CCS CC1026 4
CCS CC1026 4
Abstract:
Twenty sites have been selected from 579 for further due diligence. Key features of the Select Inventory are: -
Significant overall capacity target of 6.8GT, - Strong balance between saline formations and depleted
hydrocarbon fields with good geographic diversity, - Strong compliance with IEAGHG screening guidelines and
the Project BoD qualifications, - Proximal sites to 5/42 and Goldeneye, - Strong technical diversity of sites, -
Deselection of sites with high risk high confidence containment issues.
Context:
This project, funded with up to £2.5m from the UK Department of Energy and Climate Change (DECC - now the
Department of Business, Energy and Industrial Strategy), was led by Aberdeen-based consultancy Pale Blue Dot
Energy supported by Axis Well Technology and Costain. The project appraised five selected CO2 storage sites
towards readiness for Final Investment Decisions. The sites were selected from a short-list of 20 (drawn from a
long-list of 579 potential sites), representing the tip of a very large strategic national CO2 storage resource
potential (estimated as 78,000 million tonnes). The sites were selected based on their potential to mobilise
commercial-scale carbon, capture and storage projects for the UK. Outline development plans and budgets were
prepared, confirming no major technical hurdles to storing industrial scale CO2 offshore in the UK with sites able
to service both mainland Europe and the UK. The project built on data from CO2 Stored - the UK’s CO2 storage
atlas - a database which was created from the ETI’s UK Storage Appraisal Project. This is now publically
available and being further developed by The Crown Estate and the British Geological Survey. Information on
CO2Stored is available at www.co2stored.com.
Disclaimer:
The Energy Technologies Institute is making this document available to use under the Energy Technologies Institute Open Licence for
Materials. Please refer to the Energy Technologies Institute website for the terms and conditions of this licence. The Information is licensed
‘as is’ and the Energy Technologies Institute excludes all representations, warranties, obligations and liabilities in relation to the Information
to the maximum extent permitted by law. The Energy Technologies Institute is not liable for any errors or omissions in the Information and
shall not be liable for any loss, injury or damage of any kind caused by its use. This exclusion of liability includes, but is not limited to, any
direct, indirect, special, incidental, consequential, punitive, or exemplary damages in each case such as loss of revenue, data, anticipated
profits, and lost business. The Energy Technologies Institute does not guarantee the continued supply of the Information. Notwithstanding
any statement to the contrary contained on the face of this document, the Energy Technologies Institute confirms that the authors of the
document have consented to its publication by the Energy Technologies Institute.
2015 D04: Initial Screening & Down-Select
10113ETIS-Rep-03-2.0
February 2016
www.pale-blu.com
www.axis-wt.com
D04: Initial Screening & Down-Select Contents
Contents
Document Summary
Disclaimer:
While the authors consider that the data and opinions contained in this report are sound, all parties must rely upon their own skill and judgement when using it. The authors do not make
any representation or warranty, expressed or implied, as to the accuracy or completeness of the report. There is considerable uncertainty around the development of CO2 stores and
the available data are extremely limited. The authors assume no liability for any loss or damage arising from decisions made on the basis of this report. The views and judgements
expressed here are the opinions of the authors and do not reflect those of the ETI or any of the stakeholders consulted during the course of this project.
Twenty sites have been selected from 579 for This Energy Technologies Institute (ETI) Strategic UK CCS Storage Appraisal
further due diligence. Key features of the Select project has been commissioned on behalf of the Department of Energy and
Climate Change. The project brings together existing storage appraisal
Inventory are:
initiatives, accelerates the development of strategically important storage
capacity and leverages further investment in the building this capacity to meet
Significant overall capacity target of 6.8GT.
UK needs.
Strong balance between saline formations and The primary objective of the overall project is to down-select and materially
depleted hydrocarbon fields with good progress the appraisal of five potential CO2 storage sites on their path towards
final investment decision (FID) readiness from an initial site inventory of over
geographic diversity.
500. The desired outcome is the delivery of a mature set of high quality CO2
storage options for the developers of major power and industrial CCS project
Strong compliance with IEAGHG screening
developers to access in the future. The work will add significantly to the de-
guidelines and the Project BoD qualifications. risking of these stores and be transferable to storage developers to complete
the more capital intensive parts of storage development.
Proximal sites to 5/42 and Goldeneye.
This is the report for Work Package 3 (WP3) of the project. The objective of
Strong technical diversity of sites. WP3 was to deliver a Select Inventory of 20 potential CO2 Storage sites from an
Initial Inventory of over 500 sites. In addition a Reserve Inventory of 5 sites was
Deselection of sites with high risk high identified as a potential backup. The Initial Inventory was developed primarily
from the CO2Stored database (Energy Technologies Institute, 2010). It was
confidence containment issues. augmented with further hydrocarbon fields for which DECC hold production
records (DECC - UK Government, 2015). Whilst there were over 207 oil and
gas fields in the DECC list which were not in CO2Stored, these are almost
entirely small satellite fields which had little potential CO2 storage capacity to
Stakeholder meeting on 2nd July 2015 (Appendix 2). The methodology involved potential sites which did not meet the minimum cautionary key attribute metrics
an initial qualification step to ensure that the site met both the requirements of for a potential CO2 storage site. Some of these sites carried large-to-very large
the project screening basis of design (WP1) and also global best practice capacities, but did not meet other key criteria.
guidance where it exists. The qualification step delivered a “Qualification • Site numbers reduced from 186 to 37; total theoretical capacity
Inventory” which was then subjected to a ranking step to deliver the “Select reduced from 77,051MT to 8,295MT.
Inventory” of 20 sites together with the Reserve Inventory of 5 backups. • Removed 80% of project qualified sites.
Whilst the screening basis of design has several components of the kind of • Removed 89% of project qualified capacity.
storage sites that are required to meet these study objectives, The Project Neither of the storage sites being considered for UK CCS Phase 1 projects
qualification criteria were limited at this stage to a minimum theoretical capacity reached the qualification inventory. Goldeneye did not meet the capacity
threshold of 50MT and a maximum distance to the nearest ETI Scenarios requirement being limited to significantly less than 50MT as currently specified.
beachhead of 450km (Energy Technologies Institute, 2015). 5/42 could not be included simply because this project could only access 3D
The key document used for best practice guidance was DNV recommended over a part of the full structure. Both sites also failed on “Availability” as they
Practice 203 (Det Norsk Veritas, 2012). This referred to the IEAGHG document are both anticipated to be fully licensed to their operators and be unavailable to
on screening CO2 Storage sites (IEA Greenhouse Gas R&D Programme, 2009) other storage developers. It should be highlighted that whilst these sites are
considered to be strong CO2 storage candidates for Phase 1 CCS projects, they
do not meet the requirements of this project.
called TOPSIS (Yoon & Hwang, 1995). Six attributes were selected from the 226.011 1691.0 Saline Aquifer Bunter Closure 9 Barmston
372.000 1388.0 Saline Aquifer Forties 5 St Fergus
CO2Stored database. These were either database values such as the P50
248.005 776.0 Gas South Morecambe gas field Connah's Quay
Theoretical Capacity, simple calculations such as injectivity (permeability x 227.007 409.0 Saline Aquifer Bunter Closure 3 Barmston
thickness) or quantification of qualitative assessments such as containment risk. 266.001 243.0 Gas Hewett gas field Barmston
139.016 232.0 Saline Aquifer Bunter Closure 36 Barmston
The six attributes were: 303.001 205.0 Gas Hewett gas field (Bunter) Barmston
248.004 175.0 Gas North Morecambe gas field Connah's Quay
P50 Theoretical Capacity in MT
336.000 175.0 Saline Aquifer Grid Sandstone Member St Fergus
Injectivity in mDm 361.000 174.0 Saline Aquifer Mey 1 St Fergus
Engineered Containment Risk Factor in wells/km2 366.000 162.0 Saline Aquifer Maureen 1 St Fergus
218.000 156.0 Saline Aquifer Captain_013_17 St Fergus
Georisk Factor (dimensionless) Gas
133.001 211.0 Bruce Gas Condensate Field St Fergus
Condensate
Development Cost factor (dimensionless)
248.002 120.0 Gas Hamilton gas field Connah's Quay
Upside Potential (in MT) 217.000 81.0 Saline Aquifer Coracle_012_20 St Fergus
218.001 97.0 Oil & Gas Captain Oil Field St Fergus
The TOPSIS process required that these criteria be independent of one another 139.020 84.0 Saline Aquifer Bunter Closure 40 Barmston
and linearly distributed. Each attribute was weighted to capture the relative 141.035 271.0 Gas Viking gas field Barmston
141.002 120.0 Gas Barque gas field Barmston
significance of each and sensitivities to this weighting from Stakeholder input 252.001 76.0 Oil & Gas Harding Central oil field St Fergus
were also used in the final selection. The process performed well and was
Table 1 - The Recommended Select Inventory
verified against two simple ranking processes. There was agreement from all
approaches on the “progress or drop” position of 75% of the Qualified Inventory. Had 5/42 reached the “Qualified Inventory” then it would have been ranked
The destiny of the final 25% was finalised by expert judgement and Stakeholder around 5th overall. Had Goldeneye reached the “Qualified Inventory” then it
input. would have been ranked around 25 out of 37. This reflects the importance of
capacity in the ranking process.
