We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 34
His Majesty's Government of Nepal
Ministry of Water Resources
Department of Irrigation
Planning and Design Strengthening Project
United Nations Development Programme
(NEP®5/013)/World Bank
Design Manuals for
Irrigation Projects in Nepal
Executive Summary
February 1990
Sir M MacDonald & Partners Lid
in association with
MacDonald Agricultural Services Lid and
East Consall (P} Lid| This document should not be rolied on or used in circumstances other than those for which it was originally
| prepared and for which Sir M MacDonaid & Partners Limited was commissioned. Sir M MacDonald & Partners
Limited shall not be liable for the consequences of using this Gocument other than for the purpose for which
it was commissioned, and any user and any other person using or relying on the document for such other
purpose agrees and wil by such use or reliance be taken to confirm his agreement to indemnity
| Sir M MacDonald & Partners Limited for all loss or damage resulting therefrom.’EXECUTIVE SUMMARY
CONTENTS
Introduction S-1
Preparatory Work S-3
Preparation of Design Manuals and Guidelines S-2
3.1 Introduction S-2
3.2. Main Technical Manuals S-2
3.3 Guidelines $-5
3.4 Other Documents/Manuals 8-5
4. Use of the Manuals S-6
LAST OF TABLES
Table Nr Title Page Nr
1 List of Manuals and Guidelines 8-3
LIST OF FIGURES
Figure Nr Title Page Nr
Manual Scope. 8-4DHM
Dol
HMG
WUO
ABBREVIATIONS
Department of Hydrology
Department of Irrigation
His Majesty’s Government of Nepal
Water Users’ OrganisationsExecutive Summary
1. Introduction
The Planning and Design Strengthening Project of the Department of Irrigation has
been financed by the UNDP (NEP/85/013) and supervised by the World Bank.
This Executive Summary is for the Design Criteria component of the Project, which
concerns the establishment of design manuals for irrigation development in Nepal.
The aim of the Design Criteria component is to develop criteria and guidelines for the
planning and design of irrigation schemes in Nepal, so that a more consistent and
correct approach 10 these activities is achieved.
‘The principal activities carried out under this component were:
a) Preparatory Work
Preparation of an Inception Report
Preparation of a Design Philosophy and Approach Report
Preparation of a Design Office Management Review Report
b) Drafting of Manuals and Other Activities
Preparation of Design Manuals and Guidelines
Preparation of Standard Structure Designs and Specifications
Preparation of a Simulation Model
Reference books, which will form the core of a Departmental Reference Library, were
also procured under the Project.
2 Preparatory Work
Prior to preparation of the manuals and guidelines, a review of the present technical and
institutional aspects of irrigation planning, design and implementation was conducted.
This review formed the basis for discussion and agreement on the format and content
of the design manuals.
Three reports were prepared:
An Inception Report, which described the overall programme and direction
for the remainder of the component of the Project, and reviewed design
practice adopted on a number of completed schemes
A Design Philosophy and Approach Report which, foliowing field visits to over
25 operational irrigation schemes in both the hills and Terai, developed
approaches to irrigation planning and design so that account is taken of the
constraints faced in scheme operation, ‘These approaches have been
incorporated in the design manuals.
S-1A Design Office Management Review Report, which presented a review of
and proposals for the management of planning and design within the
Department of Irrigation. It is summarised in Appendix B.
3 Preparation of Design Manuals and Guidelines
al Introduction
The major activity of the design criteria component of the Project has been the
preparation of a series of manuals and guidelines. The documents prepared are listed
in Table | and shown in Figure 1, which indicates the range of subjects covered.
‘The documentation prepared falls into three main categories:
Main Technical Manuals, prefixed M
Guidelines. prefixed G
Other Documents, prefixed D
Each document was initially prepared in draft, and circulated for comment, Comments
received were taken into account during the drafting of the final versions,
The manuals reflect HMG policy for the irrigation sub-sector in that account has been
taken of the recently formulated Irrigation Rules and the policy documents on Scheme
Turnover and Participatory Management.
A guide to the contems of the main technical manuals is given in Figure 4.1 of
Appendix A, and a summary of each manual and guideline is presented in Appendix B.
32 Main Technical Manuals
This series comprises thirteen technical manuals which are intended for the planning and
design engineers in the Regional Directorates and Central Offices of the Department
of Irrigation. However, it is anticipated that they would also be used by consultants
engaged by the Department on the planning, design and implementation of irrigation
projects, and it is recommended that local consulrants registered with the Department
should receive copies of all the manuals.
