Gina Edit Chapter 3
Gina Edit Chapter 3
Gina Edit Chapter 3
FUEL SYSTEM
1. The fuel storage tank is designed to supply fuel on the engine good for (3) three months
operation.
2. Due to unexpected problem on delivery or any unexpected incident that would cause delay,
the designer decided to add a 25% contingency. This would guarantee about 22 days of
3. The designer decided to put a cylindrical diesel fuel oil storage tank vertically seated above
the ground considering the advantage in terms of maintenance. The dimension is assumed to
be H=2d.
4. Corrosion allowance is constructing the vessels with thicker walls to allow for the thinning.
The Peters, Timmerhaus, and West suggest 0.25 to 0.38mm annually or 3mm for 10 years.
5. The type of steel to be used is Carbon Steel (SA-285, Cr. C) with a tensile stress value of
13,700 psi. To provide air space and other auxiliaries to the storage tank the designer adds an
mf
m b=
Brake Power
mf= ( mb ¿ ¿)
Considering the fuel consumption of the diesel power plant with the plant capacity factor of %.
by interpolation.
50 %−75 % 185−184
=
48.38 %−75 % x−184
g
X = 185.06
kw−hr
g
mf= (185.06 kw−hr ¿ ¿10,350 kW)
g
( 1 kg )
mf = 1,915,371 hr 1000 g
mf =1,915 kg/hr
1.4: DENSITY OF FUEL
ρ@ 15.6
ρf=
1+0.0007(t−15.6)
ρ@ 15.6=(876) [ 1+ 0.0007(15−15.6) ]
ρ@ 15.6
ρf=
1+0.0007(t−15.6)
875.63
ρf=
1+0.0007(25−15.6)
ρ f =¿ 869.9 kg/m3
ρ@ 15.6
Where: SG @15.6 =
ρw
875.63 kg/m 3
SG @15.6 =
1000 kg/m 3
SG @15.6 = 0.88
Therefore:
SG @25 = (0.88 )[1 – 0.0007(25-15.6)]
SG @25 = 0.8742
mf
Vf=
ρf
1915 kg /hr
Vf= 3
869.9 kg/m
Since the contingencies are set to 25% of the fuel consumption per month,
Therefore:
V FOST =V f + 0.25 V f
V FOST =1.25 V f
3
V FOST =53,493.75 m
V FOST =¿ 6686.72 m3
π
V FOST = d 2 H Since: H=2d
4
Thus,
π 2
VFOST= d xH
4
π 2
VFOST = d x 2d
4
π 3
VFOST= d
2
d=
√
3 ( 2 ) ( V FOST )
π
√
d = 3 ( 2 ) ( 6686.72 m )
3
d = 16.21 m
H = 2(16.21 m) + 0.50 m
H = 32.92 m
(From Engineering Fluid Mechanics Ninth Edition (2009) by Crowe, Elger, Williams,
Pi=δ f H
Where:
δ f = SGf xδ w
Substituting:
P=¿40.95 psi
Pi=P g + Patm
Pi=55.65 psi
r = 319.09 in
P ri
t=
S EJ − 0.6 P
Where:
P = maximum allowable internal pressure, Psi
EJ = efficiency of joints
E
1.7.3c: Welding Joint Efficiency, J
(From PSME Code, page 147; the efficiency of doubled but weld for fusion weld joints is
70%.)
(From: Peters, M.S. and K.D. Timmerhaus. 1991. Plant Design and Economics for
Thus,
t = (55.65 psi)¿ ¿
t = 1.8523∈¿
t = 1.8523 in + 0.0124 in
t = 1.8647 in
(From Chatham Steel Corporation use standard size of carbon steel plate)
t = 2 ½ or 63.5 mm
Number of Tanks 8
Diameter 16.21 m
Height 32.92 m
Thickness 63.5mm
1. The plant will have one day tank for each engine and this will provide Fuel oil for (8) eight
2. The designer choses a cylindrical diesel fuel oil day tank vertically seated above the ground
3. Add a corrosion allowance of 0.315 mm for the thickness of the tank. The type of steel to be
used Carbon Steel (SA-253, Cr. C) with a tensile stress value of 13,700 psi.
