Labour Productivity Chart

This document contains 64 items listing formwork tasks, required crew sizes, hourly production rates, and estimated production over 10 hours. The tasks include formwork for footings, beams, columns, walls, slabs, stairs, parapets and more. Crew sizes typically include 2 carpenters and 1 helper, with hourly production rates ranging from 0.5 to 2 square meters. The document provides production estimates for construction formwork planning.

Uploaded by

Jahanzaib Waheed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views14 pages

Labour Productivity Chart

This document contains 64 items listing formwork tasks, required crew sizes, hourly production rates, and estimated production over 10 hours. The tasks include formwork for footings, beams, columns, walls, slabs, stairs, parapets and more. Crew sizes typically include 2 carpenters and 1 helper, with hourly production rates ranging from 0.5 to 2 square meters. The document provides production estimates for construction formwork planning.

Uploaded by

Jahanzaib Waheed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 14

Item No.

CREW SIZE Hourly Production


Production Rate Per 10 hrs.
SM
FW FORMWORK
FW01 Formwork to footings 2 CARPENTERS, 1 HELPER 1.2 12
FW02 Formwork to isolated footings 2 CARPENTERS, 1 HELPER 1.6 16
FW03 Formwork to rafts 2 CARPENTERS, 1 HELPER 1.4 14
FW04 Formwork to rafts D>0.75m 2 CARPENTERS, 1 HELPER 1.8 18
FW05 Formwork to tie beams 2 CARPENTERS, 1 HELPER 1 10
FW06 Formwork to high level tie beams D>0.45M 2 CARPENTERS, 1 HELPER 1.2 12
FW07 Formwork to Neck Columns 2 CARPENTERS, 1 HELPER 4
FW08 Formwork to U/G Water tank 2 CARPENTERS, 1 HELPER 6
FW09 Formwork to basement retaining walls 2 CARPENTERS, 1 HELPER 9
FW10 Formwork to columns (small size) 2 CARPENTERS, 1 HELPER 7
FW11 Formwork to Columns (large size) 2 CARPENTERS, 1 HELPER 9
FW12 Formwork to D/S beam internal (shallow) 2 CARPENTERS, 1 HELPER 6
FW13 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 7
FW14 Formwork to D/S beam external (Shallow) 2 CARPENTERS, 1 HELPER 4
FW15 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 6
FW16 Formwork to lift walls single core 2 CARPENTERS, 1 HELPER 6
FW17 Formwork to lift walls multi core 2 CARPENTERS, 1 HELPER 8
FW18 Formwork to slab decking (10ft) hourdi 2 CARPENTERS, 1 HELPER 1.6 16
FW19 Formwork to slab decking (>10ft) hourdi D/S beams 2 CARPENTERS, 1 HELPER 1.2 12
FW20 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.2 12
FW21 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1 10
FW22 Formwork to staircase (non spiral) 2 CARPENTERS, 1 HELPER 4
FW23 Formwork to balcony parapets 2 CARPENTERS, 1 HELPER 6
FW24 Formwork to roof parapets 2 CARPENTERS, 1 HELPER 8

D = DEPTH Page 1 of 7
U. GR. = UNDERGROUND
D/S = DECK - SLAB
> = GREATER THAN
< = LESS THAN
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)