The recommended “Select Inventory” comprised 10 depleted hydrocarbon fields
and 10 saline aquifers. 15 of the sites were discrete structural closures with 5
being in open formations. Sites are located throughout the geological column
The results have been shared and tested with a broad group of Stakeholders at
an event in London on 2nd July. The authors of the report appreciated the
constructive engagement from all those involved.
2.0 Objectives
The primary objectives for this project are to identify and materially progress the The scope of work for this WP3 has been divided into the following 4 tasks:
appraisal of five high potential CO2 Storage sites on their path towards FID
1. Procure screening data and build the Initial Inventory of potential
readiness. The desired outcome is the delivery of a mature set of high quality
storage sites.
CO2 Storage options for the developers of major power and industrial CCS
2. Deliver a "Select Inventory" of twenty sites with five reserves.
projects to access in the future. The work will add significantly to the de-risking
3. Document the screening results and develop a presentation.
of these five stores and will be available to storage developers as a basis for
4. Present the results to Stakeholders and gain approval of the Select
them to commission the more capital intensive parts of storage site appraisal.
Inventory.
The focus of this Work Package 3 (WP3) is to select a pool of twenty storage
This report documents the process and results of this WP3 down select. The
sites with five reserves on the UKCS from which the project requirements can
report is organised into a series of sections which mirror the work flow for this
be met. This "Many to Twenty" down-selection follows a screening process,
stage of the project as presented in WP1.
based on both physical character and geographic location, designed to generate
a portfolio of five sites with the greatest potential for safe, material and long term
storage of CO2. The workflow for selection complies appropriately with the
requirements of the EU Directive 2009/31/EC (THE EUROPEAN PARLIAMENT
AND THE COUNCIL OF THE EUROPEAN UNION,, 2009) on the Geological
Storage of Carbon Dioxide and other key recommended practice guidelines
such as DNV-RP-J203 Geological Storage of Carbon Dioxide. (Det Norsk
Veritas, 2012) and IEAGHG Recommended Practice (IEA Greenhouse Gas
R&D Programme, 2009).
Further details of the overall methodology and approach to this challenge are
described in the WP1 report. Minor aspects of this approach have been
modified following a detailed review of the site inventory available via the
CO2Stored database and Stakeholder review but the general method remains
the same. Methodology refinements are included in this report.
3.0 Methodology
Approach methodology for qualification and ranking are described in Sections 5.0 and 6.0
of this report.
A five step work flow for the WP3 "Many to Twenty" site selection was presented
The “Screening Basis” is a common set of requirements against which all
in WP1 and is shown here in Figure 1.
potential storage sites will be assessed. Specifically this defines the
The planned approach generally fitted well to the data available at this stage requirements to be fulfilled during the project screening in order to be able to
and was retained in full. Some further refinements of the details of the
volume of fluids produced from the reservoir for each field using • UKSAP and the CO2Stored database were designed to develop a
cumulative production data made available by DECC. UKSAP used standardised methodology for CO2 storage capacity estimation.
production data up to end-2010 and so the capacity estimates only • No other extensive, internally-consistent dataset exists.
represents the pore volume available for CO2 storage based on • CO2Stored is subject to update and refinement and improvement
historical production to that date. Further capacity would result from through a separate project.
a further 4 years production data (to 2015). The assessment here
CO2Stored will primarily be used for this “Many to Twenty” work package.
suggests that this is generally a minor contributor to uncertainty at
Subsequent WP4 and WP5 will collect and apply site specific data. The
this point.
qualifying and ranking criteria used in this work package attempt both to
• The uncertainty range applied to some of the inputs to the saline
recognise these complex uncertainty limitations within the database and to limit
aquifer data in CO2Stored have been set at +/-10% across the
the use of data which carry greatest uncertainty or lowest confidence.
dataset. This implies an unrealistic consistency of uncertainty levels.
In oil and gas, +/- 10% often does not even capture direct Finally, it was decided not to deploy economic assessments from CO2Nomica
measurement error for some attributes and so it is possible that the at this stage in the project. It was considered that simple metrics very close to
uncertainty in capacity estimates may have been under estimated. the database should be used to provide clarity and direct linkage with screening
This raises some concerns about the reliability of the P90 (too big?) decisions. Furthermore it was considered that the deployment of the
and P10 (too small?) theoretical capacity estimates which arise from sophisticated modelling of CO2Nomica may enhance confidence in site
the Monte Carlo analysis. outcomes where such confidence is not merited by the UKSAP assessment at
this time. CO2Nomica will be considered within WP4.
After consideration of these factors and also the lowering of the qualification
hurdle for capacity from 75MT to 50MT, it was concluded that a recalculation
and refinement of capacity using the UKSAP process was no longer useful for
this project as it would not change the fields under consideration.
5.0 Qualification
The Initial Inventory of potential sites stands at 579 (574 from CO2Stored
together with an additional 5 hydrocarbon field sites). The initial qualification
and compliance step seeks to ensure compliance with project needs and
recommended screening practice whilst at the same time reducing the Initial
Inventory to a more manageable size.
The final 'threshold' criteria were selected to meet two sets of requirements:
It should be noted that, to ensure that a strong population of sites survived the
qualification step, the theoretical capacity threshold set by the Basis of Design
for Screening was relaxed from 75MT to 50MT. This maintained a stronger
inventory into the ranking process. It also helped to ensure that those sites or
larger hydrocarbon fields which might have been eliminated through a marginal
failure to meet a 75MT threshold with uncertain capacity estimates would not be
eliminated too early in the process.
Table 5 - Project-Specific qualification criteria are based upon the project objectives and Basis of Design
These ensure that the Qualified Inventory only held sites which meet recognised minimum screening criteria (i.e. DNV RP 203 Screening Basis guidelines (Det Norsk
Veritas, 2012)) in addition to the project requirements. The DNV RP-J203_2012-04 Recommended Practice cites the IEA GHG 2009 report (IEA Greenhouse Gas R&D
Programme, 2009) with selection criteria recommended by (Chadwick, et al., 2008) for screening requirements for saline aquifers. It is recognised that many of these
criteria are time dependent (e.g. availability, data availability) or are indications but not proof of unsuitability (e.g. fault throws) and therefore deselection knowing what
we know today does not necessarily mean they will be deselected in the future.
Qualification Rationale
Threshold Description Data Source Impact on the Inventory
Criteria
COP<2031 Some oilfields which have been identified by significant studies as
and no having high potential for miscible CO2-EOR projects were excluded on Wood MacKenzie
significant The site should have data (Appendix 1).
the basis that when CO2 is flowing into the offshore area then they 14 sites failed this test, 9
EOR reasonable
might reasonably be considered for CO2 EOR by their license owners. Economic Impacts of through EOR potential, 3
potential. availability for use by
Availability As such they would be unavailable for CO2 storage. Goldeneye and CO2-EOR for through COP constraints
a prospective
Not 5/42 are also assumed to be unavailable as it is assumed they will Scotland, Final and 2 through CO2
developer in the 2015
currently already be licensed. Finally some of the recent and larger hydrocarbon Report (Element Storage licensing.
to 2030 timeframe.
licensed for fields are forecast to continue operations past 2030 and these are Energy Ltd, 2012)
storage. considered unavailable for the purposes of this project.
