Project Management
Project Management
Project Management
Project Management
Postgraduate Program
Department of Masters of Business Administration
Group Assignment
Participant Students
Number Name ID
Submitted to
Specific objective
To assess the type of employee motivational packages in the organization
To examine level of Employees’ motivation in the organization
To identify determinant variables for Employee Motivation in Yeka Sub-city woreda 7
Administration.
Project Scope
This study was conducted at Yeka sub-city woreda 7 administration, in around safety to enable
the employees to disclose much information concerning the Employee motivational practice.
Focusing on employees from all the various departments. The study is expected to be carried out
between May to July2022. One limitation that may be expected to come up is convincing the
employees to participate in the survey, fill in and hand in a completed questionnaire in time.
However, this will be solved by a proper explanation about the importance of the survey to
employees and the organization, as well as ensuring that the questionnaire is not too long, and is
simple to understand. The researcher will also Endeavour to hand in the tool early enough and
make frequent follow-ups.
Organization
Organizational Boundaries and Interfaces
The project is not being not done in the sub city still. Since this project is very essential and needy
after some time, it will cover all over the country. The stakeholders’ dependent on or affected by
Resource Owners
The resource owners of the project are the Project team itself and the Yeka sub-city woreda 7
administration also support the Project team in supplying resources as it is the target beneficiary
of the project when it is completed.
Project Organization
The project and subprojects are organized into project manager and team to assign their
individual responsibility while working collaborate to facilitate the work environment.
Project Manager
The project has one Project Manager with the responsibility of the controlling the overall project
Management
Project Team
The project team members are consisting of five individuals one project manager and four with
member responsibilities. The time they spend on the project is accounted for in the project like
the following tables.
Table 1: Project Team
Milestone List
The below chart lists the major milestones for the Employee motivation Project. This chart is
comprised only of major project milestones such as completion of a project phase or gate review.
There may be smaller milestones which are not included on this chart but are included in the
project schedule and WBS. If there are any scheduling delays which may impact a milestone or
delivery date, the project manager must be notified immediately so proactive measures may be
taken to mitigate slips in dates. Any approved changes to these milestones or dates will be
communicated to the project team by the project manager.
Complete Requirements Gathering All requirements for Employ Motivation Project must 5/25/2022-
be determined to base design upon 5/28/2022
Complete Requirements Analysis This is the theoretical analysis for to detail understand 5/29/2022-
the study 6/10/2022
Complete Organizing the analyzed All data organization completed 6/11/2022-
data 6/25/2022
Complete Project review All the project results are summarized 6/25/2022-
7/25/2022
In order make our project more manageable and appropriately assigned to a specific unit of work
for each individual team members and for sufficient completion we divided the project in to
smaller and manageable parts. Work
Breakdown Structure
This Communications Management Plan sets the communications framework for this project. It
will serve as a guide for communications throughout the life of the project and will be updated as
communication requirements change. This plan identifies and defines the roles of Employee
Motivation project team members as they pertain to communications. It also includes a
communications matrix which maps the communication requirements of this project, and
communication conduct for meetings and other forms of communication.
While this project requires minimal or no procurement, in the event procurement is required, the
Project Manager will work with the project team to identify all items or services to be procured
for the successful completion of the project. The Project Manager will then ensure these
procurements are reviewed by the Program Management Office (PMO) and presented to the
contracts and purchasing groups. The contracts and purchasing groups will review the
procurement actions, determine whether it is advantageous to make or buy the items or resource
required services internally, and begin the vendor selection, purchasing and the contracting
process.
In the event a procurement becomes necessary, the Project Manager will be responsible for
management any selected vendor or external resource. The Project Manager will also measure
performance as it relates to the vendor providing necessary goods and/or services and
communicate this to the purchasing and contracts groups.
Development Environment
The tools used for design, implementation, and documentation for the
project are micro soft word and laptop computer
Delivery Plan
The project will deliver to the Yeka sub-city Administration woreda 7 Administration when
completed
Quality Assurance
To address all the possible error hole at a particular levels of the project study process we use all
the cross check method to check the behavior and performance of the project. Throughout the
project each project lifecycle is crosschecked to determine if the project is fit to its target