‘The manuals present a means whereby consistency and uniformity of standards may be
achieved in the planning aad design of irrigation schemes in Nepal, This is not to say
that the approaches developed in the manuals narrow the choice of technical solutions
available; indeed, alternatives appropriate to hills and Terai are suggested in most
instances. ‘The manuals include discussion of the solutions available, the data and
investigations required for studies and design, technical criteria to be adopted, figures
showing design features and example calculations.Volume
Table 1
List of Manuals and Guidelines
Subject
Main Technical Manuals
General System Planning
Survey and Mapping
Hydrology and Agro-meteorology
Soils and Land Use
Sociology and Farmer Participation
Groundwater Irrigation
Headworks, River Training Works and Sedimentation
Distribution Systems, Canals and Canal Structures
Drainage
Engineering Cost Estimating and Economies
Infrastructure Planning
‘Tender Documents and Construction
Operation, Maintenance and Management
Guidelines on Specific Types of Project
Upgrading of Farmer Built and Operated Systems
Shallow Tabewell Development
Small/Medium Scale Project Development
Rehabilitation of Government Schemes
Other Manuals and Documents
Interim Field Design Manual (superseded by Manual D.2)
Field Design Manual
Standard Structures Designs
Simulation Model Manualsurunton gn
Figure 1
Manual Scope
. ee
Manual Project Stage |
Planning! ~~ Survey/ | Construction] Operation& |
Design Maintenance !
M1 GeneratSystem Planning
M2 SurveyandMapping
143. Hydrology and agre-meteorology
M4 SollsandLand Use
M5 SociologyandFatmer Participation
M6 _ Groundwater lmrigation
M7 Headworks,AiverTraining andSedimentation x
M8 DistributionSystems, Canals and CanalStructures (277
Ms Drainage
M.10 Engineering Cost Estimating andEconomics
M11 Infrastructure Planning
M.12 Tender Documents and Construction
1.19 Operation, Maintenance and Management
Guidetines on Specttic Types of Project
G1 Upgradingot Farmer Built and OperatedSysterns
G2 Shallow Tubewell Development
GS. Small/Medium Scale Project Development
Ga Rehabiltation of Government Schemes.
OtherManuals and Documents
D.1_ InterimFiek Design Manual (superseded by 0.2)
D2 FieléDesign Manual
D3. Standard StructuresDesigns
D4. Simulation Model Manuat
Primary appication
Seconday application
_{ordocument superseded)
8-4The manuals are designed to be reasonably self-contained, in that they aim to provide
most of the tools required for the planning and design of the majority of the components
of an irrigation system. On occasions, however, a mare sophisticated analysis may be
justified, either for reasons of technical complexity or economy. The reference literature
procured under the project will provide guidance in these cireumstances
‘The contents of the manuals are presented as sequence of developing concepts. It is
thus important that the manuals are read thoroughly and understood by the users.
Clearly, engineering judgement will be required in evaiuating the available solutions to
a particular problem, although the manuals should help in guiding this decision making.
‘The manuals should not be used blindly, and careful thought will need to given to each
specific situation encountered.
33 Guidelines
The four guidelines have been prepared to give planners guidance on specific types of
project which are seen to represent significant components of irrigation development in
the future. These types of project are:
= the upgrading of farmer built and operated schemes
the development of shallow tubewell schemes
- the development of new smali and medium scale schemes
- the rehabilitation of government managed schemes
‘The guidelines are principally concerned with the scheme implementation processes,
rather than technical detail, for which references are given to the main technical
manuals,
34 Other Documents/Manuals
The other documents prepared comprise a field design manual (Manual D.2, issued in
interim form as Manual D.1), a set of standard structure designs and specifications
(Manual 9.3) and a guide to the use of the simulation model developed under the
project (Manual D.4).
The field design manual presents a condensed version of parts of the main technical
manuals which are considered relevant to the design of schemes which are of low and
intermediate complexity. It is designed to be self-contained and is principally for use
at the district level. A simplified approach is adopted, as the document is aimed at
assistant engineers and overseers in carrying out the planning and design of smali and
medium sized projects. As with the main technical manuals, it should not be followed
blindly, and engineering judgement will need to be exercised in its use so that
sensible solutions are developed.
‘To support the field design manuals, standard structures designs have been prepared for
secondary and tertiary level sysiems, where such standardisation is considered
appropriate. Drawings of these structures have been prepared, and these are
S-5accompanied by design proforma, which are used for structure sizing. Outline quantities
for these structures have also been developed to help with costing of designs at
feasibility study level. For studies, the standard designs can be used directly with little
modification. For design and construction, their suitability must be checked and, if
necessary, modifications made to suit the local circumstances. They nonetheless provide
a good guide to the form of structure required, and on design details to be adopted.
