Objectives of On The Job Training Program
Objectives of On The Job Training Program
2|Page
For example, C1-8#16mm∅ and stirrup- 8mm∅@5”c/c
This means, the column C1 will have 8 numbers of 16mm diameter bars as
the vertical bar and 8mm diameter steel should be placed 5 inch center to center
spacing as the stirrup.
c) Column Formwork: The floor height is normally kept at 10 feet. If the slab
contains beam, then concrete has to be poured upto beam bottom level. For
example, if the beam height is given in the drawing is 1’-6”, the casting height of
column and formwork will be 8’6”. But as we know that dropping concrete more
than 5 feet height is not allowed because it will cause segregation, we should
create formwork within 5 feet height. When the first part will be cast completely,
the rest should be started.
3|Page
Figure No.4:-Pouring
No.4: Pouring Concrete into Column
2.3)) Brick Wall Construction:
Brickwork is masonry done with bricks and mortar and is generally used to build
partition walls. In our site, all the external walls were of concrete and most of the
internal walls were made of bricks. English bond was used and a ratio of 1:4 (1
cement: 4 coarse sand) and 1:6 was used depending upon upon whether the wall is 4.5
inches or 9 inches.
5|Page
2.5) Stair Casting:
The followings are the steps involved in construction of stairs,
The most important step when building concrete stairs is to use a proper
formwork. The angle of flight, dimensions of thread and riser are to be properly
checked. Usually while constructing a stair attached to wall, the line of flight, thread
and risers are marked on the wall for proper fixing of shuttering or formwork.
6|Page
Figure No.7: work for Concrete Stairs
No.7:-Building the Form-work
The boards must be at least 2” thick, as to support the weight of the concrete. The
whole structure of the form, must be supported by 4×4 posts. The wooden boards are
used to create the steps and are fastened with several screws to the lateral structure of
the formwork.
Use a spirit level, as to make sure the form is level and plumb, if you want to
obtain a neat look. The form of the concrete stairs should be connected to the ceiling.
7|Page
These steel reinforcement bars are placed in the formwork with minimum of 25
mm spacing and is tied together.
8|Page
Fig
Figure No.10:-Removal of Formwork
7. Finishing of Concrete Stairs
Once the formwork is removed, the stairs can be finished in many ways as per the
requirement of the use. It can just be finished using trowel or float to give concrete
finish, cement tiles, granite can be installed for better appearance. Even carpet or
wood can also be used to finish the stairs.
Figure
ure No.11:-Finishing
No.11 of Concrete Stairs
9|Page
2.6) Beam and slab casting:
Slab is an important structural element which is constructed to create flat and
useful surfaces such as floors, roofs, and ceilings. It is a horizontal structural
component, with top and bottom surfaces parallel or near so. To read more about slab
thickness evaluation please click here. Commonly, slabs are supported by beams,
columns (concrete
te or steel), walls, or the ground. The depth of a concrete slab floor is
very small compared to its span.
Figure
Fig No.12:-Bam & slab casting
2.7) Flooring:
Flooring is the general term for a permanent covering of a floor, or for the work of
installing such a floor covering. Floor covering is a term to generically describe any
finish material applied over a floor structure to provide a walking surface. Both terms
are used interchangeably but floor covering refers more to loose-laid
loose materials.
Materials almost
lmost always classified as floor covering include carpet, area rugs, and
resilient flooring such as linoleum or vinyl flooring. Materials commonly called
flooring include wood flooring, ceramic tile, stone, terrazzo, and various seamless
chemical floor coatings.
tings.
2.8) Plastering:
Plaster may be defined as Lean Mortar used mostly for covering masonry surfaces.
They are lean mixes of Binding Materials (Lime or Cement) with fillers material such
as Sand or Crushed stones. And the process of covering surfaces with
wi Plaster is called
Plastering.
10 | P a g e
They are specially prepared for two reasons.
reasons
i) For Protection.
ii) For Decoration.
In protective covering, the Plaster saves the Bricks or Stones from Direct
Destructive Attacks of Atmosphere such as Wind, Rain and Harmful Industrial
Gases.
As a decorative finish, Plasters are used to give many appealing shades and finish
designs to the construction.
A building aims to give shelter along with security. Other purposes such as buildings
serve several needs of society primarily as shelter from the weather, security, living
space, privacy, to store belongings, supplied electricity, and to comfortably live and work
12 | P a g e
3. CONCLUSION
The main aim of studies within this project was to investigate how a structure is
constructed within its desired properties. We get knowledge about the basic & advanced
techniques of building construction as well as saw the challenges which a civil engineer
must face during construction i.e. labour problems, cost management, environmental
challenges etc. We cleared our many doubts regarding building construction. We had
seen dewatering system at project site for construction, which is not used at our state
anymore, so it was a new thing for us.
Although are subjects more important for technicians, in the project we have been
studied some mechanic or electro-mechanic machinery such as the ready-mix plant
because basic knowledge about their working is important for an engineer but also
because was the opportunity to see and understand them.
Overall, it must be said that the construction methods and quality control on a
highway
Project needs a very good coordination and large quantities of manpower, equipment
and funds.
During the period of three months all the school teacher helped us a lot to provide all
the information about any query. So we are grateful to all the teacher of Shree Tribhuvan
Secondary School Gaushala-05, Mahottari, (Nepal), as well as we are so thankful to our
Er.Surendra Sah, Er.Pappu Roushan, Er.Raj Bahadur Sah & Er.Sushil Sah for their kind
support.
13 | P a g e
4. References
♦ Mentor’s notes
♦ Building Construction book of BC
Punmia ♦ Website of slideshare.net
♦ Under the suggestion of our technical teacher’s
team ♦ Some other notes from our senior’s
♦ Building Construction book of D.Prasad & R.K. Shrestha
14 | P a g e
5. Appendix
Fig
Figure No.15:- Brick Soling & P.C.C.
Figure
ure No.16:-Ground
No.16 Ground Beam with Column Bars
15 | P a g e
Figure No.17:-Brick
Brick Work above ground beam & back filling
Figure No.18:-Formwork
Formwork of Column and Brick work above plinth
16 | P a g e
Figure No.19:: Formwork & Shuttering work for slab casting
Figure
Fig No.20: Concreting the slab
17 | P a g e