Construction Estimate Page 1

File Name: Estimate1


Qty Craft@Hours Unit Material Labor Equipment Total

Interior wall framing, 2" x 4" studs and 1/2" gypboard


Cost per running foot, for 8' high walls
1.00 [email protected] LF 11.02 17.24 0.00 28.26
Interior wall framing, 2" x 6" studs and 1/2" gypboard
Cost per running foot, for 8' high walls
1.00 [email protected] LF 13.29 19.39 0.00 32.68
Exterior wall framing, 2" x 4" studs, 1/2" gypboard and wood siding
Cost per running foot, for 8' high walls
1.00 [email protected] LF 23.90 18.32 0.00 42.22
Exterior wall framing, 2" x 6" studs, 1/2" gypboard, insulation and wood siding
Cost per running foot, for 8' high walls
1.00 [email protected] LF 27.40 20.74 0.00 48.14
Redwood fascia
2" x 6", per LF
1.00 [email protected] LF 2.43 1.48 0.00 3.91
Joists and blocking
2" x 12"
1.00 [email protected] LF 1.79 2.67 0.00 4.46
LVL beams (laminated veneer lumber_
1.75" x 16" 1.8E
1.00 [email protected] LF 8.20 0.00 0.00 8.20
Truss joists, TJI type
11-7/8" TJI/15
1.00 [email protected] SF 3.33 0.80 0.46 4.59
Truss joists, TJI type
9-1/2" TJI/15
1.00 [email protected] SF 3.03 0.80 0.46 4.29
2" x 8" floor joists
16" centers (1.36 BF per SF)
1.00 [email protected] SF 0.92 0.61 0.00 1.53
Sill with a single row of anchor bolt holes
2" x 8" (1.40 BF per LF)
1.00 [email protected] LF 1.29 1.88 0.00 3.17
Sill with a single row of anchor bolt holes
2" x 12" (2.10 BF per LF)
1.00 [email protected] LF 2.70 1.88 0.00 4.58
Sill with a single row of anchor bolt holes
4" x 8" (2.80 BF per LF)
1.00 [email protected] LF 3.52 2.39 0.00 5.91
Posts
4" x 4"
1.00 [email protected] LF 1.26 5.16 0.00 6.42
Rough carpentry
Blocking and nailers, 2" x 6"
Construction Estimate Page 2
File Name: Estimate1
Qty Craft@Hours Unit Material Labor Equipment Total
1.00 [email protected] LF 0.73 1.59 0.00 2.32
Stud walls
2" x 4", 10' high, 1.0 BF per SF
1.00 [email protected] SF 0.74 0.98 0.00 1.72
Stud walls
2" x 6", 10' high, 1.5 BF per SF
1.00 [email protected] SF 1.09 1.41 0.00 2.50
Log rafter system
Ridge beam, main and secondary
1.00 [email protected] LF 0.00 8.42 0.00 8.42
Rafters, 2” x 6”
16" centers (1.02 BF per SF)
1.00 [email protected] SF 0.68 0.77 0.00 1.45
Fink truss, 2" x 4"
40' to 50' span
1.00 [email protected] SF 4.01 0.74 0.00 4.75
Fink truss, 2” x 6”
Up to 38' span
1.00 [email protected] SF 4.11 0.67 0.00 4.78
Fink truss, 2” x 6”
40' to 50' span
1.00 [email protected] SF 4.93 0.88 0.00 5.81
Hibor treated douglas fir (Hawaii)
4" x 8", No. 1 and Better, S4S, Timbers 12’ L
1.00 [email protected] Ea 51.50 0.00 0.00 51.50
Log rafter system
Ridge beam, main and secondary
1.00 [email protected] LF 0.00 8.42 0.00 8.42
Steel floor deck system. Consists of 18 gauge, 1-1/2" standard rib, shop prime painted steel decking,
installed over a structural steel beam and girder support system (cost of support structure not included)
covered with 3" thick 6.0 sack mix, 3,000 PSI lightweight ready-mix concrete, placed by pump,
reinforced with 6" x 6", W1.4 x W1.4 welded wire mesh. Costs shown assume shoring is not required
and include curing and finishing the concrete.
Steel floor deck system
18 gauge decking
1.00 [email protected] SF 2.06 0.70 0.23 2.99
Steel floor deck system
Welded wire mesh
1.00 [email protected] SF 0.25 0.26 0.00 0.51
Steel floor deck system
Lightweight concrete
1.00 [email protected] SF 1.21 0.27 0.11 1.59
Steel floor deck system
Cure and finish concrete
1.00 [email protected] SF 0.22 0.51 0.00 0.73
Steel floor deck system
Construction Estimate Page 3
File Name: Estimate1
Qty Craft@Hours Unit Material Labor Equipment Total
Total floor deck system
1.00 [email protected] SF 3.73 1.74 0.34 5.81
Structural steel beams, purlins, and girts
From 20 to 50 lbs per LF
1.00 [email protected] Ton 2,945.80 671.60 375.00 3,992.40
Anchor bolts
