34 28 Pressure bearing components and load bearing members with thicokness >=50mm
35 shall be certificated in accordance with EN 10204 3.2
26 29 Other non-pressure bearing components shall be certificated in accordance with EN 10204 2.2
Doc. No. BK91-1331-BSC-870-MEF-DAS-0001
DATA SHEET FOR DIESEL TANK
Revision A
(BSC-830-V-01/02/03)
Date of
13/01/2023
Issue -

Page 6 of 6

1 Attached Drawing
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25 BSC-830-V-01/02/03
26 Above shown figure is indicative only and shall not restrict the design.
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42

You might also like