Agency Action Plan 2022
Agency Action Plan 2022
Agency Action Plan 2022
STATUS of IMPLEMENTATION
Audit Observations and Recommendations
For the Calendar Year 2020
As of OCTOBER 14,2022
Part II of
AAR CY
2019, MPDC explained
Observati We recommend that the: that consultancy
on No. 15, MPDC evaluate the necessity service was only The MPDC cited the
page111 of hiring consulting services endorsed to the reason on the noted
Agency Action Plan Reason for Partial/Delay/
Person/ Target Implementation
Status of Action Taken/ Action
Ref Audit Observations Audit Recommendations Non-Implementation, if
Action Plan Dept.
Implementation to be Taken
From To applicable
to avoid incurrence of MPDO after Responsibl observation.
unnecessary expenditures. signing of the
contract
agreement dated
August 1,2018.
Part II of
AAR CY The MPDC
2020 ,Obs We recommend that the guaranteed that The MPDC submitted a
ervation LCE , ME and MPDC strictly they shall letter of explanation.
No. 17, comply with the guidelines of conform with
page 168. COA Circular No. 2013-004 COA Circular
regarding information and No.2013-004 or
publicity of PPAs. information and
Agency Action Plan Reason for Partial/Delay/
Person/ Target Implementation
Status of Action Taken/ Action
Ref Audit Observations Audit Recommendations Non-Implementation, if
Action Plan Dept.
Implementation to be Taken
From To applicable
publicity on Responsibl
programs
/projects/Activiti
es of
Government
Agencies for a
long structured
list of priority
PPA covering
the 5
development
sectors such as
physical (or
environmental),
institutional,
economic, social
and
infrastructure.
Part II of
AAR CY Deficiencies were noted We recommend that the
2020, In the procurement of
Observati infrastructure projects A. Municipal The Municipal The Municipal Engineer
on No.16, such as (a.) giving Accountant: Engineer will discourage to prepare By
page 159 advance payments after prepare POWs Administration POWs if
the targeted project iii. require inventory for by the said office has no
completion date; (b) custodian slip for the hand Administration available PPEs and Hand
awarding contract to tools issued to MEO not to include tools to be used for the
Agency Action Plan Reason for Partial/Delay/
Person/ Target Implementation
Status of Action Taken/ Action
Ref Audit Observations Audit Recommendations Non-Implementation, if
Action Plan Dept.
Implementation to be Taken
From To applicable
contractor with negative personnel before certifying anymore tools Responsibl projects.
NFCC, and (c) the completeness of and PPEs needed
procurement and supporting documents for the by the projects
inclusion of hand tools procurement of tools and commencing in
in the POW for projects equipment. the year 2021
implemented by and onward.
administration. c. Municipal Engineer
Moreover, advance exclude the hand
payment voucher tools in the
amounting to computation of
P2,937,880.65 were not project cost estimate
submitted for audit in the POW and
including those instead prepare
documents required for separate purchase
audit including those request for the tools
documents required for and equipment
the technical evaluation needed in the
and inspection of implementation of
infrastructure projects projects by
while project costs were administration . The
incorrectly/incompletel procurement of tools
y posted in subsidiary should be based on
ledgers. the current available
tools at the
Municipal
Engineering Office.
Part II of
AAR CY The implementation
2018, of infrastructure We recommend that the: The Municipal
Observati Engineer
projects funded by
on No.17. a. LCE ,through the
Page 168 the 20% Municipal Engineer .
Development Fund , i) issue termination of
Local Government contract to erring contractors
Support Fund proper who, after contract time has
Agency Action Plan Reason for Partial/Delay/
Person/ Target Implementation
Status of Action Taken/ Action
Ref Audit Observations Audit Recommendations Non-Implementation, if
Action Plan Dept.
Implementation to be Taken
From To applicable
and Special expired, have negative Responsibl
Education Fund was slippage of 10% or more in
the completion of the work
marred by (a) non-
pursuant to Section III -A(2)
submission of list of of the guidelines on
all completed and Termination of Contracts,
on-going government ii)cause the forfeiture of
projects and those their performance security
that are to be pursuant to Section
8.%.Annex E of the Revised
implemented during
IRR of RA No.9184 : and
the year as required iii) provide a copy of the
under COA Circular notice of termination and
No.2013-004 dated forfeiture of performance
January 30,2013; (b) security to the Audit Team.
unimplemented 62
projects costs b. Municipal Engineer:
i) submit the status report of
totaling all infrastructure projects of
P57,112,914.56 the municipality supported
while 43 projects with SWA to facilitate
with different verification of the reported
program of works projects accomplishments;
implemented and fast track the
implementation of the
separately. infrastructure projects and
make sure that all projects are
strictly monitored and
implemented in accordance
with plans and schedules: and
iii) render explanation on the
different POWs with same
projects but with separate
implementation and
c. LCE, ME and MPDC
strictly comply with the
guidelines of COA circular
Agency Action Plan Reason for Partial/Delay/
Person/ Target Implementation
Status of Action Taken/ Action
Ref Audit Observations Audit Recommendations Non-Implementation, if
Action Plan Dept.
Implementation to be Taken
From To applicable
No. 2013-004 regarding Responsibl
information and publicity of
PPAs.
Agency Action Plan Reason for Partial/Delay/
Person/ Target Implementation
Status of Action Taken/ Action
Ref Audit Observations Audit Recommendations Non-Implementation, if
Action Plan Dept.
Implementation to be Taken
From To applicable
Responsibl
Agency Action Plan Reason for Partial/Delay/
Person/ Target Implementation
Status of Action Taken/ Action
Ref Audit Observations Audit Recommendations Non-Implementation, if
Action Plan Dept.
Implementation to be Taken
From To applicable
Responsibl