5/8" x 21" (SSTB20)
1.00 [email protected] Ea 6.91 5.32 0.00 12.23
Hold down brackets
24-1/8" x 14" x 6-1/4" (S/HPAHD22)
1.00 [email protected] Ea 14.32 5.69 0.00 20.01
Reinforcing steel in footings, foundations and grade beams
1/2" diameter, #4 rebar (.67 lb per LF)
1.00 [email protected] LF 0.57 0.45 0.00 1.02
Welded wire mesh
4" x 4" W2.9 x W2.9 (#6 x #6), slabs
1.00 [email protected] SF 0.76 0.32 0.00 1.08
Trenching with a 1/2 CY utility backhoe
Per cubic yard, 15 CY per hour
1.00 [email protected] CY 0.00 6.52 3.00 9.52
Drilled caisson, 16" diameter
Total for 16" caisson
1.00 [email protected] VLF 42.39 5.33 10.19 57.91
Limestone flag paving in sand bed
Random ashlar, 2-1/2"
1.00 [email protected] SF 8.20 10.83 0.00 19.03
Limestone flag paving in mortar bed
Random ashlar, 2-1/2"
1.00 [email protected] SF 8.06 11.92 0.00 19.98
Cut stone
Limestone, 3" thick (60 SF)
1.00 [email protected] SF 33.27 12.67 0.00 45.94
Tongue and groove cedar siding
8' lengths
1.00 [email protected] SF 5.54 1.21 0.00 6.75
Flagstone
Veneer on walls, 3" thick
1.00 [email protected] SF 6.42 15.79 0.00 22.21
Rough stone veneer
Most common veneer (60 SF)
1.00 [email protected] SF 15.35 12.67 0.00 28.02
Marble specialties
Window stools, 5" x 1" (60 LF)
1.00 [email protected] LF 15.35 12.68 0.00 28.03
Marble specialties
Stair treads, 1-1/4" x 11" (50 LF)
Construction Estimate Page 4
File Name: Estimate1
Qty Craft@Hours Unit Material Labor Equipment Total
1.00 [email protected] LF 34.30 15.19 0.00 49.49
Housewrap building envelope
9' x 150' roll
1.00 [email protected] SF 0.14 0.22 0.00 0.36
Plywood wall sheathing
3/4"
1.00 [email protected] SF 0.78 0.94 0.00 1.72
Aluminum horizontal sliding windows. Right sash is operable when viewed from the interior. With
screen, 7/8" nailing fin setback for 3-coat stucco or wood siding. By nominal (opening) size, width ×
height. Obscure glass is usually available in smaller (1' and 2') windows at no additional cost.
Aluminum horizontal sliding window, white finish, insulating low-E glass
6'0" x 4'0"
1.00 [email protected] Ea 255.44 55.80 0.00 311.24
Double-hung insulating glass wood windows
3'0" x 4'6", twin
1.00 [email protected] Ea 532.51 33.67 0.00 566.18
Fixed octagon wood windows
24", venting insulating glass
1.00 [email protected] Ea 212.18 55.80 0.00 267.98
Half louver stile and rail interior doors
36" x 80"
1.00 [email protected] Ea 375.95 42.78 0.00 418.73
2-panel knotty alder prehung interior doors
36" x 80"
1.00 [email protected] Ea 456.29 27.90 0.00 484.19
Gypsum wallboard nailed or screwed
1/2" on walls
1.00 [email protected] SF 0.38 0.36 0.00 0.74
Gypsum drywall and accessories
1/2", 4’ x 10’
1.00 [email protected] Ea 18.13 0.00 0.00 18.13
Gypsum drywall and accessories
1/2", 4’ x 10’
1.00 [email protected] Ea 23.69 0.00 0.00 23.69
Gypsum drywall, 1/2" plain board
Walls
1.00 [email protected] SF 0.40 0.65 0.00 1.05
Gypsum drywall, 1/2" moisture-resistant greenboard
Walls
1.00 [email protected] SF 0.50 0.65 0.00 1.15
4-1/4" x 4-1/4" glazed ceramic wall tile
High gloss finish
1.00 [email protected] SF 8.84 6.02 0.00 14.86
Decorator tile panels, institutional quality
Glazed imported, decorative
1.00 [email protected] SF 25.34 4.69 0.00 30.03
Construction Estimate Page 5
File Name: Estimate1
Qty Craft@Hours Unit Material Labor Equipment Total
Ceramic tile
4-1/4" x 4-1/4", 8 tile cover 1 SF
1.00 [email protected] SF 4.56 0.00 0.00 4.56
Marble tile
6" x 6", 4 tile cover 1 SF
1.00 [email protected] SF 9.49 0.00 0.00 9.49
Natural stone mosaic tile
Good quality
1.00 [email protected] SF 18.54 0.00 0.00 18.54
Ceramic tile adhesive
Tile adhesive applied with #2 trowel
1.00 [email protected] SF 0.28 0.00 0.00 0.28
Installation of tile in thin set mortar, walls
Mosaic tile
1.00 [email protected] SF 0.60 11.17 0.00 11.77