Standard specifications for construction of irrigation systems have also been developed
and are included in Manual D.3.
A guide to the contents of Manuals D.2 and D,3 is presented in Figure A.2 of
Appendix A
The simulation model syanual (D.4), deseribes the operation of, and background to, the
computer program developed under the project as a training tool. ‘The program makes
broad use of the Mahakali Irrigation Project as a basis for simulating the operation of
a typical large Terai scheme. The program has three main components:
- an operating model, which uses a hydraulic model of the main canal to
simulate the impact on the main canal of operational decisions about gate
openings, which are made in response 10 changing inflows and water
Gemands
= production model, which allows annual decisions about cropping patterns,
inputs, etc to be ntade, and then simulates scheme crop production for &
random generation of rainfall and irrigation water availability
= tutorial, which explains the factors used to derive the model
4, Use of the Manuals
‘The manuals provide a sound technical resource for the planning and design of irrigation
schemes in Nepal. For them to be fully beneficial, they should be widely circulated
amongst Department of Irrigation staff, local consultants and other non-government
agencies concerned with irrigation development in Nepal.
To assist with the use of the manuals, it is suggested that seminars should be held for
Department of Irrigation senior staff and other potential users to introduce them to the
manuals and to indicate their application. In addition, the Department's junior staff
(mainly in the Districts) should be given specific training in the use of the Field Design
Manual and the Standard Structures Designs. This training should comprise both
classroom and field exercises, and be related to the planning and design of a specific
scheme, A series of courses, each iasting 2 to 3 weeks, is envisaged. Groups of 10 to
i5 junior engineers and overseers would attend each course.
In paraliel with this, it is suggested that a small team of Dol Design Specialists is
established to visit all regional and district offices with the aim of assisting engineers
stationed there in using the manuals. The seams would also supervise preparation of
Gesigns in the field offices and be responsible for maintaining and improving standardsof design. It is envisaged that there would be three teams of two or three engineers
each. They might typically spend three of four days at each office before moving to the
next office on their ‘rota’.
From time to time, the manuals will need to be updated, as experience is gained in their
use, as scheme emphasis or conditions change, as new techniques or designs are
developed, or as new materials are tried and proven and existing materials which
presently have only limited use become more widely available. An on-going programme
of revision will be required, and should be co-ordinated by the Central Planning, Design
and Research Division of the Department of Irrigation. As sections are updated or
revised, these should be circulated to all manual users. A register of recipients of the
manuals should thus be kept.Appendix A
Manual Contents
Figure A.1 Main Technical Manuals
Figure A.2 Field Design Manual
Standard StructuresFigure A.1
Summary of Manual Contents
se yOD a wed FORTIER
woisag ous pur emeishs uonngened
temuer veimonng jeuro uw sown “MWmEAS YONGE Bm
SuONE DIES uBktiK) Sekine
dep) w wowiCaune puny 9 ewer Budo v1 |
sd 7 oday ATMS FHT PHOS L|
owen
owe Burvueyg wore4s jm9v—0 6Figure A.2
Field Design Manual Contents
see
stuwaan 1 vows pues H
soo Puig 0) wa a
‘soy Buang prepuess WL
senspueddy redrouuy
amas 101 Kae jo one
Super pepums zt
onsnpon 5
‘noIsa0 wunsonMNs $5
owonceuant &
i
| auouronjonul sowres pue som y uedAppendix B
Manual Summaries
Title
B.1 Design Office Management Review
B2 M1 General System Planning
B3 M2_ Survey and Mapping
B4 M3 Hydrology and Agro-meteorology
BS M4 Soils and Land Use
B6 M.S Sociology and Farmer Participation
BI M4 Groundwater Irrigation
Bs M7 Headworks, River Training Works and Sedimentation
BY MA& Distribution Systems, Canals and Canal Structures
B10 M9 Drainage
BL] M10. Engineering Cost Estimating and Economies
Bi2 MLL Infrastructure Planning
B13) M.i2. Tender Documents and Construction
B.1é M13. Operation, Maintenance and Management |
B.iS Guidelines on Specific Types of Project
B16 D2 Field Design Manual
B.1? D3 Standard Structures Designs
BJ8 D¢ Simulation Model Manual
REFERENCES
Page Nr
Bei
B-2
B-3
B-4
B.S
B-5
B.S
B-6
B-6
B-7
B-7
B-8
Bes
B-9
B-9
B-10
B-i0
B- 12Appendix B
Manual Summaries
BA. Design Oftice Management Review
The Design Office Management Review makes recommendations for imptoving the
facilities and management of the Dol Central Design Office (and regional and district
design offices}, addressing the following topics:
A review of current practices and procedures.
