ARC224 Archl PROGM N
ARC224 Archl PROGM N
Course Outline
Highlights the operations of Architectural works in the preliminary stage, working drawing
stage, construction stage and post occupancy and maintenance stages. Students are exposed to
the program of works and how it relates to Architectural project execution, completion and
maintenance.
The course outline can be grouped under the following specifics;
1; Introduction (conceptual definitions of Architecture, Architect, Architectural programming
and building)
2; Architect appointment and briefing stage (inception, feasibility, surveys, brief, site acquisition,
consultants),
3; Sketch planning stage (outline proposal, design data, cost planning, scheme design, statutory
parties)
4; Working drawing stage (detailed design, production information, bills of quantities, building
regulations, tender action)
5; Site operations/construction stage (project planning, operations on site, completion/handover,
Feedback)
6; Maintenance/post occupancy stage (, maintenance, maintenance period, maintenance manual)
INRODUCTION
The course is aimed at introducing the theory and practical application of the concept of
Architectural Programming to the students as a way of letting them know the total package of
Building processes that an Architect is supposed to partake from conception (cradle) to disposal
(grave).
2
Architecture in a nutshell is said to be the Art and science of the total building process (design,
production and disposal). An Architect is the jack of all trades but master of design because he
possesses the knowledge of all trades that uses the building which he produced for them. With
due regards to functionality, aesthetics, durability, economics and health, he designs building for
the optimum use, comfort and productivity of his client because he puts himself in their position.
He is also vested with the leadership responsibility of the building industry as such he is
expected to be versatile in the design and management of material, human and financial
resources as well as the disposal of the building. Wither the Architect of today is living up to the
responsibility put on him or not, this is a different topic of discussion.
Architectural programming is said to be the research and decision-making process that helps to
identify the scope of work to be designed and performed. The owner /client does not have the
expertise to develop the project program, therefore he needs the services of the Architects
because the best time and the most cost-effective time to influence the outcome of a project is to
make changes during programming rather than to wait until the building is under construction
before tearing or pulling it down for any correction. To that effect, there is need for close
interaction/communication through integrated design approach between the Architect and others.
Architectural programming has some advantages which includes;
1; Involvement of interested parties in defining scope before design
2; Gathering and analyzing data early in the process so that design is based on sound decisions
3; Efficient use of time by avoiding redesign as requirements emerge during design development
4; Clients are involved at each stage because they are the one to occupy the building
5; It helps client make decision on their current needs and future needs for rough budgeting
before implementation
6; Helps open up lines for communications, set up agenda and fix meetings and records.
Building is any structure that is used for human habitation activities. These activities can be for
home uses and sleeping (residential), learning (educational), Business (commercial), sport and
relaxation (recreational), spiritual (religious), Health matters (medical), production process
(industrial), civic activities (institutional) e t c. This is to protect himself from the vagaries of
weather and climate and from his own negative activities and to get optimal health and
comfort.
3
The main ‘contractor’ or principal contractor for a construction project agrees, by a legal
contract, to carry out the work required by the client who is paying for the work. The main
contractor may choose to pay subcontractors to do some part of the project. A large contracting
firm employs a wide range of people, some of whom are described below.
Before a project start work on ground the main office of the contractor may have been involved
in the design details, and will employ quantity surveyors and estimators to measure the work,
calculate expected costs, tender a price and successfully gain the contract.
The contract manager is responsible for the overall running of one or more contracts and act as
the link between the main office and the project managers on site. The clerk of works or site
agent or site manager has responsibility for all personnel on site and their activities. Typical
activities include planning work, labour relations, liaisons with architects and engineers, and
maintaining links between the site and the contractor’s main office.
Large construction project will also have a site engineer who has responsibility for ‘setting out’
the exact position of all building, roads and drains. Surveyors working on site have responsibility
for measuring the amount of work completed at regular stages, such as each month, so that stage
payments can be claimed by the contractor from the client. The contractor can then pay for
supplies of materials and for subcontractors.
