Inverter Reliability Final
Inverter Reliability Final
Reliability of large-scale PV
plants and PV inverters
Inverter reliability | The renewable energy market is currently booming, with large numbers of
PV systems being installed throughout the world. However, a primary objective of any PV power
system is to ensure that the system operates continuously and reliably. As Vicente Salas from the
Universidad Carlos III de Madrid (UC3M) explains, this aspect takes on special relevance in the
case of utility-scale PV projects
R
eliability is a key risk in any project, For large-scale PV plants, financing is Figure 1. Inverter The non-functioning of some element
including PV plants, but the risk very important and complex, and involves reliability is a vital of the plant is a sensitive issue from the
aspect of ensur-
is more significant in the case of many different parties, including develop- financial point of view. The PV inverter
ing the expected
large-scale PV plants, where the cost of the ers, landowners, utilities, grid operators, performance of a is always a critical component in the PV
project is high. In those projects, where government agencies and financing institu- PV power plant. system, and for many years the inverter was
the typical design target lifetime is around tions. PV projects are a financial investment, one of the components most responsible
25–30 years, there is a discrepancy between which means they are all about returns. for failures. Fortunately, PV inverters have
the lifetime of the PV inverters (5–10 years) Additional operations and maintenance improved, thanks above all to the advances
and of the PV modules (20–25 years). In related to PV inverters, however, can erode made in power electronics, and today these
addition, while inverter interconnection, returns. products are more reliable. To increase
performance and safety standards exist, As shown in Fig. 2, many tasks – both availability and secure maximum return
there are no well-established reliability technical and non-technical – are involved on investment, a PV system requires high
standards. A reliability evaluation (simula- in the financing process of any PV plant; PV inverter reliability in order to reduce
tion and test) must be carried out in order the plant viability is linked not just to the downtime and ensure regular power
to observe failures of PV inverters and to technical tasks but to all the tasks as a generation.
better understand their failure modes and whole. The objectives of any utility-scale PV PV module technology has also
lifetime characteristics. From this it will be project include: continued to improve: the robustness of
possible to guarantee the lifetime of the • Establishing a trade-off between risk modules is evidenced by the standard
inverter. Clearly, PV inverter reliability has management and crisis management. 20- to 25-year warranties that accompany
an impact on life cycle cost, and is therefore • Implementing a long-life power plant, most PV modules today. Thus, it is reason-
an important aspect to address. with high energy yield and availability. able to expect that the PV system inverters
of age-related component failures [2]. and is even more critical in the case of a PV
In a reliability management process, the inverter, which may be required to endure
PV inverters should be designed to last both extremely hot and extremely cold
the entire life cycle (up to 30 years) of the ambient temperatures and daily tempera-
product; this process should begin with an ture variations of 30°C or more. Thermal
initial checklist of requirements, and finish management in commercial PV-powered
with an evaluation of operation in the field. inverters is accomplished by means of a
As shown Fig. 5, the reliability manage- fully integrated mechanical design that
ment process must <AQ4>take place in is simple and reliable and which delivers
parallel with other company processes, exactly the cooling that is required to each
such as product definition, development, part of the system. Forced convection
manufacturing and customer service (field cooling is used because it provides superior
deployment). cooling performance at a lower cost, and
The reliability management process with less mechanical complexity, than other
utilises individual sub-processes from other types of cooling (e.g. liquid cooling).
processes, but at the same time adds or
superimposes unique and challenging Reliability evaluation
elements (e.g. stringent qualification and Figure 4. Failure percentages of the most fragile components A reliability analysis during the design and
test procedures for materials, products and of electronic power systems. (Taken from an industry survey development of such complex equipment
processes, as well as advanced methods [2].) as a PV inverter is important in order to
and tools for failure analysis). teristics. The procedure involves a focused detect and eliminate reliability weaknesses
examination of failure point locations as early as possible and to perform
Reliability approach which takes into account the fabrication comparative studies. Different reliability
The reliability approach involves a physics- technology, process, materials and circuit evaluation techniques exist for PV systems:
based multi-level analysis and identification layout obtained from the manufacturer. they can be classified as either theoretical
of the failure points. The ultimate goal is This methodology is capable of providing (simulation tools) or practical (experimental
a system operational lifetime with a low recommendations, using intuitive analysis, tests). The simulation tool category includes
failure rate, and the only way to achieve this for increasing the reliability of components. the Markov process method, Monte Carlo
is to utilise a combination of: simulation, state enumeration method,
• Reliability-oriented design rules. Design for reliability reliability block diagram and fault tree
• Selection of top-tier suppliers and Reliability should be designed-in from the analysis.
acceptance testing of their components. very beginning of the design phase; this As regards reliability tests, those must be
• Manufacturing in well-controlled process is referred to as design for reliability carried out at each stage of development
environments. (DFR). The DFR process therefore starts and mass production. When a product
• Accelerated lifetime testing of the from topology selection, circuit design, and is developed, a reliability test will be
system (and its components) up to the component selection and application, and performed to check the design, material
wear-out point in order to determine uses a highly accelerated testing method and process; then, during mass produc-
when the product will fail, at what rate to discover design flaws in the early devel- tion, a reliability test will be performed as
and which failure mechanisms are at opment stages. The major DFR aspects a quality-assurance inspection or a failure-
fault. that should be borne in mind during a PV rate test for predicting the reliability of the
inverter design include topology selec- product. The purpose and type of reliability
Reliability prediction methodologies tion and design, and thermal design and test therefore greatly depends on the
The newest reliability prediction methodol- management [3]. device manufacturing stage.
ogy, the so-called physics-of-failure (PoF), There is a distinction between quality
emphasises the root cause of failure, failure Thermal management and reliability control. Traditional quality
Figure 5. Reliabil-
analysis, and failure mechanisms as the Thermal management is an essential part ity management control assures that the product will work
basis of an analysis of parameter charac- of the reliability of any electronic system [4] process. after assembly and as designed, whereas
reliability provides the probability that an
item will perform its intended function for
a designated period of time without failure
under specified conditions. In other words,
reliability looks at how long the product will
work as designed, which is a very different
objective from that of traditional quality
control. Therefore, certain tools and models
can be applicable to reliability but not
necessarily to quality, and vice versa.
The reliability test generally has associ-
ated time and cost implications. Testing
under normal operating conditions
requires a very long time, especially for