Details of standards to be adopted and procedures to be followed.
Guidelines and instructions to siaff on the implementation of improved practices.
Additional materials and equipment to be procured to improve the functioning
of the design office.
Under the new Dol structure, the Planning, Design and Research Division will be
responsible for the central level planning and design activities. The role of this Division
is likely to include the following tasks with respect to planning and design.
Planning Section
Prepare and regularly update the Irrigation Master Plan, together with short and
medium term detailed plans that are consistent with the Master Plan. Input to
ollicial Five Year Plans would be an important part of the latter function.
Set guidelines by which regional and district offices can select small projects.
Consolidate planning of groups of small projects into larger units (river basin
planning), where appropriate.
Assume technical responsibility for Dol feasibility studies.
Coordinate foreign aid to the irrigation sub-sector.
Consolidate annual budget submissions, relaie them to current plans and
strategies, and monitor financial and technical performance.
Design Section
Carry out detailed designs of large and/or complex works.
Prepare tender documents for large and/or complex schemes.
Engage consultants and carry out the detailed designs of specific works.Provide advice and assistance to the regional and district offices on detailed
design, preparation (and interpretation) of tender documents and specifications,
and on contract procedures.
Vet the designs prepared by the regional offices (the regional office should vet
the designs prepared by district offices within their regions).
Supervise quality control of construction works.
Obtain feedback from completed designs, and, where appropriate, update the
design criteria, standards and manuals.
In preparing the Design Office Management Review report, the role of the Planning,
Design and Research Division has been assumed to be similar to that described above.
B.2, General System Planning Manual (M.1)
‘The possibilities for increasing crop production through an expansion of the irrigated
area in the hill zone are limited. Increases in production will therefore be attained
mainly through intensification of agriculture by improving yields and increasing cropping
intensities. Provision of reliable irrigation will be a major factor in achieving cither of
these.
The Terai is estimated to have about 1.7 million ha of land suitable for itrigation, of
which 0.9 million ha is thought to receive some irrigation at present. Of this, an
estimated 05 million ha comprises technically radimentary farmer-managed surface
water systems, which may benefit from technical improvements. The potential for
development, through intensification, technical improvement and expansion, is high. In
addition, many of the existing Government schemes are not functioning at optimum
efficiency and output could be improved.
For small and medium sized schemes, one of the major tasks wilt be to mobilise farmer
support and participation from the inception of a project to its completion, and develop
their capabilities to take over most of the operation and maintenance activities
(excepting those which are clearly beyond their technical capabilities).
Irrigation planning covers the establishment of objectives for irrigation development, the
stages in development, considerations in system planning, the planning process and
system description. Objectives of any proposed development need to be clearly set out
so that suitable strategies and solution can be formulated. General objectives may be
selected from national concerns, such as the need to increase food production ot rural
employment, while more project specific objectives may be to ensure equitable and
timely water supplies to farmers or to increase cultivation intensity.
‘A project may pass through various stages during its development, including
identification, pre-feasibility, feasibility, design, construction and operation. The first
three of these stages are the main planning stages, and final commitment to construct
a project is not made until the feasibility study is completed and the project is shown to
be technically and economically viable.‘The planning process starts with project identification, and proceeds through various
stages of investigation so that a rational decision to proceed with construction can be
taken, This decision will take into account the various technical, economic, financial and
institutional issues investigated. At any stage of the process, the project may be rejected
for a variety of reasons. The project design will include not only the technical design
of the irrigation infrastructure, but also the different pravisions tequired to safeguard the
assumptions made, These may be of an institutional, agricultural, financial or technical
nature,
irrigation design deals with the dimensioning and specification of engineering works,
rather than, for example, the design of agricultural plans, or institutional arrangements.
Design is involved throughout planning, as well as in the detailed design stage. The
jevel of design and the design objectives vary according to the stage of development, and
appropriate levels of detail associated with each stage in the project cycle are set out.
The design takes into account the hydraulic and structural criteria that are appropriate
to the type of scheme being considered. The main steps in the design process include:
determination of water requirements, water availability and water balance; planning of
the distribution system and system operation; canal and structure design cast estimates;
and the review of the compieted design.