Item No. CREW SIZE Hourly Production


Production Rate Per 10 hrs.
FW 25 shutter Manufacture for pile caps 1 CARPENTER + 1 HELPER 2.00 20
FW 26 shutter Fix for pile caps I CARPENTER + 1 HELPER 1.50 30
FW 27 Deshutter footings/pile caps 1 HELPER 6.00 60
FW 28 Shutter make column necks 1 CARPENTER + 1 HELPER 1.50 15
FW 29 Shutter fix column necks 1 CARPENTER + 1 HELPER 1.20 12
FW 30 Deshutter Column necks 1 HELPER 4.80 48
FW 31 Shutter make tie beams 1 CARPENTER + 1 HELPER 1.20 12
FW 32 shutter fix tie beams 1 CARPENTER + 1 HELPER 1.00 10
FW 33 Column shutter making 1 CARPENTER + 1 HELPER 1.20 12
FW 34 Column shutter fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 35 Column deshuttering 1 HELPER 4.00 40
FW 36 Walls shutter making 1 CARPENTER + 1 HELPER 1.50 15
FW 37 Walls shutter fixing 1 CARPENTER + 1 HELPER 0.80 80
FW 38 De shutter Tie beam shutter 1 HELPER 4.00 40
FW 39 Wall formwork deshuttering 1 HELPER 3.20 32
FW 40 Staircase formwork making 1 CARPENTER + 1 HELPER 0.80 8
FW 41 staircase formwork fixing 1 CARPENTER + 1 HELPER 0,8 8
FW 42 Staircase formwork deshuttering 1 HELPER 1,6 16
FW 43 Drop beams formwork making 1 CARPENTER + 1 HELPER 1.00 10
FW 44 Drop beams formwork fixing 1 CARPENTER + 1 HELPER 0.80 8
FW 45 Drop beams formwork stipping 1 HELPER 3.20 32
FW 46 suspended slab formwork fixing 1 CARPENTER + 1 HELPER 1.20 12
FW 47 suspended slab formwork deshutter 1 HELPER 5.00 50
FW 48 Formwork fixing for sunshades 1 CARPENTER + 1 HELPER 0.70 7
FW 49 Parapet formwork making 1 CARPENTER + 1 HELPER 1.20 12
FW 50 Parapets formwork fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 51 Parapets formwork stripping 1 HELPER 4.00 40
FW 53 Fixing of lintle formwork 1 CARPENTER + 1 HELPER 0.50 5
FW 54 Deshutter lintle formwork 1 HELPER 2.00 20
FW 55 Deck formwork fixing 1 CARPENTER + 1 HELPER 1.50 15
FW 56 Deck Formwork deshuttering 1 HELPER 6.00 60
FW 57 Pipe scaffolding erection for slab 1 SCAFFOLDER 0.85 85
FW 58 inverted beam shutter fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 59 De-Shuttering Manholes, square - circular (Timber) 1 CARPENTER + 1 HELPER 4m2 40m2
FW 60 Manhole Shutter erection - square or circular(Timber) 1 CARPENTER + 1 HELPER 1,5 m2 15m2
FW 61 Metal Shutter for Manholes 1 CARPENTER + 1 HELPER 1m 2
10m2
FW 62 Metal Shutter for Precast Beams 2 CARPENTERS + 2 HELPERS 3M 2
30M2
FW 63 Metal Shutter for Pile caps 2 CARPENTERS + 2 HELPERS 3M 2
27M2
FW 64 Metal Shutters for Pile cap Beams 2 CARPENTERS + 2 HELPERS 3M2 30M2