4. The designer decided to add an allowance of ¼ or 0.25 m to the calculated height of the tank
mf
Vf =
ρf
g
mf= (185 kw−hr ¿ ¿10,350 kW)
g
( 1 kg )
mf = 1,914,750 hr 1000 g
mf =1,914 kg/hr
mf
Vf =
ρf
1,914 kg /hr
Vf =
869.9 kg/m 3
Vf = 2.200 m3/hr
Therefore;
VFODT= 17.6m3
π 2
V FODT = d H Since: H=2d
4
Thus,
π 2
VFODT = d xH
4
π 2
VFODT = d x 2d
4
π 3
VFODT = d
2
d=
√
3 ( 2 ) ( V FODT )
π
√
d = 3 ( 2 ) ( 17.6 m )
3
d = 2.238 m
H = 2d + allowance
H = 2(2.238 m) + 0.25 m
H = 4.73 m
(From Engineering Fluid Mechanics Ninth Edition (2009) by Crowe, Elger, Williams,
Substituting:
P= ( 41 kPa ) ( 0.145
1 kPa )
psi
P = 5.95 psi
Pi=P g + Patm
Pi=20.65 psi
d 2.238 m 39.37∈.
r= = x
2 2 1m
r = 44.06 in
E
2.4.3c: Welding Joint Efficiency, J
From PSME Code, page 147; the efficiency of doubled but weld for fusion weld joints is
70%.
(From: Peters, M.S. and K.D. Timmerhaus. 1991. Plant Design and Economics
Where:
P = maximum allowable internal pressure, Psi
EJ = efficiency of joints
Thus,
t = (20.65 psi)¿ ¿
t = 0.0950 in
Adding a corrosion allowance of 0.315 mm (0.0124 in):
t = 0.0950 in + 0.0124 in
t = 0.1074 in
(From Chatham Steel Corporation use standard size of carbon steel plate)
3
t= or 5 mm
16
Number of Tanks 8
Diameter 2.238 m
Height 4.73 m
Thickness 5 mm
As to the dimensions of return fuel tank, the designer decided to have a diameter and
height of about one half the diameter and height of the diesel fuel day tank. And for the
thickness, it is equal to the thickness of diesel fuel day tank. The type of steel to be used Carbon
H = ½ (4.73 m)
H = 2.4 m
Say use 3 m
t = 5 mm
P = δf H
Where:
H = height of tank
Substituting:
P=( 8.67 kN /m ) ( 3 m )
3
P = 3.771 psi
Pi=P g + Patm
Pi=18.47 psi
3.4 VOLUME OF RETURN FUEL TANK, VRFT
π 2
V RFT = d H
4
π 2
V RFT = ( 2 ) (3)
4
VRFT = 9.42 m3
Number of Tanks 8
Diameter 2m
Height 3m
Thickness 5 mm
4.1 PIPINGS FOR FUEL OIL STORAGE TANK TO FUEL OIL DAY TANK
Given: v, A,
Assumed filling time for the tank is 10 mins (reason) using a velocity of 0.5m/s
(30m/min) with maximum velocity of 1m/s (60m/min) at suction side while, the velocity at
V
Q= where: V = Volume of Day Tank
tf
3
17.6 m t f = Assumed Filling Time
Q=
10 min
m3
Q = 1.76
min
πD 2
Q = AVmax where: A =
4
2
πD
Q=( )Vmax Vmax = 60 m/min
4
4Q
D2 =
π V max
D=
√ 4Q
π V max
√
3
4( 1.76 m / min)
D=
π (60 m/ min)
From size range of Steel EN 10216 Seamless Pipe Tubes from Aesteron Steels LLP,
Wall Thickness 6 mm
πD 2
Q = AVmax where: A =
4
πD 2
Q=( )Vmax Vmax = 120 m/min
4
4Q
D2 =
π V max
D=
√ 4Q
π V max
D=
√ 4( 1.76 m3 / min)
π (120 m/ min)
D = 1.3665 m = 366.5 mm
From size range of Steel EN 10216 Seamless Pipe Tubes from Aesteron Steels LLP,
SELECTION CONSIDERATION:
In selecting motor pumps, total dynamic head and discharge capacity also called volume
flow rate are the most important parameters. Selected pumps may meet the total dynamic head or
much better if it is higher. If the discharge capacity is lower than your desired, it must be
3
Discharge flow rate of Fuel Oil 1.76 m /min
Velocity at pump discharge and suction line 1.5 & 0.5 m/sec
TDH = Hp + Z + Hf + HV
Where:
Z = is static head
Hp = pressure head
Thus,
Therefore,
Ls = 125.1 m + 22.17 m
Ls = 147.27 m
Thus,
L D = 37 m + 11.9 m
L D = 48.9 m
Hf = Hs f + Hdf
Where:
2 f s Ls V s
Hsf = gDs
Where:
fs = coefficient of friction.
