Lec 2castingpdf
Lec 2castingpdf
Lec 2castingpdf
net/publication/340256280
Casting Processes
CITATIONS READS
0 7,062
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Bio tribo corrosion characterization of Ti bio materials hydroxyapatite coating View project
All content following this page was uploaded by Ali Hameed Kamel on 28 March 2020.
Casting
By
Ass. Lect. Ali H. Almaily
[email protected]
Casting Processes
Introduction
Casting is a process in which molten metal flows by gravity or other force into a mold
where it solidifies in the shape of the mold cavity. The term casting also applies to the part
made in the process.
*Steps in casting seem simple:
1. Melt the metal
2. Pour it into a mold
3. Let it freeze
Capabilities and Advantages of Casting:
Can create complex part geometries.
Can create both external and internal shapes.
Some casting processes are net shape; others are near net shape.
Can produce very large parts.
Some casting methods are suited to mass production.
Disadvantages of Casting:
Different disadvantages for different casting processes:
Limitations on mechanical properties, porosity.
Poor dimensional accuracy and surface finish for some processes; e.g., sand casting.
Safety hazards to workers due to hot molten metals.
Environmental problems.
As shown in the figure, the gating system typically consists of a downsprue (also called
simply the sprue), through which the metal enters a runner that leads into the main cavity.
At the top of the downsprue, a pouring cup is often used to minimize splash and
turbulence as the metal flows into the downsprue.
It is shown in our diagram as a simple cone-shaped funnel. Some pouring cups are
designed in the shape of a bowl, with an open channel leading to the downsprue.
In addition to the gating system, any casting in which shrinkage is significant requires a
riser connected to the main cavity.
The riser is a reservoir in the mold that serves as a source of liquid metal for the casting
to compensate for shrinkage during solidification. The riser must be designed to freeze
after the main casting in order to satisfy its function.
Figure2.4 Cross-sectional view of a typical sand-casting mold.
Heating and Pouring
To perform a casting operation, the metal must be heated to a temperature somewhat above its
melting point and then poured into the mold cavity to solidify. In this section, we consider
several aspects of these two steps in casting.
a- Heating The Metal
Heating furnaces of various kinds are used to heat the metal to a molten temperature sufficient
for casting. The heat energy required is the sum of:
(1) the heat to raise the temperature to the melting point,
(2) the heat of fusion to convert it from solid to liquid, and,
(3) the heat to raise the molten metal to the desired temperature for pouring. This can be
expressed:
where H = Total heat required to raise the temperature of the metal to the pouring temperature,
J,Ƥ: density; g/cm3; Cs: weight specific heat for the solid metal, J/g-0C; Tm: melting
temperature of the metal, _0C; To = starting temperature—usually ambient, _0C ; Hf = heat of
fusion, J/g ; Cl =weight specific heat of the liquid metal, J/g-0C; Tp= pouring temperature, 0C ;
and V = volume of metal being heated, cm3 .
Example 2.1: One cubic meter of a certain eutectic alloy is heated in a crucible from room
temperature to 100 0C above its melting point for casting. The alloy’s density 7.5 g/cm3,
melting point 800 0C, specific heat = 0.33 J/g_ in the solid state and 0.29 J/g_ in the liquid
state; and heat of fusion =160 J/g. How much heat energy must be added to accomplish the
heating, assuming no losses?
Solution: H= (7.5)(10^6){0.33(800-25)+ 160 + 0.29(100)}= 3335 (10^6) J.
b-Pouring The Molten Metal
Factors affecting the pouring operation include: pouring temperature, pouring rate, and
turbulence.
The pouring temperature: is the temperature of the molten metal as it is introduced into the
mold. What is important here is the difference between the temperature at pouring and the
temperature at which freezing begins (the melting point for a pure metal or the liquidus
temperature for an alloy). Pouring rate: refers to the volumetric rate at which the molten
metal is poured into the mold.
If the rate is too slow, the metal will chill and freeze before filling the cavity. If the pouring
rate is excessive, turbulence can become a serious problem.
Turbulence in fluid flow is characterized by erratic variations in the magnitude and
direction of the velocity throughout the fluid. The flow is agitated and irregular rather than
smooth and streamlined, as in laminar flow. Turbulent flow should be avoided during
pouring for several reasons:
It tends to accelerate the formation of metal oxides that can become entrapped during
solidification, thus degrading the quality of the casting.
Turbulence also aggravates mold erosion, the gradual wearing away of the mold
surfaces due to impact of the flowing molten metal.
The densities of most molten metals are much higher than water and other fluids we
normally deal with. These molten metals are also much more chemically reactive than at
room temperature.
