Precast Flat Panel System

Download as pdf or txt
Download as pdf or txt
You are on page 1of 25

E L E C T I V E _ C O N S T R U C T I O N M A T E R I A L S

C o n s t r uction
M aterials

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

A precast flat panel (PFP) system is a construction


technique that provides an alternative to
traditional site -based construction.

Precast flat panel system components are mass


produced off- site, that are transpor ted to the site
a n d t h e n c o m b i n e d a n d f i t t e d t o g e t h e r. P a n e l s c a n
include elements, such as doors, windows and
f loor units. They can also include features such as
decorative wall finishes, fitted insulation and so
on. Some types can be used as load bearing
panels in cross wall construction applications.

Precast flat panel systems can reduce on-site


waste and ongoing maintenance, but they can be
difficult to transpor t and handle. Using the
precast f lat panel construction technique may
shor ten construction project completion times.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

R E I N F O R C E D C O N C R E T E WA L L E L E M E N TS

• Reinforced concrete wall elements are the characteristics features of both


large panel and cross wall construction methods; they can be used as either
loadbearing or non loadbearing or non loadbearing building elements.

• The thickness of the load bearing walls is determined by the static calculations
and the minimum allowable depth of the f loor slab which is between 14 and 20
mm. This is also sufficient to fulfill the necessary sound and fire protection
requirements.

D O U B L E WA L L E L E M E N TS

• Thin concrete walls are fitted together with intermediate steel gratings, all
necessary reinforcement is already installed between the walls.

• These double walls are delivered to the site where they are poured with filling
concrete to produce a stable, single layered wall construction element.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

SANDWICH ELEMENTS

• Reinforced Sandwich panels are manufactured in plants for use as ex ternal


walling.

• They consist of three layers: load bearing, insulating and facing.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

POROUS CONCRETE ELEMENTS

• Porous or aerated , concrete elements belong to the class of lightweight


concrete that provide great stability with minimal weight. porous concrete
units are used as wall, slab and roof elements.as load bearing elements.

• As load bearing members, they are produced in heights of up to 350mm,


widths of up 150 mm and thicknesses of up to 37.5mm.Slabs and roof panels
of porous concrete have maximum dimensions of 800 mm in length and 75mm
in width. If they are to be subjected to bending loads, load bearing, porous
concrete elements are stabilized with additional corrosion protected
reinforcing steel.

P O R O U S C O N C R E T E FA Ç A D E E L E M E N T S

• Porous concrete elements can be employed both horizontally and ver tically as
façade elements or a infill panels for frame structures.

• In addition to the bracing functions which panels provide , they also perform
functions relevant to building physics.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C E I L I N G A N D F LO O R S L A B S

• Pre fabricated concrete slab elements are produced as solid, hollow or web
panels. They offer planar structures of reinforced concrete or pre stressed
concrete which act as the par titioning elements for frame or panel
constructions.

• These elements are predominantly responsible for the absorption of bending


moments, and transfer both ver tical and horizontal loads.

UNITISED SLABS

• The elements are manufactured in widths of up to 3m and consists of a


prefabricated slab measuring approximately 5mm with exposed steel
reinforcing anchors.

• These reinforcements act as the connecting elements between the


prefabricated element

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

SOLID SLABS

• Solid slabs can rest on wall edges in a linear manner or be point-loaded on


columns.

• They are seldom applied for spans exceeding 6m as the necessary thickness
of the slab for larger span would become heav y

H A L LOW S L A B S

• Elements constructed of hollow reinforced concrete panels are highly


economical for large spans bec ause they make it possible to economize on
concrete .