Page 2 of 7
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
M MASONARY WORKS
MBW 01 Hollow Blockwork (100, 150 & 200 mm) 1 MASON, 1 HELPER 12 Nos 120 NR
MBW 02 Hollow Blockwork (large panels) 1 MASON, 1 HELPER 14 Nos. 140 NR
MBW 03 Solid blockwork 1 MASON, 1 HELPER 9,5 95 NR
MBW 04 Solid Blockwork as Raft forms 1 MASON, 1 HELPER 11 110 NR
MPL PLASTERWORK 1.2
MPL 01 Plaster (internal), walls final coat 1 MASON, 1 HELPER 1.6 16 SM
MPL 02 Plaster (internal), walls rush coat 2 HELPER 1.4 150 SM
MPL 03 Plaster (internal), walls mesh 1 HELPER 1.8 100 SM
MPL 04 Plaster (internal), walls hacking 1 HELPER 1 100 SM
MPL 05 Plaster (internal), walls guide point 1 MASON, 1 HELPER 1.2 100 SM
MPL 06 Plaster (internal), walls corner beads 1 MASON, 1 HELPER 10 SM 100 SM
MPL 07 Plaster (external), walls with grooves 1 MASON, 1 HELPER 10 SM 10 SM
MPL 08 Plaster (external), walls without grooves 1 MASON, 1 HELPER 1,2 12 SM
MPL 09 Plaster (external), walls rush coat 2 HELPER 15 SM 150 SM
MPL 10 Plaster (external), walls mesh 1 HELPER 10 SM 100 SM
MPL 11 Plaster (external), walls hacking 1 HELPER 10 SM 100 SM
MPL 12 Plaster (external), walls guide points 1 MASON, 1 HELPER 10 SM 100 SM
MPL 13 Plaster (external), walls corner beads 1 MASON, 1 HELPER 10 SM 100 SM
MPL 14 Plastering of Arches/Mullians 1 MASON, 1 HELPER 0.8 80
MPL 15 Floor screed 50mm thick 1 MASON, 1 HELPER 2 20
MPL 16 Roof screed 100 mm thick 1 MASON, 1 HELPER 1.5 15
MPL 17 Mosiac floor Tiles fixing 1 MASON, 1 HELPER 1.6 1.5
MPL 18 Floor Screed 25mm thick 1 Mason + 1 Helper 0,6 6
MCR CERAMIC WORKS
MCR 01 Ceramic tiles to walls by mortar 1 MASON, 1 HELPER 1.2 8 SM
MCR 02 Ceramic tiles to walls, mortar to corridors 1 MASON, 1 HELPER 1 9 SM
MCR 03 Ceramic tiles to walls, cut pieces 1 MASON 2 20 SM
MCR 04 Ceramic tiles to walls grouting 1 HELPER 5 50 SM
MCR 05 Ceramic tiles to walls, by glue 1 MASON, 1 HELPER 1,2 12 SM
MCR 06 Ceramic tiles to walls, corridors, by glue 1 MASON, 1 HELPER 1,3 13 SM
MCR 07 Ceramic tiles to walls, by glue, cut pieces 1 MASON 2 20 SM
MCR 08 Ceramic tiles to walls, by glue, grouting 1HELPER 5 50 SM
MCR 09 Ceramic tiles to floors 1 MASON, 1 HELPER 1 10 SM
MCR 10 Ceramic tiles to floors in halls 1 MASON, 1 HELPER 1,2 12 SM
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