In order to carry out scheme designs that are appropriate to the size and type of scheme
planned, adequate and accurate data collection is required, The type, amount and
accuracy of the data will depend on scheme type and the stage of study. Data collection
can be very time consuming, so it is important to assess what data is essential, and
where and how ii can be obtained, Various surveys may need to be undertaken to
collect the required data, such as soils and land use, topographical, hydrological,
agricultural, sociological and geotechnical.
B.3, Surveying and Mapping Manual (M.2)
The objective of surveying and mapping is to obtain information to the standards
required to support decision making while evaluating irrigation projects, and to enable
accurate designs to be prepared for schemes which are selected for implementation.
The standards of surveying and mapping are described with reference to the stage of
project development and to the type of project concerned.
The principle types of survey covered by the manual are:
- topographical
- hydrological
= groundwater
- soils and land use
= sociological
= environmental
- geotechnical
When a project is at a preliminary phase, there is generally little point in making
detailed surveys. At this stage, existing information should be used to the maximum,extent. As a project progresses, the need to improve decision making increases and
better survey and mapping data are required
‘The standards of survey are set out according to the recommended study stages, which
are:
Identification
Pre-feasibility (for large and complex medium schemes)
Feasibility
Detailed design
B.4, Hydrology and Agro-meteorology Manual (M.3)
‘The objective of the manual is to provide sufficient background on the specialist subjects
of hydrology and meteorology to enable the irrigation designer to make reasonable
assessments of such key variables as water availability, water requirements and
drainage/flood estimations in a country where basic hydrological information is scarce.
It is desirable that for larger schemes a specialist hydrologist is included in the project
design team,
Appendices to the manual include an inventory of all DHM stations giving details of
record length, summary rainfall data, and evaporation and evapotranspiration estimates
to aid the designer, as well as regional river hydrographs and drainage design charts.
For most projects, it is unlikely that the irrigation designer will find water availability
Gata for the proposed intake site, unless a gauge has been established at an earlier stage
in the design process. Several methods have been used in scheme design to estimate
river flows at a site with little or 0 data and a number are critically reviewed including
a regression technique (Water and Energy Commission, 1989), a regionalised hydrograph
iechnique (Medium Irrigation Project Design Manual, 1982), and approaches based on
the concept of “hydrologically similar’ catchments. Worked examples are provided for
each method. ‘The importance of local data for the site of interest is stressed, and it is
recommended that, as a minimum, baseflows should be measured.
The calculation of irrigation water requirements is described. Cropping calendars and
crop coefficients are provided for che most commonly cultivated crops. The Penman
method is recommended for the calculation of evaporation and evapotranspiration, For
rice, guidance is given on allowances for tand preparation and deep percolation.
Eticctive rainfall is calculated from an 80% reliable homogeneous rainfall sequence.
Field and conveyance efficiencies are recommended. The resulting irrigation water
requirements are balanced against water availability (available river flows) to give the
reliably cropped areas.
Drainage, both internal and external to schemes, is discussed, In the Terai, internal
drainage from the large bunded fields is considerable. Typical drainage rates are
proposed. Assessment of external drainage (floods) for the main rivers and cross-
Grainage should preferably be made using a long record of local data, and relevant types,
‘of frequency analysis are described. In the absence of any site measurements. two
methods are recommended. For large catchments (greater than about 100 km?) theregression technique derived by the Water and Energy Commission is recommended
while for smaller catchments the Soil Conservation Service chart method can be used.
B.S. Soils and Land Use Manual (M.4)
The manual covers soil survey planning and implementation, interpretation and
presentation of results, together with supervision and scrutiny of soil and land evaluation
studies for irrigated agricultural development, Throughout the manual, approaches have
been adapted, wherever possible, to the specific conditions of Nepal and the role of Dol
in developing irrigation projects.
An important point stressed in the manual is the need to adopt standard methodologies
and interpretations in Dol work, to facilitate evaluation and comparison of irrigation
studies. Recommendations are given on how the methods presented in the manual can
be improved, based on practical experience, so as the planning process and technical
criteria can continually be updated.
It should be noted that agricultural land evaluation and planning is a specialised subject,
and the manual indicates appropriate stages when specialist inputs are necessary.