Table 6 - Qualification criteria drawn from recommended guidelines and best practice
Permeability >300 mD <10 – 100 mD For the purposes of this qualification step, Wood Mackenzie have provided for
this project the results of an analysis of estimated Cessation of Production
Salinity >100,000 mg/l (ppm) <30,000 mg/l (ppm)
(COP) dates. Wood Mackenzie have taken a view of these dates based upon
Caprock Properties their understanding of the fields and the forward price forecast held in May 2015.
Lateral variations, More details of their forecast assumptions are included in Appendix 1.
Lateral continuity Unfaulted
faulted
At this stage it has been concluded that only hydrocarbon sites where the COP
Thickness >100 m <20 m dates fall before 2031 will be considered as qualified. This threshold currently
Much greater than Similar to the buoyancy excludes the fields in Table 8.
Capillary entry buoyancy force of force of maximum
pressure maximum predicted predicted height of CO2
height of CO2 column. column.
Table 7 - Extract from IEAGHG guidelines for saline aquifer site selection (IEA
Greenhouse Gas R&D Programme, 2009)
ALLIGIN Oil Commercial 2035 TALBOT Oil & Gas Technical 2032
SUILVEN Oil & Gas Technical 2035 FARADAY Gas/condensate Technical 2031
FRAM Oil & Gas Commercial 2034 FULHAM Gas Technical 2031
JOCELYN Oil & Gas Technical 2034 PUFFIN Gas/condensate Technical 2031
ELGIN Gas/condensate Commercial 2033 Table 8 - List of Fields with COP dates beyond 2030 – Source Wood Mackenzie
FRANKLIN Gas/condensate Commercial 2033
the North Sea: Securing a low-carbon future for the UK” (SCCS July 2015) and UK Beryl 232 82
also “Economic impacts of CO2 Enhanced oil recovery for Scotland” (Element UK Brae 104 34
UK Brent 502 154
Energy Ltd, 2012). The latter reports on a specific range of named fields which
UK Buzzard 108 31
are deemed to have significant EOR potential (Table 9). These sites were
UK Claymore 144 46
excluded from the qualified inventory on the basis that as soon as CO2 becomes
UK Clyde 41 21
available offshore then these sites are likely to remain unavailable for simple UK Cormorant 157 45
CO2 storage as EOR developments start. The Basis of Design excludes CO 2- UK Dunlin 83 24
EOR opportunities as primary storage candidates but includes them on a UK Forties 420 80
portfolio basis for upside potential. Their potential role in initiating a CCS UK Fulmar 82 81
industry as has happened in the onshore US is not considered here due to the UK Janice 129 87
complex challenges of financing and consenting two first of a kind projects at a UK Miller 75 25
UK Nelson 79 26
major power plant and major oilfield at the same time.
UK Ninian 292 94
Existing CO2Storage Sites UK Piper 140 20
UK Scott 95 29
It has been assumed for the purposes of the qualification step that both the
UK Teal 82 55
proposed Goldeneye storage site and the proposed storage site at 5/42 will be UK Thistle 82 22
developed by their current operators and will not be available for licensing by UK/NO Murchison 79 25
other third parties. Clearly both have upside capacity potential in excess of that UK/NO Statfjord 635 236
required by the UK CCS commercialisation programme, but the future Table 9 - North Sea oilfields identified as having CO2-EOR potential (Element Energy
development of this additional potential will be for the owners of those storage Ltd, 2012)
licenses to progress. Both are therefore deemed unavailable at this stage.
storage reservoir on the way to a deeper hydrocarbon target with very little data 1 out of 6 attributes 116
acquisition focussed upon the potential storage interval. At this stage however
2 out of 6 21
a single well is required to qualify. Later on in WP4 the quality of the available
data will be assessed. 3 out of 6 7
out of 6 3
Geological Containment
Total 147
Whilst all the sites in the Initial Inventory possessed the basic attributes to be
considered as a potential viable CO2 storage site, the IEAGHG guidance rightly Table 10 - Containment Risk Failure Rate
stresses the importance of containment risk in any selection process. Within the
CO2Stored database, there are six geological containment attributes. Three are
linked to the caprock system and three relate to the fault related structures in
the caprock and overburden geology.
Number of Site
Containment Attribute
Deslections
Fault Density 67
Seal Degradation 0
The DNV Recommended Practice (RP) for geological storage sites (RP-J203)
was developed to provide “a systemic approach to the selection, qualification
and management…. of sites” (Det Norsk Veritas, 2012), specifying what DNV
regard as the best industry practice. The RP (J203) is fairly broad-ranging
however it contains one performance requirement and procedure pertinent to
this work programme: the selection and qualification of geological storage sites
for long-term storage of CO2. Other RP requirements and procedures exist
which, may be applied to later work programmes (WP4 and WP5) of this project.
DNV Screening Basis Requirement Description Rationale UKSTORE Screening Basis Compliance
Well integrity: confidence that well integrity can High Well Density contributed to lower site
be established and maintained. ranking in WP3.
Positive indicators of the potential to Legal availability of the storage site over WP3-5 provide input for UK storage license and
monitor and deploy risk treatment expected life cycle. permit process.
Screening Basis Context Location of source of CO2. BoD: Beachhead locations defined.
DNV Screening Basis Requirement Description Rationale UKSTORE Screening Basis Compliance
Social and cultural context of storage site. All sites are offshore.
5.3 Results
Figure 2 summarises the results of the Qualification Screening process. From Figure 3 summarises the effect of the same qualification process but on the total
the starting Initial Inventory of 579 sites, a Qualified Inventory of 37 sites has theoretical capacity of the inventory. Note that some deselection criteria are
been developed. This “Qualified Inventory” passes all of the threshold metrics temporal and others based on indicative rather than conclusive properties, and
for both the project Basis of Design and the established recommended so deselection now does not mean deselection in the future.
guidelines for carbon storage.
Figure 2 – Impact of Qualification on Site Numbers. Figure 3 - Impact of Qualification on Theoretical Capacity.
Figure 4 illustrates the impact of each individual criteria on the Initial Inventory
and the total theoretical capacity, colour coded by store unit type. The image on
the left shows the cumulative effect of each qualification criteria on the number
of sites remaining in the inventory at each screening step. The image on the
Figure 4 - Impact of individual qualification criteria on inventory number and total theoretical capacity, coded by store unit type.
Figure 5 - Impact of the theoretical capacity (>50MT) qualification criteria on total capacity.
Figure 4 indicates that Georisk, or the geological risk to secure containment (as
opposed to the engineered containment risk associated with existing and new-
drill wells) was effective at cutting the saline aquifer site number by 51 which
were considered to have both a high risk factor linked to secure, long term
containment and high confidence in the data used to assign that risk. This was
considered a key qualification criterion - there being little point in investing
development money to investigate and derisk such stores when an abundance
of less risky candidate stores are available.. Hydrocarbon sites were excluded
from Georisk qualification at this stage and so show no impact to this cut.
