6102 - 04 - r0 - Liquid Transfer TrA
6102 - 04 - r0 - Liquid Transfer TrA
6102 - 04 - r0 - Liquid Transfer TrA
DEVELOPMENT PROJECT
PHASE 8
COMMISSIONING
DOCUMENT NUMBER REVISION 00
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 2 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
SUMMARY
After the process gas has been cooled in the pre-coolers the liquids are
collected in the gas compressor suction scrubbers and thereafter pumped
back to the inlet manifold by Liquid Transfer Pumps 5-P-0250A/B
The pumps are centrifugal type with a working discharge pressure of
26.8/30 barg, and a flow rate of 14m3/h.
Each pump is fitted with its own independent lube oil system, and the
pump stop/start commands are initiated by the field operators, however in
case of emergency the pumps can be stopped via a command from the
control room.
The selected pump is designed to run continuously, therefore a minimum
flow line back to the scubber is installed
Note:
Lubricate the mechanical seals as per API 53M : 1bar above
suction pressure, therefore the motor stop/start and shut-downs on
the OTP will be carried out with the pump motor un-coupled, and
the complete OTP will need to be done after Start-up
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 3 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
1 TEST SUMMARY
To check the equipment has been correctly installed and prepared for
commissioning in accordance with the vendors’ instructions.
Prepare the test for checking function of the pumps, motors,and level
switches
None
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 4 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
Mechanical 1
Electrical 1
Start-up 1
1 day
Not required
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 5 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
3 TEST REQUIREMENTS
3.1 PRECOMMISSIONING ACHIEVEMENTS
None
3.5 CONSUMABLES :
Potable water
Gaskets
3.6 SPARES:
3.7 SAFETY
3.8 UTILITIES
NA
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 6 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
4 TEST PREPARATION
4.1 BLIND LIST
None
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 7 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
1. Obtain Permit-to-Work.
8. Slowly open drain valves and start to lower the scrubber level
12. Continue draining level until all water has been removed from
scrubber, re-install 2” drain blank flange, using new gasket
15. Open 2 x 6” pumps inlet valves and drain off all water
18. Ensure that the liquid transfer pumps A & B motors are isolated at
the MCC. If not get the electrical engineer to isolate them both
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 8 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
19. Inspect both pumps, 5-P-0250 A & B and associated pipe-work for
damaged items that will prevent the Operational Test.
Check that the RO’s 0251 A/B are installed on minimum flow
lines
20. Ensure that the pre-test check list has been completed for the , 5-P-
0250 A & B pumps
21. Ensure that all blinds have been removed or turned to the correct
operating position.
22. Ensure that the pump , 5-P-0250 A & B outlet Non Return Valve
the Minimum Flow NRV and the Discharge Header NRV are
installed the correct way round.
23. Open up both pumps , 5-P-0250 A & B inlet strainer and check it
is not blocked. Re-install the strainer into the filter body and close
the flange.
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 9 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
6 PROCEDURE
2 Inform control room of intention to check scrubber LTs and motor stop/start
commands
11 Observe motor A start and flow through minimum flow valve and check lube
oil cooling system and flow
15 Continue running pump until lube oil temperature and pressure are stable
as per field and CR indications
16 Log pump amps, lube oil temperature and pressure TAHH 0250 A set at 95
degres C
19 Re-start Motor
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 10 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
22 Re-start motor
29 Pump B motor
35 Continue running pump until lube oil temperature and pressure are stable
as per field and CR indications
39 Re-start motor
42 Re-start motor
43 Request Electrical to trip pump motor from MCC via electrical failure
47 Re-start motor
/conversion/tmp/activity_task_scratch/637390580.doc
TOTALFINAELF OPERATIONAL TEST PROCEDURE TUNU 8
SUB-SYS: 6102 DESCR: Transfer Pumps LOCATION : NCP PAGE : 11 OF 11
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
/conversion/tmp/activity_task_scratch/637390580.doc