• Weigh t redu cti on of u p to 5 0 % are possi bl e u sing h ollow slabs com pared wi th
solid slabs of the same dimensions. Depending upon the production
t e c h n i q u e s , t h e c a v i t i e s a r e o v a l , r o u n d o r r e c t a n g u l a r.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

Fine Coarse
water cement Mild steel H.T wire
aggregate aggregate

Measuring cutting

Mixing bending threading

Mould oiling binding stressing


Filling concrete

Mould fitting Compacting

Curing and
detensioning PRODUCTION FLOW CHART
Mould
cleaning Demoulding

Curing in yard
Testing
Dispatch
AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A
P R E C A S T F L A T P A N E L S Y S T E M

S P E E D TO M A R K E T

Precast structural components are fabricated in a controlled plant environment and


can be erected in weather conditions that would delay the full erection of steel
components or CIS concrete. In general, the advantage of precast is that faster
erection reduces the overall construction schedule and overhead costs.
Compressed schedules, fewer on - site trades, and eliminating weather delays add up
to reduced project costs

QUALIT Y & DUR ABILIT Y

Precast, prestressed products provide a long ser vice life that far exceeds
field-placed concrete par tly because members are manufactured in plants
under strictly controlled conditions. The controlled plant environment has
offers easy verification of quality and a dedicated workforce. This means
h i g h - q u a l i t y p r o d u c t c a n b e m a n u f a c t u r e d e v e r y d ay, r e g a r d l e s s o f
w e a t h e r. T h e l o w w a t e r - c e m e n t r a t i o u s e d i n p r e c a s t c o n c r e t e c r e a t e s a
denser product that does not allow penetration of chlorides and other
harmful elements as easily as field -placed concrete.

I N T E G R AT E D P R O J E C T D E L I V E R Y

Structural precast components can be erected in a relatively shor t


p e r i o d o f t i m e b e c a u s e t h e y i n t e r l o c k t o s u p p o r t o n e a n o t h e r. S i m p l e r
installation requires fewer crew members, which means which means
fewer personnel to manage, fewer trades to pay and fewer trade -related
delays. Precast advantage is a cleaner and safer job site with less risk
a n d m o r e a s s u r a n c e o f a s m o o t h a n d s u c c e s s f u l p r o j e c t f l o w.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

ENHANCES SAFETY

Precast products eliminate many of the dangers associated with on -site


construction by providing a controlled, off - site fabrication environment.
Precast reduces the amount of wet trade work on site, making them
c l e a n e r, t i d i e r a n d s a f e r.

S U S TA I N A B I L I T Y

P r e c a s t i s p e r f e c t f o r t o d ay ’s f o c u s o n p r e s e r v i n g r e s o u r c e s a n d
p r o t e c t i n g t h e e n v i r o n m e n t t h o u g h s u s t a i n a b l e b u i l d i n g p r a c t i c e s . I t ’s a
perfect Green Building product. Precast reduces overall life cycle
impact on environment compared to other methods as it has lower
wastage and high potential to recycle waste.

O P T I M I Z AT I O N & F L E X I B I L I T Y

Advanced automation and technologies used in precast plants optimizes


the resource utilization, and produces an improved quality product with
reduced tolerances, thinner sections, and engineered solutions. Also, it
offers flexibility of space planning by allowing for longer spans which
create larger open f loor plans and increased f lexibilit y in design. For
architects, it can offer variety of different profiles. It is possible to cast
the member of very complex design and shapes.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

I N STA L L AT I O N
• Proper planning and preparatory works shall be required before
the actual installation of precast concrete elements in order to
ensure quality installations. The following items shall be planned
in advance.

• Method of sequence of assembly and installation, Pre cast


elements should be identified based on their location number and
tagged.
• Method of providing temporary suppor t elements should be
suppor ted temporarily before these get stabilized. Generally
structural members with adjustable ends shall be used for
securing the panels. Shims should be used adjust the panels to
ensure dimensional correctness.
• Installations tolerances Installation tolerances should be based
on design considerations should be clearly indicated.

• Handling and rigging requirements elements should be checked


for handling stresses before lifting and the cranes should have
sufficient capacity to handle the precast panels. At least 10%
impact should be considered while calculating the lifting capacity
of the crane.