The permeability cut-off (>50mD) was also selected to allow for the significant
uncertainty associated with the values held within the CO2Stored database
(Energy Technologies Institute, 2010) while also removing the 51 sites which Figure 6 - Qualification Sensitivity to Permeability Threshold
are unlikely to support the required injection rate (as per the Basis of Design). The removal of the lower permeability sites also has a significant impact on the
The IEAGHG (2009) guidelines actually suggest >300mD is required for a site total inventory capacity, dropping from around 45000 MT by over 50% to 19350
to have 'positive indicators' for carbon storage; a 10-100mD range is a MT. These losses arise from the elimination of 43 deep saline aquifers (average
cautionary indicator (IEA Greenhouse Gas R&D Programme, 2009). The depth 2940m) and 6 large low permeability Leman Sandstone gas fields.
selection of 50mD provides for the level of uncertainty associated with the
It is noted that permeability effects cost more than security, and cost is also
permeability values reported. A sensitivity analysis suggests that of 118 sites
correlated with other fundamentals (depth, water depth, distance from shore
remaining before the permeability cut off was applied just over 40% were lost
etc).
with a 50mD threshold whilst only a further 10% were lost with a 100mD
6.0 Ranking
Each of the sites in the Qualified Inventory now generally satisfies the 4. The sites then underwent ranking using the TOPSIS methodology
requirements of both the project and also best practice guidance. The next step using the criteria weightings and a TOPSIS Score assigned to each
is to consider a ranking of these sites such that a “Select Inventory” of the 20 site. These delivered a TOPSIS ranking of the Qualified Inventory.
most favourable sites can be progressed to Work Package 4 (“Twenty to Five” 5. A simple average rank for each site in the Qualified Inventory was also
site selection). calculated across all criteria in order to validate and compare with the
TOPSIS rank. This was completed assuming equal weighting for each
Ranking was carried out using 3 different techniques to ensure the best 20 sites
criteria.
were selected. Sensitivity analysis was also carried out using a set of different
6. Step 5 was repeated but using the weightings assigned in step 3. An
'perspectives' to evaluate the impact on site ranking.
average weighted rank for each site was calculated across all criteria
The ranking methodology was carried out as follows: in order to further validate and compare with the TOPSIS rank.
1. A set of 6 relatively independent factors or criteria important to a 7. The three ranking lists from steps 4, 5 and 6 were assembled and
successful CO2 storage site were chosen to evaluate each site. These compared ahead of a development of a final single ranking which was
included factors which described capacity, injectivity, containment performed manually.
(both georisk and engineering), development costs and upside 8. In total, 4 scenarios were completed using different criteria weightings
potential. to assess their impact.
2. The criteria for each site in the Qualified Inventory were then quantified 9. Results from each scenario were compared and a final “Select
from information held in CO2Stored database. These were either Inventory” of 20 sites was developed with input from Stakeholders.
deployment of existing numeric values in the database (eg Capacity), This Select Inventory was recommended to progress to WP4.
simple calculation based upon numeric values in the database (eg
TOPSIS Analysis
Injectivity) or a quantification of a qualitative coding held in the
database (eg Georisk). TOPSIS, or Technique for Order Preference by Similarity to Ideal Solution (Yoon
3. A criteria weighting exercise was carried out by the project team & Hwang, 1995) , was selected in WP1 as the tool to lead the site ranking
members after input from a Stakeholder meeting. process. The benefits of TOPSIS have been discussed in more detail in the
WP1 report are summarised here:
6.1 Criteria
The six ranking criteria selected are described in Table 15 below. In a complex system such as a CO2 storage site, it is very difficult to find totally independent
parameters. For example, capacity and permeability are both related to porosity, injectivity is dependent upon permeability and even development cost is dependent
upon depth which also controls pressure – a key element of capacity. As a result, each criterion has undergone careful consideration to ensure the set are relatively
independent. This was tested later quantitatively through a correlation search.
While the majority of the criteria are quantitative, it was necessary to quantify a in CO2Stored for containment is a consistent qualitative risk assessment ranked
qualitative value for the Georisk Containment criteria. The information available as high, medium or low. It was based on a methodology which had undergone
Site A low high medium high high medium 14 Criteria Positive Ideal Negative Ideal
Criteria
Label Solution Solution
Site B low low low low low low 6
1 Capacity 1691MT 50MT
Site C medium medium medium medium medium medium 12 2 Injectivity 1,286,651 mDm 2,743mDm
Containment
Site D high high high high high high 18 3 0.013 wells/km2 18.378 wells/km2
(Engineered)
Containment
4 6 (dimensionless) 16 (dimensionless)
low = 1 medium = 2 high = 3 (Georisk)
Development
Table 16 – Examples of Georisk Containment quantification. 5 116 (dimensionless) 751 (dimensionless)
Cost Factor
Finally, to be confident that the criteria being used in the ranking process were Upside
6 10016MT 421MT
Potential
independent of each other (a requirement of TOPSIS), a simple correlation
Table 17 - Optimal positive and negative ideal solutions for each ranking criteria
search was completed. This was achieved by plotting the data for each of the
37 sites in the qualified inventory for each pair of criteria. Figure 8 shows a
matrix of scatter plots each of which displays either poorly or completely
Injectivity
1000000
27
23
12
500000
29
2615
36
34
17
16
19
11 4
0
21
37
22
33
32
31
25
30
189876 5 3
10
13
20
14
16
24
17
35 2 1
0 1000 2000
20 20
18 27 18 27
Containment Risk
16 16
14
Engineering
14
12 12
10 10
8 8
32 32
6 6
23
34 4 34 23
4 28 36 28
3616 2 1617 12
2 17
12 17 937
21
17
21
18 9 18
24
35
68
725
531
30 3411
133
10
22 19
0 37
33
19
24
35
31
30
22
29
2611
16
15
20
25 876 5 4 3
10
14
13 2 1 0 2
14 13
20 29
16 26
15
0 1000 2000 0 1000000 2000000
18 18 18
Geo Containment Risk
16 2 16 2 16 2
14 14 14
14 14 14
13 13 13
12 31
28
22
20
15 12 3120
22 15 28 12 20
15
22
31 28
30
29
26
1976 630
7 19 26 29 26
29
30
7619
10 17
16
11 3 10 17 311
16 10 1617
311
33
18 5 1 18
5133 533118
8 37
34
27
24
23
21
17
16
12
190 8 24
1617
937
21
1034 12
2327 8 10
243721
912
17
16 34
23 27
6 36
35
32
258 4 6 35
825
32
4 36 6 425
835 36 32
4 4 4
2 2 2
0 0 0
0 1000 2000 0 1000000 2000000 0 10 20
700 9 9 9 9
17 600 17 600 17 600 17
600 3416 1634
2016 161716 34
20 34
16 16
16
20
17 17 17 20
500 500 13 500 13 500 13
13
Factor
61432 36 27 14 624 36 32 27 32 27
36
27
36
32146
24
29
22
31 400 24
23122 29 400 29
222
31 400 24 6 22 142
2931
400 2 18 18 18
18
37 35 37
5133 37
33
58735 35 3733
5
300 3312
35 87 5 300 8725 10 12 300 25 101 12 300 25 12
8 101 7
2510
30 1 30 30 30
200 4 15 200 415 200 4 112615
200 26
23
28
11 4 3
15 311 26 23 28 311 2823
26 23 3 28
19 100 19 100 19 100 19
100
0 0 0 0
0 1000 2000 0 1000000 2000000 0 10 20 0 10 20
10000 17
12 12 12 12
1. Rounded View – Uses all six criteria and initial weighting from a
pairwise consideration matrix
6.3 Benchmarking
Following the ranking process, and feedback from stakeholders, it was operators and will therefore be unavailable to other prospective storage
concluded that it would be useful to benchmark the ranking using some of the developers.
well-known CO2 storage targets in the UKCS which have been significantly
It is very important to stress that the absence of these two specific sites in the
invested in and matured through FEED programmes. The key benchmark sites
Qualified Inventory does not imply they are in any way technically unsuitable for
for consideration included:-
CO2 storage, but merely that they did not qualify under the metrics applied to
1. 5/42 – Prospective Phase 1 storage site, a saline aquifer Triassic this project.
Bunter Formation structural trap in the Southern North Sea.
The Hewett field is another potential storage site which has also undergone
2. Goldeneye – Prospective Phase 1 storage site, a depleted Lower
significant evaluation and early appraisal through projects which were partly
Cretaceous gas field in the Central North Sea.
publically funded. Hewett has made the Qualified Inventory by passing the
3. Hewett – Prospective Demo1 FEED storage site, a depleted Bunter
threshold tests.
gas field in the Southern North Sea.
In addition to Hewett, both 5/42 and Goldeneye have been used as Benchmarks
All of these sites were part of the Initial Inventory, however neither 5/42 nor
to provide useful reference points in the ranking process.