B.6. Sociology and Farmer Participation Manual (M.5)
Planning and design of new irrigation schemes, and rehabilitation of older schemes in
Nepal, have mainly depended on technical data for construction, with limited concern
for socio-economic and institutional information. Serious problems of operation and
maintenance have resulted. Dol is now concerned to involve farmers in all stages of
project development and operation,
The Sociology and Farmer Participation Manual presents guidelines for conducting
dialogue with farmers about socio-economic, institutional and organisational matters
essential for planning, designing, constructing, operating and maintaining irrigation
systems.
The manual presents methods of data collection for analysis of socio-economic
conditions in a proposed project area, and for evaluation of farmers’ water users’
organisations or the farmers’ ability to form such an organisation. Procedures for the
development of Association Organisers and principles for organising strong, viable water
users organisations are presented.
B.7, Groundwater Irrigation Manual (M.6)
‘This manual addresses the planning and design requirements specific to irrigation from
groundwater. Its scope includes hydro-geological investigations and interpretation of
results, groundwater development and irrigation planning through to selection of
pumping plant for tubewells. The manual mainly concentrates on deep tubewell
development
‘There is an extensive treatment of well drilling for investigative and production
purposes. Alternative methods are described together with well logging and testing
considerations. The approach to economic well design is given with an example,
B-Stogether with the physical design. The assessment of individual well yields and regional
abstraction limits is discussed.
‘The manual reviews the physical and social factors affecting selection of tubewell
locations, and with reference to crop water requirements, establishing the pump duties,
The treatment of pumping plant includes a review of hydrodynamic pump types and
characteristics, hydraulic and mechanical aspects, prime movers and control
requirements. The selection of materials used in pumping plant is considered, especially
with regard to corrosion implications. Procurement procedures and operation and
maintenance considerations are also covered.
The manual also discusses the design of wellhead works, including the pump house. ‘The
design of open channel and buried pipe distribution systems and appurtenant structures
is described.
B.8. Headworks, River Training and Sedimentation Manual (M.7)
In this manual, guidance is provided on intake types suitable for use in rivers in Nepal,
their location, layout, performance and design criteria, river control by weirs and
barrages, river training works and sediment removal. Sedimentation theory is outlined
and the need for a co-ordinated programme of sediment data collection is stressed.
Model studies are discussed with respect to their usefulness and limitations.
‘The manual sets out the engineering principles relevant to the design of headworks and
river training; the impact that a tiver’s form has on the site selection and subsequent
Gesign of headworks is reviewed. Concepts of sediment transport are discussed and
methods for calculating sediment movement are presented. Field methods for sediment
sampling are described.
Various types of intakes and headworks are discussed ranging from large barrages and
weirs down to double orifice and simple bank intakes. Ways of minimising the quantity
of sediment entering an intake are presented, and the design of settling basin and other
removal facilities is described.
The section on river training presents the design philosophy for these works and sets out
criteria for designing guide banks, groynes, bank protection and overtopping
embankments, Calculations of scour depths and design of rip-rap, stone pitching and
gabion works are presented.
Physical model testing is described and the range of situations for which it is appropriate
is discussed, and the principles of dimensional similarity are set out. The high cost of
modelling and the specialised skills needed to design a model and interpret its results
are noted.
B.9. Distribution Systems, Canals and Canal Structures Manual (M.8)
Part 1 deals with the distribution systems and canal design, Part 2 deals with the design
of canal structures for irrigation schemes.Part 1 of the manual deals with the principles behind planning and designing distribution
systems; both open channel and sprinkler systems. ‘The methodology for canal design
is developed from determining capacities and command levels through to the selection
of appropriate control structures.
‘The design of canal sections - unlined and lined channels together with covered canals
and pipes ~ includes recommendations for bed/depth ratios, freeboard, slopes, radii,
embankment width ete. Regime and tractive force approaches are considered and other
aspects of canal design such as seepage losses and lining types are included.
Typical problems affecting existing farmers canals and alternative solutions to these are
discussed.
The design of regulating and measuring structures and road and cross-drainage works
is considered in Part 2 of the manual together with various types of energy dissipation
structures. Small seale structures, transitions and canal protection works are included,
as are sections oF pumps and pumping stations and the mechanical design of hydraulic
gates.
Many examples of hydraulic and structural design calculations are included,
B.10. Drainage Manual (M.9)
This manual presents the approach to the design of drainage systems, drains and drain
structures for itrigation systems. It complements Manual M.8, Distribution Systems,
Canals and Canai Structures, particularly in respect to preparation of scheme layouts.