Where:
Z = viscosity
75 50
25 65
15 Z
By Extrapolation:
z = 68 centipoises
[ ]
0.424
68
fs = 0.0035+0.0007562
( 0.213 ) (0.5)(0.8742)
fs = 0.01588
Thus,
2
0.5 m
2(0.01588)(147.27 m)( )
Hsf = sec
(9.81 m/ sec 2)(0.213 m)
Hsf = 0.5596 m
2 f d Ld V d
HD = gD d
Where:
f d = coefficient of friction.
[ ]
.424
z
0 . 0035+0 .0007562
fD = DsVsS
Where:
Z = viscosity = 68 centipoises
[ ]
0.424
68
fD = 0.0035+0.0007562
( 0.154 ) (1.5)(0.8742)
fD = 0.0124
Thus,
2
1.5 m
2(0.0124)(48.9m)( )
HDF = sec
2
(9.81 m/sec )( 0.154 m)
HDF = 1.806 m
Therefore,
Hf = 0.5596 m + 1.806 m
Hf = 2.3656 m
m m 2
(1.5 −0.5 )
sec sec
HV =
m
2(9.81 2
)
sec
HV = 0.051 m
Z = 11 m
p s − pd
Hp =
Sf
2 2
420.58 KN /m −144.79 KN /m
Hp =
8.67 KN / m3
Hp = 32 m
Therefore;
TDH = 68.15 m
3
From MP Pumps Catalogue, Chemflo pump series. With a capacity of 143 m /min (377.8
gal/min) and a TDH of 68.15 m (223.6 ft). Using the selection table, the selected model is
Chemflo 8 from MP pumps Inc. Although the required capacity is higher than the
capacity of the selected pump, this would not be a problem since the function of this
pump is just to fill the tank, therefore actual filling time will be longer than the
assumptions.
Solving for actual filling time;
V
Q= where: V = Volume of Day Tank
tf
3
m3 14.3 m
t f = Actual filling time
1.2 =
min tf
t f =12mins m3
Q = 310 gpm or 1.2 (actual
min
Since the generator set has already a fitted feed pump, the diameter will be base to the
capacity of the said fitted feed pump and only suction pipe will be designed.
m3
Q = 0.011
min
suited for this kind of applications are the average velocities at pumps suction line where is
m
106.5 .
min
2
πD
Q = AVmax where: A =
4
2
πD
Q=( )Vmax Vmax = 106.5 m/min
4
4Q
D2 =
π V max
D=
√ 4Q
π V max
D=
√ 4( 0.011m3 /min)
π (106.5 m/min)
D = 0.01147 m = 11 mm
From Fig. A-6 of PPE by Morse pg. 665, we got the following:
Schedule Number 40
Since the generator set has already a fitted feed pump, the diameter will be base to the
capacity of the said fitted feed pump. Also due to lack of information, velocity will be assumed
m
137
min from the average velocity at discharged lines (From PPE by F. Morse p. 603)
m3
. Q = 0.011
min
πD 2
Q=( )Vmax Vmax = 137 m/min
4
4Q
D2 =
π V max
D=
√ 4Q
π V max
√
3
4( 0.011m / min)
D=
π (137 m/ min)
D = 0.0101 m = 10 mm
From Fig. A-6 of PPE by Morse pg. 665, we got the following:
Schedule Number 40
8.1 PIPINGS FOR FUEL OIL RETURN TANK TO FUEL OIL STORAGE TANK
The parameters to be used in the determination of appropriate specification for pipelines Suited
for this kind of applications are the assumed time to empty the tank which is 1.5 minute and the
m
137
Average velocities at pumps suction and discharge line where are 106.5 and min
respectively.