Goldeneye were able to pass the qualification requirements for this project. 5/42
was eliminated because there was not enough 3D seismic coverage available Stakeholder Input
to this project to consider it further. New 3D is available to the Operator over
Stakeholder input has been an important part of bringing the focus of a wide
the whole structure, but access to this is commercially beyond the budget for
range of expertise from industry, policymakers and academic research together
this project. Goldeneye was eliminated because it did not meet the requirement
to help sense check and inform the process and outputs from the project to date.
to have a P50 theoretical capacity of at least 50MT. Furthermore it is assumed
In the course of WP3 a workshop was completed around the detailed screening
that both of these sites will be licensed long term to the respective CO2 Storage
methodology and first pass results. A short workshop report is included as
Appendix 2 to this report
6.4 Results
The input data and the TOPSIS score for each site in the Qualified Inventory is Comparison of Results and Ranking Methods
illustrated in Figure 10. At this stage the site identity remains hidden to minimise
any bias influence. Only three sites are identified. These are the benchmarks An initial review of the three ranking methods suggests strong agreement
of 5/42, Goldeneye and Hewett. Of these only Hewett is actually a part of the regarding the bulk of the Top 20 sites. At the site rank level, there is more
Qualified Inventory. The sites are simply ordered by their P50 Theoretical variation, particularly amongst the Top 10 sites. The two plots shown in Figure
Capacity. In the plot, the green bars denote normal criteria where larger 12 compare the TOPSIS site ranking with both the "Average Rank' and
numbers are favourable, and the red bars denote reverse criteria where smaller 'Weighted Average Rank'. As would be expected, the TOPSIS and Weighted
numbers are favourable. Average Ranks (using the same criteria weighting values) are significantly better
correlated. Two outliers are circled in Figure 12, representing sites 15 and 16.
The data set was then used to calculate a TOPSIS score with the base case
This highlights the importance of using expert judgement to ultimately decide
criteria weights in place. This base case or Rounded View TOPSIS score is
whether to keep the site in the final selection or whether to place on-hold. Other
also shown in Figure 10. A key to the site number and identifiers is given at the
than these outliers, the results provide confidence that TOPSIS performed well
end of the ranking and sensitivity analysis in Figure 14.
as a tool and the ranking process is both useful and comparable between
Two additional ranking methods were added as a result of Stakeholder methods and, as such, is ready for advancing to sensitivity analysis.
feedback. These have been used to validate and sense check the TOPSIS
approach. The first of these simply looked at the rank that each site achieved
for each criteria (Capacity, Injectivity, Development Cost Factor etc) and then
averaged this position. The second performed this same calculation again, but
this time accounted for the relative weights assigned to each criteria. The results
of these ranking methods are shown alongside the TOPSIS ranks in Figure 11.
The ranks for all criteria & sites are colour-coded by whether they fall into the
top 5 sites (green), the next 15 sites (white) or sites in the drop zone below
position 20 to allow easy visual comparison of results.
A “Rounded View” base case of 20 top ranked sites was made using the results 0 - Pass / 1- Fail
Site 1 1 17 18 0
from each ranking method. Wherever there was agreement across all three Site 2 2 22 14 0
Site 3 3 13 15 0
ranking methods (TOPSIS, Average Rank, Weighted Average Rank) to
Bmk 5/42 4 11 5 1
“progress” (because the site was always in the top 20 of the Qualified Inventory) Site 4 5 15 13 0
Site 5 8 23 19 0
or to “drop” (because the site was always in the bottom 17 of the Qualified Bmk Site 6 - Hewett 9 19 16 0
Site 7 10 18 14 0
Inventory) then these were preserved. Sites were then either added or removed
Site 8 22 21 23 1
based upon their overall ranking performance. Figure 13 illustrates this process Site 9 12 14 14 0
Site 10 16 15 19 0
for the “Rounded View” base case. The right hand column carries the final result Site 11 21 12 19 0
with a simple pass or fail (green or red). Site 12 15 19 14 0
Site 13 7 21 16 0
Site 14 14 12 9 0
From Figure 13, it is clear that had the Benchmark Site 5/42 reached the Site 15 31 21 13 1
“Qualified Inventory”, then it would have performed very well in this base case Site 16 6 23 26 0
Site 17 33 27 28 1
ranking process in positions ranging from fourth to eleventh from a total list of Site 18 32 23 25 1
Site 20 23 23 25 1
39 sites (The Qualified Inventory of 37 sites plus two unqualified benchmarks). Site 19 17 17 19 0
Benchmark Site 6 – the Hewett Sandstone in the depleted Hewett gas field also Site 21 18 23 15 0
Site 22 30 24 25 1
performed well in positions ranging from ninth to nineteenth. The Final Site 23 19 24 18 0
Site 24 36 15 24 1
Benchmark Site, Goldeneye performed poorly with a highest position of Site 25 26 21 22 1
nineteenth and a lowest position of twenty ninth. This is due to the importance Site 26 20 17 12 0
Site 27 11 14 13 0
of capacity in the ranking and the fact that all other sites had a capacity Site 28 39 21 28 1
Site 29 34 20 27 1
significantly bigger than Goldeneye. Extension of Goldeneye to adjacent stores Site 30 13 17 16 0
(or other combinations of stores) was not considered. Site 31 24 23 21 1
Site 32 25 25 22 1
Site 33 38 26 31 1
Across the process, the use of weighting criteria is important to balance each Site 34 27 22 24 1
ranking criteria against the others. Site 35 37 21 29 1
Site 36 28 25 24 1
Site 37 35 21 28 1
Bmk - Goldeneye 29 19 25 1
6.5 Sensitivities
A set of four scenarios was developed to test the robustness of the ranking Overall given the nature of the screening data available and the uncertainties
process and evaluate the sensitivity of the site rankings to different criteria present, the Simple View case gained most support from the Stakeholder Group.
weightings: However specific questions and suggestions led to the following modifications
in the final Selected Inventory:-
1. Rounded View (Base Case) – This uses all six criteria and the initial
weighting from a pairwise consideration matrix. 1. Site 8 (Bruce Field) was taken forward in place of Site 16 (Britannia
2. Equal Weighting - Uses all six criteria with equal weighting. Field). The rationale behind this was that whilst Britannia has
3. Container View – This puts the technical aspects of the store first and significantly more potential upside and was closer to both St Fergus
foremost and uses the four subsurface characteristics (Capacity, and Goldeneye, Bruce had a P50 Theoretical Capacity that was over
Injectivity and both Containment criteria) equally weighted. 60% larger and a forecasted COP date several years before that of
4. Simple View – This focuses on capacity and unit cost by using only Britannia.
theoretical capacity, Development cost factor and the Upside Potential 2. Site 29 (Lennox Field) was removed as the weakest qualified site in
as a proxy for a “keep it simple” or 'large and low-cost' approach the East Irish Sea to improve the balance with the ETI Scenarios plan.
advocated by some stakeholders. It was replaced by the next strongest candidate in the Qualified
Inventory which was Site 26, a Bunter saline aquifer closure in the
Results of Sensitivity Analysis Southern North Sea.
The results for these cases were developed in exactly the same way as 3. Site 28 (Harding Central Field) was promoted and displaced Site 30
described in the previous section. Figure 14 shows the results for each into the reserve list. This was done despite the high well density on
sensitivity case together with the recommended decision in the column on the Site 28 because the Harding reservoir is known to contain injected
far right for progression to WP4 of this project. sandstones which require a higher well density to characterise
effectively and may have a significant Georisk issue which may not be
The analysis shows that there is full agreement to progress 14 top sites to the
perceived with poor well data coverage..
Select Inventory and also full agreement to drop a further 14 sites from further
consideration at this time. Stakeholder review and input helped to resolve the The outcome of the final Top 20 recommended selection is a portfolio of sites
position of the further six sites that would be progressed and the 5 sites that which pass all the qualification screening thresholds and represent the sites with
would not progress, but would be held on a reserve list. the greatest potential for success with respect to the objectives of this project.
Table 18 through Table 21 highlight the diversity of the Select Inventory. The
Top 20 sites by Geological Age
target storage reservoirs are distributed from the Permian to the Paleogene, but
interestingly include only one Jurassic reservoir. Many of the Jurassic reservoirs 1. Paleogene 5
failed to qualify on the basis of small capacity levels and deep reservoirs often
below 3000m. Further Northern Brent Province sites were excluded as they are 3. Lower Cretaceous 3
beyond the 450km threshold set out in this project basis of design.