‘The principles that should be applied in designing the drainage layout are presented and
the means of calculating drain discharges are shown. Recommended criteria for this
latter calculation are given, but with the provision that they should be critically reviewed
with respect to each scheme to which they are applied. The methadology for designing
drains is presented and typical designs for common forms of drain crossing and energy
dissipating structures are included. The manual concludes with an overview of
subsurface drainage techniques concentrating on perforated pipe, or tile, drains.
BU, Engineering Cast Estimating and Economics Manual (M.10)
The approach to cost estimating and economic appraisal of irrigation schemes is
considered. The manual aims to provide a practical approach ta the subject, but it also
presents a guide to the underlying economic concepts.
The treatment of cost estimating refers to the techniques and level of detail appropriate
to the particular stage of the project from identification to design and covers capital
works and engineering as well as operation and maintenance. The link between costs
and the level of risk and uncertainty is discussed.
‘The manual reviews the differences between financial and economic evaluations and
describes the concepts of opportunity costs, shadow pricing, sunk costs and externalities.
Least-cost and benefit-cost methods of evaluation are discussed as well as othermeasures of economic performance and the use of sensitivity analysis. The economic
optimisation of engineering alternatives is presented.
The benefit matrix approach to project evaluation is treated in some detail, covering the
principles and application. Standardised components of the benefit matrix are given,
appropriate to irrigation in Nepal. The procedures for applying and updating the benetit
matrix are presented, accompanied by an example.
B.12. Infrastructure Planning Manual (M.11)
‘The aim of this manual is to identify the infrastructure components that must be
considered by the irrigation planner when working on plans and designs for the
development or upgrading of an irrigation scheme. The emphasis is on planning, rather
than detailed design, although reference is made to appropriate guidelines and criteria
for the latter.
‘The manual concentrates on the infrastructure required for three purposes:
= access to and within the irrigation scheme;
= accommodation for those responsible for operating and maintaining the
irrigation system and providing extension services; and
- provision of basie facilities such as water supply and electricity.
‘The manus! covers subjects which impinge directly on the irrigation system design, such
as road alignments as well as construction methods and implications for long’ term
operation and maintenance, and differentiates between requirements in the hills and
Terai.
B13, Tender Documents and Construction Manual (M.12)
‘This manuai provides guidance to engineers preparing tender documents, evaluating
tenders and supervising construction. Much of the subject material has legal
implications: the manual, however, does not treat these authoritatively for not only is
Nepalese construction law a higily specialised subject which cannot adequately be
treated in a manual of this size, but also marked modifications may occur in a short
lime. The manual takes account of present practice in Nepal concerning letting and
supervising tenders (including reference to HMG Fiscal Rules) but it also is concerned
with future developments. Thus it emphasises the principles inherent in the
documentation used in tendering in Nepal and elsewhere in the Sub-continent and also
reviews the various forms of contract that might be in use in Nepal in the near future.
‘The section on evaluation of tenders should serve as an introduction to the subject for
junior engineers and, perhaps, as an aide-memoire for the more experienced evaluators
Aspects of site supervision include an overview as well as a detailed review of ways to
monitor progress; checking and approval of work; sampling, testing and quality control;
construction materials supervision; settlement of disputes; and dealing with claims.
Certification, payment and commissioning are also discussed.
B-8B.14. Operation, Maintenance and Management Manual (M.13)
‘The manual presents general guidelines on operation and maintenance of schemes which
are to be managed by the Department of Irrigation. The aim has been to provide fairly
simple and straightforward procedures which can be easily implemented and understood
by both the Department's staff and by the members of the Water Users’ Organisations
(WUO). The manual takes account of the Irrigation Regulations (BS 2045) and the
policy documents published with respect to the Turnover Program and the Participatory
Management Program.
‘The manual reviews the role in irrigated agriculture of the various governmental and
non-governmental bodies concentrating on the Department and on the various forms of
WUO. The staffing and management aspects of projects are considered. ‘The overall
management role and the duties of a scheme manager are described, as well as the
need for training, data management, a good communication system, monitoring and
evaluation and how computers can be used
The planning and delivery of appropriate quantities of water is considered in the section
on operation. This discusses a preferred system - consistent with the irrigation works
advocated in other manuals - as well as existing, possibly sub-optimal, arrangements.
The chapter on maintenance is concerned with ensuring the irrigation system is in a
suitable condition to be operated as desired. It deals with the general approach to
maintenance, reporting and ranking maintenance needs and implementation methods.
Staffing requirements and duties and the capability and applicability of various types of
maintenance equipment are considered.
The manual concludes with a review of what should be inchided in a scheme-specific
operation and maintenance manual, differentiating between manuals produced when
schemes are commissioned and the document that can be published once experience is
gained in operating the schemes.