• At site locations, panels shall be first unloaded and stacked or


directly lifted by the crane. The element shall then be installed
on the site and suppor ted by temporary jacks. The cranes shall be
released for next lifting once the temporary suppor ts are in
place. Shims shall be used to carefully align the element before
grouting.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

Location of Joints
The location of joints between external wall panels should be selected based on careful consideration of the following factors:

• Structural Considerations External wall panels may be load bearing (e.g. side walls of corner
terrace, semi-detached or detached) or non load bearing (e.g. front and rear façade panels).
In selecting panel joint locations, it is important to consider the panel stability (i.e. ability to
resist horizontal loads such as wind pressure or loads specified in the Building Regulations
Fourth Schedule).

• Aesthetics Whilst in general, panel joints are not highly visible, locations should be selected
which minimise any potential impact on the external façade aesthetics. In general, vertical
joints should align for the full height of the building and would preferably be located
symmetrically with respect to adjacent features.

• Panel Weight The weight of panels will dictate the crane capacity required for installation of
the wall panels. Apart from the disadvantage of higher cost, larger capacity cranes may not be
able to access the site. For typical conditions, a weight limitation of approximately 4 tonnes is
considered likely to be applicable. In general, the panel size should be maximized, leading to
increased speed of construction and reduced number of panel joints to be treated.

• Transport Limitations For transportation purposes, it is necessary to limit one of the panel
dimensions to 3.6m. In general, panel heights will be less than 3.6m and panel length is based
on weight or other considerations. When the required panel height exceeds 3.6m, the length of
panel will be reduced to 3.6m or less. Early planning for site access must be undertaken,
particularly when houses are built along Category 5 road.

• Internal Crack Control To minimise the risk of cracks appearing at the internal face of wall
panel joints, the following considerations are relevant: - If possible, locate panel joints at
internal wall intersections, inside service ducts or wardrobes and at other non-visible locations.
- Avoid panel joints towards midspan of floors, where beam or slab deflections could lead to
joint opening. - Avoid long continuous runs of panels, where accumulated shrinkage could result
in joint cracking.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

Mechanical, Electrical & Plumbing Fittings


• Mechanical, electrical & plumbing fittings shall be kept
open or concealed as per the requirements. For
concealed fittings, provision for grooves, blockouts
shall be made in casting moulds.
• The conduits and electrical boxes shall be embedded Fixing electrical conduits Fixing electrical boxes and conduits
and fixed in moulds before casting. For open fittings, Laying conduits on slab
these shall be fixed after erection at site.
• For firefighting systems, provision of National Building
Code (NBC) and local body law shall be adhered to.

Treatment for window openings


An effort has been made to develop a standardised approach for the
precast panel profile at window openings. The proposed detail is
considered suitable for precasting and can be applied for the majority of
projects. The profile has been developed in consideration of the
following:
• A drip was provided to the top and the side to discourage the ingress of
water.
• The protrusion at the head and jambs is provided for waterproofing and
allows the window frame to be fixed from inside the building; this results
in some savings as scaffolding would not be necessary.
• The protrusion allows sufficient space to apply grouting at the joint for
water tightness.
• The protrusion protects any sealant from direct exposure to the sun.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

A DVA N TAG E S
• Saves Construction Time: Precast Concrete construction saves
time, the risk of project delay is also less. The precast
concrete casting can be carried on simultaneously with other
w o r k s o n s i t e s u c h a s e a r t h w o r k , s u r v e y, e t c . a n d t h u s s a v e s
time.
• Qualit y Assurance: The key factors which regulate the qualit y
of construction such as curing, temperature, mix design,
formwork, etc. can be monitored for Precast Concrete. So,
improved quality construction can be performed.
• Usage of Prestressed Concrete: By using pre - stressed precast,
structural materials of high strength and load -bearing
capacity can be achieved, which can result in greater clear
span, reduced size of the cross - section of structural
members, etc.
• Cost-effective: The simplified construction process reduces the
t i m e , i n c r e a s e s t h e p r o d u c t i v i t y, q u a l i t y a n d s a f e t y a n d t h u s
the cost is reduced.
• Durability: Precast Concrete structure has a longer service
time period and minimal maintenance. The high -density
Precast Concrete is more durable to acid attack, corrosion,
impact, reduces surface voids and resists the accumulation of
dust.
• Aesthetics: As the structures are prefabricated in a controlled
factory environment, several combinations of colors and
textures can be used. A wide range of shapes and sizes are
available to choose from with smooth finishing and thus the
aesthetical value of products are increased.
• Safe Construction Platform: No raw materials have to be
stocked in site for Precast Concrete construction. It reduces
the requirement of traditional formworks and props, wastage,
workers, etc. and thus provides a safe working platform.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