Engineering Analysis of Pouring:
There are several relationships that govern the flow of liquid metal through the gating
system and into the mold. An important relationship is Bernoulli’s theorem, which states
that the sum of the energies (head, pressure, kinetic, and friction) at any two points in a
flowing liquid are equal. This can be written in the following form:
where h= head (cm), p = pressure on the liquid (N/cm2);Ƥ density (g/cm3); v = flow
velocity (cm/s); g = gravitational acceleration constant, 981 (cm/s2 ) , and F= head losses
due to friction (cm) . Subscripts 1 and 2 indicate any two locations in the liquid flow.
Bernoulli’s equation can be simplified in several ways. If we ignore friction losses and
assume that the system remains at atmospheric pressure throughout, then the equation can be
reduced to:
This can be used to determine the velocity of the molten metal at the base of the sprue.
Let us define point 1 at the top of the sprue and point 2 at its base. If point 2 is used as the
reference plane, then the head at that point is zero (h2= 0) and h1 is the height (length) of
the sprue. When the metal is poured into the pouring cup and overflows down the sprue,
its initial velocity at the top is zero (v1 = 0). Hence, Eq. above further simplifies to:
where v= the velocity of the liquid metal at the base of the sprue, cm/s ; g = 981 cm/s2 ;
and h = the height of the sprue, cm .
Another relationship of importance during pouring is the continuity law, which states
that the volume rate of flow remains constant throughout the liquid. The volume flow
rate is equal to the velocity multiplied by the cross-sectional area of the flowing liquid.
The continuity law can be expressed:
Q = v1 A1 = v2 A2
where Q = volumetric flow rate, cm3/s ; v = velocity as before; A = cross sectional area
of the liquid, cm2 .
Assuming that the runner from the sprue base to the mold cavity is horizontal (and
therefore the head h is the same as at the sprue base), then the volume rate of flow
through the gate and into the mold cavity remains equal to vA at the base. Accordingly,
we can estimate the time required to fill a mold cavity of volume V as
Where TMF = mold filling time s (sec); V= volume of mold cavity, cm3, and Q =
volume flow rate, as before.
Example 3.2: A mold sprue is 20 cm long, and the cross-sectional area at its base is 2.5 cm2.
The sprue feeds a horizontal runner leading into a mold cavity whose volume is 1560 cm3.
Determine: (a) velocity of the molten metal at the base of the sprue, (b) volume rate of flow,
and (c) time to fill the mold.
Solution:
a)The velocity of the flowing metal at the base of the sprue is given by :
Fluidity
The molten metal flow characteristics are often described by the term fluidity, a measure of
the capability of a metal to flow into and fill the mold before freezing. Fluidity is the inverse
of viscosity as viscosity increases, fluidity decreases.
Factors affecting fluidity include :
• pouring temperature relative to melting point,
• metal composition,
• viscosity of the liquid metal, and
• heat transfer to the surroundings.
Fig. 2.5 Spiral mold test for fluidity, in which fluidity is measured as the length of the spiral
channel that is filled by the molten metal prior to solidification.
Solidification Time
Whether the casting is pure metal or alloy, solidification takes time. The total solidification
time is the time required for the casting to solidify after pouring. This time is dependent on the
size and shape of the casting by an empirical relationship known as Chvorinov’s rule, which
states:
Where TTS= total solidification time( min);V= volume of the casting, cm3 ,A= surface area of
the casting, cm2 ; and Cm is the mold constant (min/cm2). Given that n = 2.
Riser Design
As described earlier, a riser, Figure 2.4, is used in a sand-casting mold to feed liquid
metal to the casting during freezing in order to compensate for solidification shrinkage.
To function, the riser must remain molten until after the casting solidifies. Chvorinov’s
rule can be used to compute the size of a riser that will satisfy this requirement. The
following example illustrates the calculation.
Example 2.3: A cylindrical riser must be designed for a sand-casting mold. The casting
itself is a steel rectangular plate with dimensions 7.5 cm 12.5 cm 2.0 cm. Previous
observations have indicated that the total solidification time (TTS) for this casting = 1.6
min. The cylinder for the riser will have a diameter-to-height ratio=1.0. Determine the
dimensions of the riser so that its TTS = 2.0 min.
Solution: First determine the V/A ratio for the plate. Its volume V = 7.5 *12.5* 2.0 = 187.5
cm3, and its surface area A = 2 (7.5 × 12.5 + 7.5 ×2.0 + 12.5 × 2.0) = 267.5 cm2. Given that
TTS = 1.6 min, we can determine the mold constant Cm ,sing a value of n = 2 in the
equation:
Since we are using D/H ratio = 1.0, then D=H. Substituting D for H in the volume and
area formulas, we get:
Risers can be designed in different forms. The design shown in Figure 2.4 is a side riser. It
is attached to the side of the casting by means of a small channel. A top riser is one that is
connected to the top surface of the casting. Risers can be open or blind. An open riser is
exposed to the outside at the top surface of the cope. This has the disadvantage of allowing
more heat to escape, promoting faster solidification. A blind riser is entirely enclosed within
the mold, as in Figure 2.4.