Construction of The Deepest Kelly System Foundation Piles
Construction of The Deepest Kelly System Foundation Piles
Construction of The Deepest Kelly System Foundation Piles
3. Scope of Works
4. Equipment
2
1. The L&M Project + KLCC Development
FY 2020
3
2. Geology & Design
FY 2020
Competent rock mapping for the piling works in the Tower area
4
2. Geology & Design
FY 2020
5
2. Geology & Design
FY 2020
6
2. Soil investigation
FY 2020
7
3. Scope of Works
Employer : Arah Moden Sdn Bhd (Company of KLCC Holding)
Enabling Works:
- Diaphragm Wall – 1.0m thickness up to 39m depth
- Structural monitoring
- Geotechnical instrumentation / monitoring
- Dilapidation survey
- Utilities Diversion – Temporary works
8
3. Scope of Works
Tower
FY 2020
Podium
Storage
Kelly section : Outer diameter is 559mm and last section diameter is 229mm. Have to
consider last section not to be too slender otherwise it will twist like a cock screw during
drilling. 5 section Kelly is not suitable for rock drilling
Weight of Kelly close to 39 tons with a mast of 36m to cater for a 32.5m Kelly will determine
the type of Base machine and counterweight required for stability to avoid overturning.
Weight of overall rig needs to be considered as proper concrete working platform is needed
10
4. Equipment
MOBILISATION AND ASSEMBLY TAKES SPECIAL PLANNING AND EXECUTION
FY 2020
11
4. Equipment – Bored Pile
The Biggest Rotary Kelly Drilling Rig
BG 48:
Mast Height 36 m
Main Winch 60 to
Kelly 5-fold Lockable
Drilling Depth 125 m
Max diameter 3.5 m FY 2020
Thank you
FY 2020
13
4. Equipment – Diaphragm Wall
Thank you
FY 2020
14
4. Diaphragm Wall – Cage Installation
Thank you
FY 2020
15
4. Diaphragm Wall – Concreting process
Thank you
FY 2020
16
5. Construction challenges of Deep Piles
Drilling :
- Performance versus Verticality Balance
- Risks of deviation with
FY 2020
- increased depth
- increased diameter
17
5. Construction challenges of Deep Piles - Drlling
FY 2020
18
5. Construction challenges of Deep Piles
SPECIFICATIONS
Kingposts:
- 1:200
Material-Installation:
- Within 36 hours from Completion of Drilling
19
5. Construction challenges of Deep Piles - Verticality for Piles L<100 m
Koden Tests for BAUER’s internal x-check
- well-known and proven, for D-walls, Barrettes and for Circular Shafts
FY 2020
20
5. Construction challenges of Deep Piles - Verticality for Piles L<100 m
FY 2020
21
5. Construction challenges of Deep Piles - Verticality for Piles L>100 m
Specified: Sonic Caliper Tests on every Pile
- Patented System by Fugro
- ultrasonic echo device similar to Koden, but 360-degree scanning
- determines contour and verticality of the pile
FY 2020
22
5. Construction challenges of Deep Piles
Fluid Support :
- Polymer was preferred against bentonite as bentonite would require desanding process
which would take 5 to 6 hours. Time was is an essence as there is a requirement in the
specification to complete pile casting within 36hours from completion of drilling.
Concrete:
- Quality ( Placing temperature was below 32oC and slump was above 220mm )
- Supply rate needed to be between 60 to 80 cum/hr. 12 cum volume trucks were used
Kingpost installation:
- Required verticality 1:200. Kingpost was one section up to length 33m and weighs to a
maximum of 84 tons. For lifting a 300 ton crane was used in some instance.
23
5. Construction challenges of Deep Piles - Polymer
FY 2020
24
5. Construction challenges of Deep Piles - Polymer
FY 2020
25
5. Construction challenges of Deep Piles - Polymer
FY 2020
26
5. Construction challenges of Deep Piles – Steel Cage
FY 2020
27
5. Construction challenges of Deep Piles – Steel Cage
FY 2020
28
5. Construction challenges of Deep Piles - Concreting
FY 2020
29
5. Construction challenges of Deep Piles - Concreting
FY 2020
30
5. Construction challenges of Deep Piles - Concreting
FY 2020
31
5. Construction challenges of Deep Piles - Concreting
FY 2020
32
5. Construction challenges of Deep Piles - Concreting
FY 2020
33
5. Construction challenges of Deep Piles – King Post
FY 2020
34
5. Construction challenges of Deep Piles – King Post
FY 2020
35
A safe job is a good job
FY 2020
36
The Deepest Kelly System Foundation Piles in Kuala Lumpur