(Rev 0, May 2000)
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60

Page 3 of 7
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
MCR CERAMIC WORKS
MCR 13 Ceramic skirting by glue 1 MASON, 1 HELPER 2,5 M 25 METRE
MCR 14 Ceramic skirting by glue to halls, corridors 1 MASON, 1 HELPER 3M 30 METRE
MTW TILING WORKS
MTW 01 Mosiac / Terrazo tiles to roofs 1 MASON, 1 HELPER 1,6 16 SM
MTW 02 Mosiac / Terrazo tiles to floors 1 MASON, 1 HELPER 1,4 14 SM
MTW 03 Mosiac skirting to halls 1 MASON, 1 HELPER 2,5 25 METRE
MTW 04 Mosiac skirting flush / recessed 1 MASON, 1 HELPER 1,4 14 METRE
MTW 05 Grouting / sealing to roof / floor tiles 1 HELPER 2,5 25 METRE
MKP KERBING / BLOCK PAVING WORKS
MKP00 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 METRE
MKP01 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 METRE
MKP02 Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 40 METRE
MKP03 kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 15 METRE
MKP04 Interlock paving on pre prepared sub - base 1 MASON, 1 HELPER 2 SM
MKP05 Screed works including preparation 1 MASON, 1 HELPER 1,5 15 SM
MKP06 Haunching ot Kerb Base (Mixing Truck) 1 MASON, 1 HELPER 10 M 100M
DRW MANHOLE/ DRAINAGE CONSTRUCTION
DRW 01 Excavation for drains / manholes 1 HELPER 5 CM
DRW 02 Backfill to drains / manholes 1 HELPER 10 CM
DRW 03 Blockwork to manholes 1 MASON, 1 HELPER 2 NOS
DRW 04 Plaster to manholes 1 MASON, 1 HELPER 2 NOS
DRW 05 Benching to manholes 1 MASON, 1 HELPER 4 NOS
DRW 06 Fix covers to manholes 1 MASON, 1 HELPER 2 NOS
DRW 07 Fix gulley traps 1 MASON, 1 HELPER 1 NO
DRW 08 Laying of P.V.C. sleeves 4" - 12" 4 HELPER 24M 240M
MLW MISCELLANEOUS LABOUR WORKS
MLW01 Bitumen paint to concrete blockwork surfaces 1 HELPER 4 40 SM
MLW02 Bitumin painting Bases / piles 1 HELPER 7.00 70
MLW03 Hacking of concrete surfaces 1 HELPER 5 50 SM
MLW04 fixing of flexcell sheets 1 HELPER 6 SM
MLW05 pile cutting/dressing 1 HELPER 1 NO
MLW06 pile cutting/dressing (small diameter) 1 HELPER 2 NOS
MLW07 Vertical sealant (12 mm) 1 HELPER 2,5 25 METRE
MLW08 Horizontal sealant (12 mm) 1 HELPER 5 50 EMTRE
MLW09 Roof preparation for lw concrete 1 MASON, 1 HELPER 5 50 SM
MLW10 Angle fillet fixing 1 MASON, 1 HELPER 4 40 EMTE
MLW11 Hourdi block shifting and fixing to slab 2 HELPER 20 200 NOS
MLW12 Polythene sheet fixing 1 HELPER 3m 30
MLW13 Shaping of Soil Blinding 1 MASON + 1 HELPER 1M 10M
MLW14 Protection Board installation 1 CARPENTER + 1 HELPER 8M2 80M2
MCW MISCELLANEOUS CARPENTARY WORKS
MCW 01 A/C subframe manufacture / fixing 1 CARPENTER 5 NOS
MCW 02 Door subframe manufacture / fixing 1 CARPENTER 4 NOS
MCW 03 Water bar fixing 1 CARPENTER 2M 20 METRE
Page 4 0f 7
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
CPW CONCRETE PLACEMENT WORKS
CPW01 Concrete to pile caps by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM
Standard rate 1 man 1 hr. 10m3
CPW02 Concrete to PCC blinding (100 mm thick) 1 MASON, 10 HELPERS 27 CM
CPW03 Concrete to slabs/beams, by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM
CPW04 Concrete to slabs / beams by crane 1 MASON, 6 HELPERS, 0.5 OPERATOR 8,10 27 CM
CPW05 Concrete to walls / columns, by pump 4 MASONS, 16 HELPERS, 2 CARPENTERS 1.2 81 CM
CPW06 Concrete by site mix 1 MASON, 12 HELPERS , 0.5 CARPENTER 1.6 9 CM
CPW07 Concrete Columns 8 HELPERS 1.40 10
CPW08 Concrete suspended slab (pump) 3 MASONS + 6 HELPERS 1.80 150
CPW09 Concrete parapets/staircases 8 HELPERS 1.00 7
CPW10 Blinding concrete 50 mm (readymix) 1 MASON + 4 HELPER 8,0 80
CPW11 Blinding concrete 50 mm (sitemix) 1 MASON + 8 HELPER 1.00 10
CPW12 Concrete footings & pile caps 1 MASON + 4 HELPER 12.00 120
CPW13 Concrete tiebeams, ground beams 1 MASON + 5 HELPER 6.00 60
CPW14 Concrete column necks 8 HELPER 1.50 15
CPW15 Concrete Ground slab 3 MASONS + 6 HELPER 1,5 15
CPW16 Concrete to precast slabs, beams 2 MASONS + 1 HELPER 3m3 30 M3
GLW GENERAL LABOUR WORKS
GLW01 Unloading reinforcement ((Flat Bed Truck) 4 HELPERS 2 Nos
GLW02 Loading reinforcement to slab (With Crane) 4 HELPERS (Flat Bed Truck loads) 40 Nos. 2 Nos
GLW03 Loading blockwork to site (with Wheel Burrow) 1 HELPER 400 Nos.
GLW04 Loading mortar to site location
GLW05 Mixing mortar for distribution 0, 3 L mixer 4 HELPER 6M3
GLW06 Site mixing of ready mix for distribution Hand mix 3M3
GLW07 Loading ready mix to site location
NTRA NON TARGET RELATED ACTIVITES
NTRA01 Stacking of formwork 2 HELPERS
NTRA02 Curing of Substructure works 2 HELPERS
NTRA03 Curing of beams / slabs Hessiant Water 2 HELPERS
NTRA04 Curing of columns (Hessiant Water) 1 MASON + 2 HELPERS 1.6 (L.M) 36 M
NTRA05 Builders work make good chases 1.2 (L.M)
NTRA06 Site cleaning 1 HELPER 25 250 M2
NTRA07 Repairs to finished works 1