Planning Authorities like KASUPDA and KEPA are responsible for ensuring that all building
plans are checked and conforms with the laid down planning and environmental laws.
Tradesmen/craftsmen have specialist skills to perform tasks and work with specific materials on
site e g carpenters, masons, tilers, electricians, interior decorators, gardeners, acoustics engineers
t c.
Inception at Client level
At the inception stage a client decides to build and seeks the help of a professional consultant
Architect.
Client function at
Architect appointment and briefing stage.
Consider the need to build
Set up organization with Chairman to manage the matter from the client end
Appoint architect
Commence exchange with architect, note and act on architect’s opinion and advice
Discuss terms of appointment of consultants
Appoint reminder of design team as advised by architect
Contribute to meeting.
Provide all information required by the architect
6
Feasibility
Under feasibility, studies will be undertaken to determine:
Design approach
Construction approach
Planning issues
Legal requirement
Site suitability
Project feasibility.
The consultant should either carry out a site investigation or arrange for one to be carried out.
Outline planning permission should be applied for and a feasibility report prepared for the client.
The site investigation should be carried out.
When feasibility report is received, the client should be able to decide, with the help of the
consultants, whether to proceed with the proposal.
Design Role
Management Role
Accept appointment from client
Obtain general background information
Introductory meeting with client
Inform client of job responsibilities professional fees, etc.
Open discussion with client organization
Obtain initial statement of requirements.
Establish with client preliminary details of project.
Obtain site plan/ Survey details
Approach QS and engineers regarding appointment
8
Design Role
Contribute to meeting as a team leader
Try out various general solutions
Assist QS in preparation of outline cost plan
Contribute to design dossiers.
Contribute to preparation of report
Complete any outstanding user studies carryout visits and interviews as necessary
Prepare full scheme design taking individual and group advice.
Pass scheme to QS and engineers.
Receive and discuss engineers’ proposals
Review scheme design finally and prepare presentation drawings.
With engineer, assist QS in preparation of final cost plan.
Management Role
Organize design team.
Compile dossiers provided by team members on final sketch design
9
Production drawings
Specification
Schedules
Contract details.
The production drawings, specification and schedules should be sufficiently detailed in order to
allow the contractor to price the works.
Bills of Quantities
The quantity Surveyor can use the production information in order to produce a bill of Quantities
which consist of general information about the project together with quantities measured from
the drawings in accordance with a standard measurement code, normally SMM7 or CESMM3.
The Bill of Quantities and the production of information will enable the contractor to produce a
tender for the project.
Tender Action
Necessary tender documents are prepared and the tender is finally awarded to a contractor who
has successfully executed major similar major projects in the past and quoted lowest among
other contractors. At the tender action stage, a list of contractors to be selected is prepared and
invitations to tender are sent out. If the contractors express a willingness to tender, the tender
documents can then be issued with a date for return clearly indicated. The following documents
should be issued to the selected contractors
Bills of Quantities
Project drawings
Form of tender
Envelopes for return of tender
Covering letter.
10
Design Role
Management Role
Organize design team and review progress, brief the client’s decision
Maintain and co-ordinate progress throughout the stage
Call meeting of design team to make reconciliations that are necessary as a result of
review.
Obtain approvals not so far obtained
Initiate letting of demolition contract if required
Maintain and co-ordinate progress
Recommend short list of tenderers
Recommend M&E tender documents
Recommend the appointment of M&E sub-contractors.
the works in detail, placing contracts with subcontractors and suppliers, and generally arranging
the site set-up and site organization.
Program of Work
Programs can be worked out and presented by the contractor for checking and approval by the
Architect as a Bar or Gantt charts. The bar or Gantt chart was developed by Henry L. Gantt, a
management scientist who lived during the early part of this century. He developed a pictorial
method of showing planned progress against actual progress against actual progress. The bar
chart shows the time, usually in months and weeks, horizontally along the top, with the activities
listed vertically down the left-hand side. See figure 3.1. The bar chart is the most commonly used
programming technique and it has a number of distinct advantages.