5. Lower Jurassic 1
The Select Inventory has a 50:50 balance of saline aquifers and depleted
hydrocarbon fields. Most of the hydrocarbon fields are gas fields in the Southern 6. Triassic 9
North Sea. Bruce is the gas condensate field with Captain and Harding Central
representing the oilfields after those with significant CO2 EOR potential have 7. Permian 2
been removed.
Table 18 - Select Inventory Sites by Geological Age
70% of the Select Inventory comprises structural traps, with the remaining 30%
representing large open aquifer systems with or without associated structural
confinement. It is anticipated that the presence or absence of structural or
stratigraphic potential on these may well be refined in WP4.
Finally, the Select Inventory provides a portfolio of sites that can service all the
major emission centres and beachheads identified in the ETI scenarios plan
(Energy Technologies Institute, 2015). With 3 sites in the East Irish Sea, 8 sites
in the Southern North Sea and 9 in the Central North Sea. Whilst there are no
Gas 7 Barmston 8
Top 20 sites by Storage Type Table 21 - Select Inventory Sites by Nearest Beachhead
Redcar 25.3
"Equal
Normal Normal Reversed Reversed Reversed Normal "Rounded View" "Container View" "Simple View" "Final Recommendation"
Weighting"
Criteria 1 Criteria 2 Criteria 3 Criteria 4 Criteria 5 Criteria 6
Engineering
Geo Containment Development Proximal Upside Manual Drop Manual Drop Manual Drop Manual Drop
Code Site Number Capacity MT Injectivity mDm Containment Risk Unit Designation Geological Age Geological Formation Storage Type Site Description Nearest Beachhead Recommended Action
Risk Cost Factor $M Potential MT Selection Selection Selection Selection
per sq km
1 2 3 4
226.011 Site 1 1691.0 33380.0 0.6 9.0 292.1 3898.0 Saline Aquifer 6. Triassic Bunter Sandstone Fm Structural/Stratigraphic Trap Bunter Closure 9 Barmston 0 0 0 0 Progress to WP4
Open, with identified structural/
372.000 Site 2 1388.0 19012.0 0.1 16.0 396.2 2534.0 Saline Aquifer 1. Paleogene Sele Fm Forties 5 St Fergus 0 0 0 0 Progress to WP4
stratigraphic confinement
248.005 Site 3 776.0 90753.0 0.4 10.0 167.1 4429.0 Gas 6. Triassic Ormskirk Sandstone FmStructural/Stratigraphic Trap South Morecambe gas field Connah's Quay 0 0 0 0 Progress to WP4
227.007 Site 4 409.0 23926.0 0.2 9.0 313.7 4287.0 Saline Aquifer 6. Triassic Bunter Sandstone Fm Structural/Stratigraphic Trap Bunter Closure 3 Barmston 0 0 0 0 Progress to WP4
266.001 Bmk Site 6 - Hewett 243.0 20500.0 0.3 11.0 299.5 3812.0 Gas 6. Triassic Bunter Shale Fm Structural/Stratigraphic Trap Hewett gas field Barmston 0 0 0 0 Progress to WP4
139.016 Site 7 232.0 11051.5 0.2 6.0 301.5 1179.0 Saline Aquifer 6. Triassic Bunter Sandstone Fm Structural/Stratigraphic Trap Bunter Closure 36 Barmston 0 0 0 0 Progress to WP4
303.001 Site 9 205.0 82749.2 0.3 8.0 276.9 3856.0 Gas 6. Triassic Bunter Sandstone Fm Structural/Stratigraphic Trap Hewett gas field (Bunter) Barmston 0 0 0 0 Progress to WP4
248.004 Site 10 175.0 109728.0 0.6 10.0 193.8 5958.0 Gas 6. Triassic Ormskirk Sandstone FmStructural/Stratigraphic Trap North Morecambe gas field Connah's Quay 0 0 0 0 Progress to WP4
Open, no identified structural/
336.000 Site 11 175.0 612500.0 2.0 8.0 304.1 9624.1 Saline Aquifer 1. Paleogene Horda Fm Grid Sandstone Member St Fergus 0 0 0 0 Progress to WP4
stratigraphic confinement
Open, no identified structural/
361.000 Site 12 174.0 48906.0 0.1 13.0 476.6 7140.0 Saline Aquifer 1. Paleogene Lista Fm Mey 1 St Fergus 0 0 0 0 Progress to WP4
stratigraphic confinement
Open, no identified structural/
366.000 Site 13 162.0 10978.0 0.1 15.0 434.9 6868.0 Saline Aquifer 1. Paleogene Maureen Fm Maureen 1 St Fergus 0 0 0 0 Progress to WP4
stratigraphic confinement
Open, with identified structural/
218.000 Site 14 156.0 430010.0 0.1 12.0 194.8 5777.0 Saline Aquifer 3. Lower Cretaceous Wick Sandstone Fm Captain_013_17 St Fergus 0 0 0 0 Progress to WP4
stratigraphic confinement
133.001 Site 8 211.0 36540.0 1.2 8.0 685.2 3923.0 Gas Condensate 5. Lower Jurassic Statfjord Fm Structural/Stratigraphic Trap Bruce Gas Condensate Field St Fergus 1 1 0 1 Progress to WP5
248.002 Site 19 120.0 175715.0 0.5 11.0 116.1 3946.0 Gas 6. Triassic Ormskirk Sandstone FmStructural/Stratigraphic Trap Hamilton gas field Connah's Quay 0 0 0 0 Progress to WP6
Open, no identified structural/
217.000 Site 27 81.0 378585.0 0.1 11.0 177.5 5946.0 Saline Aquifer 3. Lower Cretaceous Wick Sandstone Fm Coracle_012_20 St Fergus 0 0 0 0 Progress to WP4
stratigraphic confinement
218.001 Site 24 97.0 630000.0 4.6 8.0 167.1 5746.0 Oil & Gas 3. Lower Cretaceous Wick Sandstone Fm Structural/Stratigraphic Trap Captain Oil Field St Fergus 1 0 0 0 Progress to WP4
139.020 Site 26 84.0 22673.0 0.0 6.0 278.0 2127.0 Saline Aquifer 6. Triassic Bunter Sandstone Fm Structural/Stratigraphic Trap Bunter Closure 40 Barmston 0 0 0 1 Progress to WP4
141.002 Site 20 120.0 11430.0 0.6 9.0 359.4 4019.0 Gas 7. Permian Leman Sandstone Fm Structural/Stratigraphic Trap Barque gas field Barmston 1 1 1 0 Progress to WP4
252.001 Site 28 76.0 723900.0 18.4 8.0 443.1 4139.6 Oil & Gas 1. Paleogene Balder Fm Structural/Stratigraphic Trap Harding Central oil field St Fergus 1 0 1 1 Progress to WP4
248.007 Site 29 72.0 1286651.3 3.5 12.0 163.9 3982.0 Oil & Gas 6. Triassic Ormskirk Sandstone FmStructural/Stratigraphic Trap Lennox oil & gas field Connah's Quay 1 0 0 0 Reserve List
220.001 Site 16 130.0 4572.0 1.4 10.0 548.2 10016.1 Gas Condensate 3. Lower Cretaceous Britannia Sandstone Fm Structural/Stratigraphic Trap Britannia Condensate Field St Fergus 0 0 0 0 Reserve List
252.000 Site 30 64.0 424080.0 0.2 11.0 432.0 6947.1 Saline Aquifer 1. Paleogene Balder Fm Fully Confined (closed box) Balder Sandstone Member 1 St Fergus 0 0 0 0 Reserve List
244.000 Site 21 114.0 46288.0 0.1 12.0 555.4 3379.0 Saline Aquifer 1. Paleogene Sele Fm Fully Confined (closed box) Teal Sandstone Member St Fergus 0 1 1 1 Reserve List
241.000 Site 23 99.0 64860.0 0.2 12.0 412.1 1889.5 Saline Aquifer 1. Paleogene Sele Fm Fully Confined (closed box) Flugga Sandstone Member St Fergus 0 1 1 1 Reserve List
139.015 Bmk 5/42 554.0 98052.0 0.0 6.0 210.4 1057.0 Saline Aquifer 6. Triassic Bunter Sandstone Fm Structural/Stratigraphic Trap Bunter Closure 35 (5/42) Barmston 1 1 1 1 BENCHMARK ONLY
232.000 Site 15 137.0 177000.0 0.1 10.0 562.8 421.0 Saline Aquifer 1. Paleogene Horda Fm Fully Confined (closed box) Frigg Sandstone Member St Fergus 1 1 1 1 Hold
129.004 Site 17 128.0 10500.0 2.3 8.0 576.0 1495.5 Gas Condensate 4. Mid/Upper Jurassic Brae Fm Structural/Stratigraphic Trap Brae North Condensate Field St Fergus 1 1 1 1 Hold