D I S A DVA N TAG E S

• Tr a n s p o r t a t i o n I s s u e : T h e c o n s t r u c t i o n s i t e c a n b e
at a distant location from the Precast Concrete
plant. In that case, the precast members must be
carried to the site using trailers. In many cases,
the reduced costs of Precast Concrete is
compensated by the transpor tation cost.
• Handling Difficulties: Proper care and precaution
have to be taken for handling precast concrete.
U s u a l l y, p r e c a s t m e m b e r s a r e h e a v y a n d l a r g e
which makes it difficult to handle without damage.
G e n e r a l l y, p o r t a b l e o r t o w e r c r a n e s a r e u s e d t o
handle precast members.
• Modification: Limitation In case of precast
structures, it is difficult to modify the structure.
For example, if a structural wall is to be
dismantled for modification it will impact the
overall stability of the structure.
• Sensitive Connection Works: Assembling of the
precast members is one of the key points for
e n s u r i n g s t r o n g s t r u c t u r a l b e h a v i o r. C o n n e c t i o n s
between several structural members must be
supervised and done properly to ensure the
intended behavior of the connection such as
simple, semi -rigid or rigid connections. Besides
this, faulty connections may lead to water leakage
and fail sound insulation.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

A PPL I C AT I O N S

• Pre c as t p a n e l s h ave b e e n u s e d o n v i r tu a l l y eve r y t y p e o f b u i l d i n g , i n c lu d i n g s c h o o l s , o f f i c e


b u i l d i n g s , a p a r t m e n t b u i l d i n g s , tow n h o u s e s , c o n d o m i n i u m s , h ote l s , m ote l s , d o r m i to r i e s , a n d
s i n gl e - f a m i l y h o m e s .
• Pre c as t a rc h i te c tu r a l p a n e l s a re a l s o u s e d to c l a d a l l o r p a r t o f a b u i l d i n g f a ç a d e o r f re e
s t a n d i n g wa l l s u s e d fo r l a n d s c a p i n g , s o u n d p ro o f i n g a n d s e c u r i t y wa l l s .
• C o n ve n t i o n a l m o l d s R i b b e d s l a b s , b e a m s , w i n d ow p a n e l s , b ox . t y p e u n i t s a n d s p e c i a l e l e m e n t s .
• B at te r y m o l d s .
• I n te r i o r wa l l p a n e l s , s h e l l e l e m e n t s , ro o f . Fa ç a d e p a n e l s a n d f l o o r s l a b s .