Advantages of the bar chart
Simple to produce
Easily understood by everyone on site
Gives a good pictorial representation of the construction sequence
Can be updated easily
Different levels of programme can be easily related to each other, for example master,
section and operations programme
Key dates can be easily shown on the programme
Can be easily used to indicate progress and thereby aid monitoring and control of the
project
Can be drafted on a preprinted proforma.
For example, if an activity is delayed it may be difficult to assess what effect this delay will
have on future activities. Important information which should always be shown on a
programme include the following:
Name of project
Name of client
Contractor’s name
Date of production of programme
Date of any amendments
Name of person who produced the programme.
12
Operation/Construction on site
Construction is the creation, renovation, repair, and demolition of immovable structure and the
alteration of natural topography. It is the process of translating the plans, specifications and
resources into a physical facility to meet the specific requirements of owners within the schedule,
cost and quality. The project is now underway on site and constant monitoring and control of the
operation take place. Communication at this stage is important and close collaboration between
the design team and the contractor is vital to ensure a successful outcome for the client.
Sequence of construction operation
1.Site clearance, 2.Site set-up, 3.Strip topsoil, 4.Setting out, 5.Foundation excavation, 6.Drainage
excavation 7.Foundation, 8.Raising walls, 9.Hardcore, 10.Floor slab, 11.Walls to first floor level
Scaffolding, 12.First floor joist, 13.Walls to roof level, 14.Roof timbers, 15.Roof coverings,
16.Upper timber floors, 17.Non-load-bearing partitions, 18.Windows and external doors, 19.First
fix carpentry including stairs, 20.First fix electrical, 21.First fix plumbing,22.Plastering
internally. 23.Screeding,24. Second fix electrical, 25. Second fix plumbing 26. Second fix
carpentry, 27. Tiling, 28. Decoration, 29. floor finishes, 30. External rendering,31. Drainage, 32.
Landscaping, 33. Clean and clear site, 34. Snagging
Completion
At intervals, the Architect prepares interim certificate based on report and valuation. On
completion of the project (except for snagging works) the contractor should be issued with a
certificate of practical completion and the building handed over the client.
Maintenance period then sets in for a given period of tine depending on the project type. Some of
these projects can be put into use, when certain part of it are completed. When the full project is
put into use, the factors regarding the maintenance are to be carefully considered.
Feedback
This stage involves the final account settlement between the contractor and the client. Record
should be kept of costs and experience gained about construction methods and site organization
for future reference.
Design role
Review and produce all drawings as given as site instructions by the Architect
Provide all necessary specifications as they affect progress of work with respect to the
site instructions
Management Role
There is lack of feedback between the Architect and the building user or Authority. To
control building post occupancy feedback
Architects have restricted themselves to the drawing board as issues of site management
control and Building maintenance is being challenged by the builder and Quantity
surveyor is taking over specification writing and project management
Provide all building users with a common system of maintenance information recording
and retrieval for the proper guidance of maintenance operatives, the manual is prepared at
the time of construction of a building or design and manufacture of any tool and plant
Illustrate various building components, services and equipment giving their locations and
drawings
20
Provide a maintenance manual guide for soft and hard landscape (external works).
Help in instilling a routine maintenance habit to the society for good maintenance culture
and that means savings and prolonging the building service life.
It helps the owner to know the durability and when any element requires visit for cost
backing and budgeting.
Architect, it will provide a link between him and the owner by informing the owner of the
design intention and general maintenance responsibilities.
Assignment
1. Use sketches, give practical examples and outline the roles and responsibilities of the
building construction project team members and outline the leadership role of the
architect for all of them during a typical building project execution. Identify one member
for yourself as discussed in the class (Air conditioner installer) (15marks)
2. With the aid of appropriate sketches specification of materials procedural steps by step
explain the 34 sequences of building construction operation from taking over site to
handling over of the building. Building categories are: educational, institutional.
Recreational, industrial, residential, medical, commercial, storage, transportation e t c.
(15marks)