129.003 Site 18 122.0 178560.0 2.1 8.0 625.7 1825.5 Gas Condensate 4. Mid/Upper Jurassic Brae Fm Structural/Stratigraphic Trap Brae East Condensate Field St Fergus 1 1 1 1 Hold
166.002 Site 22 104.0 81600.0 1.0 8.0 751.3 1947.0 Oil & Gas 4. Mid/Upper Jurassic Tarbert Fm Structural/Stratigraphic Trap Alwyn North Oil Field St Fergus 1 1 1 1 Hold
141.058 Site 25 85.0 5720.0 0.4 8.0 432.7 5102.0 Gas 7. Permian Leman Sandstone Fm Structural/Stratigraphic Trap Victor gas field Barmston 1 1 1 1 Hold
226.007 Site 31 63.0 19068.0 0.3 11.0 271.3 2978.0 Saline Aquifer 6. Triassic Bunter Sandstone Fm Structural/Stratigraphic Trap Bunter Closure 24 Barmston 1 1 1 1 Hold
141.038 Site 32 62.0 24888.4 0.3 12.0 410.9 3928.0 Gas 7. Permian Leman Sandstone Fm Structural/Stratigraphic Trap Audrey gas field Barmston 1 1 1 1 Hold
365.001 Site 33 60.0 27800.0 7.3 6.0 435.8 3285.5 Oil & Gas 1. Paleogene Lista Fm Structural/Stratigraphic Trap Andrew oil field St Fergus 1 1 1 1 Hold
226.002 Site 34 56.0 35476.0 0.5 9.0 317.5 4179.0 Saline Aquifer 6. Triassic Bunter Sandstone Fm Structural/Stratigraphic Trap Bunter Closure 18 Medway 1 1 1 1 Hold
82.002 Site 35 53.0 182500.0 4.5 8.0 578.7 7543.0 Oil & Gas 4. Mid/Upper Jurassic Fulmar Fm Structural/Stratigraphic Trap Fulmar Oil Field St Fergus 1 1 1 1 Hold
141.003 Site 36 50.0 2743.0 0.4 6.0 315.7 1420.0 Gas 7. Permian Leman Sandstone Fm Structural/Stratigraphic Trap Amethyst East gas field Barmston 1 1 1 1 Hold
252.002 Site 37 50.0 228600.0 3.1 6.0 442.4 4165.6 Oil & Gas 1. Paleogene Balder Fm Structural/Stratigraphic Trap Harding South oil field St Fergus 1 1 1 1 Hold
218.002 Bmk - Goldeneye 37.0 79000.0 0.6 8.0 331.4 6113.0 Gas Condensate 3. Lower Cretaceous Wick Sandstone Fm Structural/Stratigraphic Trap Goldeneye Gas Condensate Field St Fergus 1 1 1 1 BENCHMARK ONLY
Top 20 sites by Geological Age Top 20 sites by Unit Designation Top 20 sites by Storage Type Top 20 sites by Beachhead
1. Paleogene 5 Saline Aquifer 10 Structural/Stratigraphic Trap 14 Medway 0
6. Triassic 9 Oil & Gas 2 Open, no identified structural/ stratigraphic confinement 4 St Fergus 9
7. Permian 2 Gas Condensate 1 Open, with identified structural/ stratigraphic confinement 2 Connah's Quay 3
Pale Blue Dot Energy | Axis Well Technology Redcar 0 Page 54 of 74
D04: Initial Screening & Down-Select 7.0 Conclusions
7.0 Conclusions
1. CO2Stored is an excellent basis for this study and represents a single 8. Both the threshold for Theoretical Capacity and permeability were
consistent source of site storage attributes, albeit with challenging maintained at low levels to accommodate data uncertainty in these key
uncertainty issues. This project could not progress in the time and factors.
scope in the absence of the CO2Stored database. 9. The Identification of the sites was hidden from stakeholders until the
2. The methodology outlined in WP1 has been successfully deployed with end of the project to try to minimise any bias.
only minor refinements to achieve the WP3 objective. 10. The 50MT capacity and 50mD permeability threshold were the most
3. The recommended Top 20 sites for progression to work package 4 impactful criteria in the qualification process. 387 sites failing the
(“Twenty to Five”) represent a broad portfolio covering a strong capacity test and 188 sites failing the permeability test. Both are
diversity of unit type, store type and geography (beachhead); this is indicative of cost rather than security.
illustrated in Table 18 to Table 22. 11. Neither Goldeneye nor 5/42 reached the Qualified Inventory.
4. The selection and screening process used here is fully compliant with Goldeneye was smaller than the threshold and 5/42 lacked the
DNV (Det Norsk Veritas, 2012) and IEAGHG (IEA Greenhouse Gas required data availability test (the project did not have access to 3D
R&D Programme, 2009) recommended best practice. seismic over most of the structure). Furthermore both sites fail on the
5. The many to twenty down-select was based substantially upon the data availability criterion because they either are or expect to be licensed to
in CO2Stored, augmented by information from Wood Mackenzie Phase1 participants.
regarding estimated Cessation of Production for oil and gas fields and 12. After careful consideration, it was concluded that updating the
general publications such as the Millennium Volume (Gluyas & CO2Stored capacities for hydrocarbon field production between 2010
Hitchens, 2003). CO2Nomica (The ETI’s storage costing tool) was not and 2015 could not be justified as only the very largest fields had
used at this stage of the project. enough capacity to meet the project qualification criteria, and many of
6. A large number of small hydrocarbon fields were missing from these either had produced very little in the period or were younger
CO2Stored. Five additional sites were added to the Initial Inventory, fields and were unavailable until after 2030.
but all were subsequently screened out on the basis of capacity. 13. The Project Requirements qualification had the overall effect of
7. The methodology has navigated issues of data uncertainty to minimise removing 68% of the Initial Inventory eliminating a large number of
the risk of site exclusion because of data uncertainty. sites with low individual capacities. Some of these sites, such as
Removed1.4% of Initial Inventory capacity. achievable with care, although the method was impacted by very high
or very low value outliers.
Removed Sites had an average theoretical P50 capacity of
17. The weighting of the criteria was important to create a balanced
3MT.
ranking.
14. The IEAGHG Qualification step resulted in the removal of a large 18. The Stakeholder group expressed a preference for the “Simple View”
number of potential sites which did not meet the minimum cautionary ranking which focussed upon Capacity and Development Cost Factor
key attribute metrics for a potential CO2 storage site. Some of these (including Upside Potential).
sites carried large to very large capacities, but failed other key tests. 19. Ranking sensitivities agreed on whether to maintain or drop sites
across 76% of the Qualified Inventory (28 out of 37).
Site numbers reduced from 186 to 37; total theoretical capacity
20. If 5/42 and Goldeneye had been qualified then 5/42 would have ranked
reduced from 77,051MT to 8,295MT.
around 5th out of 37 and Goldeneye would have ranked around 27th out
Removed 80% of project qualified sites. of 37 (because of its small capacity).
Removed89% of project qualified capacity. 21. There is a 50:50 balance of saline aquifers and depleted hydrocarbon
fields in the recommended Select Inventory of twenty sites.
Removed Sites had an average theoretical P50 capacity of 461
22. 70% of the recommended Select Inventory are structural traps.