B15. Guidelines (G.1 to G.4}
The four guidelines, presented in one volume, cover:
- upgrading of farmer built and operated systems (G.1)
- development of shallow tubewell schemes (G.2)
- development of small and medium scale projects (G.3)
+ rehabilitation of government irrigation systems (G.4)
The guidelines set out an approach to the preparation and implementation of specific
types of project which are seen to be major components of irrigation development in
Nepal in the coming 10 to 15 years. They refer to other manuals which cover the
specific technical details, The guidelines concentrate on presenting procedures to be
followed. These include the strategy for project promotion and project identification:
the requirements at feasibility study and detailed design; construction and handover; and
subsequent operation, maintenance and management, Involvement of the beneficiaries
is emphasised, as is the need for ongoing monitoring and evaluation of the effectiveness
of the approach to meet the project objectives.
B-9B16. Field Design Manual (D.2)
‘The Field Design Manual is intended to assist engineers and overseers in the district
offices to carry out studies, surveys and design, and involve farmers in scheme
implementation for small and simpler medium sized irrigation projects both in the hills
and the Terai.
‘The manual has been designed to be self-contained, so that it can be used directly by
district level staff. without reference to other sources. It is intended for the simpler
schemes; for those which are more technically complex, assistance may be required from
the regional or central offices. Due to the wide range of conditions in Nepal, the
guidelines in the manual are general, and engineering judgement is always essential in
their use and interpretation. The manual draws on the appropriate sections of the main
technical manuals.
Initially, an Interim Manual (D.1) was prepared. It was revised to conform with
technical manuais subsequently drafted, and republished as the Field Design Manual
(D.2) - which supersedes Manual D.1, Manua} D.2 should be read in conjunetion with
the Standard Structure Designs (D.3).
B.17. Standard Structure Designs (D.3)
This manual presents designs for standard and typical structures, (for secondary and
tertiary level systems), and includes an outline specification. It complememts the Field
Desigh Manual (D.2), The structures include:
~ standard details (walls, pitching, pipe bedding etc.);
regulators (Faiyum, duckbill and plain weirs and undershot gate structures);
measuring structures;
escape structures:
fail structures;
road crossings (culverts and siphons);
cross-crainage structures;
tertiary canal structures;
~ drain crossing and fall structures;
- groundwater irrigation structures.
Engineering drawings have been prepared and are accompanied by design proforma,
tables and indicative quantities. ‘The design proforma and accompanying tables will
enable the standard structures to be readily sized to suit most situations encountered in
B-10Nepal, within the limits of applicability specified. ‘The structure designs are consistent
with the design approach given in the other manuals, to which reference should be
made when designing larger structures of similar ype. ‘The indicative quantities are
suitable for use at feasibility study level, but the assumptions given should be cross-
checked for particular circumstances.
‘The outline specification covers all but very specialised subjects pertinent to irrigation
development or rehabilitation in Nepal. It is envisaged that, in most situations, abstracts
would be used in tender or contract documents,
B.18. Simulation Model Manual (D.4)
The manual describes the use and operation of a Simulation Model broadly based on
the Mahakali Irrigation Project. It has been developed in FORTRAN and has been
designed to run on an IBM compatible computer with a hard disk. As the principal use
of the model is for training, it has been necessary to make the model straightforward
and responsive, and yet simulate the true situation as closely as possible.
‘The simulation model is in the form of a training exercise to enable users to gain an
appreciation of the interacting factors in the planning, broad design and operation of an
irrigated agricultural system. Two models are operable; one is a year round simulation
of agricultural and irrigation practices; and the second concerns the daily (hydraulic)
operation of the main canal.
The year round model simulates, in ten-day time steps, the effects of water management
on crop production with various system characteristics. ‘The effects of different cropping
patterns, input levels and crop yield responses to water and inputs can be demonstrated.
The main canal operation mode simulates the operation of the main canal and
structures, such as cross-regulators, offtakes and escapes, in one-day time steps over a
tendday period. Daily outlet demands for the various canals are generated, and
discharges at the head-regulator are provided as an input. The user adjusts the gate
settings (0 try to meet each demand and a performance rating is evaluated from
considerations of success in meeting demands, consistency and equitability of supplies
and limiting wastage of water.
B-ilREFERENCES
MIP, 1982 Design Manual, Medium Irrigation Project, Sir M MacDonald and
Partners.
WECS, 1989 Regional Hydrology of Nepal (Draft, May 1989).
B- 12