Ceiling Panel Suspension Grids Typical costs, 15/16" flange, plain white. Add panel costs below.
2’ x 2’ grid with wire suspension
9/16" flange, shadow molding
1.00 [email protected] SF 0.96 0.63 0.00 1.59
Copper sheet metal roofing
Standing seam
1.00 [email protected] SF 18.54 3.38 0.00 21.92
Plywood roof sheathing
3/4"
1.00 [email protected] SF 0.78 0.52 0.00 1.30
OSB roof sheathing
Blocking for panel joints, 2" x 4"
1.00 [email protected] LF 0.49 0.47 0.00 0.96
Copper, K-style (ogee), 16 oz, including hangers. Add 25% for 20 oz. material.
Copper downspouts
Round, 4"
1.00 [email protected] LF 13.29 2.84 0.00 16.13
Particleboard underlay
3/4" x 4' x 8' sheets
1.00 [email protected] SF 0.69 0.52 0.00 1.21
Unfinished antique tongue and groove plank flooring
Oak, distressed, over 7" wide
1.00 [email protected] SF 14.21 1.94 0.00 16.15
Nylon cut pile carpet
40 oz.
1.00 [email protected] SY 24.41 5.25 0.00 29.66
Composition flooring
Epoxy terrazzo
1.00 [email protected] SF 5.39 4.84 0.00 10.23
Fiberglass trench drain system
Typical 96' fiberglass drainage system, per LF
Construction Estimate Page 6
File Name: Estimate1
Qty Craft@Hours Unit Material Labor Equipment Total
1.00 [email protected] LF 75.71 54.19 0.00 129.90
Interior acrylic latex house paint (400SF per gal)
High gloss enamel, gallon
1.00 [email protected] Gal 39.35 0.00 0.00 39.35
House wrap membrane
3' x 100' rolls or 9' x 150' rolls
1.00 [email protected] SF 0.14 0.00 0.00 0.14
Below grade vapor barrier
(fiberglass reinforced Kraft between 2 layers of polyethylene) 8' x 250' roll (2,000 SF roll)
1.00 [email protected] SF 0.21 0.00 0.00 0.21
Water closets
Floor-mount, back outlet tank type WC and trim
1.00 [email protected] Ea 340.93 86.25 0.00 427.18
Lavatory
Rectangular pedestal china lavatory and trim
1.00 [email protected] Ea 663.32 91.75 0.00 755.07
Lavatory
Counter-type rectangular china lavatory & trim
1.00 [email protected] Ea 466.59 73.40 0.00 539.99
Laundry sinks
Cast iron laundry sink and trim
1.00 [email protected] Ea 2,513.20 101.30 0.00 2,614.50
Walk-in doored bathtub, ADA-compliant
55" long x 30" wide x 40" high (tub only)
1.00 [email protected] Ea 2,060.00 0.00 0.00 2,060.00
Bathtubs
Enameled steel tub with handrail and trim
1.00 [email protected] Ea 1,020.73 192.70 0.00 1,213.43
Indoor whirlpool tub
8 jets, 2 HP, 72" x 42" x 22", corner
1.00 [email protected] Ea 2,214.50 183.50 0.00 2,398.00
Walk-in doored bathtub, ADA-compliant
55" long x 30" wide x 40" high (tub only)
1.00 [email protected] Ea 2,060.00 0.00 0.00 2,060.00
Medium density fiberboard molding
Base, 1/2" x 4-1/4"
1.00 [email protected] LF 1.47 0.45 0.00 1.92
Softwood molding, beveled window stool
1" x 5-1/2"
1.00 [email protected] LF 6.19 1.38 0.00 7.57
Cut stone
Granite, 1-1/4" thick, exterior (60 SF)
1.00 [email protected] SF 22.04 12.67 0.00 34.71
Sand bed, dry joints
Granite paving
Sand bed, 2" thick, 150 SF per CY of sand Per SF of bed
Construction Estimate Page 7
File Name: Estimate1
Qty Craft@Hours Unit Material Labor Equipment Total
1.00 [email protected] SF 0.12 1.14 0.00 1.26
Concrete walls
Using concrete (before 5% waste allowance)
1.00 [email protected] CY 125.66 0.00 0.00 125.66
Slabs, walks and driveways
4" thick
1.00 [email protected] SF 3.28 2.54 0.00 5.82
Slabs, walks and driveways
6" thick
1.00 [email protected] SF 4.09 2.62 0.00 6.71
Polyisocyanurate foam core sheating
2", R-13.0
1.00 [email protected] SF 1.14 0.70 0.00 1.84
Fiberglass batt insulation
3-1/2" Kraft faced, R-13, between ceiling joists
1.00 [email protected] SF 0.55 0.31 0.00 0.86
Crushed stone fill for drainage systems
3/4" (Number 3)
1.00 [email protected] CY 40.27 21.10 0.00 61.37
Metal sheet roofing, utility gauge

Total Manhours, Material, Labor, and Equipment:


46.1 16,998.84 1,995.95 389.79 19,384.58

Subtotal: 19,384.58

Estimate Total: 19,384.58