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C AS E ST U DY
• The selected building is one among the six similar towers of G+23 storeys, which
is under
• c o n s t r u c t i o n a t B h o i w a d a , M u m b a i b y L a r s e n & To u b r o L i m i t e d . T h i s p r o j e c t i s
under the slum rehabilitation housing scheme. The developers are M/s Omkar
R e a l t o r s , M u m b a i . C u r r e n t l y, t h i s i s t h e t a l l e s t p r e c a s t b u i l d i n g i n I n d i a . T h i s
case study is based on the drawings, design repor t and computational models
presented by L&T Ltd.
• It is a rectangular building with plan dimensions 45.8m × 19.69m. The total
height is 70m. The appropriate type of precast system for the given height of
building is the wall system, which gives adequate lateral load resistance.
Advantages like fast and repetitive construction, good qualit y and finish due to
factory controlled production, cost competitiveness etc., suppor ted the selection
of the system. The typical f loors have a projection of approximately 1m on t wo
s i d e s w i t h r e s p e c t t o t h e g r o u n d s t o r e y . To a v o i d t h e c o m p l i c a t e d d e t a i l s o f a
precast cantilever suppor ting system at the first floor level, conventional cast -in-
p l a c e c o n s t r u c t i o n w a s a d o p t e d f o r t h e g r o u n d s t o r e y.
• Stuctural Stability
The stability of the structure was considered against the gravity loads, lateral loads
from wind and
ear thquake, and the accidental loads like explosion. The precast design followed an
emulation of cast -inplace system. Inter-connected walls are provided in or thogonal
directions. The wall joints are such that an entire wall acts as an equivalent
monolithic system under lateral loads. The connections between different panels are
w e t c o n n e c t i o n s , a n d a r e a b l e t o t r a n s f e r i n - p l a n e s h e a r, f l e x u r a l t e n s i o n a n d
c o m p r e s s i o n . To i l e t p o d s , w h i c h a r e U - s h a p e d u n i t s , a c t a s s m a l l c o r e u n i t s . T h e
wall-to-floor area ratio is 5.7% for shor ter direction and 2.2% for longer direction.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C AS E ST U DY
• Connections
• Horizontal Joint: A horizontal connection
bet ween panels transfers ver tical stresses
due to gravity loads and any out -of-plane
bending due to eccentricity of the loads.
It also transfers ver tical stresses due to
cantilever action of the wall and
horizontal shear under lateral loads. The
horizontal joint bet ween panels at a f loor
level is made by projecting dowel bars
from the lower panel. They are inser ted
into the dowel tubes provided in the upper
panel and grouted at site using non -
shrink, non-metallic grout. Shear force is
• transmit ted by dowel action of the bars.
Any shear capacity of the grout is
ignored. The dowels are designed to
g e n e r a t e t h e i r t e n s i o n c a p a c i t y. T h e y a r e
placed continuously from the foundation
to the roof. Tie reinforcement overlapped
with U-bars are provided in the slabs for
slab-to-wall connection.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C AS E ST U DY
• Ve r t i c a l J o i n t : T h e v e r t i c a l j o i n t s a r e d e s i g n e d t o t r a n s f e r
shear forces under lateral loads. The joint faces are
indented to provide shear keys(9) for shear transfer with
increasing lateral loads. Beyond cracking of concrete, a
strut-and- tie action is expected to develop. Overlapping
reinforcing loops are provided along with shear keys to take
up the horizontal component of the inclined compressive
strut. A continuous ver tical bar is provided inside the
overlapping loops from the adjacent units. The loops thus
c o u p l e s t h e a dj a c e n t p a n e l s . Fo r s u f f i c i e n t o u t - o f - p l a n e
suppor t, a panel is adequately connected to the
perpendicular panel through overlapping reinforcing loops
w i t h t h e v e r t i c a l b a r. T h e e x t e r i o r w a l l p a n e l s a l o n g t h e
shor ter direction of the building, which constitute the
primary shear walls to resist the lateral forces, are
provided with six shear keys per storey height. In interior
wall joints, reduced number of reinforcement loops are
provided per storey height since the shear demand is less

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C AS E ST U DY
• Modelling
T h e a n a l y s i s o f t h e s t r u c t u r e w a s c a r r i e d o u t u s i n g t h e E TA B S s o f t w a r e p a c k a g e . T h e e n t i r e s u p e r s t r u c t u r e w a s
modelled primarily using shell elements. The walls were of shell elements and the slabs of membrane elements. A f loor
was considered as a rigid diaphragm at the respective level, to transfer the lateral forces to walls. The horizontal joints
o f t h e w a l l p a n e l s w e r e i d e a l i s e d t o s i m u l a t e a n e q u i v a l e n t m o n o l i t h i c b e h a v i o u r, i n p r e s e n c e o f t h e c o n t i n u o u s v e r t i c a l
dowel bars. Therefore, the shell elements representing the panels were made continuous at the f loor levels. A few
beams and columns present in the structure were modelled using frame elements
• Integrated Model: In this case, perfect shear transfer was assumed through monolithic behaviour of t wo adjacent
panels connected by the grouted loops. The ver tical joint strip was modelled as a 100mm wide strip of shell element.
Its thick ness and stiffness were considered same as that of the adjacent wall panels. In a grouted keyed connection,
Clause 5.3.1 of IS11447: 1985 permits the joints to be modelled monolithic. Clause 8.1 of IS15916: 2010 permits the
prec ast structure to be analysed as monolithic, provided the joints are designed to take the respective forces
• D i s c r e t e g a p m o d e l : I n t h i s m o d e l , n o s h e a r f o r c e w a s a s s u m e d t o t r a n s f e r b e t w e e n t h e w a l l p a n e l s . To i d e a l i s e t h i s
condition, a 20mm gap was provided at the ver tical joint locations. This uncoupled the adjacent walls. The walls were
connected only at the f loor levels by the diaphragm constraints