Page 5 of 7
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)

Item No. CREW SIZE NON MEASURABLE


NTRA08 Maintenance of site services 2 HELPERS
NTRA09 Operators for mixers 2/MIXER
NTRA10 Operators for compaction equipment 1 UNIT
NTRA11 Office boy ARABTEC 1 / CONSULTANT 1
NTRA12 Watchman 2 MIN
NTRA13 Storekeeper 1/SHIFT

Page 6 of 7
Item No. CREW SIZE Hourly
Production Rate

RF REINFORCEMENT
RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 25
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 20
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 18
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FIXER 20

RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 78


RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 38
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 35
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FIXER

RFC 01 Steel cutting and bending 18.25 mm 1 STEEL FIXER 50.00


RFC 02 Steel cutting and bending 8 - 16 mm 1 STEEL FIXER 40.00

EXCAVATION
EX 1 Manual Excavation 1 HELPER
EX 2 Backfill + levelling 1HELPER
EX 3 Shaping of sloped earth for blinding for bases including compaction 1 MASON + 2 HELPER
Productivity Rates for Tilling

Size. (Cms) Location Area Manpower Production Rate Remarks


(Sqm. Per day)

30 X 30 Floor Kitchen 1 Mason, 1 Helper 14 Residential Area by Sub-Contractor

30 X 30 Floor with pattern Corridor 1 Helper, 2 Masons 10 Residential Area by Sub-Contractor

40 X 40 Floor Bed room 1 Mason, 1 Helper 22-25 Residential Area by Sub-Contractor

20 X 20 Floor Store (small area) 1 Mason, 1 Helper 10 Residential Area by Sub-Contractor

30 X 60 Floor Bathroom 2 Mason, 1 Helper 6 Residential Area by Sub-Contractor

30 X 30 Floor + Wall Bathroom 2 Mason, 1 Helper 5

10 X 10 Wall Kitchen 1 Mason, 1 Helper 8-9 Residential Area by Sub-Contractor

30 X 60 Wall Corridor 1 Mason, 1 Helper 14-15 Residential Area by Sub-Contractor

30 X 30 Wall Bathroom 2 Mason, 1 Helper 7 Residential Area by Sub-Contractor

Residential Area by Sub-Contractor

Notes:

1. 1 Day = 10 hrs.