V
Q= where: V = Volume of return tank
tf
3
m
Q = 0.644
min
2
πD
Q = AVmax where: A =
4
πD 2
Q=( )Vmax Vmax = 106.5 m/min
4
4Q
D2 =
π V max
D=
√ 4Q
π V max
D=
√ 4( 0.644 m 3 / min)
π (106.5 m/ min)
D = 0.0878 m = 88 mm
From Fig. A-6 of PPE by Morse pg. 665, we got the following:
Schedule Number 40
πD 2
Q = AVmax where: A =
4
2
πD
Q=( )Vmax Vmax = 137 m/min
4
4Q
D2 =
π V max
D=
√ 4Q
π V max
D=
√ 4( 0.644 m 3 / min)
π (137 m/min)
D = 0.0774 m = 77 mm
From Fig. A-6 of PPE by Morse pg. 665, we got the following:
Schedule Number 40
SELECTION CONSIDERATION:
In selecting motor pumps, total dynamic head and discharge capacity also called volume
flow rate are the most important parameters. Selected pumps may meet the total dynamic head or
much better if it is higher. If the discharge capacity is lower than your desired, it must be
3
Discharge flow rate of Fuel Oil 0.966 m /min
Velocity at pump discharge and suction line 1.78 & 2.28 m/sec
Where:
Z = is static head
Hp = pressure head
Thus,
Therefore,
Ls = 121.6 m + 29.3 m
Ls = 151 m
Thus,
Therefore,
LD = 141.6 m + 18.2 m
LD = 159.8 m
Hf = Hs f + Hdf
Where:
2 f s Ls V s
Hsf = gDs
Where:
fs = coefficient of friction.
[ ]
. 424
z
0 . 0035+0 .0007562
fs = DsVsS
Where:
Z = viscosity
21.1 40
25 Z
26.7 30
By Interpolation:
z = 33.04 centipoises
[ ]
0.424
33.04
fs = 0.0035+0.0007562
( 0.08341 ) (1.78)(0.8841)
fs = 0.0114
Thus,
1.78 m 2
2(0.0114)(121.6 m)( )
Hsf = sec
(9.81 m/sec 2 )(0.08341 m)
Hsf = 10.74 m
2 f s Ls V s
HDf = gDs
Where:
fs = coefficient of friction.
Ls = total length of pipe at suction, m.
[ ]
.424
z
0 . 0035+0 .0007562
fD = DsVsS
Where:
Z = viscosity = 33.04 centipoises
[ ]
0.424
33.04
fD = 0.0035+0.0007562
( 0.08341 ) (2.28)(0.8841)
fD = 0.0106
Thus,
2
2.28 m
2(0.0106)(141.6 m)( )
HDF = sec
(9.81 m/sec 2 )(0.08341m)
HDF = 19.07 m
Therefore,
Hf = 10.74 m + 19.07 m
Hf = 29.81 m
2
m m
(2.28 −1.78 )
sec sec
HV =
m
2(9.81 )
sec2
HV = 0.0127 m
Z = Zd – Zs = 30 m – 0.13 m
Z = 29.87 m
p s − pd
Hp =
Sf
2 2
131 KN /m −117.2 KN /m
Hp = 3
8.67 KN /m
Hp = 1.59 m
Therefore;
TDH = 61.3 m
3
From MP Pumps Catalogue, Chemflo pump series. With a capacity of 0.966 m /min (255.2
gal/min) and a TDH of 61.3 m (201 ft), using the selection table, the selected model is
SELECTION CONSIDERATION:
In this particular matter, the designers decide to use a 152.4 mm (6 in) pipes for both
suction and discharge line for maximum operation. In selecting of pump for this system, the
3
m
designers decide to use FLOMAX 40 from MP pumps Inc. with a capacity of 2.4 (625
min
V
Q= where: V = Volume of Day Tank
tf
3 3
m 8094.8 m
2.4 = t f = Actual filling time
min tf
t f =56.2hours∨¿ m3
Q = 625 gpm or 2.4
min