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C AS E ST U DY
Comparative Study of Models

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C AS E ST U DY
PREVENTION OF PROGRESSIVE COLLAPSE
T h e Pre c as t s t r u c tu re s a re m o re s e n s i t i ve to p ro g re s s i ve c o l l a p s e a f te r i m p o r t a n t l o c a l d a m ag e.
Fo r t h e s t a b i l i t y o f s t r u c tu re, t h re e d i m e n s i o n a l i n te r a c t i o n s b et we e n s t r u c tu r a l m e m b e r s a re
n e c e s s a r y to p ro du c e a ro b u s t d e s i g n . T h e c o n n e c t i o n s a re n o r m a l ly d e s i g n e d fo r s h e a r a n d
c o m p re s s i o n . B u t i n t h e c as e o f a c c i d e n t a l l o a d i n g l i ke e x p l o s i o n , h i gh te n s i l e s t re s s e s a l o n g w i t h
l a rg e d efo r m at i o n s w i l l o c c u r. To t a ke u p s u c h fo rc e s , t h e c o n n e c t i o n s s h o u l d h ave s u f f i c i e n t
s t re n g t h , c o n t i n u i t y a n d du c t i l i t y. S t re n g t h i s to t a ke u p t h e e x t r a fo rc e s a c t i n g , c o n t i n u i t y to
re d i s t r i b u te t h e l o a d i n g i n c as e o f a c c i d e n t a l c o l l a p s e a n d du c t i l i t y to a c c o m m o d ate l a rg e
d efo r m at i o n s as we l l as fo r e n e rgy d i s s i p at i o n . To t a ke c a re o f t h e s e d e m a n d s , t i e re i n fo rc e m e n t s
i n a l l t h e t h re e d i m e n s i o n s a re a n a b s o lu te n e c e s s i t y ( Cl. 1 6 . 5 , AC I 3 1 8 - 0 8 ) . T h e i n te r n a l t i e s a re
to t a ke u p t h e l ate r a l fo rc e s f ro m s h e a r wa l l a c t i o n .

Pe r i p h e r a l t i e s e n s u re t h e d i a p h r ag m a c t i o n o f t h e s l a b s . Fl o o r to wa l l t i e s t a ke u p t h e h o r iz o n t a l
fo rc e s f ro m a n c h o r ag e o f f l o o r s to t h e i r s u p p o r t a n d ve r t i c a l t i e s e n s u re t h e c a n t i l eve r a c t i o n o f
wa l l s .

