Close Turfing

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

Method Statement -Turfing

1. INTRODUCTION
This method statement covers the following work activities associated with the requirement
of the contract document for (your project's name).
It is intended to assist site personnel in carrying out the performance of the activities. It also
serves to demonstrate to the client that we as the contractor understand the work scope
and is capable of undertaking it.

2. EQUIPMENT
a) Back Pusher
b) Water Pump and Pipe
c) Drum / Water Tank
d) Lorry
e) One Tonne Roller Compactor

3.0 GRASS / PLANT


The materials should come from approved sources by the client/consultant. The Contractor
shall arrange the nursery visit with the client/consultant to get the approved material
before delivered to the site.

3.1 Topsoil
Topsoil is the original surface layer or soil from cultivated land or forest area. It does not
generally include soil from swampy area, padi field or tin mining areas.
It is usually a darker shade of brown, grey or red than the subsoil that lies immediately
beneath it. Topsoil tends to be friable and show some degree of porosity. It should be free
from subsoil, admixture of stones, lumps, plants or roots and other extraneous matter.
Topsoil shall not deliver or used while in a muddy condition.

3.2 Axonupus Compressus (Cow Grass)


The grass should come from approved sources. The grass sod shall be cut and supplied at
the approximate size 300mm square and minimum thickness shall be 50mm with original
soil adhering to the roots. The sods shall be free from weeds and shall be delivered to site
and planted promptly to avoid desiccation.
4.0 METHOD OF PLANTING

4.1 Site Preparation


The Main Contractor is required to grade the planting area to finish grades and allowed for a
smooth and uniform to the consultant approval. The Main Contractor is required to roll,
scarify, rake and level so to obtain the even planting area. All loose stones, gravel, tree
stumps in which is not desirable is required to cart away from site to the approved dumping
area. To lay 50mm thick layer of approved black vegetable soil / top soil before turf.

4.2 Close Turfing


Turfing shall be carried out at all the terrace and slope area as specified (refer to the
construction drawing).
The grass sod used for close turfing shall be cut and supplied at approximate size of 300mm
square and minimum thickness 50mm with original sod adhering to the roots. The sods shall
be 50% pure comprised of Axonupus Compressus. Close turfing shall consist of
approximately 300mm square turfing laid side by side with gaps not exceeding 30mm. If
necessary, each sod shall be stack with 200mm peg through the sod into the soil base, to
prevent soil erosion.
The sods shall be laid onto the surface of the prepared ground with leaf turfs upwards, but
jointed as closed as possible to achieve a uniform cover. The turf shall be laid off planks
working over turns previously laid. The whole area should present an even smooth surface
when completed. Top dressing of the turf area shall be carried out immediately after the
turf is laid and monthly intervals thereafter.

4.3 Spot Turfing


Turfing shall be carried out to all the flat area as specified. The grass sod used for turfing
shall be cut and supplied at approximate size of 300mm square and minimum thickness
50mm with original sod adhering to the roots.
The sods shall be 50% pure comprised of Axonupus Compressus. Spot turfing shall consists
of approximately 300mm square turfing laid side by side with gaps on all sides of the turfing
not exceeding 300mm. If necessary, each sod shall be stack with 200mm peg through the
sod into soil base, to prevent soil erosion.
The sods shall be laid onto the surface of the prepared ground with leaf turfs upwards, but
jointed as closed as possible to achieve a uniform cover. The turf shall be laid off planks
working over turns previously laid. The whole area should present an even smooth surface
when completed. Top dressing of the turf area shall be carried out immediately after the
turf is laid and monthly intervals thereafter.
4.4 Planting of Bucida Molineti
The plant shall be of approved species shown on drawing and in healthy growing condition
obtained from an approved source. Black earth shall consist of fertile top soil obtained from
an approved source. Generally all pits for planting of trees shall not be less than 750mm x
750mm deep, spaced at intervals as shown in the drawings or approved by E.R. the bottom
and side of pits shall first be filled with layer of black earth before transplanting.

4.5 Watering
Watering shall be carried out immediately after the completion of planting. The completed
areas shall be lightly sprayed with water and keep the areas moist.

4.6 Maintenance
Maintenance shall begin immediately after each portion of turfed and planting area is
installed and shall continue for the period of maintenance as specified commencing from
the date of acceptance. Maintenance is including watering, fertilizing, spraying and mowing.

· Watering (Cow Grass and Bucida Molineti)


Watering is required to soak and penetrate the soil at a rate that will prevent saturation of
the soil. The rate of application shall be not less than 2.7 litre per square meter and on no
account shall turf be watered sparingly. During dry weather, shall be watered within 2 days
of laying and subsequently once a week.

· Weeding (Cow Grass)


Keep all planting area free from weed and undesirable grasses, by a method and by
materials approved by client / E.R / Consultant.

· Mowing (Cow Grass)


Mowing on newly established turfed areas should be delayed until it is obvious that the
grass is growing strongly. The grass should be cut when they are about 50mm – 75mm in
height can be gradually lowered at subsequent mowing until the height of 25mm to 40mm
is achieved. Remove the grass clipping during or immediately after mowing.

· Top Dressing (Cow Grass)


After established turfed areas, determine the evenness of the ground level and if any
uneven ground level the top dressing shall be applied. Mixed river sand and topsoil will be
filled up to the uneven area and also to any visible gap between sods.
· Protection (Cow Grass)
Maintenance shall include all temporary protection of all turfing areas from trespassing and
damage at all times. If any portion of turfed area is damaged, it shall be treated and replace.

· Fertilizer Application (Cow Grass)


Fertilizer shall be Christmas Island Rock Phosphate or its equivalent applies at the rate of
34gms per square meter with the approval of Consultant after planted until 6 months.

NPK 15:15:15 shall be used after 3 months planted at the rate of 100gms per square meter
and continue the application every 3 months.

· Fertilizer Application (Bucida Molineti)


Fertilizer shall be Christmas Island Rock Phosphate or its equivalent applies at the rate of
0.3kg per square meter with the approval of Consultant prior to planting, spread evenly in
pit base.

NPK 15:15:15 shall be used at the rate of 200gms for each plant every month for the first
year period. For the next year after, fertilizing shall be continued every 4 months. This
fertilizer must be applied around the plant, outside the canopy area.

· Supporting Wood (Bucida Molineti)


Supporting wood shall be used to support the plant, depend on the plant size.

· Pruning (Bucida Molineti)


Pruning shall apply from surface area.

· Control Diseases and Pests (Bucida Molineti)


Watering and cleaning the affected area at the plant. Cut and remove branches that were
attacked by worms and insects.

4.7 Handing Over


Main Contractor shall arrange joint site inspection for handing over after the end of the
period maintenance. Main Contractor shall be carried out rectification works for any defect
works.
5.0 SAFETY

5.1 Safety
1) The workers shall provide with PPE (Personal Protective Equipment) and shall be
worn all the time.
2) During fertilizer work, the workers shall provide additional equipment such as
safety goggles and mouth and nose filters to avoid contact with fertilizer.
3) Site safety member should be available at all the time.

5.2 Environmental
1) The Contractor shall ensure no open burning is allowed at the site.
2) All the waste shall be collected and disposed correctly.
3) The Contractor shall ensure there is no oil leakages from machinery (cutting
machine) which is could harm the environment.

You might also like