Jss Susppensi Rev.01

This document is a job schedule sheet for repair work on a unit. It outlines a plan to complete the work by August 2nd at Plant BRCG. The schedule details 27 total hours of work spread across 17 steps over 2 days to install and remove various components like the front suspension, brake assembly, and tires. The sheet also tracks manpower hours and includes codes for recording any delays.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views1 page

Jss Susppensi Rev.01

This document is a job schedule sheet for repair work on a unit. It outlines a plan to complete the work by August 2nd at Plant BRCG. The schedule details 27 total hours of work spread across 17 steps over 2 days to install and remove various components like the front suspension, brake assembly, and tires. The sheet also tracks manpower hours and includes codes for recording any delays.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

JOB SCHEDULE SHEET (JSS)

UNIT MODEL : HD 785-7 HM : 28,332


SERIAL NO : 65603
UNIT CODE : DT 4555
DATE TROUBLE
PLAN OF FINISH
JOB LOCATION
:
:
:
1-Aug-22
2-Aug-22
PLANT BRCG
ACTUAL : PLANT BRCG
TOTAL 1-Aug-22 8/1/2022
NO DESCRIPTION JOB %
HOURS 06.00 07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00 07.00 08.00 09.00 10.00 11.00 12.00 8 9 10 11 12 13 14 15
STEP OF JOB PROGRESS

Install komponen
17 Final Check 1 3.7%
16 Performance Test 1 3.7%
15 Cleaning Component 0.5 1.9%
14 Remove Stand 0.75 2.8%
13 Leveling Oil And Nitrogen 1 3.7%
12 Instal Tyre 2.5 9.3%
11 Instal Brake Assembly 3.5 13.0%
10 Instal Front Suspensi 3 11.1%
9 OVH Front Suspensi 4.5 16.7%
Remove Components

8 Cleaning unit 0.5 1.9%


7 Cleaning Component And Related 1 3.7%
6 Remove Front Suspensi 2 7.4%
5 Remove Brake Assembly 2.5 9.3%
4 Remove Tyre 1 3.7%
3 Release Nitrogen 0.5 1.9%
2 Instal Stand 0.75 2.8%
1 Washing Unit 1 3.7%
Total of hours 27
100.0%
Total of days Hari ke 1 2

RECORDING
Man Power
MAN POWER MAN HOURS
1 (GL) DELAY
2 PAMA SHIFT 1:
3 PAMA SHIFT 2: CODES : A NO MANPOWER C NO SPACE G ACCIDENT I WAITING COMPONEN K BY WEATHER
4 UT B NO TOOLS/EQUIPMENT D NO WELDING MACH H LOCAL SHOP J COUNTIUE JOB L BY UT RESPONSIBLE
5 UT M REUSABLE PARTS
6 UT

Kendala :
Remarks :

Plan 100%

Actual finish 100%