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C AS E ST U DY
S U M M A RY
• T h e c as e s tu dy p rov i d e d s o m e i n fo r m at i o n o n t h e d e s i g n a n d m o d e l l i n g as p e c t s o f a wa l l t y p e
p re c as t b u i l d i n g . T h e m o d e l l i n g o f ve r t i c a l j o i n t s was d o n e w i t h t wo e x t re m e c o n d i t i o n s , s i n c e
t h e re i s n o p ro p e r gu i d e l i n e s to m o d e l t h e j o i n t s m o re e c o n o m i c a l ly by c o n s i d e r i n g t h e a c tu a l
s h e a r t r a n s fe r. T h e c o n c lu s i o n s d r aw n f ro m t h e c as e s tu dy o n a p re c as t wa l l p a n e l s ys te m
b u i l d i n g a re as fo l l ow s .
• T h e e m u l at i ve m o n o l i t h i c wa l l s ys te m s e e m s to b e a d e q u ate i n m o d e r ate s e i s m i c z o n e s . T h e
p rov i s i o n s o f t i e re i n fo rc e m e n t s , re i n fo rc e d s h e a r keys a n d d owe l b a r s p rov i d e t h e re q u i re d
s t r u c tu r a l i n te g r i t y fo r t h e p re c as t s ys te m .
• T h e m o d e l l i n g o f ve r t i c a l j o i n t s w i t h o u t c o n s i d e r i n g t h e s h e a r t r a n s fe r t h ro u gh t h e s h e a r keys ,
re i n fo rc e d w i t h s h e a r l i n k s , l e a d to a c o n s e r vat i ve d e s i g n . N o n - l i n e a r s h e a r s p r i n g s c a n b e
i n c o r p o r ate d i n t h e m o d e l to g et m o re re a l i s t i c wa l l fo rc e s . T h i s w i l l l e a d to a m o re e c o n o m i c a l
design.

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


P R E C A S T F L A T P A N E L S Y S T E M

C AS E ST U DY
To avo i d p ro g re s s i ve c o l l a p s e, t h e s t r u c tu re s h o u l d b e s u f f i c i e n t ly ro b u s t a n d re du n d a n t .
I d e n t i f i c at i o n a n d p ro p e r d e s i g n o f t h e key e l e m e n t s i n t h e s t r u c tu re i s n e c e s s a r y to avo i d
p ro g re s s i ve c o l l a p s e. Ac c o rd i n g to Cl au s e 2 . 6 o f B S 8 1 1 0 - 2 : 1 9 8 5 , a key e l e m e n t a n d i t s
c o n n e c t i o n s s h o u l d b e d e s i g n e d fo r a n u l t i m ate d e s i g n l o a d o f 3 4 k N / m 2 f ro m a n y d i re c t i o n ,
w i t h o u t c o n s i d e r i n g a n y p a r t i a l s a fet y f a c to r. A s p e r Cl au s e 4 . 7 o f I S 1 1 4 4 7 : 1 9 8 5 , t h e m i n i m u m
a re a fo r t i e re i n fo rc e m e n t s s h o u l d n ot b e l e s s t h a n 4 c m 2
.
Re c o m m e n d at i o n s i n t h e s e c o d e s we re fo l l owe d to f i n d t h e d e s i g n l o a d a n d t h e re q u i re d a m o u n t o f
t i e re i n fo rc e m e n t s . H e re, t i e re i n fo rc e m e n t s we re p rov i d e d h o r iz o n t a l ly, b ot h i n te r n a l ly a n d
p e r i p h e r a l ly. T h e re i n fo rc e m e n t at t h e s h e a r key l o c at i o n s p rov i d e t h e h o r iz o n t a l t y i n g a n d t h at at
t h e j o i n t re g i o n s g i ve s t h e n e c e s s a r y ve r t i c a l t y i n g ef fe c t . T h e h o r iz o n t a l t i e s p rov i d e a c a n t i l eve r
a c t i o n to h o l d t h e d a m ag e d p a r t s . T h e ve r t i c a l t i e s h e l p to s u s p e n d t h e l owe r d a m ag e d e l e m e n t s
to t h e i n t a c t u p p e r p o r t i o n s . T h e h o r iz o n t a l a n d p e r i p h e r a l t i e s ys te m s p rov i d e a c ate n a r y a c t i o n to
b r i d g e t h e d a m ag e d p o r t i o n . T h e wa l l - to - s l a b t i e s h e l p to s u s p e n d t h e d e b r i s , a n d p reve n t t h e
d a m ag e d f l o o r f ro m f a l l i n g d ow n o n to t h e i n t a c t l owe r p o r t i o n s

AARSH MALHOTRA | JASSIMAR WAHI | RAJAT VERMA | 4A


THANK YOU

RAJAT VERMA | 4A | 180BARCH118

You might also like