2. Gang Size:

1 Mason + 1 Helper for Kitchen and Bedroom.

2 Mason + 1 Helper for Bathroom.


Designation
Sr.No Name ID.No Rate per Day Number Remarks
Mason Labour Carpenter

1 Sohag Contractor 15 14 30680602

2 Masoom Contractor 70089806

3 Tuhin Supervisor 14 13 66219251

4 Tarikol Islam 15 12 66219251 without transportation

5 Borhan 77307579

6 Sarif Contractor 55755192

7 Jasim Contractor 50182283

8 Malik Supplier 18 16 66552054

9 Abdul Mubin Supplier 13 77536403 Including Transportation

10 Muhammad Mezba 29105023305 1 120 70694098 without transportation 10 Hours

11 Sattar Hassan 28005024192 1 120 50181923 without transportation 10 Hours

12 Nozrul Islam 29005006624 1 120 33385619 without transportation 10 Hours

13 Rakibul Islam 29605015010 1 100 31449033 without transportation 10 Hours

14 Mohammad Kamal 28205030814 1 100 70953422 without transportation 10 Hours

15 Enamul Hoque 28205029803 1 100 31184155 without transportation 10 Hours

16 Mijan 28605024566 1 100 33724927 without transportation 10 Hours

17 Muhammad Rashed 29005019184 1 100 31061137 without transportation 10 Hours

18 Abdul Qadir 29205027220 1 100 30945971 without transportation 10 Hours

19 Abu Hanif 27305007929 1 100 without transportation 10 Hours

20 Kamran Hossain 29005029383 1 100 30490316 without transportation 10 Hours

21 Feroz Muhammad 29105026039 1 100 77258242 without transportation 10 Hours

22 Alnoudin Farid 28105019671 1 100 30762872 without transportation 10 Hours

23 khairul Mia 298405009721' 1 100 without transportation 10 Hours

24 Runi Mia 2929805005425' 1 100 without transportation 10 Hours

25 Aminul Islam 298705005382' 1 120 77542240 without transportation 10 Hours

26 Nasir Khan 28405007556 1 120 33295320 without transportation 10 Hours

27 Jaylal 28352428250 1 120 33434898 without transportation 10 Hours

28 Mohammad Surut 27505009597 1 120 55268479 without transportation 10 Hours

29 Shofik Ahmed 29605014942 1 120 74756208 without transportation 10 Hours

30 Khorsed Alam 28805010014 1 120 77238314 without transportation 10 Hours

31 Neamot Ullah 28005024130 1 120 30775642 without transportation 10 Hours

32 Murad Munshi 28905004313 1 120 31174376 without transportation 10 Hours

33 Rubel Hossain 29305011440 1 120 31174376 without transportation 10 Hours

34 Muhammad Masod 28305021452 1 120 31174376 without transportation 10 Hours


35 Muhammad Anisur 29105008553 1 120 31174376 without transportation 10 Hours

36 Abobakar 27905013329 1 120 50802171 without transportation 10 Hours

37 Asharul Mandal 28535677585 1 120 70166977 without transportation 10 Hours

38 Muhammad Hassan 29505013152 1 120 74450628 without transportation 10 Hours

39 Shamsul Haque 27105003449 1 120 338636612 without transportation 10 Hours

40 Muhammad Nazmul 2875011540 1 120 33179124 without transportation 10 Hours

41 Tazal Islam 27305005539 1 130 33911996 without transportation 10 Hours

42 Ruhil Amin 29205021116 1 120 31541349 without transportation 10 Hours

43 Robel Khalil 29705006261 1 120 55624283 without transportation 10 Hours

44 Abdul Salam 29405024916 1 100 60085524 without transportation 10 Hours

45 Jobadur Rahman 30205000721 1 100 31465795 without transportation 10 Hours

46 Iqbal Kholifa 29605002555 1 120 70979244 without transportation 10 Hours

47 Hridoy kazi 29005028692 1 120 30575390 without transportation 10 Hours

48 Ashik Rain 30335605099 1 100 70642353 without transportation 10 Hours

49 Riyasat Momin 29235636239 1 100 77262250 without transportation 10 Hours

50 Amirol Amshad 30335605010 1 100 70848932 without transportation 10 Hours

51 Mohammad Nausad 29535633699 1 100 31267096 without transportation 10 Hours

52 Arman 30035612884 1 100 70572362 without transportation 10 Hours

53 Rashid Alam 362022146502' 1 100 70582691 without transportation 10 Hours

54 Kisan Ram 28435646237 1 100 70848948 without transportation 10 Hours

55 Mohammad Israil 29735627223 1 100 55390120 without transportation 10 Hours

56 Mohammad Najir 28835690312 1 100 70639398 without transportation 10 Hours

57 Muhmmad Hakim 28235670935 1 100 77276241 without transportation 10 Hours

58 Mohammad Israel 29635631941 1 100 70641270 without transportation 10 Hours

59 Mohammad Shamim 28835669572 1 100 70655425 without transportation 10 Hours

60 atabul Rain 28935647839 1 100 70929606 without transportation 10 Hours

61 Muhammad Aloudin 29735627429 1 100 70655416 without transportation 10 Hours

62 Anvarul 28935659656 1 100 33828362 without transportation 10 Hours

63 Mohammad Bali 28435679771 1 100 31097980 without transportation 10 Hours

64 Mithun Biswas 29335645564 1 120 74415894 without transportation 10 Hours

65 Shuvash Chandra 29305022018 1 120 77626018 without transportation 10 Hours

66 Tapu Sikdar 30035611376 1 120 74415895 without transportation 10 Hours

67 Subrata Bagchi 29335646931 1 120 77101905 without transportation 10 Hours

68 Rakesh sarkar 29735612577 1 120 30080640 without transportation 10 Hours

69 Alim habibur 27905015525 1 100 50432465 without transportation 10 Hours

70 Mohammad Raihan 28705005885 1 100 74712881 without transportation 10 Hours

71 Mohammad Salahudin 27505008220 1 100 70934338 without transportation 10 Hours

You might also like