MT.
23. Neither of Redcar or Medway are the closest landfall to any of the sites
Some of these tests are temporal or use indicative criteria, and so in the recommended Select Inventory, but both Redcar and Medway
deselection now does not necessarily mean deselection in the future. are serviced by the Select Inventory.
In any case, 8MT exceeds the UKs likely needs for many decades.
8.0 Recommendations
The following twenty sites are recommended for progression to WP4 and for further consideration:-
Cost Factor $M
Risk per sq km
Proximal
Development
Containment
Containment
CO2stored
Engineering
Site Capacity Injectivity Upside Unit Nearest
Geological Age Geological Formation Storage Type Site Description
Code Number MT mDm Potential Designation Beachhead
MT
Risk
Geo
Structural/Stratigraphic
226.011 Site 1 1691 33380 0.6 9 292 3898 Saline Aquifer 6. Triassic Bunter Sandstone Fm Bunter Closure 9 Barmston
Trap
Structural/Stratigraphic
227.007 Site 4 409 23926 0.2 9 314 4287 Saline Aquifer 6. Triassic Bunter Sandstone Fm Bunter Closure 3 Barmston
Trap
Structural/Stratigraphic
266.001 Site 6 243 20500 0.3 11 299 3812 Gas 6. Triassic Bunter Shale Fm Hewett gas field Barmston
Trap
Structural/Stratigraphic
139.016 Site 7 232 11052 0.2 6 302 1179 Saline Aquifer 6. Triassic Bunter Sandstone Fm Bunter Closure 36 Barmston
Trap
Open, no identified
Grid Sandstone
336.000 Site 11 175 612500 2.0 8 304 9624 Saline Aquifer 1. Paleogene Horda Fm structural/ stratigraphic St Fergus
Member
confinement
Open, no identified
361.000 Site 12 174 48906 0.1 13 477 7140 Saline Aquifer 1. Paleogene Lista Fm structural/ stratigraphic Mey 1 St Fergus
confinement
Open, no identified
366.000 Site 13 162 10978 0.1 15 435 6868 Saline Aquifer 1. Paleogene Maureen Fm structural/ stratigraphic Maureen 1 St Fergus
confinement
Structural/Stratigraphic
248.002 Site 19 120 175715 0.5 11 116 3946 Gas 6. Triassic Ormskirk Sandstone Fm Hamilton gas field Connah's Quay
Trap
Open, no identified
217.000 Site 27 81 378585 0.1 11 177 5946 Saline Aquifer 3. Lower Cretaceous Wick Sandstone Fm structural/ stratigraphic Coracle_012_20 St Fergus
confinement
Structural/Stratigraphic
218.001 Site 24 97 630000 4.6 8 167 5746 Oil & Gas 3. Lower Cretaceous Wick Sandstone Fm Captain Oil Field St Fergus
Trap
Structural/Stratigraphic
139.020 Site 26 84 22673 0.0 6 278 2127 Saline Aquifer 6. Triassic Bunter Sandstone Fm Bunter Closure 40 Barmston
Trap
Structural/Stratigraphic
141.035 Site 5 271 8350 0.4 11 423 2711 Gas 7. Permian Leman Sandstone Fm Viking gas fields Barmston
Trap
Structural/Stratigraphic
141.002 Site 20 120 11430 0.6 9 359 4019 Gas 7. Permian Leman Sandstone Fm Barque gas field Barmston
Trap
Geo Containment
Development Cost
Containment Risk
Proximal
Site Capacity Injectivity Upside Nearest
Engineering
Code Unit Designation Geological Age Geological Formation Storage Type Site Description
Factor $M
per sq km
Number MT mDm Potential Beachhead
MT
Risk
Structural/Stratigraphic
248.007 Site 29 72 1286651 3.5 12 164 3982 Oil & Gas 6. Triassic Ormskirk Sandstone Fm Lennox oil & gas field Connah's Quay
Trap
Key features of the Top Twenty are: • A strong portfolio with a broad geographic spread:
o SNS, CNS and EIS.
• Significant overall capacity target of 6.8GT.
o Proximal sites to 5/42 and 5/42
• Strong balance between saline formations and depleted
o .
hydrocarbon fields.
o Strong technical diversity of sites.
• Elimination of sites with high risk high confidence containment
issues.
• Strong compliance with IEAGHG screening guidelines.
Further recommendations drawn from this work include:-
• Compliance with Project BoD qualifications.
9.0 References
Chadwick, A., Arts, R., Bernstone, C., May, F., Thibeau, S., & Zweigel, P. Pale Blue Dot Energy Ltd. (2015). A Blueprint for Industrial CCS in the UK -
(2008). Best Practice for the CO2 Storage in Saline Aquifers - Business Case. Retrieved from http://www.teessidecollective.co.uk/wp-
Observations and Guidelines from the SACS and CO2STORE projects. content/uploads/2015/06/Teesside-Collective-Business-Case1.pdf
Nottingham: British Geological Survey.
PGS. (2015). The PGS Mega surveys. Retrieved from
DECC - UK Government. (2015, March). UK Detailed Monthly OIl Production. http://www.pgs.com/upload/31007/MegaSurvey%20(1366Kb).pdf
Retrieved from https://www.og.decc.gov.uk/pprs/full_production.htm
spd. (2012). Aspen Conceptual Well Design Options - SPD-BOD-MP-CODS-
Det Norsk Veritas. (2012). DNV-RP-J203 Geological Storage of Carbon Dioxide. 0069. Aberdeen: CO2DeepStore Ltd.
Det Norsk Veritas. Retrieved from http://www2.dnvgl.com/dnv-rp-j203
THE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN
Element Energy Ltd. (2012). Economic impacts of CO2-enhanced oil recovery UNION,. (2009). DIRECTIVE 2009/31/EC OF THE EUROPEAN
for Scotland. Scottish Enterprise. PARLIAMENT AND OF THE COUNCIL ON THE GEOLOGICAL
STORAGE OF CARBON DIOXIDE. Official Journal of the European
Energy Technologies Institue. (2011). UK Storage Appraisal Project. Energy
Union, 114-135.
Technologies Institute.
UK Government. (2010). The Storage of Carbon Dioxide 9Licensing etc.)
Energy Technologies Institute. (2010). CO2Stored. Retrieved from
Regulations 2010. Retrieved from
http://www.co2stored.co.uk/home.php
http://www.legislation.gov.uk/uksi/2010/2221/pdfs/uksi_20102221_en.
Energy Technologies Institute. (2015). Carbon capture and storage - Building pdf
the UK carbon capture and storage sector by 2030 - Scenanrios and
Yoon, P. K., & Hwang, C. L. (1995). Mutliple Attribute Decision Making - An
actions. Loughborough: Energy Technologies Institute.
Introduction. Sage Publications Inc.
Gluyas, J. G., & Hitchens, H. M. (2003). United Kingdom Oil and Gas Fields
Commemorative Millenium Volume. London: Geological Society.
To keep CO2 Storage stakeholders appraised of project progress and 09:30 Welcome & Safety Briefing SJM
09:35 Purpose of Workshop SJM
enrol interest from the CCS stakeholder community 09:40 Strategic UK CCS Storage Appraisal Project SJM
Stimulate debate around the selected top twenty candidate sites & 09:55 Screening & Selection ATJ
10:15 Results ATJ
gather input to the process. 10:45 Break All
11:00 Workshop Session All
The materials assembled here represent a workshop report and were “work in 12:00 Feedback
progress” as of 2nd July. 12:20 Next Steps SJM
12:30 Close SJM
Participants
Jeb Tyrie APEC Ltd
Ken Johnson Axis Well Technology
Stephen Cawley BP
Don Reid Capture Power
Brian Allison DECC
Graham Dawe DNV GL
Den Gammer ETI
Andrew Green ETI
Benjamin Court GCCSI
Bill Senior Ind
Nick Reeves National Grid
Eva Halland NPD
David Hartney OGA
Frances Harding Pale Blue Dot Energy
Alan James Pale Blue Dot Energy
Steve Murphy Pale Blue Dot Energy
Chris McGarvey Pinsent Masons